Вы находитесь на странице: 1из 15

Society of Petroleum Engineers

SPE 25384

Bigbore Well Completions: A New Completions Technique for Arun Field


W.L. Cannan, Mobil Oil Indonesia Inc.; D.L. McKenna, RA. Sukup, and D.G. Calvert,
Mobil E&P Technical Services Inc.; and R Quitzau, S. Sardjono, and P.C. Ellison,
Mobil Oil Indonesia Inc.
SPE Members

Copyright 1993, Society of Petroleum Engineers, Inc.

This paper was prepared lor presentation at the SPE Asia Pacific Oil & Gas Conference & Exhibition held in Singapore, 8-10 February 1993.

This paper was selected for presentation by an SPE Program Committee following review of information contained in an abstract submitted by the author(s). Contents of the paper,
as presented, have not been reviewed by the Society 01 Petroleum Engineers and are subject to correction by the author(s). The material, as presented, does not necessarily reflect
any position of the Society of Petroleum Engineers, its officers, or members. Papers presented at SPE meetings are subject to publication review by Editorial Committees of the Society
of Petroleum Engineers. Permission to copy is restricted to an abstract of not more than 300 words. Illustrations may not be copied. The abstract should contain conspicuous acknowledg-
ment of where and by whom the paper is presented. Write Librarian, SPE, P.O. Box 833836, Richardson, TX 75083-3836, U.S.A. Telex, 163245 SPEUT.

ABSTRACT accordingly. Substantial increases in


gas and condensate production rates are
The prolific Arun Field in North being reali:zed with a savings in
Sumatra, Indonesia continues to investment over previous Arun Field
produce substantial amounts of drilling and completion methods
natural gas and condensate. However, utilizing con.ventional 7" completions.
the massive carbonate reef reservoir
is beginning to require special Previous completion techniques utilized
measures for more complete 7" production tubing with either cased
exploitation and recovery of the or open holle completions. The "Big
large quantities of hydrocarbon Bore" completion technique has 9-5/8"
remaining in the formation. production t.ubing with an open hole
Optimization of production requires- completion to maximize deliverabili ty.
combined efforts from Arun The primary purpose of the technique is
geologists, reservoir, production, to boost field productivity in order to
drilling, and operations personnel as meet gas dE~mand, enhance condensa te
well as technical advisors. optimization, and allow flexibility in
operations. This new completion
Although the Arun Field wells technique required extensive equipment
typically produce 30 to 100 MMSCFD design and testing to meet anticipated
per well, increased production rates production and stimulation conditions.
are being achieved by utilizing This is the first time a completion of
larger bore wells and modifying the this type has been utilized in
drilling and completion techniques Indonesia, and as far as we know, these
2 "Big Bore" Well Completions Paper #25384
A New Completion Technique for the Arun Field

are the largest bore, gas producing propane, butane, and condensate
well completions in the world. This obtained from the produced gas at the
paper discusses the performance of PT. Arun gas plant. (Fig. 1).
the wells and the various components
utilized in this new "Big Bore" The Arun formation consists mainly of
completion technique. limestone with some sections of the
reservoir containing some dolomite.
History of Arun Field The initial reservoir pressure was 7100
psi when production began in 1977.
The Arun Field is one of the most Since the Arun is a depletion drive
unique gas reservoirs in the world. reservoir, pressures have been steadily
The field is located in the northern declining throughout the production
part of the island of Sumatra history of the field.
Indonesia in the Aceh Province and
produces from a Middle Miocene Age The current reservoir pressure is
limestone reef that is approximately approximately 3000 psi and is declining
3 miles wide and 12 miles long, at about 1 psi/day at the current
trending in a north/south direction. production rate. The reservoir
0
The average pay thickness is 1000 temperature is 350 F and the gas
feet and the top of the Arun contains 15% CO 2 , approximately 50 ppm
formation is approximately 10,000 H2 S and produces wi th a condensed water
feet sub-sea. vapor yield of about 10 BBLS/MMSCFD.
These are harsh conditions from a
The field was discovered in 1971 and completion design standpoint. (Table 1)
has been developed by drilling wells
in four clusters located in strategic As the reservoir pressure drops, so
parts of the reservoir. Currently 73 does the average production rate of the
wells produce a total of 3.4 BSCFD individual wells. The average
and 115, 000 BBLS of condensate per production rate has fallen from 150
day. Approximately 1 BSCFD of this MMSCFD at an average wellhead pressure
gas is processed through a Natural of 4800 psi in 1977 to 50 MMSCFD at
Gas Liquids plant (NGL) to extract 1750 psi wellhead pressure in September
additional liquids (LPG and 1992.
condensate) and the dry gas is re-
injected into the Arun reservoir to Operational Overview
assist in sweeping the condensate to
the producing wells. The remaining The Arun Field was developed using a
2.4 BSCFD is transferred by pipeline cluster concept where a group of wells
to the PT. Arun Liquid Natural Gas are located with common surface
plant for liquifaction, and production facilities. There are four
approximately 150 MMSCFD is sold to clusters in the Arun field with
various national projects for use as locations for a total of 21 wells per
fuel. Pertamina sells LNG, liquid cluster. Production wells are
Paper #25384 W.L. CANNAN, et al 3

directionally drilled from the fractured to reduce skin effect and


clusters in order to minimize the increase individual well productivi ty.
surface area required for drilling This stimulation project will continue
and facilities and to reduce the on selected candidate wells. The "Big
environmental impact on the local Bore" Project was designed to complete
communi ty. Currently there are 73 a total of ten new production wells
producing wells, 10 gas injection wi th 9-5/8" tubing instead of the
wells, and 3 observation wells in the standard 7" size. By changing to the
Arun Field. (Fig. 1 & 2). larger tubing size individual well
production is increased and production
Development drilling is in its final requirements can be achieved while
stages and only 4 wells remain to be reducing the total drilling cost by $9
drilled and completed. This will MM and reduc:ing the total wells to be
bring the total "Big Bore" wells to drilled. By utilizing "Big Bore"
10 when drilling is completed in completions as opposed to the standard
1993. 7" wells, four fewer wells are
required. (Table 2).
Deliverability Enhancement
Projects Other proj ec:ts are being designed to
lower the wellhead pressures [2] .
Individual well performance has been These proj ects address al ternate means
declining over the life of the field of cooling the gas with minimal
due to declining reservoir pressure. pressure drop (Dehydration Project) and
Since the required LNG plant inlet the installation of compressors
pressure is fixed at 850 psi, this (Booster Compression Project) in order
header pressure to approximately 1750 to further lower the wellhead pressure.
psi in the field with the current The Dehydration Project lowers the
production facilities. This allows wellhead pressure from 1750 psi to 1300
for pressure drops to sufficiently psi. The Jroules-Thompson valves were
cool the gas and allow efficient replaced with a propane refrigeration
separation of the gas prior to system. This project was completed in
transporting it down the pipeline to 1992. The Booster Compression Project
the PT. Arun plant. This fixed will further reduce the wellhead
header pressure doesn't leave much pressure to eventually 300 psi. This
room for productivity improvements project is scheduled for completion in
except by reducing the pressure drops 1995. Both projects are designed to
in the wellbore and formation. maximize deliverabili ty and meet
production demands. This paper will
Two proj ects to increase individual focus on only the "Big Bore" completion
well performance by downhole project.
improvements were implemented. They
were acid fracturing [1] and "Big
Bore" completions. Many of the Arun
wells were successfully acid
4 "Big Bore" Well Completions Paper #25384
A New Completion Technique for the Arun Field

"Big Bore" Concept review of past experiences, but


utilization of the latest technologies
The original concept of a "Big Bore" available.
completion was developed in early
1990. The idea was to complete one The initial design of the "Big Bore"
well in each cluster with 9-5/8" wells called for a simple approach to
tubing in order to provide additional the use of the larger bore tubing.
gas deliverability on demand to meet Plans called for a similar wellhead
operational needs such as shutting in system to the current 7" completion
a well for diagnostic work or a except with a larger bore, a permanent
workover. This would provide one packer system, and premium seals on the
well in each cluster capable of being tubing string.
adjusted to meet production
requirements and the other wells The Arun Field operates with a "two
allowed to produce at full throttle, barrier" system i.e., there must be at
making operations much simpler. least two barriers in place for well
containment. So the 9-5/8" tubing
However, as the concept developed, it would be the first barrier and the 13-
was soon realized that in addition to 3/8" casing would be the second.
providing extra capacity per well, However upon closer inspection and
fewer total wells would be required further discussions it was determined
to fully develop the Arun field, at a that the wellhead system needed some
substantial cost savings. The "Big revisions due to the larger size,
Bore" wells were estimated to produce resulting loads, and type of service to
approximately 120 MMCFD as compared be encountered in the "Big Bore"
to an average of 70 MMCFD for a application.
conventional 7" Arun well.
It was also determined that the
Large bore tubing wells were not new permanent packer design that was
to the Arun Field. The original originally evaluated would cause the
completions in 1977 were designed for casing to fail under the extreme load
7" tubing, a rather large tubing size conditions and the 13-3/8" casing
at that time by any standard. Many required a premium connection since it
technological advances were made would serve as the second barrier to
during the initial stages of the Arun Arun gas.
Field 7" development to solve
problems associated with wellhead The other item that developed from
seals, tubing connections and packer discussions was that of making the
fluids used in the harsh Arun entire well full bore with minimum
environment and operating conditions internal upsets or restrictions to
[3 & 4]. The increase in production flow. This was based on concerns over
tubing size from 7" to 9-5/8" pressure drops, potential corrosion and
resulted in not only a thorough erosion, and also in maximizing the
Paper #25384 W.L. CANNAN, et al 5

options for future workovers. In Advantages


order to achieve a full bore well,
this eliminated conventional wellhead Full bore 1N'ell design with 9-5/8"
back-pressure valve preparations and tubing and a PBR provide several
downhole profiles for wireline distinct advantages over conventional
retrievable plugs. This presented a 7" completions. These advantages are:
new issue of securing the well. A
new system for Arun well containment * Eliminates the gas turbulence
was developed to secure the well in areas commonly found in conventional
order to nipple down the blow-out packer completions.
preventers and install the christmas * Eliminates the open liner lap
tree, or just to secure the well if associated with the 9-5/8" liner
required. (Fig. 3). completion.
* Allows for tubing retrieval to
After a complete review of the 5,500 feet if required by corrosion
original proposed "Big Bore" concept, problems near the surface.
several issues needed revision from * Allows for monitoring the annular
the typical 7" Arun well completion. space between the 13-3/8" production
These will be discussed in detail in casing and 9-518" tubing string.
the following discussions of the * Eliminates some of the completion
various key "Big Bore" system equipment and accessories commonly
components. found in the 7" completion.
* Require!s fewer wells and less
The "Big Bore" project was approved investment than with 7" completions.
in January 1991 and only 14 months
later the first well was drilled and Disadvantages
, tested. This represents a tremendous
effort by Mobil and many equipment Although the advantages far outweigh
manufacturers. Nearly every the disadvan"tages, it should be noted
component of the "Big Bore" wells was that the 9-5/8" wells require higher
a first in the industry since they minimum stable flow rates than the 7"
were newly designed and manufactured wells. As tubing diameter increases,
for the Arun application. Premium minimum bottom hole flowing pressure to
connections were qualified for the maintain stable production rises.
13-3/8" casing and 10" liner as well Therefore "Bi.g Bore" wells will load up
as the 9-518" tubing. A new wellhead at higher pressures than a 7"
was designed and rated for 5000 psi completion. However this is not
at 350 degrees F, API 6A Appendix F, predicted to occur until late in the
PR-2 and a liner hanger/PBR and life of the field for both 7" or 9-5/8"
isolation packer system was designed wells. "Bi.g Bore" completions will
and tested to over one million pounds load up approximately one year sooner
compressional load. A retrievable than the 7" "'ells.
bridge plug was also developed for
securing the wellbore as required.
6 "Big Bore" Well Completions Paper 125384
A New Completion Technique for the Arun Field

Comparison to Standard Arun Well (Fig. 3).

The "Big Bore" wells were designed


for maximum gas deliverability and to ftBig Bore ft Design and Qualification
have the entire Arun section open to Testing
flow. Therefore they reduced the
number of wells to be drilled to meet Prototype equipment design, testing,
the LNG sales contracts. Fourteen and manufacture represents a major role
conventional 7" wells totalling $ 84 in the success of the "Big Bore"
MM, were proposed to complete the project. This most critical step in
Arun Field development drilling the development of the project was
program. Only ten "Big Bore" wells required to safely complete the wells
totalling $ 75 MM are required. and ensure proj ect success. Following
is a discussion of the key components.
On a standard 7" Arun production
well, 30" conductor pipe is driven to Wellhead
200 feet with 20" casing set at 2000
feet and cemented to surface. A 17- The 410 stainless steel wellhead
1/2" hole is then drilled to assembly is supported by 20" surface
approximately 7300 feet where 13-3/8" pipe and can suspend and seal on both
intermediate casing is set and the 13-3/8" production casing and the
cemented to surface. From this shoe 9-5/8" tubing. Mandrel hangers were
a 12-1/4" hole is drilled into the used on both the 13-3/8" c"asing and 9-
top of the Arun limestone and a full 5/8" tubing to ensure a fullS, 000 psi
string of 9-5/8" is cemented to rating both internally and externally.
surface. At this point, either a 7" Emergency equipment is also available
liner is run and cemented across the to suspend on 7" or smaller production
Arun or the well is completed open tubing if needed. This capability
hole. Some of the 7" wells have the allows smaller tubing to be run in the
upper, leaner condensate zone, cased future to optimize well deliverabili ty
off to allow only the richer as formation pressure decreases. All
condensate zones to contribute. This components in the system were API
depends on the relative monogrammed to 5,000 psi service rating
permeabili ties of the exposed zones for the Arun application.
and the objectives of the well.
Christmas Tree Assembly
A permanent, hydraulically set packer
is run on 7" tubing and set just The christmas tree received the same
above the 9-5/8" casing shoe or 7" level of QA and QC scrutiny as the
liner top to isolate well fluids from wellhead and all component parts are
the production casing. A non- API monogrammed. The 9" bore tree and
corrosive, oil based packer fluid is wellhead are over 20 feet tall when
used in the tubing/casing annulus. fully assembled. Due to thermal
expansion of the flowline and the risk
Paper #25384 W.L. CANNAN, et al 7

of failure near the surface, the loads are calculated to be in excess of


bending moment of the wellhead was 750,000 lbs.
carefully studied. This study
resulted in utilizing an integral "Big Bore" completions also required a
flange on the lower block master permanent liner top isolation
valve to increase strength in this packer/hanger assembly for two reasons.
area. First the liner lap must be
mechanically secured and secondly the
All of the 9" bore valves on the tree use of the packer system ensures the
are hydraulically actuated and fail- integri ty of the annular space between
closed to provide quick reliable the production casing and the tubing.
action. "Big Bore" trees used the The design of the compression-set liner
first 9" gate valves qualified to API top isolation packer allows for the
6A Appendix F PR-2 requirements and transfer of the incremental thermal
are produced to PSL-3 specifications. load through the packer mandrel and
The 2-1/16" and 4-1/16" wing valves load sub in1to the top of the liner
are PSL-2. hanger. The packer accomplishes this
wi thout incrementally setting the
A two piece, single flowloop design packer slips or the packing element.
was chosen to handle the high flow This eliminc3.ted the potential for
rates and allow for installation of failure of the 13-3/8" production
an emergency tUbing spool if casing due to an incremental increase
required. The emergency spool raises in induced load.
the assembly two feet over its
standard height, so additional After the packer is set, the lower
flowloop spacers are required to seals stung into the liner hanger PBR
adjust the flow-loop elevation. (Fig. remain static. Only the tUbing seals
8) . Again, all flow-loop, spacers, stung into the packer PBR are dynamic.
and connections received particular They only move during a cold
attention in their manufacture stimulation or well kill operation.
process. All components were full Space-outs and set down weights were
body stress relieved to ensure calculated to prevent movement during
metallurgical uniformity. (Fig.4). normal production or shut in cycles.
This complete system was designed for
13-3/8 ft X 9-5/8 ft Liner Top installation in the vertical section
Isolation Packer and 10 ft Liner and would require additional design and
Hanger testing for setting in deviated
wellbores.
To accommodate the "Big Bore" design,
a liner hanger that could support the Special mills and scrapers were
tremendous incremental load produced included in the design of the liner top
by the thermal growth of the tubing isolation packer and liner hanger/PBR
string and the weight of the 10" systems to a.llow for proper clean out
liner below was required. These and dressing of the PBR's prior to the
8 "Big Bore" Well Completions Paper #25384
A New Well Completion Technique for the Arun Field

installation of seal assemblies. cemented in place if required. This


presented two potential problems
The liner top isolation packer and during design. It required the use of
liner hanger systems were closely a ported float shoe that had to support
integrated to provide a reliable, the full 350,000# liner weight without
secure system. cracking. A shoe was designed and
tested to meet and exceed these
10", 72# L-aO Liner criteria. One key point on the float
equipment was that it maintained the
Since the 10" liner is part of the same degree of integrity and high
production tubing string in a "Big standards as all other components of
Bore" completion, it must withstand the production tubulars.
the 7,500 psi pore pressure in the
Baong shale above the Arun combined Cementing Procedures
with the low bottom hole flowing
pressure during future production. In a standard 7" Arun completion, the
(Fig. 5). To prevent the liner from 9-5/8" string is single-stage cemented
collapsing required the use of 10" aD back to surface. This was not possible
72# pipe as the liner material where in a "Big Bore" well. However, Mal had
the pressure of the Baong shale is perfected the single stage cementing
present. program and wanted to simulate that
procedure on a "Big Bore" liner job.
L-80 grade steel was used due to the This required a test program on two
corrosive Arun environment and a standard 7" wells to collect the
newly developed heavy wall connection necessary circulating temperature data
was utilized to provide positive to model and develop cementing
pressure integrity during high procedures for the 10" liner job. Due
temperature production and cooler to the wall thickness of the 10" 72
stimulation cycles. tift liner conventional cement
evaluation tools are not reliable.
10" Float Equipment Instead, Mal relied on negative and
posi tive pressure testing on the liner
The float equipment for the project lap for cement evaluation.
was designed to meet project demands
and was certified to meet API RP10F 9-5/a" Tubing String
class III-C specifications (5,000
psi, 400 0 F). The equipment was Mobil had previously tested and
manufactured to Mobil specifications approved two 9-5/8" 53.5 :fIft casing
us ing 2-1 I 4 Chrome tubes. For connections. However, Mobil had never
contingency purposes, the equipment developed a connection for this size as
was designed and tested to withstand tubing. Mobil's first attempt to
full liner weight on bottom. The qualify this connection for use as
liner could then be set on bottom and tubing failed, but after switching to a
Paper #25384 W.L. CANNAN, et al 9

different seal taper and performing Due to the corrosive Arun environment a
extensive testing, it was deemed plug that met all of MOl's requirements
suitable for the "Big Bore" could not be found. This required a
application. special plug be designed, built, and
prototype te,sted to ensure it would
The 9-5/8" tubing is landed in the satisfy all of the requirements. The
liner top packer/PBR system by use of resul ting plug was designed to
a seal assembly. This seal assembly wi thstand differential pressures of
was designed and tested to maintain 4,000 psi from above and below and
sealing integrity under a temperature extremes from 350 0 to 90 0 F
differential pressure of 7,500 psi as well as meeting NACE specifications
0
wi th a temperature range of 90 to for sour service.
0
350 F. The seal assembly consists
of a combination of packing rings Planning
molded from premium seal material.
The seals remain static during normal Due to the timing, scope and magnitude
production/shut-in cycles and are of the proj ect and impact on the Arun
dynamic only during a well kill or Field del i verabili ty, technical
stimulation. specialists from corporate headquarters
provided consultation and assistance
9-5/8" Retrievable Bridge Plugs wi th the entire project from the
initial design to final manufacturing
MOl requires a well to be secured and equipment delivery. Brainstorming
with two barriers below the surface, sessions wer,e initiated early in the
resulting in the development of a 9- proj ect to discuss all phases and
5/8" bridge plug. Since the concept identify critical path items.
of the "Big Bore" wells included Contingency plans were developed for
being full bore with minimal virtually every aspect to provide
restrictions, back pressure valve al ternatives when required. This
preparations and downhole nipple helped to expedite the project and
profiles were not included in the ensure that target dates were met.
well design. This resulted in the
choice of setting a bridge plug that Training
could be set on wireline and easily
retrieved with coiled tubing. Due to Anytime a ne1N concept is developed and
the mechanics of setting and implemented training becomes an
retrieval, the decision was made to extremely important factor to the
set one plug at +/- 3000' and the success of the project. This was
other plug at +/- 5500'. This would recognized early on and plans were
permi t both plugs to be set in the developed to include a three day
straight portion of the well, training session with key company, as
alleviating any problems associated well as service company personnel who
wi th setting or retrieval in highly would be involved in the proj ect. To
deviated wellbores. achieve the maximum effectiveness in
10 "Big Bore" Well Completions Paper 125384
A New Well Completion Technique for the Arun Field

the training sessions an overview of "Big Bore" program. The average test
the entire "Big Bore" well concept, results from the first five "Big Bore"
various equipment requirements, the completions were 126 MMSCFD versus an
design, testing, field running and average of 70 MMSCFD for recent 7"
handling procedures, and field safety completions. One well, C-II-21,
were discussed. tested at a rate of over 217 MMSCFD.
(Fig. 6). The higher production rates
A detailed field operations manual are attributed not only to larger
was also assembled to fully document tubing size with less friction, but
the special running and handling also longer open hole sections. "Big
requirements for each component as Bore" wells were designed with high
well as provide detail drawings for a angle, extended reach open hole
better understanding of the design sections to maximize deliverability.
and manufacture of the components.
The original estimates predicted that
On-Site Surveillance the "Big Bore" wells would produce an
average of 70 % more than a standard 7"
Since many of the well components completion. However, this prediction
were new to Arun personnel key was based on standard Arun open hole
experts in each major area of the lengths and the existing reservoir
project were brought in for on-site pressure in 1990. Figure 7 shows the
surveillance and assistance as actual composi te IPR for wells
required. The major areas being the completed with 9-5/8" tubing versus the
wellhead installation, liner hanger simulated results with 7" tubing. This
setting and cementing, isolation clearly demonstrates the substantial
packer installation, tubular running production increases these wells are
and handling, tubing make-up, and capable of.
securing the wellbore to install the
christmas tree. This proved to be We have had tremendous success with the
extremely beneficial to the success "Big Bore" completions in increasing
of drilling and completing the first well deliverability and meeting
well and provided a vehicle for production requirements. These high
further support as needed for the rate completions along with other
remaining wells. production improvement projects have
provided more than sufficient
Results deliverability to achieve our
production targets at reduced well
The first well was spud in January count and costs.
1992 and was completed and on line in
March 1992. To date six wells have There have been no mechanical failures,
been drilled and five of them have and the results have closely matched
been completed. Four wells will be predictions. This is quite an
drilled in early 1993 to complete the
Paper 125384 W.L. CANNAN, et al 11

accomplishment considering all of the 2) M.U. Alaydrus and T.P. Bordelon :


new equipment and technology "Boosting Deliverabili ty in the Giant
involved. To our knowledge, the "Big Arun Gas Field", SPE Asia Pacific
Bore" completions are the largest Conference, Perth, Western Australia,
bore, gas production wells in the 4-7 November 1991.
world [5].
3) S.A. Cassinis: Workover Review for
Excellent teamwork and cooperation Hot, High-Pressure Gas Wells", SPE
led to the successful completion of Journal of Petroleum Technology, pages
the first "Big Bore" well in the Arun 1491-1496, August 1985.
Field.
4) H. Husein and D. Steel: "High
Acknowledgments Temperature High Rate Gas Well
Completions: A Learning Experience",
The authors thank the management of Offshore South East Asia conference,
Pertamina and Mobil Oil Indonesia Singapore, February 2-5, 1988.
Inc. for the permission to publish
this paper. The work described has 5) Managemen t Summary Technical
been a true team effort between Mobil Report, Mobil Exploration and Producing
Oil Indonesia and Mobil Exploration Technical Services, Inc., "9 5/8" Arun
and Producing Technical Services, Completions: The Big Bore Project",
involving Arun engineers, geologists, October 1992.
and operations personnel, as well as
extensive support from several
Contractors and Service Companies.

The benefits gained by the teamwork


involving extensive design, testing,
quali ty control procedures, and new
technology developed and applied on
this project will be utilized for
similar proj ects of this scope and
magnitude in the future.

References

1) W.L. Cannan, A.R. Jennings, T.P.


Bordelon, and S.Sardjono: "Increasing
Arun Well Deliverability Through
Effective Acid Fracturing", SPE
International Meeting on Petroleum
Engineering, Beijing, China, 24-27
March 1992.
SPE253 84

N
o MALACCA STRAIT

42" Go\S------'~

2ff CONDENSATE---../
Iff NGL ---J

- GAS INJECllON WElLS.

o IAn &

o ICILllIE1IIIS 10

FIGURE 1 - Arun Field Location

N
o
\i~""~
"....4 .Cl":ter-\\\
~:
q

~ r-\\\
~. C\Us\.e

q
.~.~. ler-\~
~
\
C\uS


ARUN GAS RESERVOIR -:::;.----

o 1&1:1 3

o 5

FIGURE 2 - Cluster Map
SPE253 1

.0 10M WILL
11,.. 8-11! INCH. 1\8NO
- , . 1\IIINO HAHOIII, 5I.l 1-1/' 1VItlNO HAHOOl. 5I.l

ZO, 1.13 1IPf'. 20, 133 ,.,.r,


IC-II IIITT CA.O 1C-55 'UTT CASINO

:* 2000 "-ICI 2000 "-ICI


LNllH0 ~ - - -
.-I/S, US ""',
L-'O, VAW TOP 1VIINO
13-3/', 72 ""', 1V1IN0 SEAL Any,
L-IO. NEW-VAM
CA.HO

UHP,.----
CllOftO'ml
'-11/' \tAM TOP' K
10 VAM HW-IT
:t 7500 "-I<I t 7500 "-ICI

"-1<1
..lIZ
CRN HOLE
-----11 :t '110
1-1/2 ~---"'!!!!l_
CRN HOl1
~ 17110 "-ICI

t '1,000 "-III

FIGURE 3 - 7- VI Big Bore ~ompletlon

='=--------!~p
-19,"
~ j

U-L.... - 33,?

FIGURE 4 - BI; Bore X-Mal TrH Aembly


-------_---1
SPt:.25.3 ~ 4
Casing Depth, Ft-KB
0

1000 -
'...-Fracture
\ Gradient 20" CSG. at 1600' KB
2000
lD
~
,, LOT - 13.5 PPG

....I 3000
u. \
.l:
4000 "
+'
g-
Cl
5000
Weight
\,\
C 6000
.....~
>
l-
ll>

~
'!OOO

8000
\) 13-3/8" CSG. at 7282' TVD
LOT 17.5 PPG
:"
~ 9000

9-5/8" CSG. at 9553' TVD
10000

11000 I' .
I I
8.5" Hole
TO at 10,057' TVD
5.0 7.0 9.0 11.0 13.0 15.0 17.0 19.0

~
_ , FIGURE p_re_s_s_u_re_'_E_q_U_iV_'
5 - Pore Pressure _P_P_9_______________
&: Mud Weight Curves ~ I
- - - - - - - - - - - - - - - jI

2400 I
HIGH RATE TEST
I
-
c.:>
2200

-.
---
.... ,--
iii \
......
>:..
-_. I

w 2000
0::
~
Vl
w
0::
Q.
1800
17 lO P G
-...
r-.. ~
......
".
-- ...........
........
--. , r-, -
--
- f---

". "
,
0
"I(
w 1600 ..........
-
:I:
..J
..J
- "--. / -B G BPRE WEl

~ 1400 . '."~ -- r- .- -
Co'
z
~
0
..J 1200
\ .. r -7 ru alNC WE L
"" "- ~,~
I.L.
(
'-..
"-~
1000
o 20 40 60 BO 100 120 140 160 1ao 200 220
FLOW RATE (MMSCFD)

FIGURE 6 - Flow Test - 7" VB Big Bore


SPt.2 5.384

3500
<
Vi
a-
orr...
:::3
II) 7"
II)
I)
r... 3000
a-
I) IPR
(5
::L 9-5/8" TUBING
2650
E
0
+oJ
+oJ 2500
0
CD
0'1
c:
'i
0
i:L
2000
10 30 50 70 90 110 130 150
MMSCF/0

FIGURE 7 - Typical Big Bore Well Performance

DIIIWIIO MIl ClllI'U:'IlOII r COII'ilIClII ...1/1" COlIPU:1lClM VAlIIAHCI


Productiv. Area I Acres 23,240 (-I (_I J..!!..L
Maximum Gas Pay , Feet 1,050 E.UCAIl + 1C-tIIAS 'l'IlU 311 1.110 lIZ
1 IIQH 11-.0 !'I'\ on)
Average Initial Water Saturation , Percent 10.7 I'ACICP + ./Ous 13 410 477
P\.OW CCU'IJNO 14 (14)
Av.rage Poroelty Percent 16 ... + Il-I.NOIIO ..."u;s 1O (1O)
7100 n. 1:'-3/1", cso. 540 In 135
Initial Re.ervoir Prure , Psig 7,'00 (72f L-IO, IIIT'Il (721 L-IO. III:W v~)

1110 " ....1/1,l3.1f,I.-1Cl,IUlT 122 (122)


Current Re.ervoir Pr...ure Psi 3000 4100 ". 10". lJl, L-IO. VNA 415 4Ill
lIIOO " ..... /1.3.110 L-IO, v~ ,)41 ,)41

Re.er/oir Temperature Deg. F 350 ...."... CDOlllNO 10 H (II)


NO 1M 171 1,007 Itt
Re.ervolr Datum , Feet Subsea 10,050 ( ,)4 ClAVI I ( . DAVI)
US4 1.tJ4

."
OlHlJlS
CO2 Concentration 15
...TOTAL - &,000 1,100 ""t."dOO
H2 S Concentr\2tlon , PPM 50 I'UMJN[ + ACCIEDllMS 1.000 1,000

)~TAI. 1,000 7,500 1,100

TABLE 1 - Basic Reservoir Data-Arun Field TABLE 2 - 7" vs Big Bore Tubing Completion
Cost Comparison

Вам также может понравиться