Академический Документы
Профессиональный Документы
Культура Документы
ResourceAllocation
Chapter9ResourceAllocation 1
Introduction
Thischapteraddresses:
Tradeoffsinvolvedtocrashcost
Relationshipbetweenresourceloadingand
leveling
Someapproachesusedtosolveallocation
problem
Chapter9ResourceAllocation 2
CriticalPathMethodCrashingaProject
OneimportantdifferencebetweenCPM&PERT:
CPMincludedawayofrelatingtheproject
scheduletothelevelofphysicalresources
tradetimeforcost,orviceversa
Canspecify2activitytimesand2costs
1sttime/costcombinationcallednormal
2ndcombinationcalledcrash
Normalusualaveragetime,resources
Crashexpeditebyapplyingadditionalresources
Chapter9ResourceAllocation 3
CriticalPathMethodCrashingaProject
Allocationproblemrequiresmorecareful
considerationadditionalresources?
Manythingsmakecrashingawayoflifeon
someprojects(i.elastminuteschangesin
clientspecification,withoutpermissionto
extendtheprojectdeadlinebyanappropriate
increment)
Carefulplanningiscriticalwhencrashing
projectneedtoconsiderfeasibilityof
expeditingwork(e.gequipmentavailability)
Chapter9ResourceAllocation 4
CriticalPathMethodCrashingaProject
Where:slope=costperdayofcrashingaproject
Whenslopeisnegative:indicatethetime
requiredforaprojectisdecreased,thecostis
increased
Chapter9ResourceAllocation 5
Thedollarsperdayslopeofactivitiesis
relevantonlyifthewholecrashincrementis
useful
Crashingmayinvolvearelativelysimple
decisiontoincreasegroupsofresources
(laborshovel,DitchWitchTechnology)
Ifdochangesintechnologytendtoproduce
discontinuitiesinoutcomesandalsoincost.
Chapter9ResourceAllocation 6
Principlestocrashaproject
1. Focusonthecriticalpathwhentryingto
shortentheduration[resourceready]
1. Selecttheleastexpensivewaytodoit
Chapter9ResourceAllocation 7
CrashingaProject(E.gTwoTimeCPM)
b e
a c
1 2 3 4 5 6 7 8
Chapter9ResourceAllocation 9
e
b e
b
a a c
c
d d
1 2 3 4 5 6 7 8 1 2 3 4 5 6 7 8
7-day schedule, $160 6-day schedule. $220
e e
b b
a c
a c
d
d
1 2 3 4 5 6 7 8 1 2 3 4 5 6 7 8
5-day schedule, $260 4-day schedule, $350
Chapter9ResourceAllocation 10
Networkcriticalpathisabe,projectduration
is8days,normaltotalcostis$120
Thedecisionaboutwhichactivitiestocrash
dependsonhowmuchtoreducetheduration
Onthebenefitside,someprojectshave
penaltyclausesthatmaketheparent
organizationliableforlatedelivery
sometimesbonusesforearlydelivery
Chapter9ResourceAllocation 11
Onthecostside,figurebelowshowsthetime/cost
relationshipofcrashingtheproject
400
350 All crash
300 a + b + 2d + 2e
Cost ($)
250 a + d + 2e - b
200 a+b
150 a
100
All normal
50
0
0 1 2 3 4 5 6 7 8 9
Total duration (days)
Chapter9ResourceAllocation 12
FastTracking
Anotherwaytoexpediteaproject
Termusedforconstructionprojects
Referstooverlappingdesignandbuild
phases
Designcompletedbeforeconstruction
starts,sooverlappingwillresultshorteningthe
projectduration
Buildbeforedesigncompletedmoredesign
changes
Lossproductivity,increasedcost,losstime
Chapter9ResourceAllocation 13
FastTracking(cont.)
Studiesrevealedthat:
moredesignchangesinfasttrackingthe
numberofprojectchangeordersnotsignificantly
differentthannotfasttrackedproject
Dependentoneffectivefeedbackandfeed
forwardcommunication
Chapter9ResourceAllocation 14
SOLVEDPROBLEM
8 e:cancuteby2daysforanextracostof
$60andresultsinprojectcompletionby
day10.
Thus,cute2daysatacostof$60.
Chapter9ResourceAllocation 16
RESOURCEALLOCATIONPROBLEM
AfundamentalmeasureofthePMssuccess
inprojectmgmtistheskillwithwhichthe
tradeoffsamongperformance,timeandcost
aremanaged
Theextremepointsoftherelationship
betweentimeuseandresourceare:
Timelimited
Resourcelimited
Chapter9ResourceAllocation 17
RESOURCELOADING
Theamountofindividualsresourcesanexisting
schedulerequiresduringspecifictimeperiods
Resourceloadingcanbeillustratedby:
Resourceusagecalendar
ModifiedPERT/CPMAOAdiagram(similarwith
GanttChart)
PMresponsibility:
Demandforresourcesdoesnotexceedresource
capacities
Ensurethattherequiredresources,intherequired
amounts
Chapter9ResourceAllocation 18
ResourceUsageCalendar
Chapter9ResourceAllocation 19
ModifiedPERT/CPMAOADiagram
(ReferCh08Slide26)
a d j
1 2 6 7
(4,0) (0,2) (0,6)
3 e
(2,1)
f
3
(1,1)
b g i
1 3 5
(2,1) (6,3)
(1,0)
c dummy
1 4
(3,1) h
4
(0,2)
0 5 10 15 20 25 30 35 40 45
Chapter9ResourceAllocation 20
RESOURCELEVELING
Aimstominimizetheperiodbyperiodvariationsin
resourceloadingbyshiftingtaskswithintheirslack
allowances
Purposetocreateasmootherdistributionofresource
usage
Advantages;
Muchlesshandsonmanagement
Beabletousejustintimeinventorypolicywith
rightquantitydelivered
Iftheresourcebeingleveledispeople,itimproves
moraleandresultsinfewerproblemsinthe
personnelandpayrolloffices
Chapter9ResourceAllocation 21
E.g:Network
2
a,2
[2]
c,5
1 4
[4]
b,3
[2]
3
Theactivitytimeisshownabovethearc,andresourceusage
(oneresource,workers)isinbracketsbelowthearc.
Chapter9ResourceAllocation 22
BeforeResourceLeveling
10
a 8
Workers
a
Activity
6
b
4 c c
c
2 c
b b
1 2 3 4 5 1 2 3 4 5
Days Days
Chapter9ResourceAllocation 23
AfterResourceLeveling
10
a 8
Workers
Activity
6
b
a b
4
c
2 c
1 2 3 4 5 1 2 3 4 5
Days Days
Chapter9ResourceAllocation 24
RESOURCELOADING/LEVELINGAND
UNCERTAINTY
Ifhappensexcesscapacity,thealternative
thatwecanconsider:
Chapter9ResourceAllocation 25