Вы находитесь на странице: 1из 14

Arab Republic of Egypt

Cabinet of Ministers
Egyptian Environmental Affairs Agency (EEAA)
Environmental Management Sector

Environmental Impact Assessment

GUIDELINES FOR MUNICIPAL


WASTE WATER TREATMENT WORKS

SEAM Project
Environmental Impact Assessment

GUIDELINES FOR MUNICIPAL


WASTE WATER TREATMENT WORKS

January 1999

Prepared by

SEAM Project
Egyptian Environmental Affairs Agency (EEAA)
Entec UK Ltd
1
Each step in the EIA process requires consultation
to ensure that all relevant views are being taken into
INTRODUCTION account throughout the EIA process. Ideally
This guideline identifies the main factors to be consultation should be maintained throughout the
considered when preparing an EIA for waste water EIA process with the developer and designer of the
treatment works projects which discharge effluent proposed scheme, so that modifications to the
to non marine water courses. The principals for design to reduce potential environmental impacts
EIAs for those works discharging to marine or may be introduced before completion of the final
estuarine areas will be the same as those discharging design. Consultation with the regulatory authorities,
to freshwaters, but likely environmental impacts, and also with the public, should be initiated at the
and consequently the baseline information required, Scoping stage of the EIA, and thereafter carried out
will differ considerably. They are, therefore, not as appropriate. The steps in the EIA process are
considered further in these guidelines. broadly as follows, and are outlined in following
sections of this guideline.
Not all matters in these guidelines will be applicable
to every proposal, and this checklist is not 2.1 Description of the project: What type of
exhaustive. The EIA must be tailored to suit the project is it
potential impacts of the specific proposal at the 2.2 Screening: is an EIA required
specific proposed location(s), and it is essential to 2.3 Scoping: What has to be covered and in
focus on relevant key issues. what detail
Use of this guideline alone will not be sufficient to 2.4 Baseline: What are the existing
prepare an EIA. Reference should be made to environmental conditions
relevant laws and other guidelines, such as Law 2.5 Prediction: What environmental effects will
4/1994 for the Environment, Law 48/1982 the development have
protecting the River Nile and its waterways from
2.6 Evaluation: How significant are the
pollution, Law 93/1962 concerning disposal of
predicted effects
wastewater to municipal sewers, relevant ministerial
decrees, EEAA Guidelines for Egyptian 2.7 Mitigation: Can significant negative effects
Environmental Impact Assessment, and other be avoided or made acceptable
guidelines. Developers should be fully aware of The developer is ultimately responsible for ensuring
their obligations under all laws and guidelines compliance with the statutory requirements for EIA
applicable to their situation. preparation. A developer may employ a firm of
The aim of Environmental Impact Assessment consultants to carry out the assessment. The
(EIA) is to enable the approving authority, the developer should verify the competence of the firm
public, local and central government and the recruited to prepare the EIA.
developer to properly consider the potential The EIA should be prepared by a team with
environmental consequences of a proposal, and to expertise appropriate to the study of the different
make recommendations to reduce the aspects of the development site. The team should
environmental consequences if necessary. It is be headed by a project manager, whose ultimate
important to provide sufficient information for the responsibility is to co-ordinate the inputs of
approving authority to make a decision on whether individual specialists and to provide an overview.
to approve a proposal and if so, under what For EIAs for waste water treatment works,
conditions. The EIA provides the basis for sound members of, or advisors to, the team should
ongoing environmental management. include, but not necessarily be limited to, the

2
following:
socio-economics specialist;
THE EIA PROCESS
health (water borne diseases) specialist;
The EIA process should proceed logically through freshwater biologist, microbiologist or
a number of steps. These steps work at two levels: biochemist;
technical work undertaken by specialist
terrestrial/avian fauna and flora specialist;
contributors to the assessment;
hydrologist/hydrogeologist;
a guiding principle for the EIA overall,
providing a structure for the EIA report and co- development planner or landscape architect;
ordinating the technical contributions; air quality (odour, dust and noise) specialist;

SEAM Project
2 EIA Guidelines for Municipal Waste Water Treatment Works

transport/roads specialist; guidelines classify projects based on Law 4 into


antiquities specialist; three groups, reflecting severity of possible
environmental impacts:
process engineer in wastewater treatment.
Some team members may fulfil several of the above White list projects: those with minor
roles if suitably qualified and experienced. environmental impact. Wastewater treatment
plant of 1000 PE (population equivalent) or less
Each member of the team, for their specialist fall within this category. The developer applies
subject(s), will follow the basic processes identified to the Competent Administrative Authority
above: scoping, consultation, baseline data before construction works are initiated, with a
collection, prediction and evaluation of impacts, letter of intent, accompanied by Environmental
and identification of mitigation measures. Screening Form
The following sections outline the basic steps in the is not required.
EIA process. Grey list projects: those which may result in
significant environmental impact. Wastewater
2.1 Outline of important characteristics treatment plant with a capacity of 1000 to 1
of the proposed project million PE fall within this category. The
Details of the proposed project will need to be developer applies to the Competent
obtained in order to assess potential impacts of the Administrative Authority before construction
scheme. The basic minimum in order to complete works are initiated, with a letter of intent,
the following parts of the EIA process will need to accompanied by Environmental Screening Form
include:
of such projects may be required at the
Proposed location of works; discretion of the EEAA.
General layout; Black list projects: those projects which require
General unit process and description complete EIA due to their potential impacts.
diagram(s); Wastewater treatment plant with a capacity of
Size in terms of population and population more than 1 million PE fall within this category.
equivalents, present and projected; The developer applies to the Competent
Number and type of connected industries; Administrative Authority before construction
works are initiated, with a letter of intent,
Anticipated influent and effluent characteristics,
accompanied by the scoped EIA. The EEAA
annual or monthly average discharge data;
Guidelines include in Annex 1 sectoral
Pre-construction, construction, operation and guidelines for establishments that need full EIA.
maintenance activities, estimated staffing, and
support facilities and services; Further details regarding the procedures to be
Required off site investments; followed can be found in the EEAA Guidelines.
Life expectancy of major components. In most cases, the Competent Administrative
Authority would be the Ministry of Housing, New
2.2 Screening Communities and Public Utilities. This, however,
This is the task of deciding whether or not an EIA may vary according to the nature of the proposed
is required for a particular project. Basic details of development.
the proposed development will be needed for the
project to be screened. For waste water treatment 2.3 Scoping
works the size of the population to be served by the Scoping, or identification of potential
works is the critical information required to environmental impacts, is an important early stage
determine whether an EIA is necessary. of the EIA process to ensure that the EIA is
Relevant legislation and guidelines (Law 4/1994 on properly carried out. For a project to be properly
the Environment, EEAA Guidelines on Egyptian scoped, a site visit and preliminary consultations
Environmental Impact Assessment) identify with relevant regulatory authorities must be
projects which must have an EIA, and those included (e.g. Ministry of Housing, New
projects where an EIA is discretionary or not Communities and Public Utilities, Governorate and
required. Reference to the Competent City/Town/Village authorities) at the scoping stage.
Administrative may be necessary where the Ideally public consultation should also be carried
requirement for an EIA is not clear. The EEAA out the scoping stage, but it may be more suitable

SEAM Project
EIA Guidelines for Municipal Waste Water Treatment Works 3

to postpone consultation with the public until more 2.4 Baseline Environmental Conditions
detailed assessment of potential impacts has been
completed. Consultations should involve exchange Collating existing data is always the first step in
of information about the characteristics of the collection of baseline information. It can then be
proposed project, and assistance to the consultant reviewed for its relevance to the proposed site, its
in identifying regional and local issues and/or currency, and used as a basis for determining what
sources of information of relevance to the EIA. survey work may be ne
From consultations and a preliminary assessment of Original site surveys are almost always bound to be
required for most categories of effect, such as air
baseline conditions the consultant must:
quality, odours and noise; socio-economic situation;
identify the characteristics of the proposed water quality and aquatic biology; terrestrial ecology;
development that are likely to give rise to landscape. Published information usually does not
impacts; exist at a suitable scale, or is not generally applicable to
identify what type of impacts may arise, and; the development in question. Original surveys should
determine which environmental resources and be conducted initially at a general level to identify
people in the vicinity of the proposed site are whether more detailed survey will be required.
likely to be particularly sensitive to the above Where baseline data is to be collected first hand,
impacts, and what categories of impacts are careful consideration must be given to the design of
likely to be a problem in this respect. the survey and sampling programme. Data
If either the project characteristics or the collection must focus on the key issues needing to
boundaries of the proposed site should change, be examined for the EIA (identified during the
then the potential impacts may also change, and the Scoping process), and should be collected at the
scope of the EIA will need to be reviewed. appropriate time(s) of year. Consideration of likely
monitoring requirements should be borne in mind
The EIA process will generally benefit from during survey planning, so that the data collected is
focusing attention on the key issues of concern. suitable for use as a baseline to monitor impacts or
Not all issues identified will have the same degree success/failure of mitigation measures in the future.
of relevance for all proposals. The need for long-term sampling should also be
The identification and prioritisation process should assessed as early as possible. This will maximise the
result in: time available for this to be carried out.
a list of all issues with a preliminary estimate of Data needs to be collected over a sufficiently wide
the relative significance of their impacts; area to make sure that any effects likely to be
identification of the key issues;
caused by the development can be assessed. The
area involved will not only vary for different
an explanation as to why other issues are not proposals, but for the same proposal, will vary for
considered to be key. each specialist type of data collected. For example,
The EIA should address the key issues as fully as effects on watercourses or waterbodies should be
practicable. However the level of analysis should assessed as far up and downstream as necessary to
reflect the level of significance of the impacts and assess and monitor beneficial or deleterious changes
their importance for the proposal. Lesser attention in water quality or aquatic biota. The distances
should be given to those issues which have lesser involved will depend on the characteristics of any
significance. For these latter issues, there should be existing discharge, of the watercourse(s) in question,
sufficient analysis to develop a sustainable
and on the location and characteristics of other
mitigation strategy for any potential adverse
impacts. discharges affecting the watercourse(s).
The consideration of alternatives, particularly 2.5 Prediction of Impacts
alternative sites or schemes, during the scoping
stage is often a good idea, as the amount of Impact prediction must encompass both
information on alternatives is often very limited. construction and operation of the works. Impacts
The scoping exercise can report why the preferred should be quantified wherever possible, or fully
alternative was chosen on environmental grounds. described if not quantifiable. The following should
The main part of the EIA can then concentrate on be considered:
the preferred option. Alternative processes within magnitude of impact;
the scheme may be dealt with as mitigation. duration and extent;

SEAM Project
4 EIA Guidelines for Municipal Waste Water Treatment Works

whether impacts are reversible or permanent; impacts. Many mitigation measures can be
direct and indirect effects. incorporated into the early design stages of the
Beneficial as well as adverse impacts on the project by regular communication between the
following specific aspects of the physical, socio- consultant and developer/designer of the works -
cultural and biological environment must be mitigation should be an iterative process.
assessed: Reporting of mitigation should include such specific
Water quality; features which have been incorporated during the
Social, economic and cultural environment; EIA process into the planning and design of the
proposed development.
Waste management;
Air quality;
Where mitigation has not already been incorporated
into the design or siting of the proposed works
Flora and fauna; during the EIA process, or specific commitment to
Transport and access; mitigation measures from the developer has not
Hydrology and groundwater; been obtained, mitigation measures should be
included as recommendations, and should be clearly
Visual environment and landscape;
identified as such.
Risk and hazards.
Recommendations for monitoring impacts in the
Impacts of the scheme as proposed (i.e. assuming form of an environmental management plan (EMP)
no mitigation) should be clearly identified, so that if should be included. It is not expected that a
for any reason mitigation is not implemented, the detailed EMP be prepared for the EIA however an
consequences will be clearly identified in the EIA. outline of the content and structure and
Impacts of the scheme assuming recommended commitment to prepare an EMP is required.

3
should be identified separately. If mitigation has
already been incorporated into the design of the GUIDELINES FOR THE EIA
scheme by the developer during the EIA process, REPORT
then the relevant identification of impacts without
mitigation may be omitted from the EIA report. The information provided should be clear, succinct
and objective. It should include maps, drawings,
2.6 Evaluation of impacts photos, or other descriptive detail. Only data
Criteria for evaluation of impacts must be stated. relevant to the decision-making process should be
Where possible, legislative standards or included.
international standards should be followed (e.g. The following sections outline suggested chapters,
Egyptian Law 48 water quality standards for subsections and contents for EIA reports on
discharges to the River Nile and its waterways, US proposed waste water treatment schemes
EPA guidelines for sludge reuse in agriculture, etc.). discharging effluent.
If no suitable standards exist, descriptive criteria These guidelines include all the information
may be used, but must be fully explained. required for waste water collection, treatment, reuse
Evaluation of significance of impacts should take and disposal projects described in EEAA
account of the magnitude, duration and extent of Guidelines for Egyptian Environmental Impact
impact, and whether the impact is temporary or Assessment.
permanent.
Writing a good report of EIA is a difficult task - it
All predictions of impacts have an element of must be technically robust, but at the same time it
uncertainty associated with them. The consultant must be clear, intelligible and unambiguous. Those
should identify and, where possible, quantify the making a decision on the benefits and disadvantages
level of uncertainty associated with these of a proposed development will not be technically
predictions. Some indication of probability of expert in all the areas covered by the EIA report.
occurrence of impacts should also be included. The principal advice is to keep the report short, and
2.7 Mitigation avoid use of technical terms unless absolutely
necessary. Technical appendices may be included as
Mitigation strategies must be considered both in appropriate. Suggested contents list for the EIA
relation to individual impacts and collectively for all report:

SEAM Project
EIA Guidelines for Municipal Waste Water Treatment Works 5

Table of Contents etc. A list of all approvals and licences is required


under any legislation. This list should also identify
A. Non technical or executive summary the relevant authorities involved in the assessment
B. Legislative framework and regulation of the proposal.
C. Description of the proposed development
D. Potential impacts (scoping), alternatives and C. DESCRIPTION OF THE PROPOSED
consultation DEVELOPMENT
E. Description of the existing environmental This section of the report should be brief, and may
conditions within and surrounding the site refer to a feasibility study carried out by the
F. Prediction and evaluation of significant developer or their agent. Such a feasibility report
environmental impacts should be summarised within the main EIA report,
G. Mitigating measures and alternative processes and could be incorporated as a technical appendix.
The following should be covered briefly.
H. Residual impacts
I. Monitoring plan C.1 Objectives and Scope of the
J. Conclusions Proposal
K. Technical appendices (optional) There should be a clear statement of the objectives
of the proposal, including rationale and/or need for
The non technical summary should be around 4 the development.
pages, and certainly no longer than 10 pages
(excluding plans). The main text of the EIA report C.2 The Location
should be around 60-70 pages, and certainly no The following information should be provided:
longer than 100 pages. For more technically
title details and land tenure;
complex projects, technical appendices can be used
to achieve this. Any individual technical appendix land use constraints;
should be no longer than 20 pages (excluding plans, maps, plans or photographs and a site
photos, drawings). The non technical summary description, clearly identifying the location of
may be presented as a separate report. the proposed development relative to:
? waterbodies;
A. NON TECHNICAL OR EXECUTIVE ? other land and water uses;
SUMMARY
? other waste water treatment works and
The summary must be written in non-technical potable water treatment works in the vicinity;
language to facilitate understanding by all readers. It
? vegetation communities;
should be succinct and must give an overview of:
? infrastructure, roads, utilities;
What the project is;
compatibility of the proposal with:
What the significant environmental impacts will
be; ? any strategy such as local management plans;
What has been done or is recommended to ? existing land and water uses both on the site
minimise these impacts; and on adjacent land and water;
What significant residual impacts will remain ? any historical sites or environmental
after mitigation. protection areas.
The content and structure of the summary should
C.3 Description and Layout of the
broadly follow the heading structure of the EIA
report. Proposed Development and
Associated Facilities
B. LEGISLATIVE FRAMEWORK The following information should be provided:
This chapter refers to the laws and their executive maximum land and water area affected by the
regulations considered during the planning of the proposal;
project, e.g. Law 4/1994 on the environment, Law on-site plans, layout, photomontages or similar,
48/1982 as it relates to limits of certain substances and cross sections identifying the existing and
in effluent discharges to the Nile or its waterways, proposed facilities (of both the treatment works
Law 102/1983 concerning natural reserves, and and any off site associated pipework or sewage
other relevant laws, Governorate orders, guidelines, collection systems);

SEAM Project
6 EIA Guidelines for Municipal Waste Water Treatment Works

quality and quantity of existing and proposed excess material, the sources of material to be
effluent discharges; brought to site;
design/type of discharge proposed and its details of the workforce, including source,
location; expected numbers and distribution throughout
a description of the predicted inputs to and construction;
outputs from the works, e.g. population details of potential land contamination which
equivalent to be served, predicted effluent flows, may constrain work on the site or disposal of
quality and quantity of sludge and screenings excess material.
produced, method and site(s) for sludge and
screenings treatment and/or disposal, incoming/ C.5 Other Services in the Locality
outgoing material and vehicles during operation Where applicable, outline:
of the works; the capacity and type of any nearby waste water
a description of the size and type of the works treatment facility;
proposed, e.g. method and degree of both the relationship of the proposed development
to previous or existing operations;
treatment (drying, digestion etc.), number and past environmental performance of similar
dimensions of treatment vessels, storage tanks, nearby works, including impacts on the
pumps, etc.; environment and the effectiveness of any impact
types, quantities and storage arrangements for mitigation.
chemicals used in sewage treatment (e.g.
Chlorine gas); D. POTENTIAL IMPACTS (SCOPING),
power supply requirements and proposed ALTERNATIVES AND CONSULTATION
energy conservation measures; The section summarises the outcome of the process
details of access arrangements and whether of identification and prioritisation of potential
these are completely new, upgraded or already in impacts, it should include:
existence;
all issues identified;
identification of drainage lines and on site
surface water management systems; the key issues which will need a full analysis in
the EIA;
employment during operation;
the issues which will not need a full analysis in
arrangements for effluent treatment or storage
the EIA, and the reasoned assessment of why
during maintenance and/or breakdown of plant.
they do not need full analysis.
C.4 Site Preparation and Construction A summary of the general alternatives (e.g.
Methods alternative locations, alternative schemes) should be
given, with the reasons for the selection of the
Describe the works required prior to preferred option.
commencement of operations, including:
The section should include details of who has been
any additional land requirement during
consulted, and the outcome of such consultations.
construction period;
timing, staging and hours of construction work; D.1 Potential Impacts (Scoping)
proposed construction methods including Scoping of the EIA should develop from a
temporary works, the equipment to be used; preliminary investigation of baseline conditions,
methods and route of transport of the consultation with regulatory bodies, and a
equipment to the site; preliminary site visit.
pollution control systems, e.g. erosion and For waste water treatment works, the construction
sediment control systems, wastewater holding phase is likely to give rise to negative impacts
tanks, noise and dust mitigation strategies; regarding land take, noise, dust, traffic, and
import or export of material to/from the site, movement into and off the site of materials -
including method and route of transport; especially large tanks, etc.
any stabilisation structures or earthworks During operation of any waste water treatment
including dredging, reclamation, excavation or works positive impacts may occur on the quality of
landfill, quantities of material to be moved out a watercourse to which a works already discharges,
of or onto the site, the method of disposal of and on health and living standards of local

SEAM Project
EIA Guidelines for Municipal Waste Water Treatment Works 7

residents. Negative impacts on water quality of a disposal, discharge limits to fresh waters, emissions
receiving water may also occur, if it is not currently to air and application of sludge to land must be
used for effluent disposal. consulted. Other agencies or departments might
Negative impacts are likely regarding loss of useful include those responsible for historic monuments,
land to the works, odours, noise, traffic and conservation of natural resources, etc., as
landscape. appropriate. These might include, the Egyptian
Environmental Affairs Agency (EEAA),
Disposal of sewage sludge generated may be either Governorate representatives, Ministry of Housing,
a positive impact (if of suitable quality, adequately Communities and Public Utilities, Ministry of
treated and used in agriculture), or a negative Agriculture, Food Security and Land Reclamation,
impact (if of unsuitable quality for use in Ministry of Transport, Communication and
agriculture, insufficiently treated, or disposed to Shipping, Ministry of Health, NOPWASD
landfill or other waste disposal site). Other impacts, (National Organisation for Potable Water and
both positive and negative, will occur, but will Sanitary Drainage), and relevant Community
depend on the particular site, proposal and Development Associations (CDAs).
circumstances.
The procedures or methodology used to identify E. DESCRIPTION OF THE EXISTING
and prioritise issues should be outlined. This should ENVIRONMENTAL CONDITIONS WITHIN
include: AND SURROUNDING THE SITE
relevant guidelines issued by government An overview of the existing environment should be
authorities, provisions of any relevant provided in order to place the proposal in its local
environmental protection legislation, and and regional context, and to provide baseline data
relevant strategic plans or policies; which may be used for subsequent monitoring.
relevant research or reference material, effluent General information to be provided for specific
or waste water treatment studies, and relevant issues identified as potentially important in the
preliminary studies or pre-feasibility studies. assessment of impacts from waste water treatment
proposals is discussed in the following subsections,
D.2 Alternatives and includes:
The EIA should include an assessment of the E.1 Water quality and hydraulics;
environmental impacts or consequences of E.2 Socio-economic and cultural environment;
adopting alternatives, including:
E.3 Waste management;
alternative location(s);
E.4 Air quality;
alternative schemes and layouts of the
development and services (these may be further E.5 Flora and fauna;
developed under mitigation section); E.6 Transport and access;
alternative management or operational practices E.7 Hydrology and groundwater;
(these may be further developed under E.8 Visual environment and landscape;
mitigation section); E.9 Risk and hazards.

Data must be specific to the proposed site, rather


The scoping exercise can explicitly report on what than general information on a particular area, and
grounds the preferred alternative was chosen. The the EIA should only deal with issues relevant to the
main part of the EIA can then concentrate on the proposal being assessed. Each issue and the level
preferred option. of detail should match the level of importance of
the issue in decision-making. To make the EIA
D.3 Consultation
report easier to read, it may be sensible to include
The EIA report should included details of the specialist detail for each of the following
consultation undertaken as part of the EIA process. sections as a technical appendix to the report, with
Consultees should include relevant government a summary of each section in the main EIA report.
agencies, NGOs, and the public. A brief description
of the reason for and the outcome of consultation E.1 Water Quality and Hydraulics
should be included. As improvement in water quality is usually the
For waste wat driving force for provision of waste water
regulatory powers or responsibilities concerning treatment, this aspect of the environment is of
planning control (including roads and traffic), waste primary importance in the EIA. Discussion should

SEAM Project
8 EIA Guidelines for Municipal Waste Water Treatment Works

focus on those water quality characteristics that may changes could result from secondary or cumulative
alter, and on the assimilation capacity of the water effects of the development (during construction
body to which the proposed works will discharge. and/or operation). Points to consider include:
Both positive and negative changes in water quality accidental, deliberate or managed discharge or
will need to be quantified, and therefore baseline release of materials,
data will be required. The existing microbiological, individual sources of change from works
chemical, biological and hydraulic conditions in the construction (e.g. spillage of fuels, suspended
water body to which the works currently discharges, solids such as cement dust, lubricants, etc.),
and if not the same, to which it will discharge
activities that alter flow regimes, erosion and
should the development be approved, must be sedimentation patterns and water chemistry,
assessed. Baseline data collected should be
sufficient that predicted conditions should the run-off from site and road areas.
development be approved may be calculated. For large size projects or projects in ecologically
The following water quality indicators and hydraulic sensitive areas, it is highly recommended that the
evaluation of the environmental impact for larger
conditions must be assessed for both the existing
treatment works, i.e. categorised in the high end of
and proposed effluents, and for both water courses the grey list projects and all black list projects, are
to which the works will discharge, and for any water analysed on the basis of a dynamic model.
course affected by existing discharges:
The modelling activity should preferably encompass
faecal coliforms (as indicators of faecal the water quality and hydraulic conditions for the
contamination), catchment (the sanitary drainage system), the
levels of dissolved oxygen and Biochemical treatment works and the receiving body. The
Oxygen Demand, modelling activity must consider both the existing
particulate matter (increased turbidity and and planned (future) conditions. It is
reduced light penetration), recommended that the modelling of the existing
conditions are validated against field measurements.
chemical contaminants from likely industrial or
agricultural sources such as metals, biocides and E.2 Social, Economic and Cultural Issues
hydrocarbons;
Social impacts of waste water treatment schemes
aquatic biological indicators (invertebrates); are often indirect and complex to assess, and
nutrients (nitrogen and phosphorus). consequently often not adequately addressed in
EIA. Baseline data collection should cover the
water quantity (daily inflow for small treatment
following:
works, dynamic inflow conditions for black list
treatment works (see section 2.2)) existing health of the local population (in
quantitative terms where possible) which may be
Data should be obtained from sufficiently far affected by provision or change to waste water
upstream of the proposed discharge (and existing treatment or collection (e.g. local incidence of
discharge, if any) to be able to estimate background water borne diseases);
conditions for the area/length of the watercourse
affected, or likely to be affected should the project existing potable water usage of the community,
be approved. Care should be taken that no other which may be affected after provision of waste
discharges exist between the proposed discharge water collection and treatment system;
point and the point used for sampling background existing charging structure and cost of waste
conditions. Samples should be taken as far water disposal, which may be affected by
downstream to permit assessment of the distance provision of different waste water collection and
over which the discharge will be assimilated by the treatment systems;
water course, or to the next discharge downstream if impacts of existing waste water disposal
any. systems which may be affected by provision of
Scoping should identify what may be likely sources different systems;
of industrial contaminants in the catchment area, existing and projected water treatment facilities
which may then require baseline measurement or for potable supply, which may be affected by
monitoring. provision of different waste water collection and
As well as the obvious direct changes in water treatment systems;
quality due to a changed or new effluent discharge,

SEAM Project
EIA Guidelines for Municipal Waste Water Treatment Works 9

local employment conditions which may be identification of sources of existing dust


affected during construction and operation; generation which may affect the proposed site;
existing economic situation which may be identification of sources of existing noise which
affected by provision of different waste water may affect the proposed site.
treatment, especially concerning: collection of meteorological data which will
? other developments, affect distribution and severity of air quality
? land values, impacts, in particular:
? agriculture, ? strength and direction of prevailing wind
? tourist facilities; ? rainfall frequency, duration and quantity.
identification of items or sites of cultural or collection of topographical information which
historical significance likely to be affected by the will affect distribution of air quality (e.g. steep
proposal, and an assessment of their cultural slopes, presence of tall vegetation)
and/or financial importance. identification of sensitive receptors (e.g. schools
Areas or sites of particular social or cultural and hospitals which may be affected by odours,
importance or sensitivity should be plotted on maps dust and noise; important crops or natural areas
or diagrams, shown in relation to the proposed which may be affected by dust and/or noise)
development. within the area likely to be affected by improved
or deteriorating air quality.
E.3 Waste Management Consideration should be given to providing
Disposal of waste products is an important aspect modelling studies to determine the likely
of EIA for waste water treatment works, which is distribution of odours, dust and noise during
often omitted or not fully investigated. Data on operation of the works.
existing and proposed waste management systems
should include: E.5 Flora and Fauna
likely opportunities for re-use of sewage sludge Terrestrial and/or aquatic flora and fauna or their
and/or effluent (e.g. availability of agricultural habitats which are likely to be disturbed or
land, attitudes towards use of sewage sludge in obliterated during construction or operation of the
agriculture, ease of distribution of sludge to end project must be identified and their importance
users, legislative requirements for such re-use); evaluated. As a general rule, distribution data
should be presented as habitat or species location
potential sites and routes for disposal of sewage
maps, shown in relation to position of the proposed
sludge if unsuitable for re-use in agriculture, and
quality required of sludge for disposal; works. Data collection and surveys should include:
potential sites and routes for disposal of identification, description and distribution of
screenings waste; areas of terrestrial and aquatic habitats that may
be directly or indirectly affected especially those:
potential disposal sites and routes for excess
material from the site during construction. ? supporting threatened or protected species or
habitats;
E.4 Air Quality ? of commercial importance (e.g. for
Air quality is likely to be significantly affected by agriculture, aquaculture or fisheries);
any waste water treatment works proposal, both ? of nature conservation or scenic importance.
during construction and operation. Likely major assessment of the importance of the habitats or
issues include dust sources during construction, and species identified above, in terms of
odours and aerosols produced during operation of a International, National, Regional or Local
treatment works. Noise generated during importance.
construction is also likely to have a significant
impact if the proposed site is near centres of E.6 Transport and Access
population, or if construction of a waste water
Information to allow assessment of potential
collection system is included within the proposals.
transport and access impacts should include:
Assessment of baseline conditions should include:
assessing condition and size of roads on
identification of sources of existing odours at or route(s) to be used during construction and
near the proposed site; operation of the development;

SEAM Project
10 EIA Guidelines for Municipal Waste Water Treatment Works

assessing existing traffic levels on these routes, F. PREDICTION AND EVALUATION OF


at different times of year and times of day; SIGNIFICANT ENVIRONMENTAL IMPACTS
assessing suitability of access to the site for This chapter should include a discussion of impacts
vehicle sizes and types likely to be used during during both construction and operation of the
the construction and operation of the scheme; proposed scheme. Impacts of different aspects of
investigation for the presence of particularly the proposed scheme on the above sectors of the
sensitive developments on routes likely to be environment should be considered separately.
affected, e.g. schools on construction or Criteria for evaluation of the significance of impacts
operational routes. should distinguish between impacts which are:
A detailed traffic study may be required where positive and negative;
vehicle movements are likely to significantly affect
the community. reversible and irreversible;
short term and long term;
E.7 Hydrology and Groundwater direct, indirect or cumulative.
Hydrological issues to consider which may either be Criteria should be based on local legislative
affected by the development, or affect the standards wherever possible. Where these are not
development itself include: available, acceptable international standards should
existing drainage patterns, including the be used (e.g. WHO, US EPA, etc. guidelines). In all
location of wadis and identification of areas cases the choice of the appropriate standard must
prone to flash floods, the range of water be robust and defensible. If no suitable standard is
heights/depths in the area, daily flushing regime, available, then the criteria developed and used must
storm surge or flood levels; be clearly explained in the EIA.
groundwater regime and quality, e.g. depth to Use of matrices can be very helpful in co-ordinating
groundwater level, whether groundwater is used and summarising information for this section of the
for water supply and its quality, whether control EIA report.
of groundwater is already exercised in the area; For this section of the report, impacts should be
presence and importance of structures likely to considered before or without mitigation, unless
be affected by changes in groundwater levels particular mitigation is already incorporated into the
(such as buildings, bridges, flood mitigation design and development description included in the
works). earlier part of the EIA report.
For larger treatment works, it is highly recommended Examples of potentially significant impacts of waste
that the hydrology and ground water conditions are water treatment developments include (but are not
analysed on the basis of a numerical model. restricted to):
positive impacts on water quality, health of
E.8 Visual Environment and Landscape local population, aquatic flora and fauna
The nature of the existing visual environment and currently affected by untreated or inadequately
landscape should be assessed for their sensitivity to treated discharges;
impacts such as changed or obstructed views. negative impacts on flora and fauna or local
Particularly sensitive receptors likely to be affected in inhabitants by occupation of site or direct
the vicinity should be identified, such as tourist
removal of habitats of nature conservation,
establishments, prestigious developments, schools, etc. agricultural or aquacultural importance;
E.9 Risk and Hazards positive impacts by provision of sewage sludge
Existing potential hazards to identify, and if for use in agriculture, or this impact could be
possible to quantify, which may affect or be negative if the sludge is not adequately treated;
affected by the proposals, include: negative indirect effects, e.g. dust generated
during construction affecting crop growth,
storage and handling of hazardous materials;
damage to crops by spillages or leakage onto
likelihood of release of chemicals, natural adjacent land or into irrigation waters.
occurrences such as floods, storms, landslip, fire,
positive effects on local economy allowing
explosion.
rapid development, by provision of waste water
treatment. This impact could also be negative if
increased flows to the waste water treatment
works resulted in there being inadequate capacity
to treat additional waste waters generated.

SEAM Project
EIA Guidelines for Municipal Waste Water Treatment Works 11

G. MITIGATING MEASURES AND H. RESIDUAL IMPACTS


ALTERNATIVE PROCESSES This section should give a summary of those
This section considers mitigation measures and impacts which will remain assuming mitigation has
strategies to reduce negative impacts on different been implemented. It will therefore include those
sectors of the environment. Mitigation must be impacts for which there is no suitable or only low
sustainable, integrated and feasible. levels of mitigation, and positive impacts.
Some mitigation measures should be implemented Assuming all suitable mitigation has been
at a very early stage of design of the works easily, incorporated into the design, or recommended and
but are difficult or expensive to implement once will be implemented, for waste water treatment
early design has been completed. Therefore it is works these are likely to include, but not be limited
vital that any mitigation should be discussed and to:
developed in consultation with the developer and improvements to water quality of receiving
regulatory authorities throughout the EIA process. waters;
This section of the EIA report should therefore be availability of treated sewage sludge for use as
a summary of any mitigation already implemented fertiliser;
in the ongoing design of the facility, and also improvements in local health due to reductions
include any recommended mitigation strategy to be in water borne diseases;
implemented during construction and operation of
slightly increased local employment to operate
the works.
the waste water treatment works;
This section may also include any enhancement occupation of land formerly occupied by
measures for which there is a commitment from the agriculture, natural environment or
developer, which will enhance any positive impacts development;
of the development. This may include measures
such as planned public education programmes in temporary disruption during construction;
the use and operation of water collection and visual impact of waste water treatment works.
treatment systems.
Suitable mitigation for waste water treatment works I. MONITORING PLAN
will depend on the design and layout of the works, This program should be carefully designed and
as well as the local environment, and location. related to the predictions made in the EIA and the
Examples of measures to reduce negative impacts key environmental indicators. This should be
may include, but will not be restricted to: designed to demonstrate the potential ecological
relocation of a discharge to obtain greater
sustainability of the proposal. The EIA should
dilution and/or avoid particularly sensitive outline the need for, and use of any proposed
habitats; monitoring plan, its duration and reporting
procedures, define suitable criteria for monitoring,
alteration to treatment method to obtain higher and actions to be taken in the event of non-
quality of effluent; compliance with these criteria.
provision of larger areas for sludge drying beds
Parameters which may be relevant include:
to ensure adequate drying so that sludge can be
safely re-used in agriculture; performance indicators in relation to critical
paving of roads to reduce erosion by traffic;
operational issues including:
re-routing of construction traffic to avoid ? water quality,
sensitive developments such as hospitals; ? sludge and screenings (quality and quantity),
? noise and air quality,
reduce dust damage to nearby crops;
? public health indicators,
provision of by-passes or parallel treatment
systems to avoid untreated or partially treated ? flora and fauna.
effluent being discharged to watercourse during monitoring of complaints received.
maintenance or plant breakdown;
Commitment to monitoring may be demonstrated
restrictions to working hours or changes to
by production of an environmental management
methods of working to avoid dust/odour/noise plan. This is a document designed to ensure that the
nuisance to local inhabitants. commitments in the EIA, subsequent assessment

SEAM Project
12 EIA Guidelines for Municipal Waste Water Treatment Works

reports, and approval or licence conditions, are fully actions to be undertaken if the monitoring
implemented. This should demonstrate that sound indicates a non-compliance with the defined
environmental practices will be followed during the criteria or an abnormality (e.g. inform WWTW
construction and operation of the development. It site manager in writing of parameter exceeded
should cover the following: and expected action to be undertaken);
management of construction impacts, (e.g. internal reporting procedures and links to
disposal of waste material, re-vegetation management practices and action plans (e.g.
management plans); WWTW site manager to review and remedy
disinfection processes if faecal coliform levels
management of operational impacts, (e.g. are above the specified maximum);
effluent and sludge quality and quantity
reporting procedures to relevant authorities
management, plant maintenance plans,
hazardous materials and fuel management, and, if appropriate, to the consent authority or
transport management, site security plans, the community.
emergency and contingency plans);
J. CONCLUSIONS
strategies and action plans to feed information
from the monitoring program into the This should be a summary of sections F, G and H
management practices; of the report (prediction and evaluation of impacts,
mitigation and alternative processes, and residual
Public awareness and training programmes for impacts), to emphasise:
operational staff;
which impacts are likely to be significant;
indicators of compliance with licensing and
approval requirements. how significant they will be;
which parts of the environment are likely to be
The Environmental Management Plan should affected;
describe the following monitoring details:
whether mitigation is possible;
the key information that will be monitored, its the likely success of mitigation measures adopted
criteria and the reasons for monitoring (e.g. or recommended to alleviate those impacts.
limits of parameters such as BOD, faecal
coliform bacteria, suspended solids, Ammonia This information can be presented either as text, or
and nutrients to be achieved in the effluent); as summary tables, if desired.
the monitoring locations, intervals and duration
of monitoring (e.g. sample for analysis of faecal
coliforms to be taken 10m upstream of
discharge, discharge itself, and 10m downstream
of discharge, once per week);

SEAM Project

Вам также может понравиться