RECEPCION DE OBRA 9/23/2016

RECEPCION LIQ 11/22/2016


PRONUNCIAMIENTO ENT 12/7/2016

paralizacion reinicio en cuaderno de obra 34


5/30/2016 6/23/2016 24.00 DIAS 34.00

reinicio en acta
6/24/2016 25.00 DIAS

PRESUP EXP TEC. S/. 299,660.58


MONTO ADIC DEDUCTIVO ADIC NETO PLAZO
ADICIONAL 1 S/. 39,992.02 S/. 24,483.44 S/. 15,508.58 10 DIAS C.
ADICIONAL 2 S/. 108,192.06 S/. 20,222.73 S/. 87,969.33

MGG N 1 8733.79
OR MORA PAGO ADICIONAL 1 274.08 3.14%
EN EXPEDIENTE TECNICO SE TIENE GG VARIABLE: SIN IGV S/. 17,012.47, CON IGV S/. 20074.71
GASTOS GENERALES RECONOCIBLES UND CANTIDAD COSTO FACTOR TIEMPO
RESIDENTE DE OBRA MES 1 3500 1 1.5
ASISTENTE TECNICO MES 1 2800 1 1.5
GARANTIA FIEL CUMPLIMIENTO GBL 29966.06 0.02 1.5

SIN INV IGV (18%) CON IGV (S/.)


MONTOS VIGENTES - SGOP
CONTRATO N 026-2016-MDI 253949.64 45710.94 S/. 299,660.58 OK
Deductivo N 01 -20748.68 -3734.76 -S/. 24,483.44 FALTA ADENDA
Adicional N 01 33891.54 6100.48 S/. 39,992.02 FALTA ADENDA
REAJUSTES -541.32 -97.44 -S/. 638.76 OK 541.32
Mayores Gastos Generales 2779.20 500.26 S/. 3,279.46 OK
Interes por mora en pago 0.00 0.00 VERIFICAR AHORRO
### 323538.27 S/. 5,728.41
PARCIAL POR DIA 24 DIAS MGG
5250 116.666667 2800.00
4200 0.00
898.9818 19.9773733 479.46
###