Академический Документы
Профессиональный Документы
Культура Документы
The upstream NJHPS has been constructed on the left bank of the river while the downstream
Rampur HPS is located on right bank of the river (Figure-1).The water from Rampur intake
structure is conveyed to the right bank through 10.5m dia Head Race Tunnel. The length of
HRT on left bank is 484m before it crosses the river Sutlej with 43.2m long river crossing
section. At the end of HRT, restricted orifice type surge shaft, 38 m diameter and 156 m in
height, is located. The water further enters into 3 underground pressure shafts, surface valve
house. After that water is conveyed through 3 surface penstocks of 5.4m diameter each,
bifurcating into six branches of 3.8m diameter to feed the six generating units in Surface
Powerhouse equipped with Francis turbines each having generating capacity of 68.67 MW. The
discharge from the turbines is fed through draft tube tunnels to a 179m long tail Race tunnel
system leading back to river Sutlej.
Figure 3: Collapse of Collection gallery (View from TRT Side and Draft tube tunnel 6 side)
Step2: The Bottom base slab of collection gallery in junction area where draft tube tunnel
connects with collection gallery was modelled as plate elements and analysed in STAAD Pro
by applying the reactions obtained due to the vertical loads in step1.
Step3: An inbuilt arch beam (figure 4) was provided to take the load from crown portion of
collection gallery towards the draft tube tunnel. Reaction of 2785.73kN obtained at springing
level of collection gallery in step1 was applied as uniformly distributed load on arch beam.
Step4: Complete collection gallery with draft tube tunnels (figure 5) was analysed in ANSYS
by applying all external loads.
3.3.2 Design
RCC structure of cut and cover section was designed for maximum forces obtained in the
analysis. The reinforcement was designed for maximum bending moments, shear forces and
axial loading by limit state methods as per IS: 456 (Latest Revision)
3.3.3 Construction
Before Excavation of cut and cover section, the existing flood protection wall was dismantled
and a new flood protection wall was constructed away from construction zone, close to river to
protect working area from flooding. A cement grout curtain was provided between river and
proposed cut and cover tunnel to prevent seepage of water during excavation. Due to
excavation of 22m deep open cut in very poor rock, it was planned to carry out the excavation
and concreting of a zone covering two draft tube tunnel junctions at a time. Excavation of this
zone was carried out in vertical steps of 2.5m in a length of 10m at a time and simultaneously
support was provided on the slopes. Elevation difference of 5m was maintained between two
patches of 10m. Excavation of collection gallery was done mechanically with excavator and
was taken up from two fronts; one from TRT side and other from draft tube tunnel no. 6 side.
After completing the excavation, concreting of bottom raft was taken up initially, followed by
concreting of walls and overt simultaneously with excavation of next zone. After completion of
construction of whole collection gallery, the excavated material was back filled over the
section. The construction activities of cut and cover tunnel were completed within the
scheduled time.
Figure 6: Excavation for Cut and Cover Figure 7: Reinforcement and Concreting
tunnel
the rock gave very low UCS value of 0.28 MPa. The C & values as reported were 0.14 MPa
and 23 respectively. The rock encountered was thinly foliated and was expected to lose its
strength further under saturated conditions. In such geological conditions, rock supporting
measures such as rock anchor, shotcrete and cladding may not be able to provide intended
support strength during life of the project and caving in of slopes in saturated conditions may
occur. After observing the rock exposed in the excavated portion and stability problems being
encountered, it was proposed to construct the outfall pond in the form of RCC cut and cover
tunnel. Since the channel portion, which was about 20m deep involved lesser excavation and the
rock encountered was better than that found in the pond reach, it was decided to construct it as
open channel, as originally proposed.
4.3.2 Design
RCC structure of cut and cover section was designed for maximum forces obtained in the
analysis. The reinforcement was designed for maximum bending moments, shear forces and
axial loading by limit state methods as per IS: 456 (Latest Revision)
4.3.3 Construction
Excavation of Tail race outfall was planned open excavation. It was required to excavate a
maximum depth of 31.35 m. Initially a portion of 27.5 m length of was excavated at a slope
angle of 1horizontal: 2.5 Vertical. Intermediate bench of 3 m width was provided 10 m below
the top. Excavated slope was supported with rock anchors, shotcrete with wire mesh. Drainage
holes were also provided to relive the water pressure. After completing the excavation,
concreting of bottom raft was taken up initially, followed by concreting of walls and top slab
simultaneously with excavation of next 13 m portion of outfall. After completion of
construction of whole structure, the excavated material was back filled over the section. The
construction activities of cut and cover tunnel were completed within the scheduled time.
5. CONCLUSION
Tunnel construction in the Himalayas presents various challenges in the form of unexpected
geology, challenging sites and unprecedented working conditions. In view of these, it becomes
imperative for the design as well as construction engineers to adopt techniques and
methodologies which are both flexible and efficient to ensure successful and timely completion
of projects. Large diameter hydropower tunnels passing through regions of low rock cover
present typical case studies of tunnel construction in the Himalayan Mountains. Tail race
system of 412 MW Rampur HEP presented conditions which required thorough assessment and
detailed analysis in respect of time, cost and technical implications. The construction of these
major civil structures is a good example of thorough construction planning, proactive action to
modify design as per construction requirement and best coordinated effort by construction &
design engineers. Today Rampur HPS 412 MW is successfully running in tandem with NJHPS
1500 MW and providing valuable power to the grid. The experience gained in dealing with
above mentioned issues can be utilized in other projects with similar conditions.
REFERENCES
[1]Design and Construction Report of Rampur Hydropower Project (412MW), SJVN Limited,
India.(2014)
[2]Design and construction of TRT System and under River Crossing of Head Race Tunnel
with specific reference to SJVNs Rampur Hydro Electric Project (412 MW)-India-Revati
Raman, Vivek Chand & R.K. Sharma, 13th International Conference on Underground
Construction held at Prague, Czech Republic.
THE AUTHORS:
Revati Raman He holds M. Tech. degree in Structural Engineering from IIT, Delhi and a
Masters in Business Administration from IGNOU, in addition to Bachelor Degree in Civil
Engineering from university of Pune. He was associated in the design of Rampur HEP from start
to commissioning. He is specialized in design of various component of hydroelectric project. He
is currently working as Dy. Manager and 252 MW Devsari Hydroelectric Project, 60 MW
Naitwar Mori Hydroelectric Project and 44 MW Jakhol Sankhri Hydroelectric Project in
Uttrakhand along with civil design related issue of Nathpa-Jhakri Hydro power station and
Rampur Hydro Power station. He presented a technical paper at International conference on
Underground construction at Prague, Czech Republic.
Vivek Chand graduated in Civil Engineering from Thapar University. He was associated in the
design of various component of Rampur HEP. He is specialized in design of various component
of hydroelectric project. He is currently working as Senior Engineer and looking after designs of
252 MW Devsari Hydroelectric Project, 60 MW Naitwar Mori Hydroelectric Project and 44 MW
Jakhol Sankhri Hydroelectric Project in Uttrakhand along with civil design related issue of
Nathpa-Jhakri Hydro power station and Rampur Hydro Power station. He was awarded with
Promising Young Executive award at the India Power Awards 2016, organized by the Council
of Power Utilities.