Worked Solution (Final Examination Semester 1 2013/2014)

Activity Duration (days) Cost (RM) Start Date Actual Start Date Actual Finish Date

Activity A 2 1200 06-09-13 06-09-13 07-09-13

Activity B 3 3300 08-09-13 08-09-13 13-09-13

Activity C 8 12000 10-09-13 13-09-13 23-09-13

Activity D 6 18000 15-09-13 20-09-13 27-09-13

Activity E 5 8000 23-09-13 24-09-13 30-09-13

Planning cumulative work/day


Actual cumulative work/day
06-Sep 07-Sep 08-Sep 09-Sep 10-Sep 11-Sep 12-Sep 13-Sep 14-Sep

1 2 3 4 6 7 8 9 10
1 2 3 4 5 5 5 7 8

Actual and Planne


30

Cumulative work/day
25
20
15
10
5
0

06-Sep
07-Sep
08-Sep
09-Sep
10-Sep
11-Sep
15-Sep 16-Sep 17-Sep 18-Sep 19-Sep 20-Sep 21-Sep 22-Sep 23-Sep

12 14 16 16 16 17 18 19 20
9 10 11 11 11 13 15 17 19

Actual and Planned S-Curve


25-Sep
11-Sep
12-Sep
13-Sep
14-Sep
15-Sep
16-Sep
17-Sep
18-Sep
19-Sep
20-Sep
21-Sep
22-Sep
23-Sep
24-Sep

26-Sep
27-Sep
28-Sep
29-Sep
30-Sep

Date

Planned Actual
24-Sep 25-Sep 26-Sep 27-Sep 28-Sep 29-Sep 30-Sep

21 21 21 22 23 24
21 21 21 23 24 25 26