for Maintenance of Project Highway;

(b) the amount paid in accordance with the Interim Payment Certificates;
and

(c) any sums which the Contractor considers to be due to it, with
supporting documents.

19.16.2 The Authoritys Engineer shall certify final payment within 30 (thirty) days
of the receipt of the final payment statement of Maintenance under Clause
19.16.1, segregating the items of amount payable from the items of amount
disallowed. The Authority shall make payment on the basis of the final
payment authorised by the Authoritys Engineer within a period of 30 (thirty)
days of the receipt of the Final Payment Statement from the Authoritys
Engineer.

19.16.3 If the Authoritys Engineer does not prescribe the form within 15 (fifteen)
days of the date of issue of the Completion Certificate, the Contractor shall
submit the statement in such form as it deems fit.

19.17 Change in law

19.17.1 If as a result of Change in Law, the Contractor suffers any additional costs
in the execution of the Works or in relation to the performance of its other
obligations under this Agreement, the Contractor shall, within 15 (fifteen)
days from the date it becomes reasonably aware of such addition in cost,
notify the Authority with a copy to the Authoritys Engineer of such
additional cost due to Change in Law.

19.17.2 If as a result of Change in Law, the Contractor benefits from any reduction
in costs for the execution of this Agreement or in accordance with the
provisions of this Agreement, either Party shall, within 15 (fifteen) days
from the date it becomes reasonably aware of such reduction in cost, notify
the other Party with a copy to the Authoritys Engineer of such reduction in
cost due to Change in Law.

19.17.3 The Authoritys Engineer shall, within 15 (fifteen) days from the date of
receipt of the notice from the Contractor or the Authority, determine any
addition or reduction to the Contract Price, as the case may be, due to the
Change in Law.

19.18 Correction of Interim Payment Certificates

The Authoritys Engineer may by an Interim Payment Certificate make any


correction or modification in any previous Interim Payment Certificate
issued by the Authoritys Engineer.

19.19 Authoritys claims


Four Laning of Sethiyahopu Cholopuram from km 65.960 to km 116.440 (Design Chainage)
(Existing Chainage from Km. 60.250 to Km. 111.00)section of NH-45C in the state of Tamilnadu under
NHDP Phase-IV on EPC mode 87