Академический Документы
Профессиональный Документы
Культура Документы
Abstract- The main goal of the wastewater treatment plant energy consumption point of view to reduce the annual
management consists in reducing the annual electricity costs by electricity bill, carried out in the presence of renewable
trying to supply the load demand using renewable energy
sources (such as photovoltaic panels and biogas-based energy sources (photovoltaic panels) and biogas-based
cogeneration engine). Based on real case measurements and cogeneration engine. The analysis was carried out for 4
carried on design process of the stochastic sources and seasonal characteristic days under different plant demands
cogeneration engine for covering the load demand, an and in various stochastic energy scenarios.
optimization model is implemented to minimize the annual
electricity costs. The model is tested on a characteristic day of
each year season, under various load profile and intermittent ELECTRICAL SUPPLY OF WASTEWATER TREATMENT PLANT
sources production. CONSTANTA SOUTH
The wastewater treatment is based on mechanical stage
INTRODUCTION (coarse and fine screens, grit removal and primary
sedimentation), conventional activated sludge biological stage
Urban wastewater treatment plants represent a major and treatment of sludge. The wastewater line is presented in
energy consumer of the national power system [1], with Fig. 1. The designed maximum wastewater flow rate is 3600
energy costs about 35-45% of the plant operational costs [2, l/s, equally distributed on two lines [2]. The plant is under
3]. The wastewater treatment plants energy requirements rehabilitation program in order to include advanced treatment
consist both of electrical and thermal consumptions. In a for nutrients removal, ultraviolet disinfection and new
wastewater treatment plant, the energy savings are difficult to generation capacities using renewable energy resources
be achieved as the process is ongoing. Still, investments in (biogas and solar irradiation). The plant is supplied through
new generation capacities like renewable energy sources, for two 20 kV lines, entering the plant through the transforming
reducing the annual electricity costs, can be achieved [4]. point PTA, as shown in Fig. 2. Each transformation point is
Studies for reducing energy costs have been extensively equipped with two transformers 20/0.4 kV, an exception
developed worldwide in order to identify the global being the PTA transforming point equipped with three
wastewater treatment costs and the plants carbon footprint transformers. The characteristic data of the electrical loads
[5]. The biogas resulting from wastewater treatment processes illustrated in Fig. 2 are reported in Table I.
can be used in cogeneration plants for producing
simultaneously heat and power required for the operation of
the plant [6, 7].
This paper analyzes the technical feasibility of installing
renewable energy sources (photovoltaic systems) and using
biogas-based cogeneration engines for internal electrical
energy production to reduce the annual electricity bill of this
large industrial customer. The analysis is carried on for
Constanta South wastewater treatment plant, located in the Fig. 1. Layout of wastewater treatment plant Constanta South.
southern part of the Constanta city, in the industrial area. This
20 kV
plant treats 60% of domestic and industrial wastewater
collected by combined sewer system of the Constanta city, PTA
3 transf.
the most important maritime port in Romania and the most 20/0.4 kV
PT7
PT2 PT1 PTB
important seaside touristic place. The treatment process is a 2 transf. 2 transf. 2 transf.
20/0.4 kV
2 transf.
20/0.4 kV
20/0.4 kV 20/0.4 kV
mechanical-biological one, on two lines with conventional Blowers for
1TD -coarse Secondary Mixer for sludge Maneuver room,
screen, fine settling tank, anaerobic
activated sludge process and mesophilic anaerobic digestion. aeration tanks,
screen, grit tank, pumping station
storage tank
100m3 , 300m3, treatment tank,
pumping station
grease removal for technological pumps for
Nowadays, the biogas produced in anaerobic digestion is for excess
tank, automatic water, pumping
500m3, sludge
dewatering and supernatant,
activated sludge
burnt and used for heating of the four digestors and the line 2-13TGD2
valves of primary
settling tanks,
station for excess
activated sludge
thickening plant, heating plant
pumping station
administrative building [8]. mixer for aeration
tank, sludge
line 1-13TGD1 for thickened
sludge
The present paper presents the analysis results of an pumping station
optimized wastewater treatment plant operation, from the Fig. 2. Layout of wastewater treatment plant Constanta South.
TABLE I observed, even if the energy consumptions of the plant are
CHARACTERISTIC DATA OF ELECTRICAL LOADS OF THE SLUDGE LINE
approximately constant, the specific consumptions increased
Category Characteristic data from 2008 to 2012. As shown in Fig. 3 and Fig. 4, in 2013 the
power consumption was lower as one treatment line was
- 3 pumps, 3 4.7 kW closed for rehabilitation.
Pumping station for primary
- 1 sump pump, 1 kW
sludge: Nowadays, the energy consumption of the plant is satisfied
- 1 fan, 0.37 kW
- 4 pumps for recirculated sludge, 4 58 kW using the electrical energy flowing from the upstream grid.
Pumping station for excess
- 3 pumps for excess sludge, 3 4.7 kW The power demand of the wastewater treatment plant depends
and recirculated activated
- 1 sump pump, 2.4 kW
sludge:
- 2 fans, 1.5 kW
on the volume of wastewater treated, which varies hourly,
daily, monthly, and yearly. Fig. 5 shows the typical 24 hours
Stirage tank 1000 m3: - 2 mixers, 22.5 kW
power demand of the Constanta plant, for each weather
Tank for thickened sludge
mixing 300m3
- 2 mixers, 22.5 kW season.
Tank for digested sludge 7000
- 4 mixers, 42.5 kW
Energy consumptions,
mixing 2 pieces x 500m3
- 5 pumps for mixed sludge, 47.5 kW, 6000
111 kW 5000
[MWh/year]
- 5 electric motors for centrifuges, 355 kW,
2(75+22) kW 4000
- 3 hydraulic pumps for centrifuges, 27.5
3000
Sludge thickening and kW, 115 kW
dewatering plant - 4 pumps for thickened sludge conveying, 2000
5.5 kW
- 2 spiral conveyor for dewatered sludge, 1000
25.5 kW 0
- 1 valve, 0.37 kW
- 7 fans, 2.2 kW
2008 2009 2010 2011 2012 2013
- 1 spiral conveyor for sludge thickening, Year
0.12 kW
- 1 spiral conveyor for sludge dewatering, Fig. 3. Energy consumptions of the wastewater treatment plant during
0.18 kW 2008-2013.
- 3 mixers for thickening, 30.75 kW
- 3 mixers for dewatering, 32.2 kW
Polyelectrolyte preparation
- 1 polyelectrolyte dosing pump, 0.37 kW
0.20
[kWh/m3 treated water]
Spring
1.0 Summer
ENERGY CONSUMPTION
Autumn
The main plant energy consumers are the equipments 0.8
involved in the process of wastewater treatment. The energy
consumption during the period 2008 - 2013 is illustrated in 0.6
Fig. 3. The consumption values include the energy
consumptions of equipments for wastewater treatment 0.4
processes, lightning of the plant area and power t1 t3 t5 t7 t9 t11 t13 t15 t17 t19 t21 t23
consumptions for administrative building. Fig. 4 illustrates
Time [hours]
the specific energy consumption for the period 2008 - 2013,
Fig. 5. Typical 24 hours power demand of the Constanta plant, for each
related to the volume of treated wastewater. As it can be weather season.
PROBLEM FORMULATION installed for supplying the plant during 8200 hours/year [10].
The optimization model seeks to minimize the costs of The cogeneration engine supplies 395 kWth for covering the
purchasing electrical energy along a year by using at heat demand of the treatment plant. Within the present paper,
maximum the photovoltaic system and the thermal engine fed only the electrical energy production of the engine was
with sewage gas. For the annual analysis, the simplifying considered.
assumption of considering one characteristic day from each The data of the model components are reported in Table II.
season (winter, spring, summer, and autumn) is taken [9]. TABLE II
The power consumption of the wastewater treatment plant CHARACTERISTIC DATA
is variable during each season, as shown in Fig. 5. The Component Power
Photovoltaic plant installed power 0.265 MW
production curve of the photovoltaic plant, during each
- 880 panels 300 W
season, is an input data of the optimization model. The Thermal engine 0.33 MWe/ 0.395 MWth
sewage gas for feeding the thermal engine is produced - biogas flow 142 Nm3/h
internally in the wastewater treatment plant, and the gas flow - operation time 8200 hours/year
(150 Nm3/h) is sufficient for engine supply. Purchased price of electricity 60 Euro/MW
Selling price of green electricity 70 Euro/MW
The operation costs of the photovoltaic plant and of the
thermal engine are considered to be negligible.
The electricity purchase price of the wastewater treatment
A. Objective Function from upstream grid is 60 Euro/MWh, constant all over the
The owner of the wastewater treatment plant seeks to year.
minimize the yearly energy costs expressed as: Considering the power demand illustrated in Fig. 5, four
Power exch
16 GB of RAM. The optimization model is solved 0.5
minimizing the yearly costs of the energy purchased.
The rooftop surface of the administrative buildings of the 0
wastewater treatment plant is 2300 m2. This can be used for 1 3 5 7 9 11 13 15 17 19 21 23
installing photovoltaic panels for covering a share of the -0.5
energy consumption. Considering the sizes of a 300 W PV
panel, the orientation angle and distance between the PV Time [hours]
-1
panel rows, it results a number of 880 panels.
Fig. 6. Optimization model results for 24 hours power demand during
The biogas flow rate of the plant is 150Nm3/h; thus a the winter season.
cogeneration engine Jenbacher 208 of 330 kWe can be
1.5 Load profile Winter 42168 Euro
Power engine Spring 42093 Euro
1 PV output Summer w engine 28393 Euro
Power exch
Power [MW]
REFERENCES
0 [1] D. Robescu, G.C. Lazaroiu, C. Bulac, Power quality and energy
1 3 5 7 9 11 13 15 17 19 21 23 efficiency analysis in a wastewater treatment plant, in Proc. IEEE
-0.5 2014 16th Int. Conf. on Harmonics and Quality of Power, pp. 453-457
[2] L.D. Robescu, F. Stroe, A. Presura, D.N. Robescu, Technologies for
waste water treatment, Technical Ed., Bucharest 2011, pp. 40-87
-1 [3] G.Venkatesh, Helge Bratteb, Energy consumption, costs and
Time [hours] environmental impacts for urban water cycle services: Case study of
-1.5 Oslo (Norway), Energy, vol. 36, pp. 792-800, 2011
Fig. 9. Optimization model results for 24 hours power demand during the [4] F. Hernndez-Sancho, M. Molinos-Senante, R. Sala-Garrido, Energy
summer season, without the cogeneration engine in operation. efficiency in Spanish wastewater treatment plants: A non-radial DEA
approach, Sci. Total Environ., vol. 409, pp. 2693-2699, 2011
[5] K. Mizuta and M. Shimada, Benchmarking energy consumption in
1.5 municipal wastewater treatment plants in Japan, Water Sci. Technol.,
Load profile vol. 62, pp. 22562262, 2010.
Power engine [6] A. Stillwell, D. Hoppock and M. Webber Energy Recovery from
1 PV output Wastewater Treatment Plants in the United States: A Case Study of the
Power exch Energy-Water Nexus, Sustainability, vol. 2, pp. 945-962, 2010.
Power [MW]
Fig. 10. Optimization model results for 24 hours power demand during the
autumn season.