The precast erector should set out joint location and
spacing before panel installation. This should minimize
differential variation in panel joint width and identify problems caused when the building or adjacent materials are out of dimension or alignment. 7.2.2 Delivery sequence A delivery sequence for panels should be flexible to allow for full loads, using reasonable fill-out units when necessary; control of unit position on the trailer with proper support for safety and economy; adequate advance notice of shipment; assurance of prompt unloading; and provision for on-site storage. 7.2.2.1 When possible, panels should be unloaded in a vertical position. This is usually the situation if single-story panels are shipped on frames in a vertical or upright position. Do not remove any chains, binders, or banding until the crane is hooked onto the precast element. Tie off all other panels to the trailer before picking a panel. All chains, binders, banding, protecting packing, and bracing should be carefully removed from around the panels. Comers and panels with returns of unusual length are shipped with special bracing, which should not be removed until the precast piece has been lifted slightly from the truck before installation. If belts are used in unloading, only one panel at a time should be removed. Protective material should be used between the belts and point of contact with the panel. Gangs of precast panels should not be removed with belt lifting devices unless the panels are palletized. The exterior panel should always be unloaded first from a frame or a stack. Never slide a panel out from the middle of a stack. Maintain balance on the trailer during unloading by unloading alternate sides of the vehicle. Remaining adjacent panels on the trailer should be tied or blocked to prevent tipping. 7.2.2.2 After delivery, a panel may require rotation into a new position. For example, a tall panel delivered on its side should be rotated to a vertical position. A panel may also be delivered horizontal, lifted from the delivery vehicle, and up-righted in the air. The panel is normally rotated without being allowed to touch the ground. It may be necessary to bolt a support frame to the panel before rotating. Usually two lifting lines from the crane are used, although special rotating frames have been developed for use with one crane line. 7.2.3 Lifting devices Lifting devices should be secured to panels in accordance with the lifting device manufacturer s recommendations. Thread bolts into inserts a minimum of 2.5 bolt diameters for coil inserts and a minimum of 1.5 bolt diameters for ferrule inserts to prevent stripping of the bolt or insert threads. At least two connections should be used whenever the panel is lifted so the panel or lifting line cannot spin and unscrew, causing the lifting line to become disconnected. Use bolts of a sufficient length to provide full embedment in the lifting device. Regardless of load requirements, a 1/2 in. (13 mm) bolt should be the minimum size used for handling any precast panel. Predrilled or selfdrilled expansion bolts should not be used for handling or installation purposes. Occasionally, inserts, bolts, or other devices are provided only for the convenience of field handling. When these devices are located in finished edges or exposed surfaces, bolt and insert holes will require filling and repairing. When this is necessary, the engineer/architect should be advised so that the locations and repair procedure can be approved before panel fabrication. Repairs should be executed in accordance with Section 7.7. Always measure depth of the lifting insert and have several different length bolts available to ensure the bolt fully penetrates insert depth and not only the concrete. 7.2.3.1 One lifting device is a swiveling D-ring plate bolted to a threaded anchor. The swivel and bolt diameter should be the same size. 7.2.3.2 Coil-threaded anchors are discouraged when other anchor types can be used. Insufficient thread engagement is the most common problem with this system and it is dangerous if the bolt is not fully threaded into the anchor. When using coil-threaded anchors, the following precautions should be followed. It is imperative that thread engagement be a minimum of 2.5 times the nominal bolt diameter. Because anchors are sometimes recessed, the erector should locate the actual top of the steel anchor, as some threads may be concrete cover and not steel. When in doubt, the erector should scratch the threads with a metal object to verify anchor location. Caution should be used in tightening bolts, as they may break out the opposite face of a thin panel or may strip the insert threads. This anchor type is particularly affected by foreign materials such a sandblast grit, ice, or both, which can accumulate in the insert. Take care to remove foreign materials from inserts to ensure full thread engagement. A minimum of two coil inserts should be used to lift a unit so that the unit or lifting line cannot spin, causing the bolt to unscrew from the insert. Bolts of proper length should be used to prevent extensive shimming. Bolts that are too long may bend and fail. 7.2.3.3 The precast concrete manufacturer should be consulted regarding the design intent of all installation inserts. Connection hardware should not be used for lifting or handling, unless specifically designed and designated for this purpose on the installation drawings. Some precast members that are long, heavy, or both, may have sleeves through the member or anchors with swivel hardware for use in attaching installation hardware. There are situations that require special lifting systems. These systems should be designed by a professional engineer and tested to verify the anchor will exceed a safety factor of 4-to-1 and the hardware 5-to-1. After selecting hoisting equipment, rigging should be sized to permit the precast concrete units to be lifted and installed safely. 7.2.3.4 Wire rope slings are usually the major component of the rigging assembly. Occasionally, web belts or chain mesh belts may be required. Hooks, shackles, rolling blocks, closed links, and lifting plates can be used with the slings to complete the system. All of these items are commercially available with test data to substantiate the safe working load for the available sizes of each product. Before using any of these items in a rigging assembly, it is imperative that the user consult the manufacturer s published charts and infor- The precast erector should set out joint location and spacing before panel installation. This should minimize differential variation in panel joint width and identify problems caused when the building or adjacent materials are out of dimension or alignment. 7.2.2 Delivery sequence A delivery sequence for panels should be flexible to allow for full loads, using reasonable fill-out units when necessary; control of unit position on the trailer with proper support for safety and economy; adequate advance notice of shipment; assurance of prompt unloading; and provision for on-site storage. 7.2.2.1 When possible, panels should be unloaded in a vertical position. This is usually the situation if single-story panels are shipped on frames in a vertical or upright position. Do not remove any chains, binders, or banding until the crane is hooked onto the precast element. Tie off all other panels to the trailer before picking a panel. All chains, binders, banding, protecting packing, and bracing should be carefully removed from around the panels. Comers and panels with returns of unusual length are shipped with special bracing, which should not be removed until the precast piece has been lifted slightly from the truck before installation. If belts are used in unloading, only one panel at a time should be removed. Protective material should be used between the belts and point of contact with the panel. Gangs of precast panels should not be removed with belt lifting devices unless the panels are palletized. The exterior panel should always be unloaded first from a frame or a stack. Never slide a panel out from the middle of a stack. Maintain balance on the trailer during unloading by unloading alternate sides of the vehicle. Remaining adjacent panels on the trailer should be tied or blocked to prevent tipping. 7.2.2.2 After delivery, a panel may require rotation into a new position. For example, a tall panel delivered on its side should be rotated to a vertical position. A panel may also be delivered horizontal, lifted from the delivery vehicle, and up-righted in the air. The panel is normally rotated without being allowed to touch the ground. It may be necessary to bolt a support frame to the panel before rotating. Usually two lifting lines from the crane are used, although special rotating frames have been developed for use with one crane line. 7.2.3 Lifting devices Lifting devices should be secured to panels in accordance with the lifting device manufacturer s recommendations. Thread bolts into inserts a minimum of 2.5 bolt diameters for coil inserts and a minimum of 1.5 bolt diameters for ferrule inserts to prevent stripping of the bolt or insert threads. At least two connections should be used whenever the panel is lifted so the panel or lifting line cannot spin and unscrew, causing the lifting line to become disconnected. Use bolts of a sufficient length to provide full embedment in the lifting device. Regardless of load requirements, a 1/2 in. (13 mm) bolt should be the minimum size used for handling any precast panel. Predrilled or selfdrilled expansion bolts should not be used for handling or installation purposes. Occasionally, inserts, bolts, or other devices are provided only for the convenience of field handling. When these devices are located in finished edges or exposed surfaces, bolt and insert holes will require filling and repairing. When this is necessary, the engineer/architect should be advised so that the locations and repair procedure can be approved before panel fabrication. Repairs should be executed in accordance with Section 7.7. Always measure depth of the lifting insert and have several different length bolts available to ensure the bolt fully penetrates insert depth and not only the concrete. 7.2.3.1 One lifting device is a swiveling D-ring plate bolted to a threaded anchor. The swivel and bolt diameter should be the same size. 7.2.3.2 Coil-threaded anchors are discouraged when other anchor types can be used. Insufficient thread engagement is the most common problem with this system and it is dangerous if the bolt is not fully threaded into the anchor. When using coil-threaded anchors, the following precautions should be followed. It is imperative that thread engagement be a minimum of 2.5 times the nominal bolt diameter. Because anchors are sometimes recessed, the erector should locate the actual top of the steel anchor, as some threads may be concrete cover and not steel. When in doubt, the erector should scratch the threads with a metal object to verify anchor location. Caution should be used in tightening bolts, as they may break out the opposite face of a thin panel or may strip the insert threads. This anchor type is particularly affected by foreign materials such a sandblast grit, ice, or both, which can accumulate in the insert. Take care to remove foreign materials from inserts to ensure full thread engagement. A minimum of two coil inserts should be used to lift a unit so that the unit or lifting line cannot spin, causing the bolt to unscrew from the insert. Bolts of proper length should be used to prevent extensive shimming. Bolts that are too long may bend and fail. 7.2.3.3 The precast concrete manufacturer should be consulted regarding the design intent of all installation inserts. Connection hardware should not be used for lifting or handling, unless specifically designed and designated for this purpose on the installation drawings. Some precast members that are long, heavy, or both, may have sleeves through the member or anchors with swivel hardware for use in attaching installation hardware. There are situations that require special lifting systems. These systems should be designed by a professional engineer and tested to verify the anchor will exceed a safety factor of 4-to-1 and the hardware 5-to-1. After selecting hoisting equipment, rigging should be sized to permit the precast concrete units to be lifted and installed safely. 7.2.3.4 Wire rope slings are usually the major component of the rigging assembly. Occasionally, web belts or chain mesh belts may be required. Hooks, shackles, rolling blocks, closed links, and lifting plates can be used with the slings to complete the system. All of these items are commercially available with test data to substantiate the safe working load for the available sizes of each product. Before using any of these items in a rigging assembly, it is imperative that the user consult the manufacturer s published charts and infor- The precast erector should set out joint location and spacing before panel installation. This should minimize differential variation in panel joint width and identify problems caused when the building or adjacent materials are out of dimension or alignment. 7.2.2 Delivery sequence A delivery sequence for panels should be flexible to allow for full loads, using reasonable fill-out units when necessary; control of unit position on the trailer with proper support for safety and economy; adequate advance notice of shipment; assurance of prompt unloading; and provision for on-site storage. 7.2.2.1 When possible, panels should be unloaded in a vertical position. This is usually the situation if single-story panels are shipped on frames in a vertical or upright position. Do not remove any chains, binders, or banding until the crane is hooked onto the precast element. Tie off all other panels to the trailer before picking a panel. All chains, binders, banding, protecting packing, and bracing should be carefully removed from around the panels. Comers and panels with returns of unusual length are shipped with special bracing, which should not be removed until the precast piece has been lifted slightly from the truck before installation. If belts are used in unloading, only one panel at a time should be removed. Protective material should be used between the belts and point of contact with the panel. Gangs of precast panels should not be removed with belt lifting devices unless the panels are palletized. The exterior panel should always be unloaded first from a frame or a stack. Never slide a panel out from the middle of a stack. Maintain balance on the trailer during unloading by unloading alternate sides of the vehicle. Remaining adjacent panels on the trailer should be tied or blocked to prevent tipping. 7.2.2.2 After delivery, a panel may require rotation into a new position. For example, a tall panel delivered on its side should be rotated to a vertical position. A panel may also be delivered horizontal, lifted from the delivery vehicle, and up-righted in the air. The panel is normally rotated without being allowed to touch the ground. It may be necessary to bolt a support frame to the panel before rotating. Usually two lifting lines from the crane are used, although special rotating frames have been developed for use with one crane line. 7.2.3 Lifting devices Lifting devices should be secured to panels in accordance with the lifting device manufacturer s recommendations. Thread bolts into inserts a minimum of 2.5 bolt diameters for coil inserts and a minimum of 1.5 bolt diameters for ferrule inserts to prevent stripping of the bolt or insert threads. At least two connections should be used whenever the panel is lifted so the panel or lifting line cannot spin and unscrew, causing the lifting line to become disconnected. Use bolts of a sufficient length to provide full embedment in the lifting device. Regardless of load requirements, a 1/2 in. (13 mm) bolt should be the minimum size used for handling any precast panel. Predrilled or selfdrilled expansion bolts should not be used for handling or installation purposes. Occasionally, inserts, bolts, or other devices are provided only for the convenience of field handling. When these devices are located in finished edges or exposed surfaces, bolt and insert holes will require filling and repairing. When this is necessary, the engineer/architect should be advised so that the locations and repair procedure can be approved before panel fabrication. Repairs should be executed in accordance with Section 7.7. Always measure depth of the lifting insert and have several different length bolts available to ensure the bolt fully penetrates insert depth and not only the concrete. 7.2.3.1 One lifting device is a swiveling D-ring plate bolted to a threaded anchor. The swivel and bolt diameter should be the same size. 7.2.3.2 Coil-threaded anchors are discouraged when other anchor types can be used. Insufficient thread engagement is the most common problem with this system and it is dangerous if the bolt is not fully threaded into the anchor. When using coil-threaded anchors, the following precautions should be followed. It is imperative that thread engagement be a minimum of 2.5 times the nominal bolt diameter. Because anchors are sometimes recessed, the erector should locate the actual top of the steel anchor, as some threads may be concrete cover and not steel. When in doubt, the erector should scratch the threads with a metal object to verify anchor location. Caution should be used in tightening bolts, as they may break out the opposite face of a thin panel or may strip the insert threads. This anchor type is particularly affected by foreign materials such a sandblast grit, ice, or both, which can accumulate in the insert. Take care to remove foreign materials from inserts to ensure full thread engagement. A minimum of two coil inserts should be used to lift a unit so that the unit or lifting line cannot spin, causing the bolt to unscrew from the insert. Bolts of proper length should be used to prevent extensive shimming. Bolts that are too long may bend and fail. 7.2.3.3 The precast concrete manufacturer should be consulted regarding the design intent of all installation inserts. Connection hardware should not be used for lifting or handling, unless specifically designed and designated for this purpose on the installation drawings. Some precast members that are long, heavy, or both, may have sleeves through the member or anchors with swivel hardware for use in attaching installation hardware. There are situations that require special lifting systems. These systems should be designed by a professional engineer and tested to verify the anchor will exceed a safety factor of 4-to-1 and the hardware 5-to-1. After selecting hoisting equipment, rigging should be sized to permit the precast concrete units to be lifted and installed safely. 7.2.3.4 Wire rope slings are usually the major component of the rigging assembly. Occasionally, web belts or chain mesh belts may be required. Hooks, shackles, rolling blocks, closed links, and lifting plates can be used with the slings to complete the system. All of these items are commercially available with test data to substantiate the safe working load for the available sizes of each product. Before using any of these items in a rigging assembly, it is imperative that the user consult the manufacturer s published charts and infor- The precast erector should set out joint location and spacing before panel installation. This should minimize differential variation in panel joint width and identify problems caused when the building or adjacent materials are out of dimension or alignment. 7.2.2 Delivery sequence A delivery sequence for panels should be flexible to allow for full loads, using reasonable fill-out units when necessary; control of unit position on the trailer with proper support for safety and economy; adequate advance notice of shipment; assurance of prompt unloading; and provision for on-site storage. 7.2.2.1 When possible, panels should be unloaded in a vertical position. This is usually the situation if single-story panels are shipped on frames in a vertical or upright position. Do not remove any chains, binders, or banding until the crane is hooked onto the precast element. Tie off all other panels to the trailer before picking a panel. All chains, binders, banding, protecting packing, and bracing should be carefully removed from around the panels. Comers and panels with returns of unusual length are shipped with special bracing, which should not be removed until the precast piece has been lifted slightly from the truck before installation. If belts are used in unloading, only one panel at a time should be removed. Protective material should be used between the belts and point of contact with the panel. Gangs of precast panels should not be removed with belt lifting devices unless the panels are palletized. The exterior panel should always be unloaded first from a frame or a stack. Never slide a panel out from the middle of a stack. Maintain balance on the trailer during unloading by unloading alternate sides of the vehicle. Remaining adjacent panels on the trailer should be tied or blocked to prevent tipping. 7.2.2.2 After delivery, a panel may require rotation into a new position. For example, a tall panel delivered on its side should be rotated to a vertical position. A panel may also be delivered horizontal, lifted from the delivery vehicle, and up-righted in the air. The panel is normally rotated without being allowed to touch the ground. It may be necessary to bolt a support frame to the panel before rotating. Usually two lifting lines from the crane are used, although special rotating frames have been developed for use with one crane line. 7.2.3 Lifting devices Lifting devices should be secured to panels in accordance with the lifting device manufacturer s recommendations. Thread bolts into inserts a minimum of 2.5 bolt diameters for coil inserts and a minimum of 1.5 bolt diameters for ferrule inserts to prevent stripping of the bolt or insert threads. At least two connections should be used whenever the panel is lifted so the panel or lifting line cannot spin and unscrew, causing the lifting line to become disconnected. Use bolts of a sufficient length to provide full embedment in the lifting device. Regardless of load requirements, a 1/2 in. (13 mm) bolt should be the minimum size used for handling any precast panel. Predrilled or selfdrilled expansion bolts should not be used for handling or installation purposes. Occasionally, inserts, bolts, or other devices are provided only for the convenience of field handling. When these devices are located in finished edges or exposed surfaces, bolt and insert holes will require filling and repairing. When this is necessary, the engineer/architect should be advised so that the locations and repair procedure can be approved before panel fabrication. Repairs should be executed in accordance with Section 7.7. Always measure depth of the lifting insert and have several different length bolts available to ensure the bolt fully penetrates insert depth and not only the concrete. 7.2.3.1 One lifting device is a swiveling D-ring plate bolted to a threaded anchor. The swivel and bolt diameter should be the same size. 7.2.3.2 Coil-threaded anchors are discouraged when other anchor types can be used. Insufficient thread engagement is the most common problem with this system and it is dangerous if the bolt is not fully threaded into the anchor. When using coil-threaded anchors, the following precautions should be followed. It is imperative that thread engagement be a minimum of 2.5 times the nominal bolt diameter. Because anchors are sometimes recessed, the erector should locate the actual top of the steel anchor, as some threads may be concrete cover and not steel. When in doubt, the erector should scratch the threads with a metal object to verify anchor location. Caution should be used in tightening bolts, as they may break out the opposite face of a thin panel or may strip the insert threads. This anchor type is particularly affected by foreign materials such a sandblast grit, ice, or both, which can accumulate in the insert. Take care to remove foreign materials from inserts to ensure full thread engagement. A minimum of two coil inserts should be used to lift a unit so that the unit or lifting line cannot spin, causing the bolt to unscrew from the insert. Bolts of proper length should be used to prevent extensive shimming. Bolts that are too long may bend and fail. 7.2.3.3 The precast concrete manufacturer should be consulted regarding the design intent of all installation inserts. Connection hardware should not be used for lifting or handling, unless specifically designed and designated for this purpose on the installation drawings. Some precast members that are long, heavy, or both, may have sleeves through the member or anchors with swivel hardware for use in attaching installation hardware. There are situations that require special lifting systems. These systems should be designed by a professional engineer and tested to verify the anchor will exceed a safety factor of 4-to-1 and the hardware 5-to-1. After selecting hoisting equipment, rigging should be sized to permit the precast concrete units to be lifted and installed safely. 7.2.3.4 Wire rope slings are usually the major component of the rigging assembly. Occasionally, web belts or chain mesh belts may be required. Hooks, shackles, rolling blocks, closed links, and lifting plates can be used with the slings to complete the system. All of these items are commercially available with test data to substantiate the safe working load for the available sizes of each product. Before using any of these items in a rigging assembly, it is imperative that the user consult the manufacturer s published charts and infor- The precast erector should set out joint location and spacing before panel installation. This should minimize differential variation in panel joint width and identify problems caused when the building or adjacent materials are out of dimension or alignment. 7.2.2 Delivery sequence A delivery sequence for panels should be flexible to allow for full loads, using reasonable fill-out units when necessary; control of unit position on the trailer with proper support for safety and economy; adequate advance notice of shipment; assurance of prompt unloading; and provision for on-site storage. 7.2.2.1 When possible, panels should be unloaded in a vertical position. This is usually the situation if single-story panels are shipped on frames in a vertical or upright position. Do not remove any chains, binders, or banding until the crane is hooked onto the precast element. Tie off all other panels to the trailer before picking a panel. All chains, binders, banding, protecting packing, and bracing should be carefully removed from around the panels. Comers and panels with returns of unusual length are shipped with special bracing, which should not be removed until the precast piece has been lifted slightly from the truck before installation. If belts are used in unloading, only one panel at a time should be removed. Protective material should be used between the belts and point of contact with the panel. Gangs of precast panels should not be removed with belt lifting devices unless the panels are palletized. The exterior panel should always be unloaded first from a frame or a stack. Never slide a panel out from the middle of a stack. Maintain balance on the trailer during unloading by unloading alternate sides of the vehicle. Remaining adjacent panels on the trailer should be tied or blocked to prevent tipping. 7.2.2.2 After delivery, a panel may require rotation into a new position. For example, a tall panel delivered on its side should be rotated to a vertical position. A panel may also be delivered horizontal, lifted from the delivery vehicle, and up-righted in the air. The panel is normally rotated without being allowed to touch the ground. It may be necessary to bolt a support frame to the panel before rotating. Usually two lifting lines from the crane are used, although special rotating frames have been developed for use with one crane line. 7.2.3 Lifting devices Lifting devices should be secured to panels in accordance with the lifting device manufacturer s recommendations. Thread bolts into inserts a minimum of 2.5 bolt diameters for coil inserts and a minimum of 1.5 bolt diameters for ferrule inserts to prevent stripping of the bolt or insert threads. At least two connections should be used whenever the panel is lifted so the panel or lifting line cannot spin and unscrew, causing the lifting line to become disconnected. Use bolts of a sufficient length to provide full embedment in the lifting device. Regardless of load requirements, a 1/2 in. (13 mm) bolt should be the minimum size used for handling any precast panel. Predrilled or selfdrilled expansion bolts should not be used for handling or installation purposes. Occasionally, inserts, bolts, or other devices are provided only for the convenience of field handling. When these devices are located in finished edges or exposed surfaces, bolt and insert holes will require filling and repairing. When this is necessary, the engineer/architect should be advised so that the locations and repair procedure can be approved before panel fabrication. Repairs should be executed in accordance with Section 7.7. Always measure depth of the lifting insert and have several different length bolts available to ensure the bolt fully penetrates insert depth and not only the concrete. 7.2.3.1 One lifting device is a swiveling D-ring plate bolted to a threaded anchor. The swivel and bolt diameter should be the same size. 7.2.3.2 Coil-threaded anchors are discouraged when other anchor types can be used. Insufficient thread engagement is the most common problem with this system and it is dangerous if the bolt is not fully threaded into the anchor. When using coil-threaded anchors, the following precautions should be followed. It is imperative that thread engagement be a minimum of 2.5 times the nominal bolt diameter. Because anchors are sometimes recessed, the erector should locate the actual top of the steel anchor, as some threads may be concrete cover and not steel. When in doubt, the erector should scratch the threads with a metal object to verify anchor location. Caution should be used in tightening bolts, as they may break out the opposite face of a thin panel or may strip the insert threads. This anchor type is particularly affected by foreign materials such a sandblast grit, ice, or both, which can accumulate in the insert. Take care to remove foreign materials from inserts to ensure full thread engagement. A minimum of two coil inserts should be used to lift a unit so that the unit or lifting line cannot spin, causing the bolt to unscrew from the insert. Bolts of proper length should be used to prevent extensive shimming. Bolts that are too long may bend and fail. 7.2.3.3 The precast concrete manufacturer should be consulted regarding the design intent of all installation inserts. Connection hardware should not be used for lifting or handling, unless specifically designed and designated for this purpose on the installation drawings. Some precast members that are long, heavy, or both, may have sleeves through the member or anchors with swivel hardware for use in attaching installation hardware. There are situations that require special lifting systems. These systems should be designed by a professional engineer and tested to verify the anchor will exceed a safety factor of 4-to-1 and the hardware 5-to-1. After selecting hoisting equipment, rigging should be sized to permit the precast concrete units to be lifted and installed safely. 7.2.3.4 Wire rope slings are usually the major component of the rigging assembly. Occasionally, web belts or chain mesh belts may be required. Hooks, shackles, rolling blocks, closed links, and lifting plates can be used with the slings to complete the system. All of these items are commercially available with test data to substantiate the safe working load for the available sizes of each product. Before using any of these items in a rigging assembly, it is imperative that the user consult the manufacturer s published charts and infor- The precast erector should set out joint location and spacing before panel installation. This should minimize differential variation in panel joint width and identify problems caused when the building or adjacent materials are out of dimension or alignment. 7.2.2 Delivery sequence A delivery sequence for panels should be flexible to allow for full loads, using reasonable fill-out units when necessary; control of unit position on the trailer with proper support for safety and economy; adequate advance notice of shipment; assurance of prompt unloading; and provision for on-site storage. 7.2.2.1 When possible, panels should be unloaded in a vertical position. This is usually the situation if single-story panels are shipped on frames in a vertical or upright position. Do not remove any chains, binders, or banding until the crane is hooked onto the precast element. Tie off all other panels to the trailer before picking a panel. All chains, binders, banding, protecting packing, and bracing should be carefully removed from around the panels. Comers and panels with returns of unusual length are shipped with special bracing, which should not be removed until the precast piece has been lifted slightly from the truck before installation. If belts are used in unloading, only one panel at a time should be removed. Protective material should be used between the belts and point of contact with the panel. Gangs of precast panels should not be removed with belt lifting devices unless the panels are palletized. The exterior panel should always be unloaded first from a frame or a stack. Never slide a panel out from the middle of a stack. Maintain balance on the trailer during unloading by unloading alternate sides of the vehicle. Remaining adjacent panels on the trailer should be tied or blocked to prevent tipping. 7.2.2.2 After delivery, a panel may require rotation into a new position. For example, a tall panel delivered on its side should be rotated to a vertical position. A panel may also be delivered horizontal, lifted from the delivery vehicle, and up-righted in the air. The panel is normally rotated without being allowed to touch the ground. It may be necessary to bolt a support frame to the panel before rotating. Usually two lifting lines from the crane are used, although special rotating frames have been developed for use with one crane line. 7.2.3 Lifting devices Lifting devices should be secured to panels in accordance with the lifting device manufacturer s recommendations. Thread bolts into inserts a minimum of 2.5 bolt diameters for coil inserts and a minimum of 1.5 bolt diameters for ferrule inserts to prevent stripping of the bolt or insert threads. At least two connections should be used whenever the panel is lifted so the panel or lifting line cannot spin and unscrew, causing the lifting line to become disconnected. Use bolts of a sufficient length to provide full embedment in the lifting device. Regardless of load requirements, a 1/2 in. (13 mm) bolt should be the minimum size used for handling any precast panel. Predrilled or selfdrilled expansion bolts should not be used for handling or installation purposes. Occasionally, inserts, bolts, or other devices are provided only for the convenience of field handling. When these devices are located in finished edges or exposed surfaces, bolt and insert holes will require filling and repairing. When this is necessary, the engineer/architect should be advised so that the locations and repair procedure can be approved before panel fabrication. Repairs should be executed in accordance with Section 7.7. Always measure depth of the lifting insert and have several different length bolts available to ensure the bolt fully penetrates insert depth and not only the concrete. 7.2.3.1 One lifting device is a swiveling D-ring plate bolted to a threaded anchor. The swivel and bolt diameter should be the same size. 7.2.3.2 Coil-threaded anchors are discouraged when other anchor types can be used. Insufficient thread engagement is the most common problem with this system and it is dangerous if the bolt is not fully threaded into the anchor. When using coil-threaded anchors, the following precautions should be followed. It is imperative that thread engagement be a minimum of 2.5 times the nominal bolt diameter. Because anchors are sometimes recessed, the erector should locate the actual top of the steel anchor, as some threads may be concrete cover and not steel. When in doubt, the erector should scratch the threads with a metal object to verify anchor location. Caution should be used in tightening bolts, as they may break out the opposite face of a thin panel or may strip the insert threads. This anchor type is particularly affected by foreign materials such a sandblast grit, ice, or both, which can accumulate in the insert. Take care to remove foreign materials from inserts to ensure full thread engagement. A minimum of two coil inserts should be used to lift a unit so that the unit or lifting line cannot spin, causing the bolt to unscrew from the insert. Bolts of proper length should be used to prevent extensive shimming. Bolts that are too long may bend and fail. 7.2.3.3 The precast concrete manufacturer should be consulted regarding the design intent of all installation inserts. Connection hardware should not be used for lifting or handling, unless specifically designed and designated for this purpose on the installation drawings. Some precast members that are long, heavy, or both, may have sleeves through the member or anchors with swivel hardware for use in attaching installation hardware. There are situations that require special lifting systems. These systems should be designed by a professional engineer and tested to verify the anchor will exceed a safety factor of 4-to-1 and the hardware 5-to-1. After selecting hoisting equipment, rigging should be sized to permit the precast concrete units to be lifted and installed safely. 7.2.3.4 Wire rope slings are usually the major component of the rigging assembly. Occasionally, web belts or chain mesh belts may be required. Hooks, shackles, rolling blocks, closed links, and lifting plates can be used with the slings to complete the system. All of these items are commercially available with test data to substantiate the safe working load for the available sizes of each product. Before using any of these items in a rigging assembly, it is imperative that the user consult the manufacturer s published charts and infor- The precast erector should set out joint location and spacing before panel installation. This should minimize differential variation in panel joint width and identify problems caused when the building or adjacent materials are out of dimension or alignment. 7.2.2 Delivery sequence A delivery sequence for panels should be flexible to allow for full loads, using reasonable fill-out units when necessary; control of unit position on the trailer with proper support for safety and economy; adequate advance notice of shipment; assurance of prompt unloading; and provision for on-site storage. 7.2.2.1 When possible, panels should be unloaded in a vertical position. This is usually the situation if single-story panels are shipped on frames in a vertical or upright position. Do not remove any chains, binders, or banding until the crane is hooked onto the precast element. Tie off all other panels to the trailer before picking a panel. All chains, binders, banding, protecting packing, and bracing should be carefully removed from around the panels. Comers and panels with returns of unusual length are shipped with special bracing, which should not be removed until the precast piece has been lifted slightly from the truck before installation. If belts are used in unloading, only one panel at a time should be removed. Protective material should be used between the belts and point of contact with the panel. Gangs of precast panels should not be removed with belt lifting devices unless the panels are palletized. The exterior panel should always be unloaded first from a frame or a stack. Never slide a panel out from the middle of a stack. Maintain balance on the trailer during unloading by unloading alternate sides of the vehicle. Remaining adjacent panels on the trailer should be tied or blocked to prevent tipping. 7.2.2.2 After delivery, a panel may require rotation into a new position. For example, a tall panel delivered on its side should be rotated to a vertical position. A panel may also be delivered horizontal, lifted from the delivery vehicle, and up-righted in the air. The panel is normally rotated without being allowed to touch the ground. It may be necessary to bolt a support frame to the panel before rotating. Usually two lifting lines from the crane are used, although special rotating frames have been developed for use with one crane line. 7.2.3 Lifting devices Lifting devices should be secured to panels in accordance with the lifting device manufacturer s recommendations. Thread bolts into inserts a minimum of 2.5 bolt diameters for coil inserts and a minimum of 1.5 bolt diameters for ferrule inserts to prevent stripping of the bolt or insert threads. At least two connections should be used whenever the panel is lifted so the panel or lifting line cannot spin and unscrew, causing the lifting line to become disconnected. Use bolts of a sufficient length to provide full embedment in the lifting device. Regardless of load requirements, a 1/2 in. (13 mm) bolt should be the minimum size used for handling any precast panel. Predrilled or selfdrilled expansion bolts should not be used for handling or installation purposes. Occasionally, inserts, bolts, or other devices are provided only for the convenience of field handling. When these devices are located in finished edges or exposed surfaces, bolt and insert holes will require filling and repairing. When this is necessary, the engineer/architect should be advised so that the locations and repair procedure can be approved before panel fabrication. Repairs should be executed in accordance with Section 7.7. Always measure depth of the lifting insert and have several different length bolts available to ensure the bolt fully penetrates insert depth and not only the concrete. 7.2.3.1 One lifting device is a swiveling D-ring plate bolted to a threaded anchor. The swivel and bolt diameter should be the same size. 7.2.3.2 Coil-threaded anchors are discouraged when other anchor types can be used. Insufficient thread engagement is the most common problem with this system and it is dangerous if the bolt is not fully threaded into the anchor. When using coil-threaded anchors, the following precautions should be followed. It is imperative that thread engagement be a minimum of 2.5 times the nominal bolt diameter. Because anchors are sometimes recessed, the erector should locate the actual top of the steel anchor, as some threads may be concrete cover and not steel. When in doubt, the erector should scratch the threads with a metal object to verify anchor location. Caution should be used in tightening bolts, as they may break out the opposite face of a thin panel or may strip the insert threads. This anchor type is particularly affected by foreign materials such a sandblast grit, ice, or both, which can accumulate in the insert. Take care to remove foreign materials from inserts to ensure full thread engagement. A minimum of two coil inserts should be used to lift a unit so that the unit or lifting line cannot spin, causing the bolt to unscrew from the insert. Bolts of proper length should be used to prevent extensive shimming. Bolts that are too long may bend and fail. 7.2.3.3 The precast concrete manufacturer should be consulted regarding the design intent of all installation inserts. Connection hardware should not be used for lifting or handling, unless specifically designed and designated for this purpose on the installation drawings. Some precast members that are long, heavy, or both, may have sleeves through the member or anchors with swivel hardware for use in attaching installation hardware. There are situations that require special lifting systems. These systems should be designed by a professional engineer and tested to verify the anchor will exceed a safety factor of 4-to-1 and the hardware 5-to-1. After selecting hoisting equipment, rigging should be sized to permit the precast concrete units to be lifted and installed safely. 7.2.3.4 Wire rope slings are usually the major component of the rigging assembly. Occasionally, web belts or chain mesh belts may be required. Hooks, shackles, rolling blocks, closed links, and lifting plates can be used with the slings to complete the system. All of these items are commercially available with test data to substantiate the safe working load for the available sizes of each product. Before using any of these items in a rigging assembly, it is imperative that the user consult the manufacturer s published charts and infor- The precast erector should set out joint location and spacing before panel installation. This should minimize differential variation in panel joint width and identify problems caused when the building or adjacent materials are out of dimension or alignment. 7.2.2 Delivery sequence A delivery sequence for panels should be flexible to allow for full loads, using reasonable fill-out units when necessary; control of unit position on the trailer with proper support for safety and economy; adequate advance notice of shipment; assurance of prompt unloading; and provision for on-site storage. 7.2.2.1 When possible, panels should be unloaded in a vertical position. This is usually the situation if single-story panels are shipped on frames in a vertical or upright position. Do not remove any chains, binders, or banding until the crane is hooked onto the precast element. Tie off all other panels to the trailer before picking a panel. All chains, binders, banding, protecting packing, and bracing should be carefully removed from around the panels. Comers and panels with returns of unusual length are shipped with special bracing, which should not be removed until the precast piece has been lifted slightly from the truck before installation. If belts are used in unloading, only one panel at a time should be removed. Protective material should be used between the belts and point of contact with the panel. Gangs of precast panels should not be removed with belt lifting devices unless the panels are palletized. The exterior panel should always be unloaded first from a frame or a stack. Never slide a panel out from the middle of a stack. Maintain balance on the trailer during unloading by unloading alternate sides of the vehicle. Remaining adjacent panels on the trailer should be tied or blocked to prevent tipping. 7.2.2.2 After delivery, a panel may require rotation into a new position. For example, a tall panel delivered on its side should be rotated to a vertical position. A panel may also be delivered horizontal, lifted from the delivery vehicle, and up-righted in the air. The panel is normally rotated without being allowed to touch the ground. It may be necessary to bolt a support frame to the panel before rotating. Usually two lifting lines from the crane are used, although special rotating frames have been developed for use with one crane line. 7.2.3 Lifting devices Lifting devices should be secured to panels in accordance with the lifting device manufacturer s recommendations. Thread bolts into inserts a minimum of 2.5 bolt diameters for coil inserts and a minimum of 1.5 bolt diameters for ferrule inserts to prevent stripping of the bolt or insert threads. At least two connections should be used whenever the panel is lifted so the panel or lifting line cannot spin and unscrew, causing the lifting line to become disconnected. Use bolts of a sufficient length to provide full embedment in the lifting device. Regardless of load requirements, a 1/2 in. (13 mm) bolt should be the minimum size used for handling any precast panel. Predrilled or selfdrilled expansion bolts should not be used for handling or installation purposes. Occasionally, inserts, bolts, or other devices are provided only for the convenience of field handling. When these devices are located in finished edges or exposed surfaces, bolt and insert holes will require filling and repairing. When this is necessary, the engineer/architect should be advised so that the locations and repair procedure can be approved before panel fabrication. Repairs should be executed in accordance with Section 7.7. Always measure depth of the lifting insert and have several different length bolts available to ensure the bolt fully penetrates insert depth and not only the concrete. 7.2.3.1 One lifting device is a swiveling D-ring plate bolted to a threaded anchor. The swivel and bolt diameter should be the same size. 7.2.3.2 Coil-threaded anchors are discouraged when other anchor types can be used. Insufficient thread engagement is the most common problem with this system and it is dangerous if the bolt is not fully threaded into the anchor. When using coil-threaded anchors, the following precautions should be followed. It is imperative that thread engagement be a minimum of 2.5 times the nominal bolt diameter. Because anchors are sometimes recessed, the erector should locate the actual top of the steel anchor, as some threads may be concrete cover and not steel. When in doubt, the erector should scratch the threads with a metal object to verify anchor location. Caution should be used in tightening bolts, as they may break out the opposite face of a thin panel or may strip the insert threads. This anchor type is particularly affected by foreign materials such a sandblast grit, ice, or both, which can accumulate in the insert. Take care to remove foreign materials from inserts to ensure full thread engagement. A minimum of two coil inserts should be used to lift a unit so that the unit or lifting line cannot spin, causing the bolt to unscrew from the insert. Bolts of proper length should be used to prevent extensive shimming. Bolts that are too long may bend and fail. 7.2.3.3 The precast concrete manufacturer should be consulted regarding the design intent of all installation inserts. Connection hardware should not be used for lifting or handling, unless specifically designed and designated for this purpose on the installation drawings. Some precast members that are long, heavy, or both, may have sleeves through the member or anchors with swivel hardware for use in attaching installation hardware. There are situations that require special lifting systems. These systems should be designed by a professional engineer and tested to verify the anchor will exceed a safety factor of 4-to-1 and the hardware 5-to-1. After selecting hoisting equipment, rigging should be sized to permit the precast concrete units to be lifted and installed safely. 7.2.3.4 Wire rope slings are usually the major component of the rigging assembly. Occasionally, web belts or chain mesh belts may be required. Hooks, shackles, rolling blocks, closed links, and lifting plates can be used with the slings to complete the system. All of these items are commercially available with test data to substantiate the safe working load for the available sizes of each product. Before using any of these items in a rigging assembly, it is imperative that the user consult the manufacturer s published charts and infor- The precast erector should set out joint location and spacing before panel installation. This should minimize differential variation in panel joint width and identify problems caused when the building or adjacent materials are out of dimension or alignment. 7.2.2 Delivery sequence A delivery sequence for panels should be flexible to allow for full loads, using reasonable fill-out units when necessary; control of unit position on the trailer with proper support for safety and economy; adequate advance notice of shipment; assurance of prompt unloading; and provision for on-site storage. 7.2.2.1 When possible, panels should be unloaded in a vertical position. This is usually the situation if single-story panels are shipped on frames in a vertical or upright position. Do not remove any chains, binders, or banding until the crane is hooked onto the precast element. Tie off all other panels to the trailer before picking a panel. All chains, binders, banding, protecting packing, and bracing should be carefully removed from around the panels. Comers and panels with returns of unusual length are shipped with special bracing, which should not be removed until the precast piece has been lifted slightly from the truck before installation. If belts are used in unloading, only one panel at a time should be removed. Protective material should be used between the belts and point of contact with the panel. Gangs of precast panels should not be removed with belt lifting devices unless the panels are palletized. The exterior panel should always be unloaded first from a frame or a stack. Never slide a panel out from the middle of a stack. Maintain balance on the trailer during unloading by unloading alternate sides of the vehicle. Remaining adjacent panels on the trailer should be tied or blocked to prevent tipping. 7.2.2.2 After delivery, a panel may require rotation into a new position. For example, a tall panel delivered on its side should be rotated to a vertical position. A panel may also be delivered horizontal, lifted from the delivery vehicle, and up-righted in the air. The panel is normally rotated without being allowed to touch the ground. It may be necessary to bolt a support frame to the panel before rotating. Usually two lifting lines from the crane are used, although special rotating frames have been developed for use with one crane line. 7.2.3 Lifting devices Lifting devices should be secured to panels in accordance with the lifting device manufacturer s recommendations. Thread bolts into inserts a minimum of 2.5 bolt diameters for coil inserts and a minimum of 1.5 bolt diameters for ferrule inserts to prevent stripping of the bolt or insert threads. At least two connections should be used whenever the panel is lifted so the panel or lifting line cannot spin and unscrew, causing the lifting line to become disconnected. Use bolts of a sufficient length to provide full embedment in the lifting device. Regardless of load requirements, a 1/2 in. (13 mm) bolt should be the minimum size used for handling any precast panel. Predrilled or selfdrilled expansion bolts should not be used for handling or installation purposes. Occasionally, inserts, bolts, or other devices are provided only for the convenience of field handling. When these devices are located in finished edges or exposed surfaces, bolt and insert holes will require filling and repairing. When this is necessary, the engineer/architect should be advised so that the locations and repair procedure can be approved before panel fabrication. Repairs should be executed in accordance with Section 7.7. Always measure depth of the lifting insert and have several different length bolts available to ensure the bolt fully penetrates insert depth and not only the concrete. 7.2.3.1 One lifting device is a swiveling D-ring plate bolted to a threaded anchor. The swivel and bolt diameter should be the same size. 7.2.3.2 Coil-threaded anchors are discouraged when other anchor types can be used. Insufficient thread engagement is the most common problem with this system and it is dangerous if the bolt is not fully threaded into the anchor. When using coil-threaded anchors, the following precautions should be followed. It is imperative that thread engagement be a minimum of 2.5 times the nominal bolt diameter. Because anchors are sometimes recessed, the erector should locate the actual top of the steel anchor, as some threads may be concrete cover and not steel. When in doubt, the erector should scratch the threads with a metal object to verify anchor location. Caution should be used in tightening bolts, as they may break out the opposite face of a thin panel or may strip the insert threads. This anchor type is particularly affected by foreign materials such a sandblast grit, ice, or both, which can accumulate in the insert. Take care to remove foreign materials from inserts to ensure full thread engagement. A minimum of two coil inserts should be used to lift a unit so that the unit or lifting line cannot spin, causing the bolt to unscrew from the insert. Bolts of proper length should be used to prevent extensive shimming. Bolts that are too long may bend and fail. 7.2.3.3 The precast concrete manufacturer should be consulted regarding the design intent of all installation inserts. Connection hardware should not be used for lifting or handling, unless specifically designed and designated for this purpose on the installation drawings. Some precast members that are long, heavy, or both, may have sleeves through the member or anchors with swivel hardware for use in attaching installation hardware. There are situations that require special lifting systems. These systems should be designed by a professional engineer and tested to verify the anchor will exceed a safety factor of 4-to-1 and the hardware 5-to-1. After selecting hoisting equipment, rigging should be sized to permit the precast concrete units to be lifted and installed safely. 7.2.3.4 Wire rope slings are usually the major component of the rigging assembly. Occasionally, web belts or chain mesh belts may be required. Hooks, shackles, rolling blocks, closed links, and lifting plates can be used with the slings to complete the system. All of these items are commercially available with test data to substantiate the safe working load for the available sizes of each product. Before using any of these items in a rigging assembly, it is imperative that the user consult the manufacturer s published charts and infor- The precast erector should set out joint location and spacing before panel installation. This should minimize differential variation in panel joint width and identify problems caused when the building or adjacent materials are out of dimension or alignment. 7.2.2 Delivery sequence A delivery sequence for panels should be flexible to allow for full loads, using reasonable fill-out units when necessary; control of unit position on the trailer with proper support for safety and economy; adequate advance notice of shipment; assurance of prompt unloading; and provision for on-site storage. 7.2.2.1 When possible, panels should be unloaded in a vertical position. This is usually the situation if single-story panels are shipped on frames in a vertical or upright position. Do not remove any chains, binders, or banding until the crane is hooked onto the precast element. Tie off all other panels to the trailer before picking a panel. All chains, binders, banding, protecting packing, and bracing should be carefully removed from around the panels. Comers and panels with returns of unusual length are shipped with special bracing, which should not be removed until the precast piece has been lifted slightly from the truck before installation. If belts are used in unloading, only one panel at a time should be removed. Protective material should be used between the belts and point of contact with the panel. Gangs of precast panels should not be removed with belt lifting devices unless the panels are palletized. The exterior panel should always be unloaded first from a frame or a stack. Never slide a panel out from the middle of a stack. Maintain balance on the trailer during unloading by unloading alternate sides of the vehicle. Remaining adjacent panels on the trailer should be tied or blocked to prevent tipping. 7.2.2.2 After delivery, a panel may require rotation into a new position. For example, a tall panel delivered on its side should be rotated to a vertical position. A panel may also be delivered horizontal, lifted from the delivery vehicle, and up-righted in the air. The panel is normally rotated without being allowed to touch the ground. It may be necessary to bolt a support frame to the panel before rotating. Usually two lifting lines from the crane are used, although special rotating frames have been developed for use with one crane line. 7.2.3 Lifting devices Lifting devices should be secured to panels in accordance with the lifting device manufacturer s recommendations. Thread bolts into inserts a minimum of 2.5 bolt diameters for coil inserts and a minimum of 1.5 bolt diameters for ferrule inserts to prevent stripping of the bolt or insert threads. At least two connections should be used whenever the panel is lifted so the panel or lifting line cannot spin and unscrew, causing the lifting line to become disconnected. Use bolts of a sufficient length to provide full embedment in the lifting device. Regardless of load requirements, a 1/2 in. (13 mm) bolt should be the minimum size used for handling any precast panel. Predrilled or selfdrilled expansion bolts should not be used for handling or installation purposes. Occasionally, inserts, bolts, or other devices are provided only for the convenience of field handling. When these devices are located in finished edges or exposed surfaces, bolt and insert holes will require filling and repairing. When this is necessary, the engineer/architect should be advised so that the locations and repair procedure can be approved before panel fabrication. Repairs should be executed in accordance with Section 7.7. Always measure depth of the lifting insert and have several different length bolts available to ensure the bolt fully penetrates insert depth and not only the concrete. 7.2.3.1 One lifting device is a swiveling D-ring plate bolted to a threaded anchor. The swivel and bolt diameter should be the same size. 7.2.3.2 Coil-threaded anchors are discouraged when other anchor types can be used. Insufficient thread engagement is the most common problem with this system and it is dangerous if the bolt is not fully threaded into the anchor. When using coil-threaded anchors, the following precautions should be followed. It is imperative that thread engagement be a minimum of 2.5 times the nominal bolt diameter. Because anchors are sometimes recessed, the erector should locate the actual top of the steel anchor, as some threads may be concrete cover and not steel. When in doubt, the erector should scratch the threads with a metal object to verify anchor location. Caution should be used in tightening bolts, as they may break out the opposite face of a thin panel or may strip the insert threads. This anchor type is particularly affected by foreign materials such a sandblast grit, ice, or both, which can accumulate in the insert. Take care to remove foreign materials from inserts to ensure full thread engagement. A minimum of two coil inserts should be used to lift a unit so that the unit or lifting line cannot spin, causing the bolt to unscrew from the insert. Bolts of proper length should be used to prevent extensive shimming. Bolts that are too long may bend and fail. 7.2.3.3 The precast concrete manufacturer should be consulted regarding the design intent of all installation inserts. Connection hardware should not be used for lifting or handling, unless specifically designed and designated for this purpose on the installation drawings. Some precast members that are long, heavy, or both, may have sleeves through the member or anchors with swivel hardware for use in attaching installation hardware. There are situations that require special lifting systems. These systems should be designed by a professional engineer and tested to verify the anchor will exceed a safety factor of 4-to-1 and the hardware 5-to-1. After selecting hoisting equipment, rigging should be sized to permit the precast concrete units to be lifted and installed safely. 7.2.3.4 Wire rope slings are usually the major component of the rigging assembly. Occasionally, web belts or chain mesh belts may be required. Hooks, shackles, rolling blocks, closed links, and lifting plates can be used with the slings to complete the system. All of these items are commercially available with test data to substantiate the safe working load for the available sizes of each product. Before using any of these items in a rigging assembly, it is imperative that the user consult the manufacturer s published charts and infor- The precast erector should set out joint location and spacing before panel installation. This should minimize differential variation in panel joint width and identify problems caused when the building or adjacent materials are out of dimension or alignment. 7.2.2 Delivery sequence A delivery sequence for panels should be flexible to allow for full loads, using reasonable fill-out units when necessary; control of unit position on the trailer with proper support for safety and economy; adequate advance notice of shipment; assurance of prompt unloading; and provision for on-site storage. 7.2.2.1 When possible, panels should be unloaded in a vertical position. This is usually the situation if single-story panels are shipped on frames in a vertical or upright position. Do not remove any chains, binders, or banding until the crane is hooked onto the precast element. Tie off all other panels to the trailer before picking a panel. All chains, binders, banding, protecting packing, and bracing should be carefully removed from around the panels. Comers and panels with returns of unusual length are shipped with special bracing, which should not be removed until the precast piece has been lifted slightly from the truck before installation. If belts are used in unloading, only one panel at a time should be removed. Protective material should be used between the belts and point of contact with the panel. Gangs of precast panels should not be removed with belt lifting devices unless the panels are palletized. The exterior panel should always be unloaded first from a frame or a stack. Never slide a panel out from the middle of a stack. Maintain balance on the trailer during unloading by unloading alternate sides of the vehicle. Remaining adjacent panels on the trailer should be tied or blocked to prevent tipping. 7.2.2.2 After delivery, a panel may require rotation into a new position. For example, a tall panel delivered on its side should be rotated to a vertical position. A panel may also be delivered horizontal, lifted from the delivery vehicle, and up-righted in the air. The panel is normally rotated without being allowed to touch the ground. It may be necessary to bolt a support frame to the panel before rotating. Usually two lifting lines from the crane are used, although special rotating frames have been developed for use with one crane line. 7.2.3 Lifting devices Lifting devices should be secured to panels in accordance with the lifting device manufacturer s recommendations. Thread bolts into inserts a minimum of 2.5 bolt diameters for coil inserts and a minimum of 1.5 bolt diameters for ferrule inserts to prevent stripping of the bolt or insert threads. At least two connections should be used whenever the panel is lifted so the panel or lifting line cannot spin and unscrew, causing the lifting line to become disconnected. Use bolts of a sufficient length to provide full embedment in the lifting device. Regardless of load requirements, a 1/2 in. (13 mm) bolt should be the minimum size used for handling any precast panel. Predrilled or selfdrilled expansion bolts should not be used for handling or installation purposes. Occasionally, inserts, bolts, or other devices are provided only for the convenience of field handling. When these devices are located in finished edges or exposed surfaces, bolt and insert holes will require filling and repairing. When this is necessary, the engineer/architect should be advised so that the locations and repair procedure can be approved before panel fabrication. Repairs should be executed in accordance with Section 7.7. Always measure depth of the lifting insert and have several different length bolts available to ensure the bolt fully penetrates insert depth and not only the concrete. 7.2.3.1 One lifting device is a swiveling D-ring plate bolted to a threaded anchor. The swivel and bolt diameter should be the same size. 7.2.3.2 Coil-threaded anchors are discouraged when other anchor types can be used. Insufficient thread engagement is the most common problem with this system and it is dangerous if the bolt is not fully threaded into the anchor. When using coil-threaded anchors, the following precautions should be followed. It is imperative that thread engagement be a minimum of 2.5 times the nominal bolt diameter. Because anchors are sometimes recessed, the erector should locate the actual top of the steel anchor, as some threads may be concrete cover and not steel. When in doubt, the erector should scratch the threads with a metal object to verify anchor location. Caution should be used in tightening bolts, as they may break out the opposite face of a thin panel or may strip the insert threads. This anchor type is particularly affected by foreign materials such a sandblast grit, ice, or both, which can accumulate in the insert. Take care to remove foreign materials from inserts to ensure full thread engagement. A minimum of two coil inserts should be used to lift a unit so that the unit or lifting line cannot spin, causing the bolt to unscrew from the insert. Bolts of proper length should be used to prevent extensive shimming. Bolts that are too long may bend and fail. 7.2.3.3 The precast concrete manufacturer should be consulted regarding the design intent of all installation inserts. Connection hardware should not be used for lifting or handling, unless specifically designed and designated for this purpose on the installation drawings. Some precast members that are long, heavy, or both, may have sleeves through the member or anchors with swivel hardware for use in attaching installation hardware. There are situations that require special lifting systems. These systems should be designed by a professional engineer and tested to verify the anchor will exceed a safety factor of 4-to-1 and the hardware 5-to-1. After selecting hoisting equipment, rigging should be sized to permit the precast concrete units to be lifted and installed safely. 7.2.3.4 Wire rope slings are usually the major component of the rigging assembly. Occasionally, web belts or chain mesh belts may be required. Hooks, shackles, rolling blocks, closed links, and lifting plates can be used with the slings to complete the system. All of these items are commercially available with test data to substantiate the safe working load for the available sizes of each product. Before using any of these items in a rigging assembly, it is imperative that the user consult the manufacturer s published charts and infor- The precast erector should set out joint location and spacing before panel installation. This should minimize differential variation in panel joint width and identify problems caused when the building or adjacent materials are out of dimension or alignment. 7.2.2 Delivery sequence A delivery sequence for panels should be flexible to allow for full loads, using reasonable fill-out units when necessary; control of unit position on the trailer with proper support for safety and economy; adequate advance notice of shipment; assurance of prompt unloading; and provision for on-site storage. 7.2.2.1 When possible, panels should be unloaded in a vertical position. This is usually the situation if single-story panels are shipped on frames in a vertical or upright position. Do not remove any chains, binders, or banding until the crane is hooked onto the precast element. Tie off all other panels to the trailer before picking a panel. All chains, binders, banding, protecting packing, and bracing should be carefully removed from around the panels. Comers and panels with returns of unusual length are shipped with special bracing, which should not be removed until the precast piece has been lifted slightly from the truck before installation. If belts are used in unloading, only one panel at a time should be removed. Protective material should be used between the belts and point of contact with the panel. Gangs of precast panels should not be removed with belt lifting devices unless the panels are palletized. The exterior panel should always be unloaded first from a frame or a stack. Never slide a panel out from the middle of a stack. Maintain balance on the trailer during unloading by unloading alternate sides of the vehicle. Remaining adjacent panels on the trailer should be tied or blocked to prevent tipping. 7.2.2.2 After delivery, a panel may require rotation into a new position. For example, a tall panel delivered on its side should be rotated to a vertical position. A panel may also be delivered horizontal, lifted from the delivery vehicle, and up-righted in the air. The panel is normally rotated without being allowed to touch the ground. It may be necessary to bolt a support frame to the panel before rotating. Usually two lifting lines from the crane are used, although special rotating frames have been developed for use with one crane line. 7.2.3 Lifting devices Lifting devices should be secured to panels in accordance with the lifting device manufacturer s recommendations. Thread bolts into inserts a minimum of 2.5 bolt diameters for coil inserts and a minimum of 1.5 bolt diameters for ferrule inserts to prevent stripping of the bolt or insert threads. At least two connections should be used whenever the panel is lifted so the panel or lifting line cannot spin and unscrew, causing the lifting line to become disconnected. Use bolts of a sufficient length to provide full embedment in the lifting device. Regardless of load requirements, a 1/2 in. (13 mm) bolt should be the minimum size used for handling any precast panel. Predrilled or selfdrilled expansion bolts should not be used for handling or installation purposes. Occasionally, inserts, bolts, or other devices are provided only for the convenience of field handling. When these devices are located in finished edges or exposed surfaces, bolt and insert holes will require filling and repairing. When this is necessary, the engineer/architect should be advised so that the locations and repair procedure can be approved before panel fabrication. Repairs should be executed in accordance with Section 7.7. Always measure depth of the lifting insert and have several different length bolts available to ensure the bolt fully penetrates insert depth and not only the concrete. 7.2.3.1 One lifting device is a swiveling D-ring plate bolted to a threaded anchor. The swivel and bolt diameter should be the same size. 7.2.3.2 Coil-threaded anchors are discouraged when other anchor types can be used. Insufficient thread engagement is the most common problem with this system and it is dangerous if the bolt is not fully threaded into the anchor. When using coil-threaded anchors, the following precautions should be followed. It is imperative that thread engagement be a minimum of 2.5 times the nominal bolt diameter. Because anchors are sometimes recessed, the erector should locate the actual top of the steel anchor, as some threads may be concrete cover and not steel. When in doubt, the erector should scratch the threads with a metal object to verify anchor location. Caution should be used in tightening bolts, as they may break out the opposite face of a thin panel or may strip the insert threads. This anchor type is particularly affected by foreign materials such a sandblast grit, ice, or both, which can accumulate in the insert. Take care to remove foreign materials from inserts to ensure full thread engagement. A minimum of two coil inserts should be used to lift a unit so that the unit or lifting line cannot spin, causing the bolt to unscrew from the insert. Bolts of proper length should be used to prevent extensive shimming. Bolts that are too long may bend and fail. 7.2.3.3 The precast concrete manufacturer should be consulted regarding the design intent of all installation inserts. Connection hardware should not be used for lifting or handling, unless specifically designed and designated for this purpose on the installation drawings. Some precast members that are long, heavy, or both, may have sleeves through the member or anchors with swivel hardware for use in attaching installation hardware. There are situations that require special lifting systems. These systems should be designed by a professional engineer and tested to verify the anchor will exceed a safety factor of 4-to-1 and the hardware 5-to-1. After selecting hoisting equipment, rigging should be sized to permit the precast concrete units to be lifted and installed safely. 7.2.3.4 Wire rope slings are usually the major component of the rigging assembly. Occasionally, web belts or chain mesh belts may be required. Hooks, shackles, rolling blocks, closed links, and lifting plates can be used with the slings to complete the system. All of these items are commercially available with test data to substantiate the safe working load for the available sizes of each product. Before using any of these items in a rigging assembly, it is imperative that the user consult the manufacturer s published charts and infor- The precast erector should set out joint location and spacing before panel installation. This should minimize differential variation in panel joint width and identify problems caused when the building or adjacent materials are out of dimension or alignment. 7.2.2 Delivery sequence A delivery sequence for panels should be flexible to allow for full loads, using reasonable fill-out units when necessary; control of unit position on the trailer with proper support for safety and economy; adequate advance notice of shipment; assurance of prompt unloading; and provision for on-site storage. 7.2.2.1 When possible, panels should be unloaded in a vertical position. This is usually the situation if single-story panels are shipped on frames in a vertical or upright position. Do not remove any chains, binders, or banding until the crane is hooked onto the precast element. Tie off all other panels to the trailer before picking a panel. All chains, binders, banding, protecting packing, and bracing should be carefully removed from around the panels. Comers and panels with returns of unusual length are shipped with special bracing, which should not be removed until the precast piece has been lifted slightly from the truck before installation. If belts are used in unloading, only one panel at a time should be removed. Protective material should be used between the belts and point of contact with the panel. Gangs of precast panels should not be removed with belt lifting devices unless the panels are palletized. The exterior panel should always be unloaded first from a frame or a stack. Never slide a panel out from the middle of a stack. Maintain balance on the trailer during unloading by unloading alternate sides of the vehicle. Remaining adjacent panels on the trailer should be tied or blocked to prevent tipping. 7.2.2.2 After delivery, a panel may require rotation into a new position. For example, a tall panel delivered on its side should be rotated to a vertical position. A panel may also be delivered horizontal, lifted from the delivery vehicle, and up-righted in the air. The panel is normally rotated without being allowed to touch the ground. It may be necessary to bolt a support frame to the panel before rotating. Usually two lifting lines from the crane are used, although special rotating frames have been developed for use with one crane line. 7.2.3 Lifting devices Lifting devices should be secured to panels in accordance with the lifting device manufacturer s recommendations. Thread bolts into inserts a minimum of 2.5 bolt diameters for coil inserts and a minimum of 1.5 bolt diameters for ferrule inserts to prevent stripping of the bolt or insert threads. At least two connections should be used whenever the panel is lifted so the panel or lifting line cannot spin and unscrew, causing the lifting line to become disconnected. Use bolts of a sufficient length to provide full embedment in the lifting device. Regardless of load requirements, a 1/2 in. (13 mm) bolt should be the minimum size used for handling any precast panel. Predrilled or selfdrilled expansion bolts should not be used for handling or installation purposes. Occasionally, inserts, bolts, or other devices are provided only for the convenience of field handling. When these devices are located in finished edges or exposed surfaces, bolt and insert holes will require filling and repairing. When this is necessary, the engineer/architect should be advised so that the locations and repair procedure can be approved before panel fabrication. Repairs should be executed in accordance with Section 7.7. Always measure depth of the lifting insert and have several different length bolts available to ensure the bolt fully penetrates insert depth and not only the concrete. 7.2.3.1 One lifting device is a swiveling D-ring plate bolted to a threaded anchor. The swivel and bolt diameter should be the same size. 7.2.3.2 Coil-threaded anchors are discouraged when other anchor types can be used. Insufficient thread engagement is the most common problem with this system and it is dangerous if the bolt is not fully threaded into the anchor. When using coil-threaded anchors, the following precautions should be followed. It is imperative that thread engagement be a minimum of 2.5 times the nominal bolt diameter. Because anchors are sometimes recessed, the erector should locate the actual top of the steel anchor, as some threads may be concrete cover and not steel. When in doubt, the erector should scratch the threads with a metal object to verify anchor location. Caution should be used in tightening bolts, as they may break out the opposite face of a thin panel or may strip the insert threads. This anchor type is particularly affected by foreign materials such a sandblast grit, ice, or both, which can accumulate in the insert. Take care to remove foreign materials from inserts to ensure full thread engagement. A minimum of two coil inserts should be used to lift a unit so that the unit or lifting line cannot spin, causing the bolt to unscrew from the insert. Bolts of proper length should be used to prevent extensive shimming. Bolts that are too long may bend and fail. 7.2.3.3 The precast concrete manufacturer should be consulted regarding the design intent of all installation inserts. Connection hardware should not be used for lifting or handling, unless specifically designed and designated for this purpose on the installation drawings. Some precast members that are long, heavy, or both, may have sleeves through the member or anchors with swivel hardware for use in attaching installation hardware. There are situations that require special lifting systems. These systems should be designed by a professional engineer and tested to verify the anchor will exceed a safety factor of 4-to-1 and the hardware 5-to-1. After selecting hoisting equipment, rigging should be sized to permit the precast concrete units to be lifted and installed safely. 7.2.3.4 Wire rope slings are usually the major component of the rigging assembly. Occasionally, web belts or chain mesh belts may be required. Hooks, shackles, rolling blocks, closed links, and lifting plates can be used with the slings to complete the system. All of these items are commercially available with test data to substantiate the safe working load for the available sizes of each product. Before using any of these items in a rigging assembly, it is imperative that the user consult the manufacturer s published charts and infor-