The conversation was needed to bring a close understanding and more work order for
the following points:
1) Parameter psAssReSendMax relevant.
2) Baseline parameter follow up
3) U900 project trail follow up:
4) CPICH power setting update:
1- parameter psAssReSendMax:
The roll out for parameter psAssReSendMax from 0 to 2, in different BSCs is giving a
good acceptable improvement on TBF drop rate.
A Mobilis/Netas presentation is composed (not totally completed) for your kind view
and to approve for the remaining BSCs:
Meanwhile, the trail is selecting 3 non-congested sites (13107, 13731, and 13652),
and after TRXs removing, it is obvious that KPIs are affected, then tow optimization
actions are taken to compensate:
Your advice is needed in order to plan a meeting with Mr. Moured Kacet/Mr. Ali
Ramdani to clarify our interests toward the KPIs. And also to discuss point 3.
This is the last point in the meeting; the CPICH power update to 33dB was requested
by ARPT, plus the implementation is done at the beginning of February month, our
interest was: how far the operation criteria are considered? So, the bellows are
discussed:
NB: The 10% diagram consist of evaluating the number of degraded cells and to
quantify the KPI affected.