PROJECT MANAGEMENT
Home Project M anagement Top 10 Primavera Interview questions and M odel Answers
Categories
PROJECT MANAGEMENT (HTTP://WWW.PLANNINGENGINEER.NET/CATEGORY/PROJECT-MANAGEMENT/)
Date
FEBRUARY 7, 2013
Comments
3 COMMENTS (HTTP://WWW.PLANNINGENGINEER.NET/TOP-10-PRIMAVERA-INTERVIEW-QUES TIONS -AND-MODEL-
ANS WERS /#COMMENTS )
http://www.planningengineer.net/top-10-primavera-interview-questions-and-model-answers/ 1/11
2/15/2017 Top 10 Primavera Interview questions and Model Answers | Planning Engineer Est.
(http://www.planningengineer.net/top-10-primavera-
interview-questions-and-model-answers/)
the most common Management Interview Questions for primavera interview and what is the model answer to
all of them, Best Interview Questions and Answers
Preparing for a primavera Interview is not difficult if you know what you are doing, Just read and search about
the company history and current ongoing projects and check Sample Interview Questions and Answers for your
job position. for primavera interview check out this Primavera Interview questions and Answers for your
reference.
Q1:What are the difference between free float, total float and what is different between Float and
Slack?
This is very common question in a primavera interview, Float and slack are the two different words for the same
meaning.
http://www.planningengineer.net/top-10-primavera-interview-questions-and-model-answers/ 2/11
2/15/2017 Top 10 Primavera Interview questions and Model Answers | Planning Engineer Est.
(http://www.planningengineer.net/wp-
content/uploads/2013/02/Top-10-Primavera-
Interview-questions-and-Model-Answers.gif)
Top 10 Primavera Interview questions and Model Answers
Free Float : amount of time , an activity can be delayed without delaying the successor activity
Total Float : amount of time , an activity can be delayed without delaying the project finish date.
Constrains in primavera is to fix the early or late start or finish date of an activity as per following options:
5) Start / Finish On
6) Expected Finish
http://www.planningengineer.net/top-10-primavera-interview-questions-and-model-answers/ 3/11
2/15/2017 Top 10 Primavera Interview questions and Model Answers | Planning Engineer Est.
The sequence of activities which describe the longest path from the data date to the end of the project. In a
schedule without any constraints, this will be all activities with zero total float.
(if you have constrains which force negative float, simply filtering on total float equal to or less than zero can
bring up activities which are not on the critical path)
Q4:What is WBS?
WBS means Work Breakdown Structure. it represents a hierarchical breakdown of a Project into elements and
deliverables.
The open end activity is the activity that does not have any successor. Normally open end activity is not accepted
in schedule because the total float will be calculate from the end of the project and these entire activities late
dates gather at the end of the project and can not be prepare a logical late start plan.
Q6:What is the difference between Retained Logic & Override Logic in progress update?
If a project is generally running according to plan and activities are not progressed out of sequence then there will
be virtually no difference between the two methods. BIG differences come when activities are progressed out of
sequence.
I believe in retained logic. Invariably that will produce the longest critical path but if activities have been
progressed out of sequence, there could be some resulting illogical dependencies remaining, in particular resulting
from dependencies with durations.
Progress override invariably produces a shorter critical path and again there could be some illogical lack of
dependencies resulting from activities having been progressed out of sequence.
This is one of the Hard primavera Interview Questions, try to explain without confusion.
http://www.planningengineer.net/top-10-primavera-interview-questions-and-model-answers/ 4/11
2/15/2017 Top 10 Primavera Interview questions and Model Answers | Planning Engineer Est.
Progress is measured primarily against the baseline. If the baseline has been loaded with cost and/or resources,
earned value management can be used for this purpose. If not, progress is measured as variance to baseline
dates.
Budget at Completion (BAC)
Planned Value (PV) = budget at Completion (BAC) x Planned % Complete
Earned Value (EV) = budget at Completion (BAC) x Actual% Complete
Actual Cost (AC) = No formula What youve actually spent on the project
Schedule Performance Index (SPl) =Earned Value (EV) / Planned Value (PV)
Schedule Variance (SV) =Earned Value (EV) Planned Value (PV)
Cost Performance Index (CPI) =Earned Value (EV) / Actual Cost (AC)
To Complete Performance Index (TCPI) =(Budget at Completion (BAC) Earned Value (EV) ) / (Budget at
Completion (BAC) -Actual Cost (AC) )
Cost Variance (CV) = Earned Value (EV) -Actual Cost (AC)
For more information see this article: EVM earned value management (/?p=1013)
Resource allocation is assigning resources to activities,determine the amount of labor, equipment and money
required for any activity.
Resource leveling is Resource requirements of all scheduled activities are compared to the maximum quantity
available at the time of leveling.An activity is delayed if too few resources are available at any time during the
activitys duration.The maximum quantity for a resource is determined through the Max units/time for a particular
resource in the Resources Tab.
An S-curve is a graph showing cumulative cost or value (measured in terms of money or manhours) against time.
On a typical project, these graphs follow an S shape, hence the name. Typical data to be plotted on an S-Curve
includes:
http://www.planningengineer.net/top-10-primavera-interview-questions-and-model-answers/ 5/11
2/15/2017 Top 10 Primavera Interview questions and Model Answers | Planning Engineer Est.
Q10:What are the difference between flag and milestone activity in primavera?
Mile stone & flags both are events rather then activities. Some client likes to use flags rather than mile stone due
the following differences.
Latest Courses
1- With the use of flags the logic of main event can be easily tracked as these can not be created without
predecessor as stand alone allocating the constraint.Where as mile stone can.
2- Flags can not update manually as Primavera automatically update the status where as milestone can be update
manually.
3- Flags can not be constraint only driven by predecessor where as milestone can.
Advice: at the end of your primavera interview thank the interviewer by sending him thanking interview email
following to your interview.
Hany Ismael
(Http://Www.Planningengineer.Net/Lp- Hany Ismael (Http://Www.Pla
Profile/Admin) (Http://Www.Planningengineer.Net/Lp-
Profile/Admin)
Professional Planning Engineer Advanced
(PPE) Online Workshop Claims Management, Extension Prima
of Time (EOT) and Delays
http://www.planningengineer.net/top-10-primavera-interview-questions-and-model-answers/ 6/11
2/15/2017 Top 10 Primavera Interview questions and Model Answers | Planning Engineer Est.
of Time (EOT) and Delays
Tag: Interview Answers (http://www.planningengineer.net/tag/interview-answers/), interview planning
engineer
37 (http://www.planningengineer.net/tag/interview-planning-engineer/),
0 $665.00 interview primavera
52
(http://www.planningengineer.net/tag/interview-primavera/),
68 6Interview questions $399.00
Hany Ismael MSc, PMP is a Civil Engineering post graduate from the Liverpool University, Certified
Project Management Professional PMP, involved in various multi level construction projects since 14
years, and currently working as General Manager of Planning Engineer Est. Hany believes in sharing
knowledge and he is rapid in updating himself of latest project management tools and techniques such
as Primavera and Excel.
Heads Up WHAT'S THE FIRST WORD how to create work breakdown structure
YOU SEE? WBS using standard Division of work
(http://www.planningengineer.net/heads- (http://www.planningengineer.net/how-to-
up-whats-the-first-word-you-see/) create-work-breakdown-structure-wbs-
February 7, 2013 using-standard-division-of-work/)
14 February, 2013
http://www.planningengineer.net/top-10-primavera-interview-questions-and-model-answers/ 7/11
2/15/2017 Top 10 Primavera Interview questions and Model Answers | Planning Engineer Est.
(http://www.planningengineer.net/how-to-solve-
(http://www.planningengineer.net/catch-your-future-job-construction-claims-specialist/
3 COMMENTS
http://www.planningengineer.net/top-10-primavera-interview-questions-and-model-answers/ 8/11
2/15/2017 Top 10 Primavera Interview questions and Model Answers | Planning Engineer Est.
LEAVE A REPLY
Default Comments(3)
Facebook Comments
Google+ Comments
Your email address will not be published. Required fields are marked *
Comment
http://www.planningengineer.net/top-10-primavera-interview-questions-and-model-answers/ 9/11
2/15/2017 Top 10 Primavera Interview questions and Model Answers | Planning Engineer Est.
POST COMMENT
info@planningengineer.net (mailto:info@planningengineer.net)
FOLLOW US:
COMPANY
About Us (http://www.planningengineer.net/about-us/)
Blog (http://www.planningengineer.net/blog/)
Contact (http://www.planningengineer.net/contact/)
http://www.planningengineer.net/top-10-primavera-interview-questions-and-model-answers/ 10/11
2/15/2017 Top 10 Primavera Interview questions and Model Answers | Planning Engineer Est.
Copyright 2016 planningengineer.net | All materials, unless otherwise noted, were developed originally for Planning
Engineer Website. In the event that there is still a problem or error with copyrighted material, the break of the copyright is