SUBMNITTED ACTUAL

Sl No ACTIVITY START FINISH START FINISH

Receipt Of Fencing Permit from Municipality

Receipt of NOC From Municipality

Obtaing Building Permit

Civil Defense Approval

Basement

Excavation

PCC Laying

Raft Slab

Ground Floor slab Part1

Ground Floor slab Part2

Access for Basement works

Roof floor Slab- Part 1

Roof floor Slab- Part 2

Ground floor finising

Access to EOT crane erection

Access of 132kV GIS erection

Access to Roof (A/C Equipment)

Access to Battery room

Access to control, DC and LVAC Rooms

Access to SCADA Rooms , 33kV & 11kV rooms

Access to Capacitor & NER Rooms

Access of Power Transformer Room

Access of HVDT Room

Access to AT Room

Access to fire pump erection

Access to Fire Water tank erection

Electrical

Cable Tray Installtion works in Basement


A3-DHAID -MEP MICRO LEVEL SCHEDULE AS ON 03.02.16
BOQ TOTAL INSTALLATION/ T & C
DESCRIPTION Unit Qty REMARKS
Ref. DURATION Start Date End Date
A3M MECHANICAL WORKS 8-Feb-16 17-Feb-16
A3M 1 Fire Protection and Detection System 1 10 8-Feb-16 17-Feb-16
A3M1B Fixed Water Spray System for IBT Transformer 1 10 8-Feb-16 17-Feb-16
Removal, reinstallation and retesting of Fixed Water
1B.01 1 10 8-Feb-16 17-Feb-16
Spray System for IBT room.
A3M1D Automatic Fire Detection and Alarm System
A3M1E Portable Fire Extinguishers

1E.01 Portable Fire Extinguishers C02 (5kg) and DCD (4.5kg), complete set 1 1 9-Feb-16 9-Feb-16

A3M1F Fire stopping

1F.01 Fire stopping for cable and cable tray entries, wall and floor openings 1 2 10-Feb-16 11-Feb-16