Schedule of Work

We are currently in contact with Professor Glasper to organize a time to meet for
interviews and observation. We hope to have this step completed by late March.

DEADLINE
TASK ROLE* STATUS

Feb 20 1st Draft-Team Charter Janae Complete


@1:59pm

Feb 20 @ 1st Draft-Team Schedule Aileen Complete


2pm

Feb 24 @ Final-Letter of Inquiry Erin Complete


2pm

Feb 26 Revise Charter Everyone Complete

Feb 27 @ Final-Team Charter Cecily Complete


2pm

Feb 26 Revise Schedule Everyone Complete

Feb 27 @ Final-Team Schedule Janae Complete


2pm

March 5 Complete 1st Draft of Proposal Everyone Complete

March 6 @ Turn in 1st Draft- Ethnographic Research Aileen Complete


2pm Proposal

March 10 - 12 Revise Proposal Everyone Complete


March 13 @ Turn in Final-Proposal for Ethnographic Erin Complete
2pm Research Report

March 17 - April Complete 1st draft of Report Everyone Complete


15

April 17 @ Turn in 1st Draft- Ethnographic Report Cecily Complete


2pm

April 20 - 25 Revise Report Everyone Complete

April 26 @ Turn in Final- Ethnographic Report Everyone Complete


2pm

*the Role column indicates the person who will oversee the assignment and make sure
it is complete, but every group member should participate in every assignment.
*subject to change based on availability