Академический Документы
Профессиональный Документы
Культура Документы
Guideline
ICT Division
July 2016
Fifth Edition
Page 1 of 101
No Date Revision History Prepared by Approver
1st Edition of Telecommunication TDE Technical
1 27th July 2007 Engineering Unit
Guideline Committee
2nd Edition of Telecommunication TDE Technical
2 29th August 2008 Engineering Unit
Guideline Committee
Removal of Integral Bearer (IB) type of
fiber optic cable from type of fiber optic
cable used in TNB as instructed in Fiber Optic Unit General
3 20th April 2010
Engineering Instruction Pemansuhan TDE Manager (IIDO)
Penggunaan Kabel Optik jenis IB di
Pepasangan TNB
Operational
4 16th August 2010 Update on Synchronization Specialist Group Technical
Committee
IIDO Technical
5 22nd June 2010 Review on Storage Battery Capacity Engineering Unit
Committee
Inclusion of Dual AC system IIDO Technical
6 29th July 2010 Engineering Unit
requirement for Dual SMR system. Committee
Introduction of Type IV DC System for IIDO Technical
7 12th January 2011 Specialist Group
NLDC and COIT. Committee
Installation of MDF in the same IIDO Technical
8 12th October 2011 Engineering Unit
equipment rack. Committee
Inclusion of Ethernet Data Channel Unit IIDO Technical
9 12th October 2011 Access Unit
for PDH Equipment Committee
3rd Edition of Telecommunication IIDO Technical
10 20th April 2012 Engineering Unit
Guideline Committee
1. Review on Multipair Copper Cable
for Current Differential Protection
Technical Support IIDO Technical
11 2nd August 2012 2. Review on Teleprotection Services Unit Committee
Equipment Scheme for
132kV/275kV/500kV
Review in the following chapters :-
1. Chapter 1 : Introduction
2. Chapter 3 : Telecommunication
ICT
Room General Requirements
26th December Telecommunication IIDO Technical
12 3. Chapter 4 : Telecommunication
2012 Guideline Review Committee
Cables
Workgroup
4. Chapter 9 : Switchmode Rectifier
(SMR)
5. Chapter 10 : Battery
4th Edition of Telecommunication Technical Support IIDO Technical
13 2nd January 2013
Guideline Services Unit Committee
1. Review of Appendix E: Optical Fibre
& Cable Characteristics
Technical Support IIDO Technical
14 29th March 2013 2. Review of Chapter 10: Battery. Services Unit Committee
Change of color code for negative (-
) polarity from black to blue color.
1. Review of Chapter 3 :
25th February Telecommunication IIDO Technical
15 Telecommunication Room General
2014 Room Taskforce Committee
Requirements Air Conditioning
Review in the following chapters :-
ICT
Chapter 2 : General Synchronization
Telecommunication
16 14th January 2015 Guideline
Guideline Review
Chapter 3 : Telecommunication Room
Workgroup
General Requirements
Page 2 of 101
Chapter 4 : Telecommunication Cables
Chapter 5 : SDH Multiplexer Equipment
Chapter 6 : UTILITY SDH Equipment
Chapter 7 : Wavelength Dense
Multiplexer (WDM)
Chapter 8 : IP Network
Chapter 9 : PDH Optical Line Terminal
Equipment And Higher Order
Multiplexer Equipment
Chapter 10 : Access Multiplexer
Equipment
Chapter 11 : Digital Teleprotection
Equipment
Chapter 12 : 48VDC Power System
Review of Chapter 8 on the following
sub-chapter:
8.2 WAN (Wide Area Network):
IV. CE Router
Telecommunicati
8.3 LAN (Local Area Network): TNB ICT Network
17 10th May 2016 on Technical
Architecture
Space and environmental Committee
requirement for LAN
equipment
Type of Access Switch
Page 3 of 101
Table of Contents
Acknowledgement.................................................................................................. 10
References .............................................................................................................. 11
List of Tables .......................................................................................................... 12
List of Figures ........................................................................................................ 12
Glossary.................................................................................................................. 14
1. Introduction ...................................................................................................... 16
1.1 Objective of Guidelines .................................................................................... 16
1.2 Scope of Guidelines ......................................................................................... 16
1.3 Responsibility ................................................................................................... 16
1.4 Suggestions and Contributions ........................................................................ 16
2. General Synchronization Guideline ................................................................ 17
2.1 Introduction....................................................................................................... 17
2.2 Standards ......................................................................................................... 17
2.3 General Guideline ............................................................................................ 18
2.4 SDH/PCM Access Node Synchronization ........................................................ 19
2.5 GNSS Based Synchronous Supply Unit (SSU) ............................................... 20
2.6 Network Management System (NMS) ............................................................. 20
2.7 Network Time Protocol (NTP) .......................................................................... 20
3. Telecommunication Room General Requirements ........................................ 21
3.1 Introduction....................................................................................................... 21
3.2 Telecommunication Service Termination Boundary ........................................ 21
3.3 Telecommunication and Associated Equipment .............................................. 21
3.4 Telecommunication Room Facilities ................................................................ 22
3.5 Room Size ........................................................................................................ 22
3.6 Room Location in the Building ......................................................................... 23
3.7 Floor Type ........................................................................................................ 23
3.8 Ceiling Height ................................................................................................... 23
3.9 AC Power Supply ............................................................................................. 23
3.10 Room Lighting .................................................................................................. 23
3.11 Air Conditioning ................................................................................................ 23
3.12 Windows in the Room ...................................................................................... 24
3.13 Station Earthing ................................................................................................ 24
3.14 Main Distribution Frame (MDF) ........................................................................ 24
3.15 Optical Fiber Distribution Panel (ODP) ............................................................ 24
3.16 Room Access ................................................................................................... 25
3.17 48V DC Battery and Charger ........................................................................... 25
3.18 Operational Telephone (PLC) .......................................................................... 25
3.19 Fire Protection System ..................................................................................... 25
3.20 Remote Alarm Facility ...................................................................................... 26
3.22 Safety and Health Requirements ..................................................................... 26
4. Telecommunication Cables ............................................................................. 26
Page 4 of 101
4.1 Introduction....................................................................................................... 26
4.2 Fiber Optic Cables ........................................................................................... 26
4.2.1 Types of Fiber Optic Cables ............................................................................ 27
4.2.2 OPGW Configuration Requirements ............................................................... 28
4.2.3 New Optical Fiber Type Test........................................................................... 30
4.2.4 New Optical Fiber Factory Acceptance Test ................................................... 30
4.2.5 Optical Fiber Site Acceptance Test ................................................................. 30
4.2.6 Documentation ................................................................................................ 30
4.3 Installation Guideline ........................................................................................ 31
4.3.1 Standard Requirement for Installation of Fiber Optic Cable in TNB ............... 31
4.3.2 Standard Requirement for Installation of OPGW (132-500kV) and Long Span
ADSS 31
4.3.3 Standard Requirement for Installation of Short Span ADSS (415 V).............. 31
4.3.4 Standard Requirement for Installation of Duct Optical Fiber Cable ................ 32
4.3.5 Standard Requirement for Installation of Approach Cable ............................. 32
4.3.6 Installation of Fiber Optic Aerial Cable on Low Voltage (LV) Poles ................ 32
4.3.7 Installation of Duct Fiber Optic Cable ............................................................. 33
4.3.8 Installation of Concrete Cable Marker & Cable Route Marker ........................ 37
4.3.9 Installation of Cable Slack ............................................................................... 37
4.3.10 Installation of Manhole .................................................................................... 37
4.3.11 Installation of Splice Closure ........................................................................... 37
4.3.12 Standard Requirement for Jointing Of Optical Cable ...................................... 38
4.3.13 Standard Requirement for Installation of OPGW Repair/Patch Rods............. 38
4.3.14 Yoke plate installation guide ........................................................................... 39
4.3.15 All Dielectric Self Supporting (ADSS) Fiber Optic Cable Sagging Guideline .. 39
4.3.16 Fiber Termination at Substation ...................................................................... 39
4.3.17 Permit to Work (PTW) and Safety Precautions ............................................... 39
4.4 Signal Cable ..................................................................................................... 39
4.4.1 Type of Signal Cable ....................................................................................... 39
4.5 Control Cable ................................................................................................... 40
4.5.1 Type of Control Cable ..................................................................................... 40
4.5.2 Multicore Cable ............................................................................................... 41
4.5.3 Multipair Copper Cable for Current Differential Protection Relay ................... 41
5. SDH Multiplexer Equipment ............................................................................. 41
5.1 Introduction....................................................................................................... 41
5.2 Standards ......................................................................................................... 41
5.3 Hierarchy .......................................................................................................... 42
5.4 Equipment Architecture .................................................................................... 42
5.5 SDH Multiplexer Features ................................................................................ 43
5.6 Switch ............................................................................................................... 43
5.7 Optical Amplifier/Booster Unit .......................................................................... 43
5.8 Regenerator ..................................................................................................... 43
5.9 Construction ..................................................................................................... 43
5.10 Power Supply ................................................................................................... 43
5.11 Protection ......................................................................................................... 43
5.12 Synchronization ................................................................................................ 44
5.13 Data Communication Channels ....................................................................... 44
5.14 Alarm Facilities ................................................................................................. 44
Page 5 of 101
5.15 Loopback Features .......................................................................................... 44
5.16 Local Management Interface............................................................................ 44
5.17 Optical Line Terminal Interface ........................................................................ 44
5.18 Access Interfaces ............................................................................................. 44
5.19 Synchronization Interface ................................................................................. 45
5.20 Network Management Interface ....................................................................... 45
5.21 Auxiliary Data Channel Interface...................................................................... 45
5.22 Engineering Order Wire Interface .................................................................... 45
5.23 Alarm Interface ................................................................................................. 45
5.24 Digital Distribution Frame ................................................................................. 45
5.25 Inspection and Testing ..................................................................................... 45
5.26 Recommended SDH Multiplexer Equipment Optical Connectivity Practice and
Testing 45
6. UTILITY SDH Equipment .................................................................................. 46
6.1 Introduction....................................................................................................... 46
6.2 Standards ......................................................................................................... 46
6.3 Hierarchy .......................................................................................................... 47
6.4 Equipment Architecture .................................................................................... 47
6.5 UTILYTY SDH Equipment Features ................................................................ 48
6.6 Switch ............................................................................................................... 48
6.7 Optical Amplifier/Booster Unit .......................................................................... 48
6.8 Regenerator ..................................................................................................... 48
6.9 Construction ..................................................................................................... 48
6.10 Power Supply ................................................................................................... 49
6.11 Protection ......................................................................................................... 49
6.12 Synchronization ................................................................................................ 49
6.13 Data Communication Channels ....................................................................... 49
6.14 Alarm Facilities ................................................................................................. 49
6.15 Loopback Features .......................................................................................... 50
6.16 Local Management Interface............................................................................ 50
6.17 Optical Line Terminal Interface ........................................................................ 50
6.18 Access Interface ............................................................................................... 50
6.19 Synchronization Interface ................................................................................. 51
6.20 Network Management Interface ....................................................................... 52
6.21 Alarm Interface ................................................................................................. 52
6.22 Digital Distribution Frame ................................................................................. 52
6.23 Inspection and Testing ..................................................................................... 52
7. Wavelength Dense Multiplexing (WDM) .......................................................... 53
7.1 Introduction....................................................................................................... 53
7.1.1 Concept ........................................................................................................... 53
7.1.2 Type of WDM .................................................................................................. 53
7.2 Standards ......................................................................................................... 53
7.3 Equipment Architecture .................................................................................... 54
7.4 DWDM Features............................................................................................... 54
7.5 Construction ..................................................................................................... 55
7.6 Power Supply ................................................................................................... 55
7.7 Protection ......................................................................................................... 55
Page 6 of 101
7.7 Control or Processor Unit ................................................................................. 55
7.8 Optical Amplifier Unit (if required) .................................................................... 55
7.9 Multiplexer De-multiplexer Unit ........................................................................ 55
7.10 Transponders ................................................................................................... 56
7.11 Optical Supervisory Channel (OSC) ................................................................ 56
7.12 Local Management Interface............................................................................ 56
7.13 Network Management Interface ....................................................................... 56
7.14 User Interface ................................................................................................... 56
7.15 Alarm Facilities ................................................................................................. 56
7.16 Loopback Features .......................................................................................... 56
7.17 Inspection and Testing ..................................................................................... 56
7.18 Extra-Long Haul Links ...................................................................................... 57
8. IP-Network......................................................................................................... 57
8.1 Introduction....................................................................................................... 57
8.2 WAN (Wide Area Network) .............................................................................. 63
8.3 LAN (Local Area Network) ............................................................................... 71
9. PDH Optical Line Terminal Equipment and Higher Order Multiplexer
Equipment .............................................................................................................. 72
9.1 Introduction....................................................................................................... 72
9.2 Hierarchy .......................................................................................................... 72
9.3 Optical Line Terminal Equipment Features ...................................................... 72
9.4 Third Order Multiplex Equipment ..................................................................... 72
9.5 Second Order Multiplex Equipment ................................................................. 72
9.6 Equipment Architecture .................................................................................... 72
9.7 Alarm and Supervisory Facilities ...................................................................... 73
9.8 Loopback Features .......................................................................................... 73
9.9 Local Management System .............................................................................. 73
9.10 Network Management Interface ....................................................................... 73
10. Access Multiplexer Equipment ........................................................................ 73
10.1 Introduction....................................................................................................... 73
10.2 Construction ..................................................................................................... 73
10.3 Primary Multiplexer Equipment (PMUX) .......................................................... 73
10.4 Digital Add Drop Multiplexer Equipment (ADM) ............................................... 74
10.5 Digital Cross Connect Multiplexer Equipment (DXC)....................................... 74
10.6 Access Multiplexer Equipment Timing Signal .................................................. 74
10.7 Voice Frequency Channel Unit ........................................................................ 74
10.8 PCM Subscriber Unit ........................................................................................ 74
10.9 Function for PCM Subscriber Unit on Exchange Side ..................................... 74
10.10 Function for PCM Subscriber Unit on Subscriber Side .................................... 74
10.11 V.24/V.28 Asynchronous Data Channel Unit (DIU 1) ...................................... 74
10.12 Synchronous 64kbit/s G.703 Co-directional Data Channel Unit (DIU 2) ......... 74
10.13 Synchronous n x 64kbit/s V.35 Data Channel Unit (DIU 3) ............................. 75
10.14 Ethernet Data Channel Unit (DIU 4) ................................................................ 75
10.15 Main Distribution Frame (MDF) ........................................................................ 75
10.16 Digital Distribution Frame (DDF) ...................................................................... 75
10.17 Local Access .................................................................................................... 75
Page 7 of 101
10.18 Network Management Interface (NMS) ........................................................... 75
11. Digital Teleprotection Equipment (TPE).......................................................... 76
11.1 Introduction....................................................................................................... 76
11.2 Uses of TPE ..................................................................................................... 76
11.3 Number of TPEs ............................................................................................... 76
11.4 TPE Configuration ............................................................................................ 76
11.5 Number of PSE Commands ............................................................................. 76
11.6 TPE Scheme Configurations ............................................................................ 77
11.7 TPE Scheme for 132kV System Using PDH Equipment ................................. 77
11.8 TPE Scheme for 132kV System Using SDH Equipment ................................. 77
11.9 TPE Scheme for 132kV System Using UTILITY SDH Equipment ................... 78
11.10 TPE Scheme for 275kV System Using PDH Equipment ................................ 78
11.11 TPE Scheme for 275kV System Using SDH Equipment ................................. 79
11.12 TPE Scheme for 275/500kV System Using UTILITY SDH Equipment ............ 79
11.13 TPE Scheme for 500kV System Using PDH Equipment ................................. 80
11.14 TPE Scheme for 500kV System Using SDH Equipment ................................. 80
11.15 SNCP for Protection Scheme for 500kV System Using SDH Equipment ....... 81
11.16 Number of PSE Commands ............................................................................. 81
11.17 Equipment Mounting ........................................................................................ 81
11.18 Channel Fail ..................................................................................................... 81
11.19 Command Input ................................................................................................ 81
11.20 Command Output ............................................................................................. 82
11.21 Electronic Counters or Internal Registers ........................................................ 82
11.22 Transmission Time ........................................................................................... 82
11.23 Equipment Addressing ..................................................................................... 82
11.24 Alarms .............................................................................................................. 82
11.25 Power Supply Variations .................................................................................. 82
11.26 Command filtering and extension..................................................................... 82
11.27 Current Differential (CD) .................................................................................. 82
11.27.1 Channel Interface (for CD) .............................................................................. 82
11.27.2 Signal Cable Length ........................................................................................ 83
11.27.3 Multipair Copper Cable for Current Differential Protection Relay ................... 83
11.27.4 Fiber Optic Cable for Current Differential Protection Relay .......................... 83
12. 48 VDC Power System...................................................................................... 83
12.1 Introduction....................................................................................................... 83
12.2 Dual System Connectivity ................................................................................ 83
12.2.1 Nokia PDH........................................................................................................ 84
12.2.2 SAFN PDH ....................................................................................................... 84
12.2.3 Overall Dual DC Connectivity........................................................................... 85
12.3 Switch Mode Rectifier (SMR) System .............................................................. 86
12.3.1 Type and Capacity ........................................................................................... 86
12.3.2 Rectifier AC Source .......................................................................................... 86
12.3.3 DC System Earthing ......................................................................................... 87
12.3.4 Operating Temperature .................................................................................... 87
12.3.5 Module Protection ............................................................................................ 87
12.3.6 Local Access .................................................................................................... 87
12.3.7 Remote Monitoring ........................................................................................... 87
Page 8 of 101
12.3.8 Indication and Alarm Facilities ......................................................................... 87
12.3.9 Float Charge..................................................................................................... 88
12.3.10 Low Voltage Disconnect Value ........................................................................ 88
12.3.11 Upgradeability .................................................................................................. 88
12.3.12 Energy Efficiency ............................................................................................. 88
12.3.13 SMR System Configuration .............................................................................. 88
12.3.14 SMR Cabinet .................................................................................................... 89
12.3.15 DC Distribution Panel ....................................................................................... 89
12.3.16 DC Termination Block ...................................................................................... 90
12.3.17 Portable Charger .............................................................................................. 90
12.4 Battery .............................................................................................................. 90
12.4.1 Introduction....................................................................................................... 90
12.4.2 Design .............................................................................................................. 90
12.4.3 Battery Capacity ............................................................................................... 91
12.4.4 Switch-fuse Isolator .......................................................................................... 91
12.4.5 Battery Rack ..................................................................................................... 92
12.4.6 Color Code for Polarity and Cable ................................................................... 92
12.4.7 Terminal ........................................................................................................... 92
12.4.8 Installation ........................................................................................................ 92
12.4.9 Battery Cable.................................................................................................... 92
12.4.10 Battery Bank Replacement .............................................................................. 93
12.4.11 Discharge Test Ratio (DTR) Definition ............................................................. 93
12.4.12 Standby Time (ST) Definition ........................................................................... 93
12.4.13 Battery Disposal ............................................................................................... 94
12.4.14 Battery Disposal ............................................................................................... 94
Appendix A: Recommended Room Layout for 132kV and 275/500kV
Substations............................................................................................................. 95
Appendix B: Guideline for Optical Fiber Site Acceptance Test .......................... 96
Appendix C: TEMPLATE TO CALCULATE SPAN EQUIVALENT BETWEEN
SUSPENSION TOWER WITH YOKE PLATE INSTALLATION AND TENSION ...... 98
Appendix D: Optical Fibre & Cable Characteristics and Power Budget
Calculation .............................................................................................................. 99
Page 9 of 101
Acknowledgement
The permanent working group would like to thank the people, from various departments within
ICT who have contributed either directly or indirectly in drafting, finalizing and updating this
valuable document.
The committee also significantly values the comments and contributions from other TNBs
Divisions.
Page 10 of 101
References
Page 11 of 101
List of Tables
List of Figures
Page 12 of 101
Figure 6: Telecommunication Room Boundary ........................................................................ 21
Figure 7 : Telecommunication Room Facilities ........................................................................ 22
Figure 8 : MDF Arrangement in SDH and PDH Equipment ..................................................... 24
Figure 9: Fiber Optic Cables Used in TNB ............................................................................... 27
Figure 10: OPGW Configuration for 132/275/500 kV New Transmission Line to New or
Existing Substation .................................................................................................. 28
Figure 11: OPGW/ADSS Cable Configuration for 132 kV Single Circuit Loop-in-out into
Existing Double Circuit Line
29
Figure 12: OPGW/ADSS Cable Configuration for 275 kV Single Circuit Loop-in-out into
Existing Double Circuit Line ..................................................................................... 30
Figure 13: OPGW/ADSS Cable Configuration for 132/275 kV Double Circuit Loop-in-out Into
Existing Double Circuit Line ..................................................................................... 30
Figure 14: Documentation Required for New Fiber Optic Link ................................................. 31
Figure 15: Installation of Duct Optical Cable ............................................................................ 34
Figure 16: HDPE Corrugated Pipe Fiber Optic and Power Cable for 33kV Laid in Ground on
Road ....................................................................................................................... 36
Figure 17: HDPE Corrugated Pipe Fiber Optic and Power Cable for 33kV Laid in Ground on
Road Shoulder ........................................................................................................ 36
Figure 18: Components of DWDM System .............................................................................. 55
Figure 19: IP-MPLS Network Hierarchy Diagram ..................................................................... 58
Figure 20 : TNB IP-MPLS Connectivity .................................................................................... 58
Figure 21: Tier-1 Drawing ......................................................................................................... 59
Figure 22: Tier-2 Drawing ......................................................................................................... 60
Figure 23: Tier-3 Drawing ......................................................................................................... 60
Figure 24: Tier-4 Drawing ......................................................................................................... 61
Figure 25: Concept of the VRF Feature Diagram ..................................................................... 63
Figure 26: LAN Equipment Configuration for Users More Than 200 ....................................... 63
Figure 27: LAN Equipment Configuration for Users Less Than 200 ........................................ 64
Figure 28: TPE scheme configuration for 132 kV System Using PDH Equipment .................. 77
Figure 29: TPE scheme configuration for 132 kV System Using SDH Equipment .................. 77
Figure 30: TPE scheme configuration for 132 kV System Using UTILITY SDH Equipment .... 78
Figure 31: TPE scheme configuration for 275 kV System Using PDH Equipment .................. 78
Figure 32: TPE scheme configuration for 275 kV System Using SDH Equipment .................. 79
Figure 33: TPE scheme configuration for 275/500 kV System Using UTILITY SDH
Equipment ............................................................................................................. 79
Figure 34: TPE scheme configuration for 500 kV System Using PDH Equipment .................. 80
Figure 35 : TPE scheme configuration for 500 kV System Using SDH Equipment ................. 80
Figure 36 : SNCP for Protection Scheme for 500kV System Using SDH Equipment .............. 81
Figure 37: Termination on Digital Distribution Frame for 2Mbps G.703 ................................... 83
Figure 38 : Dual DC system connectivity for Nokia PDH ......................................................... 84
Figure 39: Dual DC System for SAFN-S PDH .......................................................................... 84
Figure 40 : Dual DC System Connectivity (Single DB) ............................................................. 85
Figure 41: Dual DC System Connectivity (Dual DB) ................................................................ 85
Figure 42: Configuration of Single DC System for Offices and Substations (below 132kV) .... 88
Figure 43: Configuration of Dual SMR System for All New Substation (132kV and above) .... 89
Page 13 of 101
Glossary
DTMF Dual Tone Multi Frequency LCAS Link Capacity Adjustment Scheme
Page 14 of 101
LVD Low Voltage Disconnect RSOH Repeater Section Overhead
Telecommunication Management
PCM Pulse Code Modulation TMN
Network
PSE Protection Signaling Equipment VRLA Valve Regulated Seal Lead Acid
Page 15 of 101
1. Introduction
1.3 Responsibility
Technical Support Services (TeSS) Section, Telecommunication Infrastructure
Management Department (TIM), ICT Division is the custodian of this document.
General Manager
Telecommunication Infrastructure Management Department (TIM),
ICT Division
Level 12, Bangunan Dua Sentral
No 8, Jalan Tun Sambanthan
50470 Brickfields
Kuala Lumpur
Tel No: 03-2180 2319
Fax No: 03-2180 2200
Page 16 of 101
2. General Synchronization Guideline
2.1 Introduction
a. To prevent transmission errors in a SDH network, the SDH equipment clock shall
be synchronized to a high precision Primary Reference Clock (PRC) unit that
conforms to ITU-T Recommendation G.811 (Stratum 1).
b. PRC shall be the highest level (Level 1) of synchronization in the SDH transmission
network.
c. Synchronization Supply Unit (SSU) shall be the second level (Level 2) of
synchronization.
d. SSU shall conform to ITU-T Recommendation G.812 (Stratum 2).
e. Local Node clock (also known as internal clock) shall be the third level (Level 3) of
synchronization.
f. Local Node clock shall conform to ITU-T Recommendation G.813 (Stratum 3).
g. TNBs synchronization hierarchical structure is shown in Figure 1.
LEVEL 1
STRATUM 1 (G.811)
PRC AT NLDC PRC AT COIT
(MASTER) (SLAVE)
LEVEL 2
STRATUM 2 (G.812)
LEVEL 3
STRATUM 3 (G.813)
2.2 Standards
The synchronization network shall comply with the latest revision of the following ITU-
T standard and recommendation.
Page 17 of 101
ITU-T Standard Description
Max. 10 SSU
Page 18 of 101
2.4 SDH/PCM Access Node Synchronization
a. PCM access nodes shall receive clock from the SDH node where available. This is
illustrated in Figure 3 below.
Int. Rx
PCM PCM
Timing Direction
Internal Clock
SDH SDH
Int. Rx
PCM PCM
Timing Direction
Sync cable
SSU SDH SDH SDH
Rx
Ext. Int.
PDH PDH
PCM PCM
PCM PCM
Timing Direction
Page 19 of 101
2.5 GNSS Based Synchronous Supply Unit (SSU)
a. Global Navigation Satellite System (GNSS) based synchronous supply units (SSU)
will provide network synchronization clock sources for SDH and PDH networks,
cross-connect and PBX equipment.
b. The equipment shall produce timing signals that comply with ITU-T
Recommendations G.811.
c. The SSU can be mounted in the same rack as the SDH equipment or in an
independent 19 rack.
d. The SSU shall have external alarm indication facility.
e. The SSU shall have at least one (1) voltage free alarm contact for remote
monitoring purposes.
f. The SSU shall have at least two (2) synchronization 2 MHz inputs and ten (10)
2MHz synchronization outputs.
g. The SSU shall have at least two (2) -48VDC power supply inputs. The DC Power
supply inputs shall be connected to two different power supply sources.
h. The GNSS receiver shall be equipped with transient voltage surge suppressor to
protect the clock from transient voltage surge coming from the antenna.
i. The GNSS antenna shall also be equipped with lightning arrestor whenever
necessary.
Page 20 of 101
3. Telecommunication Room General
Requirements
3.1 Introduction
Telecommunication Room is defined as a room where the telecommunication and
associated equipment are installed to provide telecommunications services for TNB.
Joint box/
Splice ODP
Closure
Telecommunication Equipment
48V DC
System
Telemetering
Fault Recorder
Power Quality
WAIS/WAMS
MDF/Ethernet DDF/Terminal
CCTV
Patch Panel Block
SIMS
ISMS
Intranet
LEGEND
Comm Box
ICTs equipment/panel
Customers equipment/panel
ICTs cabling
Customers cabling
Page 21 of 101
e. Integrated Communications Equipment (ICE)
f. Primary Reference Clock (PRC)
g. Synchronization Supply Unit (SSU)
h. MPLS Router
i. Switch
j. IP-PBX /PABX
k. 48V DC System
l. Modem
m. Radio/wireless equipment
n. Digital Teleprotection Equipment
o. Optical Distribution Panel
p. Ethernet Patch Panel
q. Terminal Block for RTU/Protection Relay
r. Digital Distribution Frame (DDF)/Main Distribution Frame (MDF)
s. Telephone Sets
Temperature AC Power
Raised Floors Station Earthing
Sensor Supply
Page 22 of 101
3.6 Room Location in the Building
a. The recommended location of the Telecommunication Room should be next to the
Relay Room to ensure the limitation on length of cable and the teleprotection signal
for current differential protection (CD) scheme is met.
b. For 33kV and 11kV Distribution Substations, the telecommunication equipment
shall be placed in the control room.
c. Floor plan with escape route shall be displayed in the telecommunication room.
275/500 2.0 HP 4
*Room size as dictated by Clause 3.5 above
Table 3: Air Conditioning Unit Cooling Capacity
c. Tray shall be installed under all air conditioning units. Each tray shall be installed
with proper water outlet piping
Page 23 of 101
3.12 Windows in the Room
The windows (if present) in the room must be of tinted glass. This is to reduce sunlight
penetration and prevent it from raising the room temperature.
EPSA 19"
Top Rack Unit S5 S3 S1
S6 S4 S2
1A 2A 3 A 4A 5 A 6A 1 B 2B 3B 4B 5B 6B
STM -1
SYNTH1N ST M- 1
SYNTH1N ST M-1
A21E1 (E1 1-21)
SUB /S UB (1)
W20 (Spare)
W20 (Spare)
DI U1 (1)
DI U1 (2)
I U2 (1)
I U2 (2)
I U2 (3)
I U2 (4)
RING
B PU
NDA
CU
ISA-ES1
CONGI
SERGI
P63E1
P63E1
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
10
1
9
5
CO NT ROL UNIT A
CHANNE L UNIT 1
CHANNE L UNIT 1
NDA
NDA
1 2 3 4 5 1 2 3 4 5
HK A larm A UX Channel S Y NC / E 1 A UX
B lock B lock B lock
HK A larm #1 V. 11 #1
1
S Y NC
HK A larm #2 V. 11 #2
G .703
RS-232
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
2 Mbit /s B lock 2 Mbit / s B lock
1 to 21 E 1 (21 S pare)
TX 1E1 7E 1 S pare
RX 1E 1 7E 1 S pare
Ground Ground
Ground
IU2 (1-2)
IU2 (3-4)
Ground
SDH PDH
Page 24 of 101
c. ODP shall be designed for bottom or top entry, and suitable for indoor use.
d. The ODP shall have the dimension of 42U height, 0.6m width and 0.6m depth with
lockable door.
e. Each direction of transmission line with fiber has a separate 19 patch tray.
f. Each patch tray shall have terminating capacity according to the total number of
cores of the fiber optic cable installed.
g. The ODP shall be installed in TNB substations and offices with fiber optic cable
termination.
Page 25 of 101
3.20 Remote Alarm Facility
a. A remote extension of the alarm indications shall be provided to National Operation
Center (NOC) and the nearest 24 hour manned station or National Load Dispatch
Center (NLDC) via a Remote Alarm Monitoring System or a SCADA Remote
Terminal Unit.
4. Telecommunication Cables
4.1 Introduction
The types of telecommunication cables used in TNBs Telecommunication Network
consist of optical and copper cables.
Page 26 of 101
All-dieletric
Optical Ground Duct Fiber
Self-supporting Approach cable
Wire (OPGW) Optic cable
(ADSS)
275kV Line 1 or 2 48
OPGWa. (Optical
1 275kV/ 132kV
Line 1 and 2 48
1 Ground wire) (quad circuit)
132kV Line 1 or 2 48
33kV Single line 48
500kV NA
275kV 48
Page 27 of 101
No power cable 24/48
5 Indoor Optical Laid in cable riser or
No voltage
Fiber cable tray 24/48
Submarine Laid beside submarine
6 Any voltages 2 X 48
Optical Fiber power cables
Lashed Aerial Wrapped on earth wire
7 Any voltages 48
Cable
Table 4 : Type of Fiber Optic Cables
No optical
Line Line No. of
Type of Tower fiber/
Voltage Configuration OPGW
cable
Double
500 kV PMU to PMU 2 48
Circuit
132/ Single/ Double Table 5
PMU to PMU 1 48
: 275 kV circuit
132/
Quad circuit PMU to PMU 2 48
275 kV
Requirement for New Transmission Line to New or Existing Substation
PMU A PMU B
1 x OPGW
48 Core
Figure 10: OPGW Configuration for 132/275/500 kV New Transmission Line to New or
Existing Substation
c. OPGW and ADSS requirements for existing transmission line to new substation
are summarized in Table 6.
Page 28 of 101
No
Line Type of
Line No. of optical Other
Voltage Tower
Configuration OPGW fiber/ Requirements
cable
Single circuit 3 way splice
Double/
loop-in-out into closure at
132 kV Quad 1 48
existing line with loop-in-out
Circuit
OPGW/ADSS point
Single circuit 2x3 way splice
Double/
loop-in-out into closures at
275 kV Quad 2 48
existing line with loop-in-out
Circuit
OPGW/ADSS point
3 way splice
closure at
Double circuit 1 48
loop-in-out
Double/ loop-in-out into
132/ point
Quad existing line with
275 kV OPGW/ADSS 2x2 way splice
Circuit
closures at
2 48
loop-in-out
point
Single circuit T-off 3 way splice
Double/
132/ into existing line closure at
Quad 1 48
275 kV with loop-in-out
Circuit
OPGW/ADSS point
To complete
optical fiber
Single circuit T-off
installation
Double/ or LILO into
132/ between the
Quad existing line 1 48
275 kV existing line. 3
Circuit without
way splice
OPGW/ADSS
closure at T-
off/LILO point
Table 6 : OPGW Requirement for Existing Transmission Line to New or Existing
Substation
3 way Splice
Closure
PMU A PMU B
New 1 x OPGW
48 Core
PMU C
Figure 11: OPGW/ADSS Cable Configuration for 132 kV Single Circuit Loop-in-
out into Existing Double Circuit Line
Page 29 of 101
3 way Splice
Closure
PMU A PMU B
New 1 x OPGW
48 Core
PMU C
Figure 12: OPGW/ADSS Cable Configuration for 275 kV Single Circuit Loop-in-out into
Existing Double Circuit Line
2 way Splice
Closure
PMU A PMU B
New 1 x OPGW
48 Core
PMU C
Figure 13: OPGW/ADSS Cable Configuration for 132/275 kV Double Circuit Loop-in-out
Into Existing Double Circuit Line
4.2.6 Documentation
Documentations listed in Figure 14 shall be provided for every new fiber optic link.
Page 30 of 101
Drawings
OTDR Records
Information
Page 31 of 101
b. ADSS could be installed point to point without the use of joint box (no
approach/underground cable is required).
Page 32 of 101
1. In every corners, road crossing, and junctions cable should be tensioned with
tension set
2. In one straight line fiber optic cable installation, tension set should be installed
in every five span.
3. 10 meters poles should be used for road crossing line in the event where the
fiber has not enough clearance, angle iron extension should be installed.
4. Cable from overhead installation to underground installation should be
enclosed with GI pipe (3.5m).
5. The cable sagging should be not more than 2% of cable span.
6. GI pipe should be used for bridge, road and drain crossing.
7. Access cable at splice closure should be coiled maximum 1 meter with
maximum five coils.
8. Fiber optic cable should not be installed on wooden pole, pole mounted
transformer and pole with bare conductor.
9. Wooden pole should be changed to concrete pole prior to cable installation.
10. Bare conductor should be changed to ABC conductor prior to cable
installation.
1. The trench depth shall be 1500 mm. The duct shall be placed at 150 mm away
from the trench base. The sand bedding shall be 150 mm below and above the
duct. The width of the trench shall be 300 mm. Please refer to Figure 1 for
more details.
2. The duct shall be made from 100 mm diameter High Density Polyethylene
(HDPE) pipes.
3. In situations where more than one (1) cable needs to be laid, existing 100 mm
HDPE pipe shall be used. The width of the trench shall be 300mm. Figure 14
for more details.
4. The ducts shall be installed in a Class C Galvanized Iron (GI) pipe for road
crossings and bridge crossings. The GI pipe shall be 100 mm diameter.
5. The duct ends shall be sealed with a removable watertight material.
Page 33 of 101
300 mm
300mm
1250 mm
Backfill Earth
Warning Tape
1500mm
> 50 mm
150 mm
Sand
100mm
Duct
150 mm
1. Before the cables are laid, the bottom of the trench shall be filled with sifted/
stone free sand and pinned down to a thickness of 150 mm to form a bed.
2. The duct shall be buried at the same level as the power cables.
3. For single circuit, the width of the trench shall be at least 600mm. As for double
circuit, the width shall be at least 1200mm. Refer to Figure 3 for more details.
4. After the cables are laid, the first 150mm depth of backfill above the cables is
to consist of sifted/ stone free sand over which protective covers are to be
placed.
5. Cable protective reinforced concrete slabs shall be laid to cover the full width
of the trench on top of the first sand filling. The cable protective covers shall be
Page 34 of 101
of reinforced concrete of Grade 20 in accordance to BS 8110 (1997), and
unless otherwise approved, shall be of the following dimensions:
i. 1000mm long x 300 mm wide x 50mm thick- for one circuit of power cables
ii. 1000mm long x 150 mm wide x 50mm thick- for optical fiber/ pilot/ alarm
cables
6. The duct shall be placed at least 150mm from the trench base. The base shall
be filled with stone-free sand of 150mm thickness.
7. Where pipe ducts are required across a road, which may be crossed by
trenching, HDPE Pipe shall be used. These pipes shall be encased in Grade
20 concrete in accordance to BS 8110 with 100mm minimum cover at the top,
bottom and sides and a minimum thickness of 50mm of concrete between
adjacent pipes.
8. For excavation on tar macadam, the duct shall be made from at least 100mm
diameter High Density Polyethylene (HDPE) pipes. These pipes shall be
encased in Grade 20 concrete in accordance to BS 8110 with 100mm minimum
cover at the top, bottom and sides and a minimum thickness of 50mm of
concrete between adjacent pipes. For laying of cables on road, please refer to
Figure 15.
9. For excavation on road shoulder, the duct shall be made from at least 100mm
diameter double wall corrugated High Density Polyethylene (HDPE) pipes. As
for laying of cables on the road shoulder, refer to Figure 16.
10. Where a road may only be crossed by directional drilling (HDD), High Density
Polyethylene (HDPE) Pipe shall be used.
11. After all cables and concrete slabs have been laid, the trenches shall be re-
filled in 150mm layers, each layer being well rammed and consolidated.
12. The conditions or requirements of the road resurfacing structure shall follow as
given by the relevant authority. If no standard is set by the local authority, then
the road resurfacing structure shall follow the existing road condition or 220mm
of crusher run and 75mm of tar macadam. The road reinstatement resurfacing
shall be done by a specialized road resurfacing contractor registered with any
public authority.
13. The duct ends shall be sealed with a removable watertight material.
Page 35 of 101
GROUND LEVEL GROUND LEVEL
75 TAR MACADAM 75
300 300
CRUSHER RUN
475 475
1500
BACKFILLING
BACKFILLING 1500
50 50
CONCRETE SLAB
150 150mm DIS. HDPE DOUBLE 150
150 150
FIBER OPTIC
150 150
SAND BEDDING
100 150 150 100 100 100 100 150 150 100 100 100 150 150 100
1200 600
Figure 16: HDPE Corrugated Pipe Fiber Optic and Power Cable for 33kV Laid in
Ground on Road
300 300
475 475
1500
BACKFILLING
BACKFILLING 1500
50 50
CONCRETE SLAB
150 150mm DIS. HDPE DOUBLE 150
150 150
FIBER OPTIC
150 150
SAND BEDDING
100 150 150 100 100 100 100 150 150 100 100 100 150 150 100
1200 600
Figure 17: HDPE Corrugated Pipe Fiber Optic and Power Cable for 33kV Laid in Ground
on Road Shoulder
Page 36 of 101
4.3.8 Installation of Concrete Cable Marker & Cable Route
Marker
a. Where cables are laid direct in ground, cable route markers (indicating the
direction) shall be provided at intermediate points along the route at not more than
3 metres apart, in handhole/manhole and at all points where trench changes
direction and branches off. Cable route marker shall be made of metal/aluminium
and tied to the cable using steel tie.
b. For installation within TNBs substation, the cable marker shall be placed every 10
meter and wherever there are changes in the cable direction.
c. Where cables are laid direct in ground, cable route markers shall be provided at
intermediate points along the route at not more than 30 metres apart and at all
points where trench changes direction and branches off.
d. For installation with power cable, the cable marker shall be constructed from
concrete and the word TNB CABLE WITH FIBER OPTIC shall be engraved on
the cable marker.
e. For installation without power cable, the cable marker shall be constructed from
concrete and the word TNB FIBER OPTIC shall be engraved on the cable marker.
f. Concrete cable marker shall be placed at not more than 3 metres apart and at all
points where trench changes direction and branches off.
a. Distance between hand holes shall be in the range of 150m - 200m for straight line
or one hand hole at every corner.
b. Manhole shall be of JB 30/JRC 7 or as per requirement by local authorities.
a. Weather proof splice closures/joint boxes shall be mounted at the second cross
arm level of the transmission towers and 3m above the ground on substation
gantry/terminal tower (subjected to alteration). Sufficient spare length of optical
cable shall be provided to facilitate future splicing.
b. The mounting bracket suitable for lattice and tubular tower on installation of splice
closures shall be provided.
c. Downlead optical fiber cables shall be securely fastened to the tower body by
downlead clamps. The distance between clamps shall not be greater than 2m.
Sufficient length of downlead cables shall be provided to facilitate splicing at ground
level.
Page 37 of 101
d. For ADSS cable in high risk (eg: monkey bite) area, cable downlead shall be
protected by suitable non-metallic spiral or tubular cable protectors.
e. At the substations gantry approach cables shall be protected by suitable non-metallic
spiral or corrugated HDPE(20mm) / tubular cable protectors or flexible conduit. The
coiling device suitable for coiling the ADSS and approach cable shall be provided. The
said conduit or protectors end shall be seal with a weather proof sealant.
f. Loop cable at tower splice closure to be coiled 1m diameter vertically inside a
coiling device.
g. In the case of jointing at suspension tower, special bracing set (main angle iron)
need to be installed at the tower body structure where later tension set will be
installed.
Prior to splicing/jointing procedure, the contractor shall measure the loss of the optical
fibers in each section and then proceed to test the fiber splice/joint using two-point
measurement technique. The optical loss measured by OTDR shall not exceed (unless
approved by Engineer) the following requirement: -
a. The rectification of strand breakage for OPGW cables could be done using
repair/patch rods.
b. The installation of OPGW Repair/Patch Rods at the damaged area is
recommended for cases whereby the outer strands are broken, but the fiber optic
links attenuation reading are within the recommended values as per ICT TNBs
Optical Fiber Characteristics Specifications
c. The OPGW Repair/Patch Rods are designed to protect the damaged area of the
OPGW cable, and hence avoiding further damages to the fiber optic cable.
d. The OPGW Repair Rods are ideal for emergency situations, whereby the loose
strands might risk unwinding further and cause unwanted tripping on the existing
transmission lines.
e. For detailed guideline on applying OPGW repair/patch rods on OPGW Cable with
strands breakage please refer to Engineering Guideline ICT/TeSS/GL/3/2013 :
Guideline on applying OPGW repair/patch rods on OPGW Cable with
strands breakage.
Page 38 of 101
4.3.14 Yoke plate installation guide
Installation of Yoke plate on Transmission Suspension tower during OPGW
breakdown must comply with the following conditions:
1. The equivalent span for Yoke plate to be installed on the Suspension Tower
should be the same. This will be determined according to the formula given.
2. Any modification on the tower structure is strictly prohibited.
(Reference: Letter dated 27 Jun 2013 from Ir. Ho Peng Choong, Senior GM
Asset Development Transmission to GM TIM)
Please refer to Appendix C for the template to calculate span equivalent between
suspension tower with yoke plate installation and tension.
Page 39 of 101
No Type Voltage Description No of pairs
500kV
4 cores to be
Underground Pilot Owned by Transmission and
2 275kV reserved for
Cable Distribution
ICTs use
132kV
- Used as data cable from outside
Shielded Twisted
Communication Room
3 Pair (STP) Cable 2/4/5
(Protection application for
Current Differential)
-
Screened Twisted 2 or 8 or 10
4 Used as internal signal cable
Pair or 20
-
Unshielded
Used as data cable inside
5 Twisted Pair (UTP) 4
Communication Room
Cable
- Connectivity to Service provider
Telephone Cable (Telekom) and User 1 or 2
6
(analog/digital trunk)
-
Coaxial Cable
Used as data cable for
7 Unbalanced 75 1
communication equipment
ohm
Table 7: Type of Signal Cable
1 Multicore cable for RTU, SCS and SAS. 7 cores (3 cores used)
Page 40 of 101
4.5.2 Multicore Cable
a. Multicore cable for teleprotection cable is required between Telecommunication
Protection Signaling (TPS) equipment and protection relay.
b. Multicore cable for alarm facilities is to serve remote alarm facilities such as battery
charger, communication failure and common station alarm to or from facia-
indication panel. Alarm facilities shall be supplied at 110V DC or 48V DC.
c. All multicore cable shall be supplied and laid by the user/customer.
5.1 Introduction
a. This chapter describes the guidelines on technical requirements of SDH Multiplexer
Equipment. SDH Multiplexer Equipment shall be known as The equipment
hereafter in this document.
b. The equipment is used for the transmission of digital signals at the ITU-T
Recommended SDH hierarchical bit rates of 155Mbit/s, 622Mbit/s, 2.4Gbit/s,
10Gbit/s over single mode optical fibers in the 1310nm or 1550nm wavelength
windows.
5.2 Standards
The equipment shall comply with the latest revision of the following ETSI and ITU-T
standard and recommendation.
Standard Description
Page 41 of 101
ITU-T G.707,G.708, Bit rate structure, network node interfaces and multiplex
G.709 structures in the Synchronous Digital Hierarchy
5.3 Hierarchy
Table 10 shows SDH Transmission Hierarchy and the line rate associated with it.
Page 42 of 101
5.5 SDH Multiplexer Features
a. The equipment shall have multi service provisioning platform-supporting SDH,
PDH, Ethernet and Packet Based Interfaces.
b. Ethernet over SDH shall support GFP, LCAS and VCAT features in accordance
with ITU-T G.7041 and G.7042 Recommendations.
c. The equipment shall be able to operate as either an add-drop or digital cross
connect multiplexer.
5.6 Switch
a. The equipment shall provide non-blocking, full connectivity and timing transparent
Low and High Order (LO/HO) cross-connections.
b. The equipment switch shall be able to provide cross-connections between line-to-
line, line to access and access-to-access ports at VC-12, VC-3 and VC-4 levels.
c. Concatenation at VC-12 and VC-4 levels shall be available.
d. Virtual concatenation (VCAT) at VC-12 level shall be available.
5.8 Regenerator
STM-1/4/16/64 Regenerator equipment shall be able to extract and regenerate signals
for extra long-haul links when the optical power budget margin as required in TNB
standard is not achieved even by the use of Optical Amplifier/ Booster.
5.9 Construction
The equipment sub rack shall be:
a. Based on IEC 297 for 19 rack or ETSI equipment practice.
b. Compliant with IEC/ ETSI specifications for EMC/ EMI requirements.
c. Equipped with the front access connection frames.
5.11 Protection
The equipment shall be equipped with:
a. Equipment protection.
I. N+1 protection for access interface unit.
II. 1+1 protection for Control or processor unit.
III. 1+1 protection for switch unit.
IV. 1+1 protection for centralized power supply unit.
V. Distributed power supply does not require protection.
b. Network protection employing SNCP for network protections and supporting
1+1 MSP features.
Page 43 of 101
5.12 Synchronization
a. The equipment shall have the capability of supporting SSM and prioritization of
timing sources.
b. The equipment shall have the following synchronization sources:
I. Internal
II. External
III. Line
IV. Tributary
c. The equipment shall comply with ITU-T G.813 recommendation for internal clock
source.
d. The equipment shall be able to operate under the following modes;
I. Freerunning mode
II. External-timing mode
III. Holdover mode
IV. Line mode
Page 44 of 101
5.19 Synchronization Interface
The equipment shall have input and output synchronous timing interfaces.
Page 45 of 101
6. UTILITY SDH Equipment
6.1 Introduction
a. This chapter describes the guidelines on technical requirements of UTILITY SDH
Equipment.
b. The UTILITY SDH Equipment will be used primarily to serve critical operational
services such as teleprotection services, operational telephone, SCADA, wide area
protection, fault recorder, metering, power quality and administrative services such
as email, internet, intranet and other Ethernet services.
c. The UTILITY SDH shall be able to function as add-drop multiplexers, digital cross-
connect multiplexers and terminal multiplexers. The equipment shall be used for
transmission of digital signals at the ITU-T Recommended SDH hierarchical bit rate
of at least 155Mbit/s over single mode optical fiber in the 1310nm or 1550nm
wavelength window.
6.2 Standards
The equipment shall comply with the latest revision of the following standard and
recommendation.
Standard Description
ITU-T G.652 Characteristics of a single-mode optical fiber and cable
Characteristics of a cut-off shifted, single-mode optical fiber
ITU-T G.654
and cable
Physical/electrical characteristics of hierarchical digital
ITU-T G.703
interfaces
Synchronous frame structures used at 1544, 6312, 2048,
ITU-T G.704
8448 and 44 736 kbit/s hierarchical levels
Network node interface for the Synchronous Digital
ITU-T G.707
Hierarchy (SDH)
Sub STM-0 network node interface for the Synchronous
ITU-T G.708
Digital Hierarchy (SDH)
ITU-T G.781 Synchronization layer functions
Types and general characteristics of Synchronous Digital
ITU-T G.782
Hierarchy (SDH) multiplexing equipment
Characteristics of Synchronous Digital Hierarchy (SDH)
ITU-T G.783
equipment functional blocks
Management aspects of Synchronous Digital Hierarchy
ITU-T G.784
(SDH) transport network elements
Timing characteristics of SDH equipment Slave Clocks
ITU-T G.813
(SEC)
Timing requirements of slave clocks suitable for use as node
ITU-T G.812
clocks in synchronization networks
Error performance of an international digital connection
ITU-T G.821 operating at a bit rate below the primary rate and forming
part of an Integrated Services Digital Network
The control of jitter and wander within digital networks which
ITU-T G.823
are based on the 2048 kbit/s hierarchy
Page 46 of 101
The control of jitter and wander within digital networks which
ITU-T G.825
are based on the Synchronous Digital hierarchy (SDH)
End-to-end error performance parameters and objectives for
ITU-T G.826
international, constant bit-rate digital paths and connections
Optical interfaces for equipments and systems relating to the
ITU-T G.957
synchronous digital hierarchy
ITU-T Q.811 Lower layer protocol profiles for the Q and X interfaces
ITU-T Q.812 Upper layer protocol profiles for the Q and X interfaces
Environmental Engineering (EE); Environmental conditions
ETSI ETS 300 019
and environmental tests for telecommunications equipment;
Transmission and Multiplexing (TM); Synchronous Digital
ETSI ETS 300 147
Hierarchy (SDH); Multiplexing structure
Transmission and Multiplexing (TM); Generic requirements
ETSI ETS 300 417
of transport functionality of equipment;
Electromagnetic compatibility and Radio spectrum Matters
ETSI 300 386 (ERM); Telecommunication network equipment;
Electromagnetic Compatibility (EMC) requirements
IEC 61000 Electromagnetic compatibility (EMC)
ITU-T G.7041 Generic framing procedure
Link capacity adjustment scheme (LCAS) for virtual
ITU-T G.7042
concatenated signals
IEEE Standard for N Times 64 Kilobit per Second Optical
IEEE C37.94-2002 Fiber Interfaces between Teleprotection and Multiplexer
Equipment
IEEE Standard Environmental and Testing Requirements
IEEE 1613-2003 for Communications Networking Devices in Electric Power
Substations
Communication networks and systems in substations - Part
IEC 61850-3:2002 3: General requirements
6.3 Hierarchy
Table 12 shows UTILITY SDH Transmission Hierarchy and the line rate associated
with it.
Page 47 of 101
b. The UTILITY SDH shall consist the following plug-in units:
I. Control Unit
II. Cross Connection Unit
III. Synchronization Unit
IV. Line Terminal Unit
V. Access interface Unit
VI. Power Supply Unit
VII. Equipment management function
VIII. Alarm supervision function
c. The equipment shall be modular in design and support hot swapping of modules.
6.6 Switch
a. The equipment shall provide non-blocking, full connectivity and timing transparent
Low and High Order (LO/HO) cross-connections.
b. The equipment switch shall be able to provide cross-connections between line-to-
line, line to access and access-to-access ports at DS0 (64kbps), VC-12, VC-3 and
VC-4 levels.
c. The cross-connect switch shall also support the unidirectional point-to-point and bi-
directional point-to-point connection.
d. Concatenation at VC-12 and VC-4 levels shall be available.
e. Virtual concatenation (VCAT) at VC-12 level shall be available.
a. Optical amplifiers or boosters shall be used for extra-long haul links when the
optical power budget margin as required in TNB standard is not achieved.
b. The optical fiber characteristic and power budget calculation is attached in
Appendix D.
6.8 Regenerator
STM-1/4/16 Regenerator equipment shall be able to extract and regenerate signals for
extra long-haul links when the optical power budget margin as required in TNB standard
is not achieved even by the use of Optical Amplifier/ Booster.
6.9 Construction
Page 48 of 101
I. Based on IEC 60297 for 19 rack or ETSI ETS 300 119 equipment practice.
II. Compliant with IEC/ ETSI specifications for EMC/ EMI requirements.
III. Equipped with the front access connection frames.
IV. The Utility SDH sub rack, main distribution frame (MDF), digital distribution
frame (DDF), alarms indicators, Protection Signaling Equipment sub rack and
all other interfaces shall be housed in the same rack.
6.11 Protection
The equipment shall be equipped with:
a. Equipment protection.
I. 1+1 protection for control or processor unit.
II. 1+1 protection for switch unit.
III. 1+1 protection for centralized power supply unit.
IV. Distributed power supply does not require protection.
b. Network protection employing SNCP for network protections, supporting 1+1
MSP features and LCAS for Ethernet protection.
6.12 Synchronization
a. The equipment shall have the capability of supporting SSM and prioritization of
timing sources.
b. The equipment shall have the following synchronization sources:
I. Internal
II. External
III. Line
IV. Tributary
c. The equipment shall comply with ITU-T G.813 recommendation for internal clock
source.
d. The equipment shall be able to operate under the following modes:
I. Freerunning mode
II. Through-timing mode
III. External-timing mode
IV. Holdover mode
V. Line-timing mode
The equipment shall have data communication channels for transmission of network
management information using D1-D3 and D4-12 bytes of the RSOH and/or MSOH
bytes. Interworking between different vendor equipment shall be supported.
The equipment shall have individual alarm indications on each unit and common alarm
displayed on the rack alarm unit.
Page 49 of 101
6.15 Loopback Features
a. The equipment shall have loopback features for testing and maintenance
purposes.
b. The configuration shall be software configurable.
The equipment shall provide local connection for human machine interface for service
and maintenance.
a. Optical Line terminal unit shall provide the aggregate interface for transmission at
STM-1 and STM-4 synchronous level.
b. Optical connectors shall be FC/PC or LC/PC type suitable for single mode optical
fibers complying with ITU-T Recommendations G.652, G.653 and G.654.
c. The equipment shall be provided with ALS and restart facilities to comply with ITU-
T G.958 Recommendations.
a. 2Mbit/s
The 2Mbit/s electrical characteristics should comply with the following
specification:
Descriptions Specifications
Type of Interface Electrical, according to ITU-T
Rec.G703
Bit Rate 2048 kbit/s
Code HDB3
b. 34/45Mbit/s
The 34Mbit/s electrical characteristics should comply with the following
specification:
Descriptions Specifications
Type of Interface Electrical, according to ITU-T
Rec.G703
Bit Rate 34368 kbit/s
Code HDB3
Descriptions Specifications
Type of Interface Electrical, according to ITU-T
Rec.G703 and to ANSI TS 102 Rec.
Bit Rate 44.736 kbpss
Code B3ZS
Page 50 of 101
c. 10/100/1000 Ethernet Interfaces
The 10/100 Ethernet interfaces should comply with the following specification:
Descriptions Specifications
Type of Interface Electrical, full compliant to IEEE
802.3 standard, 10Base-T and
100Base-T
Bit Rate Autosensing: 10Mb/s and 100Mb/s
Connector RJ45
The 1000 Ethernet interfaces should comply with the following specification:
Descriptions Specifications
Type of Interface Electrical, full compliant to IEEE
802.3 standard, 10Base-T,
100Base-T and 1000Base-T
Bit Rate 1.25Gbit/s
Connector RJ45
d. C37.94 Interface
C37.94 interfaces should comply with the following specification:
Descriptions Specifications
Type of Interface Comply with IEEE Std C37.94
2002
Bit Rate N X 64kbps
Connector ST or BFOC/2.5
e. FXO/FXS Interface
f. RS232 Interface
Descriptions Specifications
Type of Interface Comply with EIA/TIA232-C or ITU-T
V.24 standard
Bit Rate 9.6kbps to 19.2kbps
Signal level 5 to 15 volts
Descriptions Specifications
Type of Interface Comply with ITU-T G.703
Bit Rate 2048kHz or 2048kbps
Page 51 of 101
6.20 Network Management Interface
a. The equipment shall have Q3 or open interface standard for northbound NMS
Interface.
b. The equipment shall comply with TMN standards as stated in M.3000 series ITU-
T Recommendations Q.811/Q.812 or Open Standard, which is internationally
accepted.
Page 52 of 101
7. Wavelength Dense Multiplexing (WDM)
7.1 Introduction
7.1.1 Concept
Wavelength-division multiplexing (WDM) is a technology which multiplexes a
number of optical carrier signals onto a single optical fiber by using different
wavelengths (i.e., colors) of laser light.
7.2 Standards
The equipment shall comply with the latest revision of the following ETSI and ITU-T
standard and recommendation.
Standard Description
Characteristics of a single-mode optical fibre and cable
ITU-T G.652
Optical safety procedures and requirements for optical transport
ITU-T G.664
systems
Transmission characteristics of optical components and
ITU-T G.671
subsystems
Physical transfer functions of optical networks elements
ITU-T G.680
ITU-T G.692 Optical interfaces for multichannel systems with optical
amplifiers
Spectral grids for WDM applications: DWDM frequency grid
ITU-T G.694.1
ITU-T G.697 Optical monitoring for DWDM systems
Multichannel DWDM applications with single channel optical
ITU-T G.698.1
interfaces
Amplified multichannel DWDM applications with single channel
ITU-T G.698.2
optical interfaces
ITU-T G.707 Network node interface for the synchronous digital hierarchy
(SDH)
Page 53 of 101
ITU-T G.709 Interfaces for Optical Transport Network (OTN)
Architecture of optical transport networks
ITU-T G.872
Management aspects of the optical transport network element
ITU-T G.874
Optical interfaces for equipments and systems relating to the
ITU-T G.957
synchronous digital hierarchy
Principles for a telecommunications management network
ITU-T M.3010
ETSI ETS 300 019 Environmental Conditions and environmental tests for
telecommunications equipment.
ETSI EN 300 386 Electromagnetic compatibility and Radio spectrum Matters
(ERM);
Telecommunication network equipment;
ElectroMagnetic Compatibility (EMC) requirements
ETSI EN 300 132-2 Equipment Engineering (EE);Power supply interface at the input
to telecommunications equipment;Part 2: Operated by direct
current (dc)
Page 54 of 101
7.5 Construction
The equipment sub rack shall be:
I. Based on IEC 297 for 19 rack or ETSI equipment practice.
II. Compliant with IEC/ ETSI specifications for EMC/ EMI requirements.
III. Equipped with the front access connection frames.
7.7 Protection
The equipment shall be equipped with:
a. Equipment protection:-
I. 1+1 protection for Control or processor unit.
II. 1+1 protection for centralized power supply unit.
III. Distributed power supply does not require protection.
Terminal A Terminal B
Transponder
Transponder
Mux-Demux
Mux-Demux
Interface
Interface
Optical Line Amplifiers Optical
Amplifier Amplifier
7.9.1 Multiplexer
The multiplexer contains a wavelength-converting transponder for each data
signal and an optical multiplexer. Each wavelength-converting transponder
receives an optical data signal from the client-layer, such as Synchronous
optical networking [SONET /SDH] or another type of data signal, converts this
signal into the electrical domain and re-transmits the signal at a specific
wavelength using a laser. These data signals are then combined together into
a multi-wavelength optical signal using an optical multiplexer, for transmission
over fiber
Page 55 of 101
7.9.2 De-Multiplexer
The de-multiplexer consisting of an optical de-multiplexer and one or more
wavelength-converting transponders separates the multi-wavelength optical
signal back into individual data signals and outputs them on separate fibers for
client-layer systems (such as SONET/SDH).
7.10 Transponders
The Equipment shall support transponders to translate the transmit wavelength of a
client-layer signal into one of the DWDM system's internal wavelengths in the 1,550 nm
band.
Page 56 of 101
7.18 Extra-Long Haul Links
The following methods to maintain optical signal integrity are to be used for extra-long
haul links:
7.18.1 Regenerator
Regenerator equipment shall be able to extract and regenerate signals for
extra long-haul links when the optical power budget margin as required is not
achieved by the use of built-in equipments optical amplifier.
8. IP-Network
8.1 Introduction
a. This chapter describes the guidelines on technical requirements of IP Network in
TNB.
b. IP Network can be divided by two:-
I. WAN (Wide Area Network).
II. LAN (Local Area Network).
c. WAN Network adopts IP Multiprotocol Label Switching (MPLS) technology. The
WAN network comprises of the following routers:
Provider Edge (PE) or Label A MPLS router that operates at the edge of an MPLS
Edge Router (LER) network and acts as the entry and exit points for the
network. It is responsible to push an MPLS label onto
an incoming packet and pop it off the outgoing packet.
Customer Edge (CE) The router at the customer premises that is connected
to the provider edge of a service provider IP/MPLS
network.
d. LAN (Local Area Network) adopts Ethernet technology. The LAN comprise of wired
and wireless network.
Page 57 of 101
I. Wired The wired network consists of Core, Distribution and Access
Switches.
II. Wireless The wireless network contains of Bridge and Access.
IP - Network
WAN LAN
(Wide Area Network) (Local Area Network)
Page 58 of 101
c. Standard location for the routers:-
Connectivity
No. Link Physical Bandwidth
1 PP Optical Fiber via DWDM network 1Gbps
e. Design:-
I. The design of IP-MPLS based on the Tier 1, Tier 2, Tier 3 and Tier 4:-
1. Tier-1 site consists of one P router and two PE routers for the MPLS
VPN services. There are redundant GE links created between the PE
routers and the Layer 3 switches in the same Tier-1 site for the access
to the local Data Center.
Page 59 of 101
2. Tier-2 site consists of one PE router, which is responsible to
aggregate all connections from CE routers of branch
offices/substations in the region.
Page 60 of 101
Figure 24: Tier-4 Drawing
II. Routing protocol for IP MPLS using OSPF (Open Shortest Path First)
III. IP MPLS network scalability
1. Maximum number of PE connected to each P is 18 (Subject to
additional module at P).
2. Maximum numbers of CE connected to each PE is 50.
P Routers
No. Criteria Data Centre
The minimum number of
1 Routed Ethernet interface of P 1 slot 24 ports
router
The requirement of Application
2 Specific Integrated Circuit Yes
(ASIC)-based processor
3 Minimum no of Slots 6
4 Rugged Type No
5 Power Supply 48V DC and redundant
Page 61 of 101
PE Router
No. Criteria Offices Substation
The minimum number of
1 Routed Ethernet interface of 1 slot 24 ports 1 slot 24 ports
PE router
The requirement of
Application Specific
2 Yes Yes
Integrated Circuit (ASIC)-
based processor
3 Minimum no of Slots 4 4
3 Rugged Type No No
48V DC and
4 Power Supply 48V DC
redundant
CE Router
No. Criteria Offices Substation
The minimum number of
1 Routed Ethernet interface of 3 3
CE router
The requirement of To be installed as
2 Not Applicable
Asynchronous module and when required.
3 Rugged Type No Yes
48V DC and
4 Power Supply DC/ AC*
redundant
* Refer to item LAN Network Requirement at TNB Premises
Page 62 of 101
Figure 25: Concept of the VRF Feature Diagram
VI. Security Between Application/Corporate Networks
1. A firewall or redundant firewalls will be installed as the control point
between the service separation for Tier 2 and Tier 3.
CE Router
Core Switch
Page 63 of 101
ii. Less than 200 users
CE Router
Connectivity
No. Function Cable Type Minimum Bandwidth
Client Noncritical - PC,MFP,IP
1 UTP Cat5E Cable 100Mbps
Phone, EASY access
2 Client Critical Server UTP Cat 5E Cable 1Gbps
3 Inter-floor Multimode fibre* 1Gbps
4 Inter-building Singlemode fibre* 1Gbps
Inter-building (Less than
5 STP Cat5E Cable 1Gbps
70metres)
* SFP transceivers shall be used as the optical to electrical converter.
d. Wireless equipment.
Equipment Type
No. Criteria Wireless Access Wireless Bridge
Point
1 Type Controller Based Standalone
WPA2 Enterprise with WPA2 with AES-
2 Security (Minimum)
AES-CCMP CCMP
3 Data Rate (Minimum) 54Mbps 54Mbps
4 Antenna External External
Page 64 of 101
Equipment Type
No. Criteria Wireless Access Wireless Bridge
Point
Recommended Number
5 25 Not Applicable
of User per Access Point
6 Power Supply Type AC or POE AC
TNB Premise
Figure 23 : LAN Network Configuration at TNB premise (Multiple floor office premise)
LAN configuration for TNB premises (offices) are divided into 3 type of
premise category:
Page 65 of 101
TNB Premises (Offices) Critical Site Categorization:
Install UPS at selected sites. Voltage Regulator at selected sites AC-type CE Router
(1) Power Supply
UPS Protection Period : 2 with UPS
hours Option for limited size office:-
UPS Protection Period
Voltage Regulator at selected AC-type CE Router with UPS : 1 Hour
sites
UPS Protection Period : 2 Hours
Page 66 of 101
Item/Office Category Big Medium Small
(4)
No
(4) Rugged Type
(5) Requirement of
Asynchronous Not Applicable
module
Page 67 of 101
Switch requirement for LAN at TNB premises (offices):
48/ 24 ports
(3) Minimum Gigabit
Ethernet Network Port In specific case where there is a requirement for POE, the Switch shall support POE ports.
Page 68 of 101
Item/Office Category Big Medium Small
Network Room Specs & Other General Requirement at TNB premises (offices):
(3) Room-type Sealed from dust for Main Network & Distribution Network Room
Page 69 of 101
Item/Office Category Big Medium Small
(5) Room Door Opening Outswing door type for room access
Type
(7) Raised floor Minimum height > 0.3 m from ground finish level
Page 70 of 101
Item/Office Category Big Medium Small
Page 71 of 101
9. PDH Optical Line Terminal Equipment and
Higher Order Multiplexer Equipment
9.1 Introduction
This chapter describes the guidelines on PDH Optical Line Terminal Equipment and
Higher Order Multiplexer equipment.
9.2 Hierarchy
The hierarchy level on the PDH system is shown in Table 12 below:
1 E1 2.048 Mbps
2 E2 8.448 Mbps
3 E3 34.368 Mbps
4 E4 139.264 Mbps
Table 21: PDH Hierarchy
Page 72 of 101
VI. Management interfaces
10.1 Introduction
This chapter describes the guidelines on the technical requirements of access
multiplexer equipment, which consists of primary multiplexer equipment, digital drop
and insert equipment, digital cross connect equipment, voice frequency and data
interface units.
10.2 Construction
a. Mechanical construction shall be based on ETSI or 19 construction practice.
b. The sub rack shall be suitable for mounting on to racks, which comply with ETSI
ETS 300 119 or IEC 297 standard for racks and cabinets.
c. The equipment shall comprise of plug-in units, sub-racks, alarms, synchronising
and management interfaces.
Page 73 of 101
iv. Used for local access.
Page 74 of 101
10.13 Synchronous n x 64kbit/s V.35 Data Channel Unit (DIU 3)
a. Synchronous n x 64kbit/s V.35 Data Channel Unit (DIU3) shall operate at n x 64
kbit/s, n being 1, 2 up to 31.
b. Synchronous n x 64kbit/s V.35 Data Channel Unit is to provide interface to routers
used for operation and business/administrative applications.
Page 75 of 101
11. Digital Teleprotection Equipment (TPE)
11.1 Introduction
This chapter describes the guidelines on Digital Teleprotection Equipment. TPE is used
to transmit tripping commands or data produced by protective relays to remote station for
rapid tripping and isolation of faulty transmission lines.
Page 76 of 101
11.6 TPE Scheme Configurations
a. TPE scheme configuration for 132 kV System Using PDH Equipment is shown in
Figure 27.
b. TPE scheme configuration for 132 kV System Using SDH Equipment is shown in
Figure 28.
c. TPE scheme configuration for 132kV System Using Utility SDH Equipment is
shown in Figure 29.
d. TPE scheme configuration for 275 kV System Using PDH Equipment is shown in
Figure 30.
e. TPE scheme configuration for 275 kV System Using SDH Equipment is shown in
Figure 31.
f. TPE scheme configuration for 275kV / 500kV System Using Utility SDH Equipment
is shown in Figure 32.
g. TPE scheme configuration for 500kV System Using PDH Equipment is shown in
Figure 33.
h. TPE scheme configuration for 500kV System Using SDH Equipment is shown in
Figure 34.
i. SNCP for Protection Scheme for 500KV Using SDH Equipment is shown in Figure
35.
Figure 28: TPE scheme configuration for 132 kV System Using PDH Equipment
Figure 29: TPE scheme configuration for 132 kV System Using SDH Equipment
Page 77 of 101
11.9 TPE Scheme for 132kV System Using UTILITY SDH
Equipment
Figure 30: TPE scheme configuration for 132 kV System Using UTILITY SDH Equipment
PDH PDH
Current Differential Current Differential
Main 2, L2 Main 2, L2
G.703 G.703
Breaker Failure Breaker Failure
PSE PSE
L2 L2
PMUX PMUX
Figure 31: TPE scheme configuration for 275 kV System Using PDH Equipment
Page 78 of 101
11.11 TPE Scheme for 275kV System Using SDH Equipment
Current Differential Current Differential
Main 1, L1 Main 1, L1
G.703 G.703
Breaker Failure Breaker Failure
PSE PSE
L1 L1
PMUX PMUX
SDH SDH
Current Differential Current Differential
Main 2, L2 Main 2, L2
G.703 G.703
Breaker Failure Breaker Failure
PSE PSE
L2 L2
PMUX PMUX
Figure 32: TPE scheme configuration for 275 kV System Using SDH Equipment
Figure 33: TPE scheme configuration for 275/500 kV System Using UTILITY SDH
Equipment
Page 79 of 101
11.13 TPE Scheme for 500kV System Using PDH Equipment
Figure 34: TPE scheme configuration for 500 kV System Using PDH Equipment
Figure 35 : TPE scheme configuration for 500 kV System Using SDH Equipment
Page 80 of 101
11.15 SNCP for Protection Scheme for 500kV System Using SDH
Equipment
SUBSTATION B SUBSTATION A
LEGEND :
Figure 36 : SNCP for Protection Scheme for 500kV System Using SDH Equipment
Page 81 of 101
11.20 Command Output
a. Command signal extension shall be provided at the receiver end and shall be
adjustable from 0 to not less than 100 ms.
b. Configuration facilities to prevent unwanted or false tripping due to interference at
input and during transmission shall be available.
11.24 Alarms
a. Failure of any active equipment including failure of DC power supply shall be
indicated by visual alarms.
b. Voltage free contacts to be provided for remote alarm monitoring.
Page 82 of 101
Direction Direction
No. 1 No. 2
Legend :
DDF- digital Distribution frame
12.1 Introduction
This chapter describes the guidelines on 48VDC power system design and
configuration.
Page 83 of 101
12.2.1 Nokia PDH
For Nokia PDH equipment equipped with Enhance Power Supply Adaptor
(EPSA), dual DC input connectivity is as in Figure 38.
Page 84 of 101
12.2.3 Overall Dual DC Connectivity
Overall dual DC connectivity is in Figure 40 and Figure 41.
CAMS Point
Equipment with
Single DC Input
(e.g. Router (CE),
DC System Brand A
switch, hub,
(Existing)
modem, etc)
Circuit
Breaker 1
Distribution
Board
Circuit
Breaker 2
Equipment with
Dual DC Input
DC System Brand B (e.g. SDH, Utility
SDH, PDH, DWDM,
etc)
CAMS Point
CAMS Point
Circuit
Breaker 1
Equipment with
Dual DC Input
Distribution
DC System Brand B (e.g. SDH, Utility
Board
SDH, PDH, DWDM,
etc)
CAMS Point
Page 85 of 101
12.3 Switch Mode Rectifier (SMR) System
Minimum
Charger Total SMR
DC System Location
Type Capacity for
N Modules
Type 0 48V, 20A DC Single Offices
Type I 48V, 40A DC Dual 132kV Substation
Page 86 of 101
12.3.3 DC System Earthing
a. The SMR systems ground shall be set to positive earth.
b. The SMR earthing system shall be connected to substation main earth
copper bar using minimum 16mm 2 earth cable terminated using
copper cable lug.
12.3.11 Upgradeability
The SMR system shall be modular to allow the flexibility for capacity
upgrades.
SMR SYSTEM 1
SURGE
ARRESTER MODULE 1 MCB
DC
R
CIRCUIT
BREAKER
AC
MAIN DC
CIRCUIT
MODULE 2 BREAKER
DC
Y
CIRCUIT
BREAKER AC SPARES
FOR
FUTURE
MODULE N+1
AC TERMINAL BATTERY BANK A
DC
SOURCE 1 BLOCK
B DISTRIBUTION PANEL
CIRCUIT
BREAKER AC
Page 88 of 101
DUAL SMR SYSTEM CONFIGURATION
SMR SYSTEM 1
SURGE
ARRESTER
MODULE 1 MCB
DC
R
CIRCUIT
BREAKER
AC
MAIN DC
CIRCUIT
MODULE 2 BREAKER
DC
Y
CIRCUIT
BREAKER AC SPARES
FOR
FUTURE
MODULE N+1
AC TERMINAL BATTERY BANK A
DC
SOURCE 1 BLOCK
B DISTRIBUTION PANEL
CIRCUIT
BREAKER AC
SMR SYSTEM 2
SURGE
ARRESTER
MODULE 1 MCB
DC
R
CIRCUIT
BREAKER
AC MAIN DC
CIRCUIT
MODULE 2 BREAKER
DC
Y
CIRCUIT
BREAKER AC SPARES
FOR
FUTURE
Figure 43: Configuration of Dual SMR System for All New Substation
(132kV and above)
Page 89 of 101
12.3.16 DC Termination Block
a. The termination block shall be screwed type.
b. Each termination block size shall have the following MCB rating as
shown in Table 29.
12.4 Battery
12.4.1 Introduction
This chapter describes the guidelines on 48V battery design and
configuration.
12.4.2 Design
a. The battery shall be used to supply the telecommunication equipment
whenever there is no AC input or the SMR failed.
b. The nominal system voltage shall be 48 V DC.
c. The battery shall be charged by the SMR and shall also be able to
provide back up supply to the equipment in the case of AC failure via
the DC distribution panel.
d. The battery shall be from Valve Regulated Sealed Lead Acid (VRLA)
type using gas recombination technique.
e. The battery shall comply with IEC60896-21 (Stationary lead-acid
batteries Part 21: Valve regulated types method of test) and
IEC60896-22 (Stationary lead-acid batteries Part 22: Valve regulated
types Requirements).
Page 90 of 101
12.4.3 Battery Capacity
a. For new 48VDC system, the battery capacity shall be follow as Table
30.
Minimum
Minimum
Charger Total SMR
DC System Battery Capacity Location
Type Capacity for
per system
N Modules
Type 0 48V, 20A DC Single 80 Ah Offices
Type I 48V, 40A DC Dual 120 Ah 132kV Substation
Estimate Minimum
Compatibility with
Battery type total load Battery Capacity
Charger Type
station per system
Type 0 <10.0 A 80 Ah Type 0
Type I 10.1-20.0 A 120 Ah Type I
Type II 20.1 35.0 A 150 Ah Type I ,Type II
Type III 35.1 50.0 A 300 Ah Type II, Type III
Type IV >50 A 600 Ah Type IV
c. For each type a compact version can be used where the battery is
located inside the charger chassis. The compact version should only
be used when there are space constraints and there are no other
alternatives available.
Page 91 of 101
12.4.5 Battery Rack
a. The battery shall be installed on suitable racks. The battery rack shall
be isolated from ground potential.
b. The compact type shall have an internal battery bank contained within
the charger rack.
c. For non-compact design, the battery rack shall have a minimum of 12
inch or 30 cm working clearance between the battery and the upper
tier rack.
d. For compact design, the rack shall have a minimum of 5 inch or 3U
working clearance between batteries and charger.
e. The rack shall provide ample air-circulation in the battery storage area
and is able to withstand heavy load of battery.
12.4.7 Terminal
The battery terminal and inter cell connectors shall be covered with
suitable insulation material to prevent accidental contact or short circuit.
12.4.8 Installation
a. The battery bank shall be installed in an air-conditioned room.
b. The battery shall be made accessible for easy maintenance, testing
and inspection.
c. The Material Safety Data Sheet (MSDS) should be made available
during installation
No of
No Type Voltage From To
cores
AC Distribution Equipment/
I AC cable 415V AC 4
Board Charger
AC Distribution Equipment/
2 AC cable 240V AC 3
Board Charger
3 DC Cable for equipment 48V DC Charger 48V Equipment 2
Page 92 of 101
12.4.10 Battery Bank Replacement
The calculated values of Discharge Test Ratio (DTR) and Standby Time
(ST) calculation will determine the course of Action to be taken for a
battery bank as shown in the Table 33 below:
* If there are two or more battery banks connected to a single charger, the load current
is equally divided by the number of battery banks connected.
Page 93 of 101
12.4.13 Battery Disposal
The disposal of VRLA batteries should comply to schedule wastes
criteria under Environmental Quality Act 1974
c. The dimension should be able to fit within standard ICT 19inch rack
d. The output shall be Type G 3-pin socket
Page 94 of 101
Appendix A: Recommended Room Layout for
132kV and 275/500kV Substations
4.5m
SDH /
Battery Network
Utility SDH
Equipment
132 kV Substation
Equipment
48V DC SDH /
Access
Charger Utility SDH
Equipment
4.5m
Equipment
48V DC Access
Charger ODP
Equipment
5.5m
SDH /
Network
Utility SDH
Equipment
Equipment
Battery
275/500 kV Substation
Access Access
Equipment Equipment
48V DC
Charger
Access Network
Equipment Equipment
5.0m
48V DC
Charger SDH /
Utility SDH Spare ODP
Equipment
Battery
Spare Spare ODP
Page 95 of 101
Appendix B: Guideline for Optical Fiber Site
Acceptance Test
1. The following ways of testing and measuring are carried out to ensure:-
Optical fiber does not have any damage core.
Optical fiber has been spliced correctly.
Transmission loss should be lower than specified value.
2. Pre-installation Testing:
This typically consists of an OTDR (Optical Time Domain Reflectometer) test performed
at 1550 nm.
All optical fiber cables must be bi-directionally OTDR-tested prior to shipment and the
test report attached to the reel.
Bi-directional testing is important to verify results and to make certain that no potential
problems were missed.
This test will verify the characteristics of the cable and check for any shipping damage.
TNBs personnel and the contractor must jointly conduct the tests in order to preclude
future difficulties should a cable be damaged during construction.
3. Post-installation Testing
Cable should be tested once it has been strung or placed in the conduit, and prior to
splicing to make sure that there has been no installation damage.
Installation testing is usually done with an OTDR.
4. Splice Loss Test
Visual Appearance Test of Spliced Fiber
It is done after each splice to ensure that a clean, low-loss connection was made.
For jointing work result, judge the quality of the splicing by using the monitor of
fusion splicing machine.
Take note on any abnormalities.
Splicing Loss Test
Measurement is made in both directions of the spliced work section and the
averaged value of these two measurements is recorded on a standard test sheet.
5. End to End Test
End to End Test of Fiber Optic Cable
The testing method is performed end-to-end using OTDR from both directions.
The results should be compared to the pre-installation test.
Measured result shall be recorded on a standard test sheet.
End to End Test of Terminal
Transmission loss is measured by light source and optical power meter.
Repeat above output measurement and input measurement until you can get the
same value without error.
It is highly recommended that an ongoing testing program be established after the
system is powered up.
Page 96 of 101
6. It is important that the personnel testing the fiber uses the same brand and model of test
equipment and the same testing profile. Use of different test equipment and profiles will
result in confusion and inconsistent test results.
7. TNB Telecommunication personnel in charge must be able to understand the test results
to verify that all specifications have been met.
8. A sample of Site Acceptance Test Form is depicted below:
FORMULA
PLOSS (dB) = PIN (dBm) - POUT (dBm)
INPUT OUTPUT
TOTAL REMARKS
POWER POWER POWER LOSS 10 dB
CORE POWER (ACCEPTED/NOT
(PIN) (POUT) (dB) ATTENUATOR
LOSS (dB) ACCEPTED)
(dBm) (dBm)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
TNB REPRESENTATIVE CONTRACTOR REPRESENTATIVE
SIGN
NAME
DATE
Page 97 of 101
Appendix C: Template To Calculate Span
Equivalent Between Suspension Tower With
Yoke Plate Installation And Tension
Page 98 of 101
Appendix D: Optical Fiber & Cable
Characteristics and Power Budget Calculation
1. Optical Fiber Characteristics
2. Cable Characteristics
Page 99 of 101
3. Power Budget Calculation
The power budget calculation uses the following parameters: