Вы находитесь на странице: 1из 6

Procedures Used for Strengthening Pavias Cathedral, Italy

Giorgio Macchi, Prof.; Stefano Macchi, Eng.; Studio Tecnico Macchi, Milano, Italy. Contact: giorgio12011930@hotmail.it
DOI: 10.2749/101686615X14355644771171

Abstract The Intervention on the Pillars


This paper deals with the two kinds of pathologies of Pavias Cathedral discussed
and the Laboratory Model
in a previous paper, and the intervention techniques implemented for its strength- The intervention chosen for the pillars
ening. Their conception and some details of the methods are described here. For was the last of the options listed above,
the retrofitting of the pillars (first pathology), an innovative procedure was used, which involves the transfer of the load
based on the horizontal precompression of the infill and on the partial transfer from the lining to the infill.8,9
of the load from the marble lining to the infill, while for the cracked dome (sec-
ond pathology), the increase in strength was achieved by a simple application of The basic intervention is summarised
carbon-fibre strips to the main ribs. in the following steps:
Keywords: historical monuments; structural strengthening; innovations 1. Pretensioned tendons (each a 15 mm
diameter strand) were applied
around the pillar, one hoop every
Introduction (mean), while the infill was a poor con- 700 mm. This temporary safeguard
glomerate of rubble and stones bonded aimed to avoid further fractures,
The precarious situation of Pavias by a hydraulic lime mortar. Moreover, ensure the stability of the lining and
Cathedral is common in heritage build- a defective superposition of the marble increase the strength of the core
ings, which are usually heavy masonry blocks had resulted in the vertical force slightly during the work.
structures whose hazardous condition acting only on a horizontal external 2. Stainless steel bars AISI 410 of 16
is caused by their own weight and a strip of 100 mm. The already present mm diameter were applied inside
brittle compression collapse. fracturing of the marble lining of the 32 mm holes drilled across the pillar
pillars increased with the collapse of (Fig. 1). The bars were mechanically
The case was in fact similar to that of anchored in the marble blocks of the
Pavias Civic Tower13: it had also been the Civic Tower, leading to an overall
falling off of marble blocks. In 1989, the opposite linings. At one end, the bars
standing for 800 years, but after the had a special inverted cone anchor
increase in its weight in the sixteenth construction was on the verge of col-
lapse (first pathology).2,3 (Fig. 2), which worked inside the
century, it was in danger every day block and did not appear on the sur-
without showing any sign of distress, Investigations and research on the face. At the other end, the bars were
until its sudden collapse in the year intervention techniques began in 1989. tensioned by jacks and anchored
1989. No accidental force was in action For the first pathology, the interven- by a steel plate of 60 mm diameter,
at that moment. tion on the pillars was chosen from which was later hidden by a marble
In such a case, the intervention tech- among four available alternatives6: plug. The role of the bars, applied in
niques aimed at avoiding the collapse six different directions, was to create
addition of a new bearing lining;
should be quite different from those a low radial precompression of the
demolition and rebuilding of the
used against the effects of accidental core, and provide a tensile resistant
pillars;
actions, typically earthquakes, torna- connection between the opposite
dismantling and re-assemblage of
does, explosions and others, for which linings, which would be subjected
the lining after strengthening of the
the best measures are providing ductil- core;
ity or energy dissipation. partial transfer of the load from the
On the contrary, in the case of the lining to the core of the pillars, and
risk of compression collapse, the mea- strengthening without dismantling
sures are more difficult, and are usu- of the lining.
ally addressed by an increase in the
strength of the materials or a reduction The fourth alternative was chosen for
of the mass.4,5 reasons of heritage conservation,4,7 BAR
3

and implemented by means of an inno-


1

The eight main pillars of the church


R

vative technique, described here.


BA

BA

(built over a period of 150 years) were


2
BAR

The large octagonal dome made of


5

BA
very slender and weak, and were built R

with the usual technique, where the brickwork (30 m in diameter) was an BAR 4
6

marble was only a lining of 350 mm additional matter of concern because


of four large meridian cracks that
had resulted in an opening of 60 mm,
Peer-reviewed by international ex- caused by another unfortunate event:
perts and accepted for publication
by SEI Editorial Board the sudden rupture of one of the iron
chains causing the rupture of the dome,
Paper received: October 30, 2014 with a deflection of 300 mm (second
Paper accepted: June 19, 2015 pathology). Fig. 1: Stainless steel pretensioned bars

Structural Engineering International Nr. 1/2016 Scientific Paper 11


efficient cross-section obtained for
the stone lining of the pillars (Fig. 6)
was at least 2 m2, which would be able
to carry 1600 t at a mean stress of 8
N/mm2, while the remaining 600 t of
permanent load would be supported
by the remaining area (the infill) at a
mean stress of 0.9 N/mm2. The stress
ratio would correspond to the elastic
moduli ratio, and the expected results
would be as follows:
Fig. 4: Flat jack inserted with manometer Improved properties of the infill,
because of the precompression, and
5. The joint was cut again with the a better connection with the lining,
diamond-edged disk. Now the joint because of the grouting.
had a calibrated thickness of 4.5 mm Partial transfer of the load on the
between the two parallel surfaces, core, and reduction of the load on
with an adequate resistance (Fig. 5, the lining.
Fig. 2: Inverted cone anchor phase 5). Elimination of the stress concentra-
6. Flat jacks were introduced in the tion on the crust of the lining.
reconstituted joint and raised to the Widening of the resistant area
design pressure. This area was now of the lining and levelling of its
efficient enough to carry the load, compression.
and the work could proceed to the The application of flat jacks was
following steps with new cuts (Fig. 5, needed since the simple cut of the
phase 6). joints would lead to local collapses,
7. The flat jacks were removed and and because the core did not have
the permanent fill of the joint intro- enough resistance for the total load.
duced, step by step. Three different Its deformations would not be accept-
types of filling material were tested, able in any case. The expected vertical
and the one that had a lower stiff- shortening of each joint was about 0.5
Fig. 3: Flat jack ness was applied where a higher mm. This small amount was enough
deformability was required for a for the expected partial redistribution
reduction of the bending moment. of stresses, and its effects on the entire
to outward lateral pressure by the
structure would be controlled.
infill. There was no bond between The procedure was repeated on the
the bar and the marble in order to subsequent joints from the top to The probability of earthquakes in
ensure durability and reversibility. the base of the pillars, with the work Pavia is negligible, so that the state
3. The horizontal joints of the lining being carried out on all the eight pil- of stress under permanent loads and
were cut by a diamond-edged disk lars simultaneously in order to ensure wind provides a good measure of the
to a depth of 260 mm and a thick- symmetry between them. The area of safety level.10,11
ness of 4.5 mm. The aim of the cut
was to release the existing exces-
sive compression of the crust and
to allow a small settlement of the
joint so that it would operate in such
a way that a partial transfer of the
load to the core was achieved, as
well as to allow the removal of the
weak mortar from the inner part of
the joint and its subsequent recon-
stitution. The cut was effected in
steps; during each step, the cut sec-
tion of the joint was made resistant
again by the insertion of flat jacks
(Figs. 3 and 4).
4. The existing lime mortar in the inner
part of the joint was weak and easily
removed. It was replaced by a liq-
uid cement grout, which filled the
Phase 5 Phase 6
void over the entire thickness of
the marble. After it had hardened,
it resulted like a new marble, with
Cutting Flat-jacking
a strength of 15 N/mm2 and an ade-
quate E modulus. Fig. 5: Vertical section of the lining and the flat jack work

12 Scientific Paper Structural Engineering International Nr. 1/2016


Sollecitazione
Min principal
neglected in order to get a first under-
N/(mm2)
0
standing of the static behaviour, and
0.8
1.6
2.4
the numerical analysis of the octagon
3.2
4 was performed with the finite element
4.8
5.6
6.4
code (Fig. 10). A more refined analysis
7.2
8 was required for the brickwork dome
as an isolated body. This was done by
Y improving the linear analysis with an
X evolutionary procedure that took into
account the crack formation.
Fig. 7: Upper section (Units: N/mm2)
Again, three types of elements were
Sollecitazione used: eight-node brick elements were
Min principal
N/(mm2) used for pillars, arches and loggia; shell
0
0.8 elements were used for shells and ribs;
1.6
2.4
3.2
and truss elements were also used.
4
4.8
5.6
6.4 Materials Used in the Numerical
Fig. 6 At the end, after removal of the jacks 7.2
8 Model
3.1 The following moduli of elasticity (E)
The entire procedure of the interven- were used (N/mm2):
tion was tested in 1997 at the Structural
Laboratory of the University of Pavia Material Modulus (E)
on a pillar model, which represented Ornavasso marble 70 000
in full scale a portion of the real pillar. Mortar 1200
The model had a 1.15 m 0.70 m cross- Marble linings 50 000
Z
section, and seven superimposed lay- Y Brickwork 3000
ers of the lining blocks. The defective X
Infill 3000
joints were simulated in the model, and
the infill was made using granite peb- Fig. 8: Pillar under service load vertical The results are shown in the contours,
bles and low-strength mortar. All ele- stresses (Units: N/mm2) which essentially depict the maximal
ments were tested separately in order and minimal stress.
to achieve the best simulation of the 8.3 Sollecitazione
Min principal
real situation. The work on the joints, N/(mm2)
0 Two different models were taken into
which consisted of the insertion of the 8.4 0.8
1.6
2.4 account for the isolated dome: a solid
flat jacks, the redistribution of stresses 3.2
4 dome and a dome cracked along the
and the final fill introduction, was suc- 4.8
5.6
6.4 axes of the four widest shells, where
cessfully performed under a constant 7.2
8
cracks of 60 mm cut the shells as effec-
load of 162 t, and the global vertical
tive joints.
shortening was 3 mm, as expected. The Y

time effect was rapidly extinguished: X


2.1 Results of the Analysis of the Dome
after 160 days of loading, the vertical
2
load applied to the model was raised Fig. 9: Lower section (Units: N/mm ) The results of the analysis were less
by 50%, with almost no effect. worrying in comparison with those
technique, the only intervention that
State of Stress after Intervention could ensure both the stability and Min principal
for the First Pathology (Pillars) the conservation of the construction 0
0.08
0.16
Figures 79 show the vertical stresses materials of the monument. The labo- 0.25
0.33
0.41
in the Cathedrals pillars under perma- ratory tests of the model, under load 0.5
0.58
nent loads, obtained by linear elastic for 6 years, proved that the technique 0.66
0.75
0.83
analysis. The maximum compression in was realistic and the expected results 0.91
1
the lining was reduced to 8.3 N/mm2, were attainable. The intervention on
which is an allowable stress for marble the pillars was satisfactorily completed
masonry. The compression in the infill in July 2006.
was very low (about 0.9 N/mm2), but
sufficient to contribute significantly Numerical Analysis and
to the strength of the entire structure Intervention on the Dome
because of the large area involved.
In spite of the conceptual separation
The intervention on the fractured pil-
between the two pathologies, the struc-
lars of the Pavia Cathedral was chosen
tural analysis had to take into account
from among four alternatives; after tak-
several interactions between the pil-
ing into consideration the merits and
lars and the dome.
difficulties of each of them, the par-
tial transfer of the load was deemed The deficiencies of symmetry and of Fig. 10: Stresses in the ribs before
to be, in spite of its apparently complex the joints described above were initially fracturing of the dome (Units: N/mm2)

Structural Engineering International Nr. 1/2016 Scientific Paper 13


eight main ribs (Fig. 15). The conse-
quence of this, shown in the contours,
was that the main ribs were subjected
to an upper tension (instead of the
compression shown for a dome with-
out cracks (Fig. 10). Such a longitu-
dinal tension of the external (upper)
edge was one of the causes of trans-
versal (horizontal) cracks. Such a dam-
age was also found on the ribs of the
Brunelleschi Cupola in Florence,13,14
which was subjected to a similar set of
four meridian cracks.
This result required an intervention to
strengthen the main ribs. The analysis
Max principal of the cracked dome showed that the
0.5
0.45
iron chains placed in 1895 were insuf-
0.41
0.37
ficient; therefore now, even after retro-
0.33
0.29
fitting, the dome still had four major
0.25
0.20
cracks, but the stability against the
0.16
0.12
thrust is provided by a new stainless
0.08 steel chain of 50 mm diameter applied
Fig. 11: Crack in the drum 0.04
0 at a level of 43 m. Another effect of the
Fig. 13: Principal tension in the oculus cracks is a circumferential movement
(Units: N/mm2) of the main ribs and, therefore, a rela-
tive horizontal movement of the top of
the pillars and increased stresses in the
pillars (Fig. 15). The large cracks on the
oculi of the drum (Figs. 12 and 13) are
also explained by the continuity of the
meridian cracks (Fig. 11). The analysis
also showed a vertical bending of the
thick drum (Figs. 1417).

Max principal
0.5
0.45
0.41
0.37
0.33
0.29
0.25
0.20
0.16
0.12
0.08
0.04
0

Fig. 12: Crack on the oculus Fig. 14: Principal tension in a main rib
(Units: N/mm2) Fig. 16: Damages to the drum

obtained for the pillars. They were,


however, very variable as a conse-
quence of the size of the structural ele-
ments not always being appropriate to
their role. The first expected result con-
firmed the presence of the four merid-
ian cracks12 caused by the horizontal
circumferential tension on the dome
under the excessive load (cracks of the
same shape as that appeared during Z
the collapse of 1895). The results also
show that the deformed shape caused Y X
by the four meridian cracks involved
a considerable deflection (about 300
mm) of the crown and, therefore, a
considerable bending (hogging) of the Fig. 15: Hogging of ribs and pillar bending

14 Scientific Paper Structural Engineering International Nr. 1/2016


Sollecitazione
Min principal
N/(mm2)
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
2

Fig. 17: Vertical stresses on the corridor of


the loggia (N/mm2)
Fig. 19: Modelling of transversal crack formation on the ribs and the required
reinforcement

Z
NSC2

X Y

NP4

NP3

NSL2

Fig. 18: Outer carbon-fibre strips on main Y NSL1


ribs
Z
X NP2
NP1 NSC1
Works on the Dome
Fig. 20: Meridian carbon-fibre strips (view and plan in red)
Few works were necessary on the
dome, in spite of the fragility of the
individual elements. Together with sev-
eral minor works, the following were Conclusions Finally, the difficult requirement of
considered essential: reversibility, or at least replace-
The structural interventions on Pavias ability, was satisfied during the inter-
A stabilization of the thinnest brick- Cathedral may be appreciated from vention on the pillars, so that the same
work shells (only 120 mm thick), the point of view of heritage conserva- repair could be repeated in the future.
with a carbon-fibre net (blue lines in tion, because all the original materials
Fig. 20). were left in their original position, and The works described above adhered
A longitudinal strengthening of the only a few reinforcements were added strictly to the UNESCO criteria7, and
eight ribs by the application of lon- in the most critical locations. The several expert restorers were involved
gitudinal (outer) 100 1 mm strips strengthening was inspired and guided for years using their traditional exper-
of carbon fibre (Figs. 1820). by recent criteria governing the con- tise to conceptualise innovations for
A stainless steel circumferential ring servation of precious monuments. respecting the precious association
at the lantern. between marble and brickwork in the
The hydraulic lime grouting at defi- The first concept deals with the con- huge monument.
cient points of the drum. servation itself, and states that the
monument should be preserved for The pressure in the 284 flat jacks was
The reopening of the windows of checked to ensure that the design
the loggia to increase the internal future generations and any alteration
to its symbolic value, its historic value, compression of 8 N/mm2 under per-
luminosity. manent loading was not exceeded on
and its appearance and aesthetic value
The interventions left all the origi- should be avoided. the marble of the pillars, so that no fur-
nal materials in the original position, ther spalling of the marble lining was
This goal was reached, in our case, noticed for the following ten years.
and only a few reinforcements were
thanks to the innovative intervention The tension in the stainless steel bars
added in the most critical locations.
on the pillars and that on the dome. was also found stable for ten years.
The cracks were left visible in order
The second one is a materialistic The essential contribution of the infill,
to maintain the memory of the histori-
criterion, according to which the origi- after its precompression and reloading,
cal events (Fig. 16). The risky open-
nal materials themselves had to be is ensured by the absence of creep.
ing on the corridor in the wall of the
drum (Fig. 17) did not require any preserved; in the Pavia restoration, The static condition of the brickwork
strengthening. the original materials were preserved. dome was also satisfactory, after the

Structural Engineering International Nr. 1/2016 Scientific Paper 15


minimalist intervention described Structural Analysis of Historical Constructions. [9] Macchi G. Consolidamento del Duomo di
above. No increase of the crack thick- CIMNE: Barcelona, 1998; p39, Colloqui. Pavia. Ruolo dellinnovazione nella diagnosi e
nellintervento (ARCO Ferrara 2007).
ness was recorded during an online [3] Macchi G. Pavia Cathedral Problems,
precision monitoring, by which the Diagnosis, Choice of intervention on pillars. [10] Macchi G. Seismic risk and dynamic identi-
verticality of the dome was also con- Erhalten Historisch Bedeutsamer Bauwerke fication in towers. Keynote lecture, Proceedings
trolled and found constant within a (16/1999). Universitat Karlsruhe, 1999, 315. of MONUMENT 98. Workshop on Seismic
few millimetres. [4] Macchi G. Ars sine scientia nihil est. Ruolo Performance of Monuments, Lisbon, Portugal,
della scienza nella conservazione strutturale 1998, K7K17.
dei monumenti. In Casabella 636 luglio-agosto. [11] Menon A., Lai CG, Macchi G. Seismic
CASABELLA, Milano. 1996.
Acknowledgements hazard assessment of the historical site of Jam
[5] Macchi G., Ghelfi S. La Torre restituita. in Afghanistan and stability analysis of the
The authors are grateful to Lucia Gremmo, Indagini strutturali. Bollettino dArte. Vol. III, Minaret. J. Earthquake Eng. 2004; 8; 251294.
Superintendent of the Architectural Heritage Parte 1. Libreria dello Stato, Roma, 2005, 37254. [12] Macchi S. Structural identification of Pavia
in Milan and Giuseppina Vago, as well as to
[6] Macchi G, Macchi S. Retrofitting alterna- Cathedral by monitoring of the seasonal move-
Fritz Wenzel and Jean Louis Taupin for their
tives of Pavias Cathedral. Struct. Eng. Int. 2015; ments, IABSE Colloquium Inspection and
valuable assistance in the diagnosis and in the
4: 442449 Monitoring of the Architectural HeritageSeriate,
development of the intervention, which has
Italy, 1997.
now been implemented. [7] Lemaire R. Lingnieur et la sauvegarde du
patrimoine monumental. Structural Preservation [13] Benvenuto E. An Introduction to the History
of the Architectural Heritage. IABSE Symposium, of Structural Mechanics: Part II. Springer-Verlag:
References Rome, 1993. New York, 1990; 11.411.5.

[8] Macchi G., Macchi S. Un metodo innovativo [14] Chiarugi A., Fanelli M, Giuseppetti G.
[1] Macchi G. Monitoring medieval structures in
per il consolidamento dei pilastri del Duomo di Diagnosis and strengthening of the Brunelleschi
Pavia. Struct. Eng. Int. 1993; 3(1):69.
Pavia. ConvegnoRestauro e consolidamento dei Dome, IABSE Symposium Structural
[2] Macchi G. Problems related to the original beni architettonici e ambientali, Universit di Preservation of the Architectural Heritage,
conceptionThe case of Pavia Cathedral. In Napoli, 2003. Rome, 1993.

The Story of the Koror Bridge:


A Brief History
The Original Design
Construction
Bridge Performance
The Repair
The Collapse
What Would Have Happened If No Repairs To
the Bridge Had Been Made?
Why Was The De ection of the Bridge o Much
Larger Than Anticipated?
Initiation of the Collapse
Other Failures Hypotheses
Discussions

Members: Download the electronic copy free in the Members Area


of www.iabse.org, buy hardcover copy in the onlineshop.

www.iabse.org/onlineshop
Hardcover ePDF
Members: CHF 50 free
Non-Members: CHF 70 CHF 20

16 Scientific Paper Structural Engineering International Nr. 1/2016

Вам также может понравиться