US$-Vehiculo-Km
REGION TOGRAFIA SUPERFICIE ESTADO AUTO CAMTA BUS MED BUS GRAN CAM 2E CAM 3E ARTICULADO
M = Selva
C = Sierra
A = Accidentada
L = Llana
O = Ondulada
ASF = Asfaltada
AFI = Afirmada
SAF = Sin Afirmar
TRO = Trocha
B = Bueno
R = Regular
M = Malo
INDICE MEDIO DIARIO
FCE.LIGEROS = 1.096971
FCE.PESADOS= 0.998231
ESTACION: Estacion- 2
UBICACIN: DISTRITO SANTA- PROVINCIA DEL SANTA- ANCASH
DIAS: LUN MAR MIER
FECHAS: 03/11/15 04/11/15 05/11/15 06/11/15 07/11/15 08/11/15 09/11/15
MES : NOV
Tipo de Vehculo Lunes Martes Mircoles Jueves Viernes Sbado Domingo
Automovil 46 48 35 30 35 47 40
Camioneta 12 18 11 17 24 20 23
C.R. 15 16 12 14 15 15 14
Micro 17 15 8 4 12 8 10
Bus Grande 15 6 10 8 9 9 9
Camin 2E 11 18 18 14 11 11 18
Camin 3E 18 15 19 19 19 4 17
TOTAL 134 136 113 106 125 114 131
FCE.LIGEROS = 1.096971
FCE.PESADOS= 0.998231
ESTACION: Estacion- 3
UBICACIN: DISTRITO SANTA- PROVINCIA DEL SANTA- ANCASH
DIAS: LUN MAR MIER
FECHAS: 03/11/15 04/11/15 05/11/15 06/11/15 07/11/15 08/11/15 09/11/15
MES : NOV
FCE.LIGEROS = 1.096971
FCE.PESADOS= 0.998231
*IMD1 Tramos:1,2
*IMD2 Tramo:3
Distribu
Tipo de Vehculo IMD
cin (%)
Automovil 42 32.81
Camioneta 21 16.41
C.R.(Camioneta ) 16 12.50
Micro ( Bus Mediano) 11 8.59
Bus Grande 10 7.81
Camin 2E 12 9.38
Camin 3E 16 12.50
IMD 128 100.00
*IMD2 TRAMO 3
Distribu
Tipo de Vehculo IMD
cin (%)
Automovil 39 30.00
Camioneta 21 16.15
C.R.(Camioneta ) 16 12.31
Micro ( Bus Mediano) 12 9.23
Bus Grande 12 9.23
Camin 2E 16 12.31
Camin 3E 14 10.77
IMD 130 100.00
COV = Covunit x IMD x Long tramo x 365 dias
COSTO DE OPERACIN VEHICULAR SIN PROYECTO COSTO DE OPERACIN VEHICULAR SIN PROYECTO
TRAFICO NORMAL DIAS= 365 L1 (Km) = 4 *IMD1 TRAFICO NORMAL DIAS = 365 L2 (Km) =
UNIDADE CAMIONETA OMNIBUS CAMIONES CAMIONETA
TRAMO 1 AUTOS CAMIONETA TOTAL TRAMO 2 UNIDADES AUTOS CAMIONETA
S RURAL BUS MEDIANO 2E 3E RURAL
COV unitario 1.60 1.40 1.40 3.22 5.69 6.47 COV unitario 1.51 1.31 1.31
0 2014 0.00 2014
1 2015 97,832.38 42,801.67 32,610.79 51,711.40 99,611.15 151,110.79 475,678.19 1.00 2,015 208,330.56 90,407.60 68,881.98
2 2016 100,161.72 42,801.67 32,610.79 51,711.40 99,611.15 151,110.79 478,007.53 2.00 2,016 213,290.81 90,407.60 68,881.98
3 2017 100,161.72 42,801.67 32,610.79 51,711.40 99,611.15 151,110.79 478,007.53 3.00 2,017 213,290.81 90,407.60 68,881.98
4 2018 100,161.72 44,839.84 32,610.79 51,711.40 99,611.15 151,110.79 480,045.70 4.00 2,018 213,290.81 94,712.73 68,881.98
5 2019 100,161.72 44,839.84 34,648.97 51,711.40 99,611.15 151,110.79 482,083.88 5.00 2,019 213,290.81 94,712.73 73,187.11
6 2020 102,491.07 44,839.84 34,648.97 51,711.40 99,611.15 151,110.79 484,413.22 6.00 2,020 218,251.06 94,712.73 73,187.11
7 2021 102,491.07 44,839.84 34,648.97 56,412.44 99,611.15 151,110.79 489,114.26 7.00 2,021 218,251.06 94,712.73 73,187.11
8 2022 102,491.07 44,839.84 34,648.97 56,412.44 99,611.15 151,110.79 489,114.26 8.00 2,022 218,251.06 94,712.73 73,187.11
9 2023 104,820.41 44,839.84 34,648.97 56,412.44 99,611.15 151,110.79 491,443.60 9.00 2,023 223,211.32 94,712.73 73,187.11
10 2024 104,820.41 46,878.02 34,648.97 56,412.44 99,611.15 151,110.79 493,481.78 10.00 2,024 223,211.32 99,017.85 73,187.11
COSTO DE OPERACIN VEHICULAR CON PROYECTO COSTO DE OPERACIN VEHICULAR CON PROYECTO
TRAFICO TOTAL DIAS = 365 L1 (Km) = 4 TRAFICO TOTAL DIAS = 365 L2 (Km) =
UNIDADE CAMIONETA OMNIBUS CAMIONES CAMIONETA
TRAMO 1 AUTOS CAMIONETA TOTAL TRAMO 2 UNIDADES AUTOS CAMIONETA
S RURAL BUS MEDIANO 2E 3E RURAL
COV unitario 0.855 0.940 0.940 1.828 2.292 3.133 COV unitario 0.855 0.940 0.940
0 2,014 0 2,014
1 2,015 59,897.38 32,943.56 24,707.67 34,686.03 46,840.96 82,331.67 281,407.25 1 2,015 134,769.10 74,123.00 55,592.25
2 2,016 61,145.24 32,943.56 24,707.67 34,686.03 46,840.96 82,331.67 282,655.11 2 2,016 137,576.79 74,123.00 55,592.25
3 2,017 61,145.24 32,943.56 24,707.67 34,686.03 46,840.96 82,331.67 282,655.11 3 2,017 137,576.79 74,123.00 55,592.25
4 2,018 61,145.24 34,316.21 24,707.67 34,686.03 46,840.96 82,331.67 284,027.76 4 2,018 137,576.79 77,211.46 55,592.25
5 2,019 61,145.24 34,316.21 27,452.96 34,686.03 46,840.96 82,331.67 286,773.06 5 2,019 137,576.79 77,211.46 61,769.17
6 2,020 63,640.96 34,316.21 27,452.96 34,686.03 46,840.96 82,331.67 289,268.78 6 2,020 143,192.16 77,211.46 61,769.17
7 2,021 63,640.96 34,316.21 27,452.96 37,354.18 46,840.96 82,331.67 291,936.94 7 2,021 143,192.16 77,211.46 61,769.17
8 2,022 63,640.96 34,316.21 27,452.96 37,354.18 46,840.96 82,331.67 291,936.94 8 2,022 143,192.16 77,211.46 61,769.17
9 2,023 64,888.82 34,316.21 27,452.96 37,354.18 46,840.96 82,331.67 293,184.80 9 2,023 145,999.85 77,211.46 61,769.17
10 2,024 64,888.82 35,688.85 27,452.96 37,354.18 46,840.96 82,331.67 294,557.45 10 2,024 145,999.85 80,299.92 61,769.17
COSTO DE OPERACIN VEHICULAR SIN PROYECTO
9 *IMD1 TRAFICO NORMAL DIAS = 365 L3 (Km) = 6 *IMD2
OMNIBUS CAMIONES CAMIONETA OMNIBUS CAMIONES
TOTAL TRAMO 3 UNIDADES AUTOS CAMIONETA
RURAL
TOTAL
BUS MEDIANO 2E 3E BUS MEDIANO 2E 3E
3.05 5.31 6.09 COV unitario 1.05 1.05 1.05 2.31 3.68 4.50
0 2014
110,061.43 209,259.65 320,178.70 1,007,119.93 1 2,015 90,033.24 48,479.44 36,936.72 60,605.25 129,087.92 137,854.72 502,997.29
110,061.43 209,259.65 320,178.70 1,012,080.18 2 2,016 92,341.79 48,479.44 36,936.72 60,605.25 129,087.92 137,854.72 505,305.84
110,061.43 209,259.65 320,178.70 1,012,080.18 3 2,017 92,341.79 48,479.44 36,936.72 60,605.25 129,087.92 137,854.72 505,305.84
110,061.43 209,259.65 320,178.70 1,016,385.30 4 2,018 92,341.79 50,787.98 36,936.72 60,605.25 129,087.92 137,854.72 507,614.38
110,061.43 209,259.65 320,178.70 1,020,690.42 5 2,019 92,341.79 50,787.98 39,245.26 60,605.25 129,087.92 137,854.72 509,922.92
110,061.43 209,259.65 320,178.70 1,025,650.68 6 2,020 94,650.33 50,787.98 39,245.26 65,655.69 129,087.92 137,854.72 517,281.91
120,067.01 209,259.65 320,178.70 1,035,656.26 7 2,021 94,650.33 50,787.98 39,245.26 65,655.69 129,087.92 137,854.72 517,281.91
120,067.01 209,259.65 320,178.70 1,035,656.26 8 2,022 94,650.33 50,787.98 39,245.26 65,655.69 129,087.92 137,854.72 517,281.91
120,067.01 209,259.65 320,178.70 1,040,616.51 9 2,023 96,958.88 50,787.98 39,245.26 65,655.69 129,087.92 137,854.72 519,590.45
120,067.01 209,259.65 320,178.70 1,044,921.64 10 2,024 96,958.88 53,096.53 39,245.26 65,655.69 129,087.92 137,854.72 521,899.00
0 2,014 - 0 2,005 -
1 2,015 1,341,424.05 1 2,006 992,653.79
2 2,016 1,347,351.39 2 2,007 997,040.03
3 2,017 1,347,351.39 3 2,008 997,040.03
4 2,018 1,353,871.47 4 2,009 1,001,864.89
5 2,019 1,366,911.63 5 2,010 1,011,514.60
6 2,020 1,380,896.76 6 2,011 1,021,863.60
7 2,021 1,389,568.26 7 2,012 1,028,280.51
8 2,022 1,389,568.26 8 2,013 1,028,280.51
9 2,023 1,395,495.61 9 2,014 1,032,666.75
10 2,024 1,402,015.69 10 2,015 1,037,491.61
INVERSION EN ACTIVOS FIJOS A PRECIOS PRIVADOS
PROYECTO: ALTERNATIVA 02
COSTO OBRAS CIVILES ( a precios privados)
ADOS
3,187,000
ALTERNATIVA N01
RESUMEN DE COSTOS DE INVERSION PRECIOS PRIVADOS
ITEM DESCRIPCION INC TOTAL
TOTAL
COSTOS DE MANTENIMIENTO PERIODICO C/P
51,000.00
MANTENIMIENTO 51,000.00
MANO DE OBRA CALIFICADA 5,000.00
Operario 3,000.00
Oficial 2,000.00
MANO DE OBRA NO CALIFICADA 2,000.00
Peones 2,000.00
MATERIALES 30,000.00
Asfalto liquido 10,000.00
Mezcla asfaltica en frio 20,000.00
EQUIPOS 14,000.00
Plancha compactadora 5,000.00
Volquete 8,000.00
ALTERNATIVA N02
RESUMEN DE COSTOS DE INVERSION PRECIOS PRIVADOS RESUMEN DE COSTOS DE INVERSION PRECIOS SOCIA
ITEM DESCRIPCION INC TOTAL ITEM
1.00 EXPEDIENTE TECNICO ( 3% ) 3% 96,510.00 1.00
2.00 OBRAS CIVILES 3,187,000.00 2.00
3.00 IMPACTO AMBIENTAL 30,000.00 3.00
4.00 SUPERVISION DE OBRA 5% 160,850.00 4.00
PRESUPUESTO DE INVERSION
PRESUPUESTO TOTAL COSTOS PRIVADOS 3,474,360.00
TOTAL
COSTOS DE MANTENIMIENTO PERIODICO
91,000.00
MANTENIMIENTO 91,000.00
MANO DE OBRA CALIFICADA 5,000.00
Operario 3,000.00
Oficial 2,000.00
MANO DE OBRA NO CALIFICADA 2,000.00
Peones 2,000.00
MATERIALES 70,000.00
Asfalto liquido 20,000.00
Mezcla asfaltica en caliente 50,000.00
EQUIPOS 14,000.00
Rodillo 5,000.00
Volquete 8,000.00
Herramientas y otros Equipos 1,000.00
RESUMEN DE COSTOS DE INVERSION PRECIOS SOCIALES Fc=0.79
DESCRIPCION INC TOTAL
EXPEDIENTE TECNICO ( 3% ) 3% 76,242.90
OBRAS CIVILES 2,517,730.00
IMPACTO AMBIENTAL 23,700.00
SUPERVISION DE OBRA 5% 127,071.50
PRESUPUESTO DE INVERSION 2,744,744.40
TOTAL
COSTOS DE MANTENIMIENTO PERIODICO
68,250.00
MANTENIMIENTO 68,250.00
MANO DE OBRA CALIFICADA 3,750.00
Operario 2,250.00
Oficial 1,500.00
MANO DE OBRA NO CALIFICADA 1,500.00
Peones 1,500.00
MATERIALES 52,500.00
Asfalto liquido 15,000.00
Mezcla asfaltica en caliente 37,500.00
EQUIPOS 10,500.00
Plancha compactadora 3,750.00
Volquete 6,000.00
Herramientas y otros Equipos 750.00
COSTOS DE OPERAC.Y MANT.- PRECIOS PRIVADOS
BENEFICIOS
AO COV SIN PROYECTO COV CON PROYECTO
INCREMENTALES
2014
2015 1,985,795.40 1,341,424.05 644,371.36
2016 1,995,393.54 1,347,351.39 648,042.15
2017 1,995,393.54 1,347,351.39 648,042.15
2018 2,004,045.39 1,353,871.47 650,173.92
2019 2,012,697.23 1,366,911.63 645,785.60
2020 2,027,345.80 1,380,896.76 646,449.05
2021 2,042,052.43 1,389,568.26 652,484.16
2022 2,042,052.43 1,389,568.26 652,484.16
2023 2,051,650.56 1,395,495.61 656,154.96
2024 2,060,302.41 1,402,015.69 658,286.72
EVALUACION ECONOMICA ALTERANTIVA N01 - PRECIOS PRIVADOS
Costos Beneficios
Ao FLUJO NETO
Incrementales Incrementales
0 2,014 2,401,920.00 - (2,401,920.00) 3794409.4447584
1 2,015 800.00 644,371.36 643,571.36 -83000
2 2,016 800.00 648,042.15 647,242.15 -83000
3 2,017 800.00 648,042.15 647,242.15 -83000
4 2,018 800.00 650,173.92 649,373.92 -83000
5 2,019 14,500.00 645,785.60 631,285.60 -22500
6 2,020 800.00 646,449.05 645,649.05 -83000
7 2,021 800.00 652,484.16 651,684.16 -83000
8 2,022 800.00 652,484.16 651,684.16 -83000
9 2,023 800.00 656,154.96 655,354.96 -83000
10 2,024 14,500.00 658,286.72 643,786.72 (22,500.00)
Costos Beneficios
Ao FLUJO NETO
Incrementales Incrementales
2,014 2,401,920.00 - (2,401,920.00) 2,043,143.55
2,015 800.00 644,371.36 643,571.36 (83,000.00)
2,016 800.00 648,042.15 647,242.15 (83,000.00)
2,017 800.00 648,042.15 647,242.15 (83,000.00)
2,018 800.00 650,173.92 649,373.92 (83,000.00)
2,019 14,500.00 645,785.60 631,285.60 (22,500.00)
2,020 800.00 646,449.05 645,649.05 (83,000.00)
2,021 800.00 652,484.16 651,684.16 (83,000.00)
2,022 800.00 652,484.16 651,684.16 (83,000.00)
2,023 800.00 656,154.96 655,354.96 (83,000.00)
2,024 14,500.00 658,286.72 643,786.72 (22,500.00)
Costos Beneficios
Ao FLUJO NETO
Incrementales Incrementales
0 2,014 1,897,516.80 (1,897,516.80) 2997583.46135914
1 2,015 600.00 476,834.80 476,234.80 -62250
2 2,016 600.00 479,551.19 478,951.19 -62250
3 2,017 600.00 479,551.19 478,951.19 -62250
4 2,018 600.00 481,128.70 480,528.70 -62250
5 2,019 10,875.00 477,881.34 467,006.34 -16875
6 2,020 600.00 478,372.30 477,772.30 -62250
7 2,021 600.00 482,838.28 482,238.28 -62250
8 2,022 600.00 482,838.28 482,238.28 -62250
9 2,023 600.00 485,554.67 484,954.67 -62250
10 2,024 10,875.00 487,132.17 476,257.17 (16,875.00)
Costos Beneficios
Ao FLUJO NETO
Incrementales Incrementales
2,005 1,897,516.80 - (1,897,516.80) 1614083.40227
2,006 600.00 476,834.80 476,234.80 -62250
2,007 600.00 479,551.19 478,951.19 -62250
2,008 600.00 479,551.19 478,951.19 -62250
2,009 600.00 481,128.70 480,528.70 -62250
2,010 10,875.00 477,881.34 467,006.34 -16875
2,011 600.00 478,372.30 477,772.30 -62250
2,012 600.00 482,838.28 482,238.28 -62250
2,013 600.00 482,838.28 482,238.28 -62250
2,014 600.00 485,554.67 484,954.67 -62250
2,015 10,875.00 487,132.17 476,257.17 -16875
4,624,804.79
4,624,804.79
3,422,355.54
3,422,355.54
Inversion + Inversion + Inversion +
60.00% 85.00% 110.00%
Costos Beneficios
Ao FLUJO NETO
Incrementales Incrementales
0 2,014 3,474,360.00 - (3,474,360.00) 4126410.84249 0
1 2,015 3,000.00 644,371.36 641,371.36 -78000 691050.85
2 2,016 3,000.00 648,042.15 645,042.15 -78000 701002.575
3 2,017 3,000.00 648,042.15 645,042.15 -78000 722745.625
4 2,018 3,000.00 650,173.92 647,173.92 -78000 747107.55
5 2,019 54,500.00 645,785.60 591,285.60 -12500 755896.75
6 2,020 3,000.00 646,449.05 643,449.05 -78000 771852.725
7 2,021 3,000.00 652,484.16 649,484.16 -78000 791986.125
8 2,022 3,000.00 652,484.16 649,484.16 -78000 807060.625
9 2,023 3,000.00 656,154.96 653,154.96 -78000 827436.75
10 2,024 54,500.00 658,286.72 603,786.72 -12500 843150
Costos Beneficios
Ao FLUJO NETO
Incrementales Incrementales
2,014 3,474,360.00 - (3,474,360.00) 2,221,913.53 -
2,015 3,000.00 644,371.36 641,371.36 (78,000.00) 691,050.85
2,016 3,000.00 648,042.15 645,042.15 (78,000.00) 701,002.58
2,017 3,000.00 648,042.15 645,042.15 (78,000.00) 722,745.63
2,018 3,000.00 650,173.92 647,173.92 (78,000.00) 747,107.55
2,019 54,500.00 645,785.60 591,285.60 (12,500.00) 755,896.75
2,020 3,000.00 646,449.05 643,449.05 (78,000.00) 771,852.73
2,021 3,000.00 652,484.16 649,484.16 (78,000.00) 791,986.13
2,022 3,000.00 652,484.16 649,484.16 (78,000.00) 807,060.63
2,023 3,000.00 656,154.96 653,154.96 (78,000.00) 827,436.75
2,024 54,500.00 658,286.72 603,786.72 (12,500.00) 843,150.00
Costos Beneficios
Ao FLUJO NETO
Incrementales Incrementales
0 2,014 2,744,744.40 - (2,744,744.40) 3259864.57 0
1 2,015 600.00 476,834.80 476,234.80 -62250.00 511377.63
2 2,016 600.00 479,551.19 478,951.19 -62250.00 518741.91
3 2,017 600.00 479,551.19 478,951.19 -62250.00 534831.76
4 2,018 600.00 481,128.70 480,528.70 -62250.00 552859.59
5 2,019 10,875.00 477,881.34 467,006.34 -16875.00 559363.60
6 2,020 600.00 478,372.30 477,772.30 -62250.00 571171.02
7 2,021 600.00 482,838.28 482,238.28 -62250.00 586069.73
8 2,022 600.00 482,838.28 482,238.28 -62250.00 597224.86
9 2,023 600.00 485,554.67 484,954.67 -62250.00 612303.20
10 2,024 10,875.00 487,132.17 476,257.17 -16875.00 623931.00
Costos Beneficios
Ao FLUJO NETO
Incrementales Incrementales
2,014 2,744,744.40 - (2,744,744.40) 1755311.69 0.00
2,015 600.00 476,834.80 476,234.80 -62250.00 511377.63
2,016 600.00 479,551.19 478,951.19 -62250.00 518741.91
2,017 600.00 479,551.19 478,951.19 -62250.00 534831.76
2,018 600.00 481,128.70 480,528.70 -62250.00 552859.59
2,019 10,875.00 477,881.34 467,006.34 -16875.00 559363.60
2,020 600.00 478,372.30 477,772.30 -62250.00 571171.02
2,021 600.00 482,838.28 482,238.28 -62250.00 586069.73
2,022 600.00 482,838.28 482,238.28 -62250.00 597224.86
2,023 600.00 485,554.67 484,954.67 -62250.00 612303.20
2,024 10,875.00 487,132.17 476,257.17 -16875.00 623931.00
(7,296,156.00)
641,371.36
645,042.15
645,042.15
647,173.92
591,285.60
643,449.05
649,484.16
649,484.16
653,154.96
603,786.72
(3,376,923.58)
-2.40%
Inversion +
110.00%
(5,763,963.24)
476,234.80
478,951.19
478,951.19
480,528.70
467,006.34
477,772.30
482,238.28
482,238.28
484,954.67
476,257.17
(2,825,762.11)
-3.24%
ESCENARIOS ANTE EL INCREMENTO O DISMINUCION DE LA INVERSION A PRECIOS P
PRECIOS PRIVADOS
ESCENARIOS A
ALTENATIVA N01 ALTENATIVA N02
LA VARIAC.EN
LOS COSTOS
VAN TIR B/C VAN TIR
+30% 848,299 16.00% 1.38 -597,436 6.81%
+20% 1,088,491 18.20% 1.25 -250,000 8.58%
+10% 1,328,683 20.73% 1.38 97,436 10.59%
0 1,568,875 23.67% 1.65 444,872 12.91%
-10% 1,809,067 27.17% 1.74 792,308 15.64%
-20% 2,049,259 31.41% 2.00 1,139,744 18.91%
-30% 2,289,451 36.71% 2.90 1,487,180 22.93%
PRECIOS SOCIALES
ESCENARIOS A
LA VARIAC.EN ALTENATIVA N01 ALTENATIVA N02
LOS COSTOS
VAN TIR B/C VAN TIR
+30% 471,429 14.28% 1.29 -629,967 5.72%
+20% 661,181 16.39% 1.16 -355,492 7.43%
+10% 850,933 18.81% 1.28 -81,018 9.37%
0 1,040,684 21.63% 1.54 193,457 11.61%
-10% 1,230,436 24.97% 1.62 467,931 14.24%
-20% 1,420,188 29.01% 1.86 742,406 17.39%
-30% 1,609,939 34.04% 2.68 1,016,880 21.25%
PROYECTO
DESCRIPCION
ALTERNATIVO 01
LTENATIVA N02
B/C
1.25
1.13
1.24
1.13
1.56
1.79
2.56
LTENATIVA N02
B/C
1.17
1.06
1.17
1.07
1.47
1.68
2.41
PROYECTO
ALTERNATIVO 02
3,474,360.00
444,872
12.91%
SOCIALES
VARIACION DE COSTOS DEL PROYECTO ALTERNATIVO N01 FRENTE AL PROYECTO
Inversion +
ALTERNATIVAS INDICES 0.00% 10.00%
Proyecto Alternativo 01 VAN 1,040,684.33 850,932.65
TIR 21.63% 18.81%
Proyecto Alternativo 02 VAN 193,456.73 193,456.73
TIR 11.61% 11.61%
ANALISIS DE SENSIB
1,200,000.00
800,000.00
600,000.00
400,000.00
200,000.00
f(x) = - 0.00x + 193456.73
-
0.00% 10.00%% Variacin
20.00%Costo Proye
30.00%
SOCIALES
VARIACION DE COSTOS DEL PROYECTO ALTERNATIVO N01 FRENTE AL PROYECTO
Inversion +
ALTERNATIVAS INDICES 0.00% 10.00%
Proyecto Alternativo 01 VAN 1,040,684.33 850,932.65
TIR 21.63% 18.81%
Proyecto Alternativo 02 VAN 193,456.73 193,456.73
TIR 11.61% 11.61%
ATIVO N01 FRENTE AL PROYECTO ALTERNATIVO N02
ANALISIS DE SENSIBILIDAD
= - 1897516.80x + 1040684.33
= - 0.00x + 193456.73
10.00%% Variacin
20.00%Costo Proyecto
30.00% Alternativo
40.00% 01 50.00% 60.00%
Alt -1 2,401,920.00
Alt -2 3,474,360.00
COSTOS DE TOTAL
MANTENIMIENTO
PERIODICO C/P
51,000.00
MANTENIMIENTO 51,000.00
MANO DE OBRA CALIFICA 5,000.00
Operario 3,000.00
Oficial 2,000.00
MANO DE OBRA NO CALIF 2,000.00
Peones 2,000.00
MATERIALES 30,000.00
Asfalto liquido 10,000.00
Mezcla asfaltica en frio 20,000.00
EQUIPOS 14,000.00
Plancha compactadora 5,000.00
Volquete 8,000.00