Академический Документы
Профессиональный Документы
Культура Документы
PROJECT:friendsapartmentltd
REF:456111560546
ADDRESS:
_______________________________ nca:
456111560546
Architect;tarus/steve
Week:28outof75+addedworkhowmanyweeks?
ContractStartDate:1/9/2016
ContractcompletionDate:28/2/2018
Maincontractor:_kensteel_constructionltd
Clerkofworks/zachariah
+toprogramme2weeksaheadof
Progress
plumbing
Plaster to ground
unit ceiling 100
Walls %
Plaster to parking 0%
bay
ceilling 9/24
flooring 0%
1st Formwork to 100
floor column, suspended %
slab, staircase ,lift
rcc
Reinforcement- to 100 Col-17.3-
column, suspended % 26.6
slab, staircase ,lift Slab-18.7-
rcc 26.0
Service s to ditto 100
%
Concretes 100
collumns % 20/28th/1/1
Suspended slab 7 16/12/16
Staircase 1 13/12/16&
2
Lift shaft wall 1
2
unit A
Superstructure 100 25th week Architectural
walling % 2/2/17 Review 6 to
9
Precast lintel 100
%
electrical 100 1st fix
% ongiong
plumbing 100 1.Relocation 1st fix
% of stack pipe ongoing
for kitchen
sink whb
shifted to h
to f
2.location of
drain pipe for
air
conditioner
machine at
balcony front
& rear
Plaster to ceiling 0%
Beams
Walls/collumns
Rendered floor 0%
Tiles to floor
Sample unit
Unit B
Superstructure 100 complete
walling %
Precast lintel 100 complete
%
electrical 1st fix
plumbing 1st fix
Plaster to ceiling 100 6/3 to complete
Beams % 24/3/17
Walls/collumns
Walls/collumns
Rendered floor
Tiles to floor
Walls/collumns
Rendered floor 0%
Tiles to floor
Unit B
Superstructure 100 20/3/17 to
walling %
Precast lintel 0%
electrical
plumbing 1.Initially wc
s were close
couple and
later
changed to
wall hang
2.additional
stack pipe
for wc
belonging to
bedroom 01
Plaster to ceiling 100
Beams %
Walls/collumns
Rendered floor
Tiles to floor
Superstructure 100 21/3/17 to
Unit walling %
C
Precast lintel 0%
electrical
Plumbing
Plaster to ceiling
Beams
Walls/collumns
Rendered floor
Tiles to floor
Walls/collumns
Rendered floor 0%
Tiles to floor
Unit B
Superstructure 0%
walling
Precast lintel 0%
electrical
plumbing Washroom
RELOCATION
OF WC at
unit A -m/br
& br o1-14th
3/17
Plaster to ceiling 0%
Beams
Walls/collumns
Rendered floor 0%
Tiles to floor 0%
Superstructure 0%
Unit walling
C
Precast lintel 0%
electrical
Plumbing
Plaster to ceiling 0%
Beams
Walls/collumns
Rendered floor
Tiles to floor
4th Formwork to 100
floor column, suspended %
slab, staircase ,lift
rcc
Reinforcement- to 100
column, suspended %
slab, staircase ,lift
rcc
Service s to ditto 100
%
Concretes 0%
collumns
Suspended slab O 100 23/3/17 & E TO A
TO E % remains
Staircase 1
2
Walls/collumns
Rendered floor 0%
Tiles to floor 0%
Unit B
Superstructure 0%
walling
Precast lintel 0%
electrical
plumbing
Plaster to ceiling 0%
Beams
Walls/collumns
Rendered floor 0%
Tiles to floor 0%
Superstructure 0%
Unit walling
C
Precast lintel 0%
electrical
Plumbing
Plaster to ceiling 0%
Beams
Walls/collumns
Rendered floor
Tiles to floor DATE
VISITORS DATE
INCLUDES STATORY
INSPECTORS
1 Municipal engineer 21/3/17
2 Project civil 21/3/17
engineer
PLANT/MATERIALS
DELIVERED TO
SITE
1 Ceramic tiles for 413
sample unit B1 cartoons
finishes
2 Wall hang cistern no 4 cartoons
wc/fittings
WORKS: dates
MATERIALS
TESTED OR
COMMISSIONED
1 4th floor concrete 23/3/17
slab grid o to eb----2 24/3/17
days
CLERK
PREPARED BY
OFWORKS
:-----zachariah
SIGN:-----
DATE:-----28/3/2017