Вы находитесь на странице: 1из 8

Our energy working for you.

TM

Power topic #GLPT-6174-EN | Technical information from Cummins Power Generation

Random Access vs Dead Bus


Paralleling
White Paper
By Rich Scroggins, Technical Advisor Sales Application Engineer

The overwhelming majority of Random Access


paralleled generator sets in operation Paralleling
today use a paralleling method known
In a random access paralleling system all
as Random Access Paralleling to generator sets receive a start command at
synchronize and connect generator the same time and independently build up
their voltage and speed to rated values at
sets to a paralleling bus. An alternate
which point they are ready to close to the
paralleling method known as dead paralleling bus. The generator sets will not be
bus or dead field paralleling is being in sync with each other so the generator set
controls must have some kind of arbitration
promoted by some generator set
scheme which allows only one generator
and control manufacturers as having set to close to the dead bus. When one
some performance advantages with generator set wins the arbitration it sends a
signal to the other generator sets preventing
respect to random access paralleling,
them from closing their breakers and then
specifically speed to parallel and closes its own paralleling breaker to the
the ability to energize large banks of bus. At this point the other generator sets
recognize that the bus is now live and they
transformers. In this paper we will
synchronize and close to the bus.
examine the capabilities of these two
paralleling methods. In a random access system it is not
predetermined which generator set will be
the one to close to the dead bus. It is a
robust paralleling method because if a single
generator set fails or is slow to come up to
speed the rest of the generator sets are not
affected. There is no single point of failure.
Dead Bus Paralleling AVR or excitation system. Circulating currents are
caused by generators building up internal voltage at
In a dead bus paralleling system generator sets different rates as excitation is increased. Although
start with their paralleling breakers closed to the the terminal voltages of the paralleled generator sets
bus. All generator sets start with their excitation will be the same because they will be electrically
circuits disabled. This allows generator sets to be connected, the internal voltages of the generators
connected in parallel without being in sync because may be different due to different internal reactances of
no voltage is being generated. As engines reach a the generators, different exciter resistances, different
preset speed the generator set controls turn on and levels of saturation, different residual voltage levels
ramp up excitation levels. This causes the voltage on of the generators at the start of the excitation ramp,
the bus to build up and forces the generator sets to and different transient characteristics of the engine
come into sync with each other. There is a variation as it is ramping up to nominal speed. Current will
of this method known as dead field paralleling in flow from generators with higher internal voltage to
which the generator sets start with the paralleling generators with lower internal voltage resulting in
breakers open and then close them as the engine some generators being back fed which causes stress
starter disengages. Exciter paralleling, run up to the windings and excitation system.
synchronization and close before excitation are
other terms that describe this same basic paralleling In a random access paralleling system the closed
algorithm. loop load sharing algorithm will effectively eliminate
any circulating current. During the excitation ramp in
Because there is no need for arbitration or a dead bus paralleling system the voltage reference
synchronizing multiple generator sets, dead bus of the AVR is increased linearly with no feedback. The
paralleling can bring a paralleling bus to rated control is not correcting for any of these differences so
speed and voltage quickly. This, however, is a less there could be substantial current circulating between
robust method of paralleling as each generator the generator sets.
set represents a single point of failure. A control
or excitation system fault on any generator set
compromises the entire system.
Speed of Paralleling
Most control systems that use dead bus or dead field The sequence of operations in a random access
paralleling employ a timer based system for removing paralleling system consists of three main steps:
generator sets that fail to start. If the engine has failed
1. Generator sets start and ramp up to rated speed
to reach a predetermined speed before the delay
and voltage.
expires the control opens the breaker disconnecting
the failed generator set from the paralleling bus, 2. As generators reach rated speed and voltage they
allowing the rest of the generator sets to energize arbitrate with each other so that only one generator
the bus. If the breaker fails to open however, the set is allowed to close to the dead bus.
unpowered alternator will be connected directly to the 3. The remaining generator sets synchronize and
bus effectively putting a low impedance three phase close to the energized paralleling bus.
fault on to the system as the bus backfeeds the
alternator. Similarly a failure of the excitation system Cummins diesel generator sets are designed to meet
that prevents the alternator from building up voltage NFPA 110 (Standard for Emergency and Standby
will have the same effect. Power Systems) requirements that life safety loads
are restored within 10 seconds of a power outage.
With this type of system the control, excitation system The time it takes to ramp up speed and voltage will
and paralleling circuit breaker for each generator typically range from 6 to 9 seconds depending on
set all represent single points of failure for the entire generator set size and model. This is the longest
system. This is in contrast to a random access segment of the total time to parallel and dead bus
system where the generator sets are not connected paralleling does not result in faster ramping to rated
to the bus until they are ready to load so any failed speed and voltage.
02 Power Topic #GLPT-6174-EN

generator set will have no effect on any working


generator set. The first start arbitration time depends somewhat on
how many generators will parallel in the system. With
The other risk associated with dead bus paralleling four generators using the Cummins PowerCommand
is the potential for circulating currents between 3.3 controller, we see an average time of 1.1 seconds
generator sets causing diode or MOV failures, between the first generator being ready to load
nuisance tripping of breakers or other failures of the and the first generator closing its breaker to a dead
paralleling bus.

power.cummins.com

2016 Cummins Power Generation


The time it takes to synchronize the remaining Figure 1 shows a transformer equivalent circuit.
generators to the paralleling bus depends in part As voltage is applied to the primary terminals of
on how much their phase angles differ from the the transformer the level of inrush current that the
phase angle of the connected generator. This phase transformer will draw is a function of the magnetizing
angle difference is an uncontrolled variable and impedance of the transformer (Xm). The magnetizing
therefore the total paralleling time will have some impedance is non-linear. It varies due to saturation
variation. Cummins experience has shown that this effects. As the flux in the transformer core is driven
synchronizing time ranges from less than 1 second to saturation levels the impedance becomes very low
up to 6 seconds. Because each generator set resulting in the high level of inrush current.
synchronizes to the bus independently the number
of generator sets in the system does not impact the The initial phase angle of the voltage waveform and
synchronizing time. the residual flux in the transformer core at the instant
that voltage is applied to the transformer primary
winding also affect the level of inrush current. Initial
phase angle and residual flux result in a dc offset of
Energizing Transformers the flux in the core of the transformer which decays
When energizing transformers the key concern is the as the transformer becomes energized. The effects
transformer inrush current. The high level of current of the initial phase angle and the residual flux may be
during magnetization can result in nuisance tripping additive or may cancel each other out. The result of
of overcurrent or undervoltage devices. The level of this is that the same transformer will draw different
inrush current is very difficult to model and predict levels of inrush current each time it is energized and
because it depends on a number of factors that are each of the three phases will draw different levels of
highly variable and not well documented. inrush current.

R1 X1

I1 I2

Magnetizing Rm Xm
Current

03 Power Topic #GLPT-6174-EN

Figure 1. Transformer equivalent circuit

power.cummins.com

2016 Cummins Power Generation


Transformer Inrush Current

3000

2000

1000
Current - Amp

-1000

-2000

-3000

-4000
0 1 2 3 4 5 6 7 8 9
15
Time - Seconds

Figure 2 Inrush Current of a 50 MVA transformer being energized by a 2.5 MW generator set.

Estimating Inrush Current


Another challenge in estimating a maximum inrush Conventional wisdom on how large of a transformer
current is that data on transformer saturation a single generator set can energize varies between 5
is generally not published so estimations and and 20 times the kVA rating of the generator set. The
assumptions must be made. As an example, SKM limiting factor typically is that the peak inrush current
system analysis software simply prompts the users will be high enough to trip a circuit breaker. Cummins
to enter a single point to represent inrush current Power Generation has modeled transformer inrush
for analyzing system protection and coordination current when energized by a generator set. Figure 2 is
schemes. In their documentation they recommend a graph developed by a model of a 2.5 MW generator
8 - 12 times transformer full load current for 0.1 set energizing a 50 MVA transformer.
seconds. This is a reasonable approximation for
transformers which are fed by a stiff source such as From the graph we see that the instantaneous
a utility substation transformer. When energizing a peak current is about 3300 amps. The alternator
transformer with a synchronous generator the inrush reactances and the magnetizing impedance of the
current will be limited by the physics of the generator. transformer limit the inrush current. The three different
Characteristics of the alternator decrement curve colors in the graph represent the three phases and
and the excitation system need to be considered in illustrate the concept of the inrush current being
estimating inrush current. different on each of the three phases as the initial
04 Power Topic #GLPT-6174-EN

phase angle at the instant of connecting the source


will be different for each of the phases.

power.cummins.com

2016 Cummins Power Generation


Genset Voltage
4200
4100

4000

3900
Voltage - Volt

3800

3700

3600

3500

3400
0 1 2 3 4 5 6 7 8 9
Time - Seconds
Genset Frequency
60.5

60
Frequency - Hz

59.5

59

58.5

58

57.5
0 1 2 3 4 5 6 7 8 9

Time - Seconds

Figure 3 Voltage and frequency recovery after a transformer inrush event.

Figure 3 displays the voltage and frequency recovery


during this inrush event. It shows that the voltage
Random Access Paralleling in
recovers to nominal in about a second and a half and Power Plant Applications
frequency recovers in about 3 seconds. The dip in the
In a random access paralleling application the first
voltage recovery corresponds to the under frequency
generator set to connect to the paralleling bus
roll off function in the voltage regulator.
is required to energize all of the transformers in
the system. The previous example consisted of a
In this model we see a voltage dip of about 20%
2.5MW (3.125 MVA) genset energizing a 50 MVA
and a frequency dip of about 2 Hz. The voltage is
transformer; a transformer roughly 16 times the size
recovered and stabilized within about 1.5 seconds.
of the generator set. The model would yield the same
The peak inrush current is about 7.6 times the
result for any combination of transformers connected
generator set full load current rating. In this application
in parallel at the terminals of the genset with a
overcurrent protective devices would need to
summed power rating of 50 MVA (such as 10 5 MVA
have their instantaneous trip settings higher than
transformers).
7.6 times the nominal current to prevent nuisance
tripping. When the generator set control has integral
overcurrent protection the instantaneous overcurrent
05 Power Topic #GLPT-6174-EN

setting of protective devices may be set to a high level


without risk of damaging the alternator windings or
properly sized cables. The Cummins PowerCommand
AmpSentry function is UL listed as an overcurrent
protective device and provides this protection.

power.cummins.com

2016 Cummins Power Generation


A more common topology in power plant applications
is one in which each generator set is connected G
0.4Kv
G
0.4Kv
G
0.4Kv
G
0.4Kv
G
0.4Kv
directly to a single transformer and the transformer 2.744MVA
8.7%
2.744MVA
8.7%
2.744MVA
8.7%
2.744MVA
8.7%
2.744MVA
8.7%

secondary windings are all connected in parallel to a


T-NEA T-NEA T-NEA T-NEA T-NEA
common bus. Figure 4 is an example of this topology. Yd5
0.4/30kV
Yd5
0.4/30kV
Yd5
0.4/30kV
Yd5
0.4/30kV
Yd5
0.4/30kV
3.15MVA 3.15MVA 3.15MVA 3.15MVA 3.15MVA

Under steady state operation each generator 6% 6% 6% 6% 6%

is providing magnetizing current for only one


transformer, however, during a black start using
random access paralleling a single generator will be
energizing all of the transformers.

On start up the generator sets go through the


arbitration process to determine which genset is the
first to close to the bus. When that first generator
closes it energizes its transformer. As voltage builds
up on the secondary side of that transformer the
other transformers become energized through their
secondary windings. Although the total number of
transformers that a single generator is energizing may Figure 4 Common power plant topology
be the same, the inrush current seen by the generator
will be significantly less in this topology because
500 kW generator set is connected to a 1500 kVA
the total current is limited by the transformer that is
step up transformer. The high voltage winding of
connected directly to the generator set.
that transformer is connected to 11 x 2700 kVA
This topology was used as a black start system for transformers. The single 500 kW generator set
a wind farm. Figure 5 is a partial one line drawing successfully energizes 31.2 MVA of transformers, or
from that application. In this application a single nearly 50 times the generator set kVA rating.

06 Power Topic #GLPT-6174-EN

Figure 5 Wind farm single line diagram

power.cummins.com

2016 Cummins Power Generation


Performance of Random Conclusions
Access Paralleling Systems Dead bus paralleling has been used in the past as
a low cost paralleling method because generators
Dead bus paralleling is often specified as a method
could be paralleled without the use of an external
for energizing large transformer banks and paralleling
synchronizer. As generator set controls evolved to
multiple generators quickly. Cummins generator sets
the point where the synchronizer function became
with Power Command controls using random access
integral to the control, the cost advantage of a dead
paralleling are able to match dead bus paralleling
bus paralleling system was negated. Recently there
performance in both of these areas.
has been increased interest in energizing large
transformer banks and bringing large systems on line
One such example consists of 14 2.5 MW generator
quickly which has made dead bus paralleling seem
sets each connected to a step up transformer
attractive, however dead bus paralleling introduces
and paralleled on the high voltage side of the
failure modes that are not present in random access
transformers. With this system 35 MW of power was
paralleling systems.
brought on line in less than 15 seconds.
Appropriate overcurrent protection settings allow
In this application the first generator set was ready to
single generator sets to energize transformers many
load in 7.5 seconds. Arbitration between generator
times their size, particularly when the generator set
sets took 1.5 seconds so the first generator set
controls have a current regulation function such as
closed its breaker to begin energizing all of the
Cummins PowerCommand AmpSentry. Systems
transformers just over 9 seconds after the system
controlled by Cummins PowerCommand controls
started. As the remaining generator sets sensed that
have consistently demonstrated the capability
voltage was available on the low voltage side of their
to parallel multiple generator sets within 10 15
connected transformer they synchronized to that
seconds, even when energizing transformers is part of
voltage and closed their breakers. All generator sets
the sequence. A well designed system using random
were on line 14.25 seconds after starting.
access paralleling offers the best combination of
system speed and reliability.

07 Power Topic #GLPT-6174-EN

power.cummins.com

2016 Cummins Power Generation


About the author
Rich Scroggins is a Technical Advisor switchgear controls and networking and remote
in the Application Engineering group at monitoring products and has developed and
Cummins Power Generation. Rich has conducted seminars and sales and service training
been with Cummins for 18 years in a variety internationally on several products. Rich received
of engineering and product management his bachelors degree in electrical engineering from
roles. Rich has led product development the University of Minnesota and an MBA from the
and application work with transfer switches, University of St. Thomas.

08 Power Topic #GLPT-6174-EN

power.cummins.com

2016 Cummins Power Generation Inc.


All rights reserved. Cummins Power Generation
and Cummins are registered trademarks of
Cummins Inc. Our energy working for you.
is a trademark of Cummins Power Generation.
GLPT-6174-EN (02/16)

Вам также может понравиться