CONTRACT NO: SOGT-CT-CTR-0501

CONTRACT TITLE: OFFSHORE TRANSPORTATION, INSTALLATION AND PRE-COMMISSIONING FOR PCSB SOGT PROJECT

DOCUMENT: PROPOSED BASELINE SCHEDULE

Activity ID Activity Name Original Start Finish Total 2012


Duration Float Mar Apr May Jun Jul Aug

SOGT PLs & PLEMs 459d 4h 11-Apr-11 A 30-Jul-12 32d 5h

PROJECT MILESTONES 459d 4h 11-Apr-11 A 30-Jul-12 0d

Contract 459d 4h 11-Apr-11 A 30-Jul-12 0d


MS-CON-1010 Effective Award Date 0d 11-Apr-11 A
MS-CON-1030 Commencement of Works 0d 09-May-12* 0d
MS-CON-1020 Completion of Mobilisation 0d 09-May-12* 0d
MS-CON-1040 Pre-Commissioning 0d 17-Jun-12* 0d
MS-CON-1050 Mechanical Completion 0d 25-Jul-12* 0d
MS-CON-1060 Commissioning Intital Acceptance 0d 30-Jul-12* 0d
Proposal 93d 22-Apr-12 23-Jul-12 6d 4h
MS-GEN-1020 Completion of Mobilisation 0d 22-Apr-12 17d 4h
MS-GEN-1030 Commencement of Works 0d 22-Apr-12 17d
MS-GEN-1040 Pre-Commissioning 0d 15-Jun-12 2d 4h
MS-GEN-1050 Mechanical Completion 0d 03-Jul-12 22d 4h
MS-GEN-1060 Commissioning Initial Acceptance 0d 23-Jul-12 6d 4h
TRANSPORTATION (LINEPIPES) 44d 21h 09-Apr-12 24-May-12 99d 3h

250C CB + Tug #01 39d 21h 09-Apr-12 19-May-12 104d


Loadout #01 20d 09-Apr-12 29-Apr-12 3h 7h
72d
Loadout #08 16d 21h 02-May-12 19-May-12 104d
250C CB + Tug #02 39d 9h 12-Apr-12 22-May-12 3h
101d
Loadout #02 20d 7h 12-Apr-12 03-May-12 15h
71d
Loadout #09 17d 9h 04-May-12 22-May-12 12h
101d
250C CB + Tug #03 38d 21h 15-Apr-12 24-May-12 15h3h
99d
Loadout #03 20d 14h 15-Apr-12 06-May-12 70d
Loadout #10 17d 21h 06-May-12 24-May-12 17h3h
99d
250C CB + Tug #04 20d 21h 18-Apr-12 09-May-12 114d
Loadout #04 20d 21h 18-Apr-12 09-May-12 3h
114d
250C CB + Tug #05 20d 21h 21-Apr-12 12-May-12 3h 3h
111d
Loadout #05 20d 21h 21-Apr-12 12-May-12 111d 3h
250C CB + Tug #06 20d 21h 24-Apr-12 15-May-12 108d
Loadout #06 20d 21h 24-Apr-12 15-May-12 3h
108d
250C CB + Tug #07 20d 9h 27-Apr-12 18-May-12 3h
105d
Loadout #07 20d 9h 27-Apr-12 18-May-12 15h
105d
123d 9h 01-Mar-12 02-Jul-12 15h
27d
ONSHORE CONSTRUCTION
19h
OEP Onshore Works @ SOGT, KImanis, Sabah 123d 9h 01-Mar-12 02-Jul-12 27d
Mobilisation 14d 01-Mar-12 14-Mar-12 19h
23d
Construction Of Cofferdam (for 36" PL) 35d 10-Mar-12 13-Apr-12 9d
Holdback Anchor & Winch (for 36" PL) 16d 30-Mar-12 14-Apr-12 8d
System Function Test (for 36" PL) 1d 15-Apr-12 15-Apr-12 8d
Beach Pull (36" PL) 3d 21-Apr-12 23-Apr-12 2d 5h
Assist on 36" PLEM to SOGT PL Pre-commissioning 5d 12h 19-May-12 27-May-12 2d 5h
Construction Of Cofferdam (for 28" PL) 25d 21-Mar-12 14-Apr-12 23d
Holdback Anchor & Winch (for 28" PL) 21d 25-Mar-12 14-Apr-12 23d
Winch System Function Test (for 28"PL) 1d 15-Apr-12 15-Apr-12 23d
Beach Pull (28" PL) 3d 06-May-12 09-May-12 2d 5h
Assist on 28" PLEM to SOGT PL Pre-commissioning 5d 12h 27-May-12 03-Jun-12 2d 5h
28" Gooseneck and Onshore Pipeline Installation (KP0.057 to KP0) 8d 29-May-12 06-Jun-12 27d
Post-Trench in g Reinstatement Work (28" PL) 26d 07-Jun-12 02-Jul-12 20h4h
27d
36" Gooseneck & Onshore Pipeline Installation (KP0.057 to KP0) 8d 29-May-12 06-Jun-12 27d
Post-Trench in g Reinstatement Work (36" PL) 26d 07-Jun-12 02-Jul-12 20h4h
27d
OFFSHORE INSTALLATION 119d 5h 13-Mar-12 10-Jul-12 52d 4h

PRE-INSTALLATION SURVEY 16d 13-Mar-12 29-Mar-12 20d


Mobilisation 3d 12h 13-Mar-12 16-Mar-12 14h
11d
Pre-Installation Survey 10d 12h 16-Mar-12 27-Mar-12 20d
Demobilisation 2d 27-Mar-12 29-Mar-12 14h
20d
INSTALL 28" & 36" PLs, PLEMS & SPMs' HOSES (1MAS 300) 86d 20h 14-Apr-12 10-Jul-12 14h4h
52d
Mob LB 1 Mas 300 7d 14-Apr-12 21-Apr-12 2d 5h
Install 36" X .6 Km Beach Pull 3d 21-Apr-12 24-Apr-12 2d 5h
Install 36" X 9.7 KM Pipeline upto PLEM end 11d 18h 24-Apr-12 06-May-12 2d 5h
Install 28" X 0.6 Km Beach Pull 3d 2h 06-May-12 09-May-12 2d 5h
Install 28" X 11.2 Km Pipeline upto PLEM end 10d 6h 09-May-12 19-May-12 2d 5h
Pre-commision 36" Pipeline from PLEM end to Onshore Location 7d 12h 19-May-12 27-May-12 2d 5h
Precommission 28" Pipeline from PLEM end to Onshore Location 7d 12h 27-May-12 03-Jun-12 2d 5h
28" Pipeline PLEM-2 Installation 6d 03-Jun-12 09-Jun-12 2d 5h
36" Pipeline PLEM-1 Installation 5d 18h 09-Jun-12 15-Jun-12 3d 15h
Install L-1390 SPM 1d 12h 15-Jun-12 17-Jun-12 3d 15h
Install Hoses for L-1390 SPM (36") 8d 17-Jun-12 25-Jun-12 3d 15h
Install L-3380 SPM 1d 12h 25-Jun-12 26-Jun-12 3d 15h
Install Hoses for L-3380 SPM (28") 6d 12h 26-Jun-12 03-Jul-12 3d 15h
DeMob 1 MAS 300 7d 12h 03-Jul-12 10-Jul-12 52d 4h
SPM CHAINS INSTALLATION (TYPE 2 DP VESSEL) 18d 22h 30-May-12 18-Jun-12 74d
Mobilisation 5d 30-May-12 04-Jun-12 12h
88d
36" SPM Chains Installation 1d 04-Jun-12 05-Jun-12 10h
86d
36" SPM Chains Pre-Tensioning 3d 6h 05-Jun-12 08-Jun-12 18h1h
25d
28" SPM Chains Installation 2d 16h 09-Jun-12 12-Jun-12 23d
28" SPM Chains Pre-Tensioning 3d 6h 12-Jun-12 15-Jun-12 19h
23d
Demobilisation 2d 12h 15-Jun-12 18-Jun-12 19h
74d
POST-TRENCHING WORKS 36d 22-Apr-12 28-May-12 12h
95d
Mobilisation 7d 22-Apr-12 29-Apr-12 45d
Post-Lay Trenching of 36" PL 11d 29-Apr-12 10-May-12 23h
45d
Post-Lay Trenching of 28" PL 11d 10-May-12 21-May-12 23h
45d
Demobilisation 7d 21-May-12 28-May-12 23h
95d
PL POST-INSTALLATION SURVEY 10d 6h 13-May-12 23-May-12 99d
Mobilisation 2d 18h 13-May-12 16-May-12 22h
5d 17h
Post-Installation Survey 6d 12h 16-May-12 22-May-12 10d 5h
Demobilisation 1d 22-May-12 23-May-12 99d
22h

Actual Work Critical Remaining Work Page 1 of 1 Date Rev... Checked Approved
22-Jun-11 A nain.saim azmi.mdsaid
Remaining Work Milestone
08-Oct-11 B nain.saim azmi.mdsaid