Project Name : Al-Shuoruk

Report Date : 11-Apr-17 ISSUE REGISTER


Location
Date of Closure

Building
Villa no.
ID Category Scope Description Priority Date Raised Status

Block

Floor
Area
Recent Visit Date

Waste Regular collection of littered materials (On


1 Overall N/A N/A N/A N/A N/A High 23/02/2017 3/4/2017 Closed 3/4/2017
Management going)
Waste
2 Overall N/A N/A N/A N/A N/A Muddy/Silty roads High 23/02/2017 11/4/2017 Open
Management
Waste External- 95/ Stockpiled waste materials adjacent from
3 N/A
96
N/A N/A N/A Medium 15/02/2017 19/3/2017 Closed 19/3/2017
Management villas Block 95 and 96
Waste External- Stockpiled waste materials and waste build-up
4 N/A N/A N/A N/A N/A High 15/02/2017 11/4/2017 Open
Management villas (see attached drawing)
Cracks on pavement due to settlement (portions
5 Quality Infrastructure N/A N/A N/A N/A N/A High 15/02/2017 3/4/2017 Closed 3/4/2017
of pavement must be repaired) - out of scope
Civil Roads are constructed at wrong slopes, and
6 Quality N/A N/A N/A N/A N/A High 23/02/2017 3/4/2017 Closed 3/4/2017
Works without drainage system - out of scope
7 Quality Structural N/A 72 N/A N/A N/A Poor workmanship (idle-suspended works) Medium 15/02/2017 11/4/2017 Open
8 Quality Blockworks N/A 72 N/A N/A N/A Poor workmanship (idle-suspended works) Medium 15/02/2017 11/4/2017 Open
External- Poor quality curbstone (Damaged and size
9 Quality N/A N/A N/A N/A N/A High 9/3/2017 3/4/2017 Closed 3/4/2017
Villas variation)
10 Quality Arch./Civil N/A 74 N/A N/A N/A Crack in boundary walls Medium 15/02/2017 11/4/2017 Open
Poor Method of Storage and handling of
11 Quality Overall N/A N/A N/A N/A N/A High 11/4/2017 11/4/2017 New
Client Supplied Materials (CSM)
None wearing of Personal Protective
12 Health & Safety Overall N/A N/A N/A N/A N/A Medium 15/02/2017 11/4/2017 Open
Equipments (PPE) - Contractor
13 Others Electrical N/A N/A N/A N/A N/A Relocation of electrical post High 23/02/2017 28/3/2017 Closed 28/3/2017
Record No. Issued By: Noted By:

007 Nasser Alabdalkarim


Head of Quality Control
Distribution : QC Department Const'n/Conslt Contractor

* NOTE ALARGAN PROJECTS - QSD-2017-F-001---


Date Format: Day/Month/Year