Академический Документы
Профессиональный Документы
Культура Документы
POWER2015
June 28-July 2, 2015, San Diego, California
POWER2015-49551
Feng Weizhong
General Manager
Shanghai Waigaoqiao No.3 Power Generation Co., Ltd.
Shanghai, China 200137
ABSTRACT:
Optimization and innovation of all systems are needed to 2. HIGH EFFICIENCY OF COAL-FIRED POWER
increase the energy saving and reduce emissions in coal- The construction of very efficient large Super Critical/Ultra
fired power plants. Design changes can be made that are Super Critical (SC/USC) units with the shutting down of old
inexpensive, low risk and effective. low efficiency units has improved the average efficiency
and reduced the environmental impact of Chinas thermal
A series of optimization and innovation designs have been power generation industry over the last decade. However,
developed to significantly increase the efficiency of the potential for further structural improvements will be less
2x1000MW ultra supercritical (USC) units in China. The as the small low efficiency units are closed down.
turbine efficiency limitations due to solid particle erosion
are eliminated by these improvements. The normal The electric power industry has discussed developing new
deterioration of the turbine efficiency has also been Advanced-Ultra Super Critical (A-USC) high efficiency
eliminated. power plants using high temperature 700C steam units.
Since the end of the last century, many countries have been
The units net efficiency at the rated operation conditions developing 700C high efficiency A-USC units.
including the Flue Gas Desulphurization (FGD) and
Selective Catalytic Reduction (SCR) systems now exceeds The theoretical net efficiency of 700C, single reheat units
46.5% for a single reheat system. can be 46-47% (including the FGD and SCR systems) with
20C cooling water temperatures, which is 3~3.2% higher
Key Words: efficiency improvement, ultra-supercritical, than that of 600C units.
innovation.
However, the materials and costs of 700C units have
1. BACKGROUND limited their development. The first 700C high efficiency
Global climate change concerns are requiring the electric A-USC demonstration unit has been postponed, so, the
power industry to improve emission reductions and possibility of commercialization of 700C A-USC units
environmental protection. The Chinese government has before 2020 is unlikely. Thus the Chinese power industry
committed to reducing the CO2 emissions per unit GDP in cannot expect to install 700C A-USC units to improve
2020 by 40%-45% relative to 2005. energy savings and reduce emissions before 2020.
In addition, coal is not only the most important primary The second solution to continue making energy efficiency
energy source in the world, but is also the largest source of gains and reducing environmental impacts is using
CO2 emissions and air pollution. Recently, higher levels of Integrated Gasification Combined Cycles (IGCC) systems.
haze have made coal the focus of conflict.
In 2007, Mitsubishi Heavy Industries of Japan constructed
Chinas energy resources structure is Deficient in Oil, Lean the most efficient IGCC demonstration unit (250MW), at the
in Gas and Rich in Coal", so Chinas coal-fired power Nakoso power plant. In November, 2012, China Huaneng
capacity has reached 900GWe. Therefore, to reduce the Group also constructed an IGCC demonstration unit
conflict between the environment and the continued (265MW) in TianJin. However, there are still a lot of
development of the electric power industry, the only choice technical and budget bottlenecks for IGCC units; much
is to develop more efficient coal-fired power systems.
4. MAJOR ENERGY CONSERVATION AND Two FGD heat recovery systems were put into operation in
EMISSION REDUCTION IMPROVEMENTS IN THE June and October, 2009. They have been very successful.
WAIGAOQIAO NO.3 POWER PLANT They have experienced only a limited amount of corrosion,
The conventional approaches for improving the efficiency, which is not enough to impact the design life of the system.
such as increasing the steam parameters (temperature and
3 Copyright 2015 by ASME
3.01%. After the seals were installed in the hot ends and
4.1.2 AIR PREHEATER SEALING along the axial directions, the power use was further reduced
The rotating air preheater is typical for large boiler. The to 2.7% without the FGD power. The boiler hot air
Waigaoqiao No.3 power plant uses a rotor rotating type of temperature also increased which increased boiler efficiency
air-preheater with a diameter of 17 m and height of 2.5 m. with a unit efficiency increase of 0.29%.
The design air leakage is less than 5% and is still less than
6% after one year operation. 4.1.3 BOILER STARTUP ENERGY CONSERVATION
SYSTEM
There are many advantages of the rotor rotating type air pre- The startup of large super and ultra supercritical units
heater, but the non-linear mushroom deformation of the consumes large quantities of water, electric power, oil, coal
rotor during the operation makes the clearances between the and steam. Also, the unit is more susceptible to damage
rotating and stationary parts difficult to control which during this time, compared to normal operating conditions,
increases the air leakage. The air leakage then consumes due to the effect of the sticky flue gas constituents (a result
more power due to the increased air flow rate with the of firing oil), on the precipitator. At many plants, this oil
power increasing related to the air leakage rate to the third build up is avoided by switching off the precipitator during
power. The heat transfer rate is also reduced which will the oil firing, and combined oil-coal firing period. This
reduced the boiler efficiency. causes the pollutant emissions to increase during this phase.
The air leakage was reduced by adding a Flexible Sealing The startup procedures for once through boilers used
System. The system did change the original equipment worldwide were analyzed to find the best method. The result
design as the seal has a controlled wear rate and is flexible was that traditional startup method was completely replaced
enough to seal the radial, axial and circumferential by a new startup method that is more effective.
clearances. The seal is flexible enough to compensate for the
non-linear changes between the rotating and stationary parts, 1Boiler filling without the boiler feedwater pump, start
so the air leakage is significantly reduced. up and flushing without ignition.
This system can be flushed without starting the boiler
With this seal the unit power consumption rate was below feedwater pump or igniting the burners to heat the boiler.
3.5% at the rated operating condition (including the FGD This saves large quantities of fuel and power and is easy to
and SCR systems). When the seal was first applied to only control. The high temperature water in contact with the
5. CONCLUSIONS
Recognizing that character of Chinas energy resources
structure is Deficient in Oil, Lean in Gas and Rich in
Coal, clean utilization of coal must be the priority of
Chinas energy development strategy. Due to insufficient