PROJECT CASE STUDY

IMPLEMENTATION OF ISO 9001


FAUJI FERTILIZER BIN QASIM LIMITED
SUBMITTED TO:
SIR ABDUL BASIT
SUBMITTED BY:
Hammad Haider
Saba Aziz
Ibrahim Ali
Ammar Ahmed
Saqib Altaf

CLASS: BBA-8(A)

1
Table of Contents
Implementation of ISO 9001 on FFBL

Abstract............................................................................................................................................4
Overview Fauji Fertilizer Bin Qasim Limited.................................................................................5
REASONS FOR SEEKING CERTIFICATION..............................................................................5
THE QUALITY SYSTEM..........................................................................................................5
The quality system before ISO.................................................................................................5
The quality system after I.S.O..................................................................................................5
Implementation of ISO 9001 techniques in Fauji Fertilizer Bin Qasim Limited............................2
A) Customer focus:....................................................................................................................2
B) Leadership:...........................................................................................................................2
C) Engagement OF people :......................................................................................................2
D) Process Approach :...............................................................................................................3
E) Improvement:........................................................................................................................3
F) Evidence Based Decision making:.......................................................................................3
G) Relationship Management :..................................................................................................3
Quality Issues at Fauji Fertilizer Bin Qasim Limited (FFBL).........................................................4
1) Procured material quality control is weak:...........................................................................4
2) Plants are old as compared to the competitors:....................................................................4
3) No separate labs for checking procured material:................................................................4
4) Tall hierarchy creates communication difficult:...................................................................4
5) Lack of evaluation:...............................................................................................................4
6) Poor new product reliability.................................................................................................5
7) Damage to environment:.......................................................................................................5
Recommendations for the Quality Issues at Fauji Fertilizer Bin Qasim Limited (FFBL)..............5
Procured material quality control is weak:..................................................................................5
Plants are old as compared to the competitors:............................................................................5
No separate labs for checking procured material:........................................................................6
Tall hierarchy creates communication difficult :..........................................................................6
Lack of evaluation:.......................................................................................................................6

2
Poor new product reliability:........................................................................................................6
Environmental safety:..................................................................................................................7
LESSON LEARNED.......................................................................................................................7
IMPACT OF ISO 9001 IN FAUJI FERTILIZER (BQL):...............................................................7
Benefits to Fauji fertilizer organization.......................................................................................7
Benefits to Fauji fertilizer (BQL) customers:..............................................................................8
PLANS FOR THE FUTURE...........................................................................................................8
References........................................................................................................................................8

3
Abstract

Total Quality management is not a technique but its a holistic philosophy of a


company that goes over everywhere around the organization with an-intend to
provide the organizations customers with products and services that satisfy
their specific needs. For every business success depends on its quality
structure and its important for every business to set their quality standards in
order to meet their customer needs and for their long term success. In this
essence there are a lot of quality standards but in this case we are focusing on
ISO 9001 & ISO 14000 and we had to examine these standards on FAUJI
FERTILIZER BIN QASIM against the back drop of Total Quality
Management.

4
Overview Fauji Fertilizer Bin implement all program activities in Ghaggar
Qasim Limited Phattak Bin Qasim Town, Karachi.

The Company started out in 1993 as Fauji REASONS FOR SEEKING


Jordan Fertilizer Company (FJFC), a joint CERTIFICATION
venture of Fauji Foundation. At that time it According to Major Malik the supply chain
is the largest producer of fertilizer with the analyst at FFBL, for fauji fertilizer quality
capacity of 1,670 metric tons per day of was considered to be the fundamental
Granulated Urea and 1,350 metric tons of requirement for their long-term survival and
Di-Ammonia phosphate (DAP). FFBL plant to compete in a new local and international
site is a modern Granular Urea and Di- markets. The main aim for certification was
Ammonia Phosphate (DAP) fertilizer seemed to be the need for developing an
manufacturing complex, built at a cost of effective quality system.
US$ 468 million and located on 350 acres in FFC believed that certification from the
the Eastern Zone of Bin Qasim, Karachi. I.S.O establishes an effective system which
They are sole producer of DAP and Granular can improve their business performance as
Urea, it is making a significant contribution well as their product quality.
towards agricultural growth in the country,
by meeting around 50% of the demand of THE QUALITY SYSTEM
DAP and about 10% of Urea in the domestic The quality system before ISO
market. They are the first Pakistani
Company to enter into a Joint Venture Before the implementation of I.S.O: quality
Project for Phosphoric Acid with Morocco was recognized as only meeting the
in 2008. This has proven to be a huge asset customer specifications for FFC. Its quality
for the company. They continue to sustain system was only emphasized on a problem-
growth strategically. FFBL is so committed solving approach which was unstructured
and dedicated, they continue to strive for and function oriented. Their standards
excellence collaboratively. FFBL take the operations, working conditions and
social responsibility on themselves, it is the instructions were inadequate and the quality
primary concern of FFBL,they have component of document control was
distinguished themselves as a good inadequate. Some were obsolete and they
neighbor, not only they consistently were not investigated routinely. The
delivered outstanding returns to procedure was a continuous change over
shareholders, but they strive hard to be a numerous years, which along these lines
good employer, to be a catalyst for the social included distinctive supervisors and which
and economic development of the catered for the changing prerequisites of
communities in which they operate, and aim ISO. Be that as it may, a few methodology
to minimize environmental impact. In Nov were set up in specific areas, for example,
2010, a long-term CSR Program was the Lab facility for scouring.
launched in collaboration with a renowned
The quality system after I.S.O
NGO, Human Development Foundation
(HDF) As per MOU the NGO has to

5
After ISO execution, they had accomplished and support goods and services to meet
a total cultural change: everyone was customer needs and expectations and
responsible for quality. And this provide quality fertilizer which not only
responsibility was delegated to the lowest boost the crop yield but also helps the
hierarchical level. In a quality administration land to increase its fertility.FFBL aims to
program, quality was characterized as maintain long term and good relations
addressing clients' needs and wishes and with its customers and therefore also
was implicit thus of aggregate duty. The organize vocational trainings program in
critical thinking methodology was order to provide them with the
organized, participatory, and handle awareness.
arranged (cross-useful). The organization
built up a quality confirmation office which
was accountable for the accompanying B) Leadership: At FFBL there is a culture
work: of eternal trust and value, FFBL claims
to be an equal opportunity Employer and
Implementation of ISO 9001 therefore at all levels there is open level
techniques in Fauji Fertilizer Bin of communication. The managers are
Qasim Limited connected to lower levels staff and they
answer and ask if the production staff
The seven quality management principles have some query regarding the operation
are: and functioning of machines or
whatsoever the issue is .As FFBL is run
QMP 1 Customer focus by retired Army personnel so they have a
QMP 2 Leadership system of ethical and moral values also.
QMP 3 Engagement of people No one is given edge or superiority over
QMP 4 Process approach other and they have a policy of
QMP 5 Improvement accountability at all levels whether at the
QMP 6 Evidence-based decision top most position or the lower level
making position. The group leaders/managers
QMP 7 Relationship management are empowered and provided with all the
necessary resources that they need
A) Customer focus: After having the brief during that course of work. The
interview with SCM section manager he authority is provided to the designated
enforces that it is FFBL top priority to staff but again there is a system of
deal customers with care and to deal accountability too
them with utmost fair means and provide
them quality material they need, Fauji, s C) Engagement OF people : As told earlier
main customers are the Farmers because Fauji have a culture of Enhanced trust
they will use the fertilizer in the crop and collaboration throughout the
production .Fauji tries to maintain organization, they engage their workers
contacts with them, through telephone or at all levels , the workers are motivated
personal visits to the sites. Fauji listen to work for the larger interest of the
and answers to their queries also.FFBL organizations and not to think for
Plan, design, develop, produce, deliver individual benefit but as a firm as

6
whole .There is both on the job and off resource policy and many more. On
the job training given to develop and daily basis they encounter different
polish the organizational skills of challenges yet they didnt divert
employees .There is absolute themselves from their main focus which
empowerment and the vision mission is providing quality fertilizers through
and core activities are translated and the best chemicals proper mechanisms
shared with the common people so that that will enhance the fertility and crop
every staff must be on-board and FFBL yield as well.
truly promotes collaboration and heavily
relies on involving employees to the F) Evidence Based Decision making: At
accomplishment of its primary objective FFBL they have a policy of
Determining, measuring and monitoring
D) Process Approach : At FFBL key indicators to validate the
specifically the higher authority and the organizations performance. The
management focuses on Consistent and management Make that all data needed
predictable outcomes through a system available to the relevant people.
of aligned processes the process are not Furthermore they also ensure that data
taken in isolation rather than the outputs and information are sufficiently
are inputs for the other processes and accurate, reliable and secure. Moreover
hence therefore FFBL considers the organization Analyze and evaluate
important that all activities should be data and information using suitable
aligned and in the end should tie up with devices. Ensure people are experienced
the corporate policy or the mission of the to analyses and evaluate data as needed.
organization .What FFBL does it that Make decisions and take actions based
they recognize and analyze the resource on evidence, balanced with experience
constraints that they might have before and sensitivity. All the work is done on
opting for the work. FFBL Manage risks the basis of numeric data and anything
that can affect outputs of the processes that does not satisfy the proper data
and overall outcomes of the quality evidences is not valid and is not taken
management system through the proper into account therefore her at FFBL there
monitoring phase and hence the process is strict compliance with the fact and
that are faulty will not be continued figures .
anymore and shall be start from the
beginning again . G) Relationship Management :At FFBL they
ensure and it is there main objective that
E) Improvement: like any other Successful they possess A well-managed supply
organizations have an ongoing focus on chain that provides a stable flow of
improvement FFBL undoubtedly goods and services and for balancing the
possess a culture and an environment of supply chain there need to be effective
continuous improvement which is the relationship between tall the partnering
main and absolute function of TQM , the neighbors or the chain members in the
upper management promotes and spread whole Supply chain .FFBL promotes
a spirit of improvement in there dialogue and discussion policy with all
processes policies , work load , Human its stakeholders whether they are their

7
customer , their suppliers , their depreciating time to time and within a
shareholders , their employees or the passage of time if not given proper
society members who owns or are attention to them will totally become
affected by the organization . obsolete or will not be able to produce
the optimal level. The plants should be
replaced as Engro fertilizer are using
Quality Issues at Fauji Fertilizer new plants which are very new as
Bin Qasim Limited (FFBL) compared to FFBL .The FFBL only has
the industrial paint on annual basis but
1) Procured material quality control is thats just not enough .There is a right
weak: It is a usual concept that in any time that old machines should be
organizations there is a procurements replaced with new ones.
departments and for any firm in order to
function the items are needed to be 3) No separate labs for checking procured
procured which are either used directly material: FFBL does not have its own
in the production process or there are very own lab for material testing that
some indirect materials such as have been procured whether they are
stationery or other miscellaneous items. optimal and fit to be used in the
Here at FFBL according to the supply production process .Because sometimes
chain section manager the items that are it happens that the quality claimed is not
procured other than the chemical needed up to mark and products are not checked
for the making of fertilizer not of the before being inserted into machinery
said quality and sometimes it effects the .The competitors of Fauji fertilizer have
functioning of the machines which may their own separate labs which make
result in the process halt for example if them stand out.
the FFBL procures Shell helix oil it does
not check before putting it in machine
that whether this lubricant will support 4) Tall hierarchy creates communication
the machinery or will work for longer difficult: Fauji Fertilizers follows a tall
time but they just use it believing that hierarchy which are as follows section
what the company Shell claims is manager , manager , senior manager ,
hundred percent true and once a steel director and then it follows on .Due to
pipe was procured for some industrial this hierarchy system that Fauji follows
usage and afterwards the company came the communication becomes very
to know that this was not 100 percent difficult and it is very difficult for the
steel and eventually it resulted in the engineer or lower level employee
breakdown of that pipe and the working in the plant to pass-on the
manufacturing process stopped for some message to higher level officer and as it
hours. takes longer time for the message to
pass-on and as it is much time-
2) Plants are old as compared to the consuming activity so it usually happens
competitors: According to the section that the wrong message is delivered
manager SCM, the plants that are being which can lead to reduce the
used in FFBL are very old and they are effectiveness of the overall process
8
is a damage to the environment as well
5) Lack of evaluation: Successful because that gases also damages our
organization search for their problems, ozone layer and is a cause to global
issues on entire company and take warming all around the city .These gases
feedback from their lower management are also common causes of Heat wave
because lower management knows better also.
what problems they face in their
manufacturing process and other system Recommendations for the Quality
of organizations so that they can resolve Issues at Fauji Fertilizer Bin Qasim
their problem and improve the process Limited (FFBL)
which leads them to excellence. But
unfortunately fauji fertilizer ignore these Procured material quality control is weak:
opportunities, they dont take feedback
from their employees which hinder their As per the recommendation suggestion that
performances. Fauji also lacks taking we being the researcher would like to say
feedback from their potential customers that FFBL should develop a proper
who are farmers , the company should procurement department though, they
take proper classes and should introduce already have one but a proper department
such measures which would encourage with a procurement demand and rules should
to take some insights from them be there which should constitute of the
following things like in other corporate
6) Poor new product reliability : The FFBL firms.
main product is white fertilizer and black
fertilizer .The black fertilizer is there to Plants are old as compared to the
make the land fertilize and make it competitors:
suitable for planting while the white
fertilizer is for boosting and increasing After going through a detail analysis on the
the crop yield which will enhance and FFBL machinery it was observed that the
make the crop grow more and more .but machines which are being used are very old
in recent days as per the manager the and are from the very old era of late 50s and
white crop could not result in proper 60s though they are being repaired on an
functioning and several farmers compassionate ground but as we see that
complaint that this was no as affective as world is progressing at a very rapid pace so
it used to be a year ago because the more efficient and better machinery is
crops output was just normal required which will result in more effective
outcomes with low-fuel cost and more profit
7) Damage to environment: Due to can be achieved through effective measures.
emissions of gases and hazardous If we look at the maintenance system of
substances the health of the employees FFBL it is quiet good
gets affected and due to this the ratio of As follows:
workers working in the plant who gets Preventive Maintenance: Periodic
absent due to poor health increases and maintenance (as per OEM
due to this reason what happens guidelines).
ultimately is loss in production and there

9
Predictive Maintenance: Condition barriers lead to many problems such as
monitoring / Field data analysis. inaction : a false message could lead to fail
Corrective Maintenance: On-line and to act , Misinterpretation : it can lead to the
shutdown maintenance. falsely act to person which should not be
performed or negative image is established
Machinery is very old the methods are at times , Bad work relationship : lead to
very good to operate more effectively disengaged and even conflicting
they should come up with modern relationships among colleagues, or between
technology and machines used for more supervisors and subordinates if there will be
results by other majors firms like Engro no effective communication then distorted
fertilizer uses modern and advance or unclear messages delivered will cause
machines it should be adopted by FFBL
problems for the organization so , there
as well. More effective and better
should be an operating system which every
machines will not only increase revenue
or save cost but it will also make the employees could you most of the technical
work easier for people for whom that or officials while for the lower which there
was a very difficult task to do. messages should be forwarded in terms of
voice message or calls because they are not
skilled and cant use the system properly so
No separate labs for checking procured
this would make the organization for
material:.
appropriate and effective.
If you are making a specific product and that
is your core component so necessary Lack of evaluation:
measures for the quality checks should be
there because if the product does not meet Evaluation is the key to a successful
the desired expectation of the customer you organization because if you would not take
might lose your market share and business the feedback you will eventually be at a
so, in order to save this chaos FFBL after great risk of organization downfall. FFBL
research analysis should make proper labs does not have a system in which you
that should inspect the type of material and evaluate or take recommendation form the
standards of the operations are being lower management neither from the middle
followed or not. like for fertilizer right management as guided by the upper
proportion of Nitrate of soda , management organizations works according
Superphosphate , copper sulphate , to that. To meet the requirement, the
Manganese sulfate etc. all of these Company introduced a comprehensive
chemicals should be check and should be confidential questionnaire covering boards
used as per the requirement of the composition / scope, its objectives /
production standards . functions, companys performance and
monitoring etc. The Board evaluated all the
factors in depth and based on inputs
Tall hierarchy creates communication received from the Directors all the aspects
difficult : were evaluated.
As mentioned earlier the organization is
working on old norms and Communications Poor new product reliability:

10
As the environment and weather conditions khan stated the importance of ISO 9001 and
have changed so does it had made its impact focuses on the need to adopt quality systems
on the soil of the earth. So changes have which are appropriate for Fauji Fertilizer
been there and the FFBL has not adopted the Company. Furthermore he stated that quality
new methods with the changes in the earth management system enable your company
as other companies had they are still to approach perfection. As when processes
working on the same method which is improve, it become more consistent, and
obviously not resulting in the better results then you achieve your target objectives with
which are obviously not fruitful for the greater regularity and then you will see
organization. New methods with good tangible results and in end your process
approaches should be adopted as it results in waste will decrease as the waste is money
better outcomes. which is lost forever and waste will lead to
have poor quality and inefficiency but
Environmental safety: implementing ISO 9001 will improve
efficiency, reduce waste and will save the
FFBL recognizes its responsibility towards money of the organization.
protecting, preserving and improving the
environment since commissioning of its
Ammonia, Urea and DAP plants. FFBL IMPACT OF ISO 9001 IN FAUJI
management believes that protecting FERTILIZER (BQL):
the environment is not only an ethical and
legal obligation but also a mechanism for The supply chain manager of Fauji Fertilizer
success. FFBL certified for Environmental Bin Qasim Ltd Major Malik Muhammad
Management System (ISO 14001:2004) in khan share his experience of quality system
implemented and stated that quality
2006 to strengthen its dedicated efforts
management system based on ISO 9001 has
towards the prevention of pollution in air,
been very affirmative and constructive for
water and soil. FFBL is forerunner fertilizer the growth of our company. It has provide
industry in the country which opted for plenty of benefits for both organization as
environment friendly Phosphate based well customers of Fauji Company.
cooling water treatment program. There is Following are some of the benefits.
still a lot of work that needs to be done in
order to save the environment and resulting Benefits to Fauji fertilizer organization
causes that would be taking place after the
hazardous gases, as these things causes the ISO 9001 Provides senior
depletion of ozone layer so CFC emission management with an efficient
free substance should be used besides management process
chemical waste causes various problems in
the society for that proper treatment facility Implementing ISO 9001 will lead to
should be used where they should turn that Set out areas of responsibility across
waste into an useful resource of energy. the organization

LESSON LEARNED Communicates a positive message to


The supply chain manager of Fauji Fertilizer staff and customers
Bin Qasim Ltd Major Malik Muhammad

11
Identifies and encourages more PLANS FOR THE FUTURE
efficient and time saving processes
FAUJI understood that ISO 9001 affirmation
Highlights deficiencies
was not the finish of adventure. Rather, it set
up the base whereupon the quality
Reduces the costs
superstructure ought to be constructed, not
just as a way to pick up attention and
Provides continuous assessment and
attractiveness additionally to accomplish
improvement
persistent quality change.
Marketing opportunities MR. Khan underlined that the quality
framework introduced in consistence with
ISO 9000 must be intended to expand
effectiveness, profitability and to
Benefits to Fauji fertilizer (BQL) customers: accomplish persistent change in quality. The
Plants at Bin Qasim facility are totally
Improved quality and service certified under ISO 9001 and the plants have
been certified according to proper quality
Delivery on time management principles but What Supply
chain manager believes is that there were
Right first time attitude still some loopholes which they highlighted
which needs to be sorted out through a
Fewer returned products and mechanism of proper evaluation and
complaints monitoring tool
Independent audit demonstrates
commitment to quality

12
References

http://asq.org/learn-about-quality/total-quality-management/overview/tqm-history.html
http://www.philipcrosby.com/25years/read.html
http://www.iioc.org/external-reports/total-quality-management-iso-9000-certification-and-performance-
improvement/
https://www.iso.org/the-iso-story.html
http://www.qualitymag.com/articles/88303-management-the-future-of-quality-iso-standards
http://www.ffbl.com/ffbl/FFB__Annual_Report_2014_complete_final%20-%20Copy%20(2).pdf
Fauji fertilizer annual report of 2015