Preconstruction Activities for Lot 1 and Lot 2 KF WWTPs

Task Assignments & Schedules

1 GM (SS)
Assigning Quantity Surevyors to Check
WWTP 1 & Staff Mobilization: Assigning RE
WWTP 2 Surveying and site pegging
Sewer outfalls
2 Process (AK)
Design Review
Check Plant Layout & Process Drawings
Check P& ID
WWTP 1
Check EM BoQ
Prepare design for new units (Coarse screen)
Prepare Plant Hydraulic Profile Drawings
Design Review
Check Plant Layout & Process Drawings
Check P& ID
WWTP2
Check EM BoQ
Prepare design for new units (Coarse screen)
Prepare Plant Hydraulic Profile Drawings
3 Structural & QS
Check & Confirm BoQ against Civil & Structural Drawings

WWTP 1

Ammend Civil / Structural Drawings for PTU (Blower Room),


Distribution Chamber
Prepare Missed Civil, Structural Drawings
Check & Confirm BoQ against Civil & Structural Drawings
WWTP 2

Ammend Civil / Structural Drawings for PTU (Blower Room)


Prepare Missed Civil, Structural Drawings
4 EM (TA)
Check EM Drawings
Check P& ID
WWTP 1 Check EM BoQ
Prepare technical specification for new EM items
Prepare Plant pipework drawings
Check EM Drawings
Check P& ID
WWTP2 Check EM BoQ
Prepare technical specification for new EM items
Prepare Plant pipework drawings
2 CMS (BT)
WWTP 1 & Review Contract Document
WWTP 2 Respond to Client's Queries on Contract Agreement
or Lot 1 and Lot 2 KF WWTPs

signing Quantity Surevyors to Check 19-Aug-16


ff Mobilization: Assigning RE
veying and site pegging 24-Aug-16
wer outfalls 24-Aug-16

sign Review 22-Aug-16


eck Plant Layout & Process Drawings 22-Aug-16
eck P& ID 22-Aug-16
eck EM BoQ 22-Aug-16
pare design for new units (Coarse screen) 29-Aug-16
pare Plant Hydraulic Profile Drawings 7-Sep-16
sign Review 29-Aug-16
eck Plant Layout & Process Drawings 29-Aug-16
eck P& ID 29-Aug-16
eck EM BoQ 29-Aug-16
pare design for new units (Coarse screen) 7-Sep-16
pare Plant Hydraulic Profile Drawings 7-Sep-16
S
eck & Confirm BoQ against Civil & Structural Drawings 29-Aug-16
A) Biological Treatment (Pre-Anoxic, Anaerobic,
Denitrification and Aration tanks)
B) Final Clarification Tanks (MLSS Recirculation PS/
Sludge Recirculation PS/ Sludge Recirculation PS/ Air
Collector PSAir Collectors /Mixing System)
C)
D) Chlorination Tanksludge tank and Gravity
Aerated storage
Thickener
E) Dewatering Building / Blower Building / Energy
Building
F) PTU
G) Chemical Building
H) Control Building
I) Lifting Pump Station
J) Guard House
K) Site and Compound works
mend Civil / Structural Drawings for PTU (Blower Room),
tribution Chamber 9-Sep-16
pare Missed Civil, Structural Drawings 9-Sep-16
eck & Confirm BoQ against Civil & Structural Drawings 29-Aug-16
29-Aug-16
A) Biological Treatment (Pre-Anoxic, Anaerobic,
Denitrification and Aration tanks)

B) Final Clarification Tanks (MLSS Recirculation PS/


Sludge Recirculation PS/ Sludge Recirculation PS/ Air
Collector PSAir Collectors /Mixing System)
C) Chlorination Tank
D) Aerated storage sludge tank and Gravity
Thickener
E) Dewatering Building / Blower Building / Energy
Building
F) PTU & Distribution Chamber
G) Chemical Building
H) Control Building
I) Lifting Pump Station
J) Guard House
K) Site and Compound works
mend Civil / Structural Drawings for PTU (Blower Room) 9-Sep-16
pare Missed Civil, Structural Drawings 9-Sep-16

eck EM Drawings 22-Aug-16


eck P& ID 22-Aug-16
eck EM BoQ 22-Aug-16
pare technical specification for new EM items 29-Aug-16
pare Plant pipework drawings 7-Sep-16
eck EM Drawings 29-Aug-16
eck P& ID 29-Aug-16
eck EM BoQ 29-Aug-16
pare technical specification for new EM items 7-Sep-16
pare Plant pipework drawings 14-Sep-16

view Contract Document Do ne


spond to Client's Queries on Contract Agreement
Unit 1.
Lifting
Pump
Station