Академический Документы
Профессиональный Документы
Культура Документы
4U Course
Chapter 3
CHAPTER 1
1. Engineering Offshore Structures
1 General Background
Historically it is true to say that in the initial stages of development of offshore oil
platforms the designs evolved from land-based structures and were constructed
on site. The engineering design knowledge was either borrowed or extrapolated
from traditional fields of civil engineering and naval architecture. During the
1950s, however, new technology began to be developed for this type of
structure. Since then many advances have been made particularly in the field of
materials. Governments legislation in the various host countries with offshore
oil has also played a role in shaping the design of production platforms and the
various other structures seen offshore. Economics are very important and play
a leading role in platform design. For example it is only possible to justify the
expenditure for a massive eight-legged steel of a huge concrete gravity platform
when the hydrocarbon reserves in a particular field are large enough to not only
warrant the initial capital cost but will also guarantee a good income for a long
period of time. There is also a growing concern for the environment and this
consideration influences certain aspects of structural design. Another factor of
prime importance is safety of personnel. There are two facets to this:
1.1. Safe To Operate
The first facet is the usual concern of engineers to design a structure which
is elegant if possible, conservative in its use of materials, fit for the design
purpose, able to operate for the prescribed length of time, safe to operate
and within the allowed budget.
1.2. Government Legislation
The other facet is government legislation. This is put in place to ensure that
structures are fit in all aspects, including safety, for the purpose they are
designed to fulfil.
2. Design Specifications
The requirements for an offshore platform will necessitate the consideration of a
number of factors and involve drawing up DESIGN SPECIFICATION. The full
design specification will contain many different factors, but by way of illustration
the following list should serve to indicate some factors affecting load bearing
and cost.
2.1. Materials
These should be readily available from suppliers in the required form and
should meet the requirements of the design specification.
2.2. Working Life
This may typically be 25 years
Tuition Notes for 3.4U Course
Chapter 2
2.3. Loading
The platform should provide a safe working environment for the purpose
of recovering hydrocarbon reserves. It must be capable of withstanding
the loads imposed on it by the drilling and other works performed in and
on the work areas and it must withstand the forces imposed by wind and
wave action.
2.4. Environment
The open sea, which will impose very harsh conditions indeed on the entire
structure but especially the jacket. Due consideration must be made to the
effects of corrosion because of this environment.
2.5. Maintenance
This should be kept to the barest minimum. Cue consideration must be
given to the underwater maintenance being especially singled out wit a view
to not only minimising bit but also to use the most cost effective means of
achieving any necessary works.
2.6. Weight
The weight of the deck modules must be considered so that the jacket can
be designed to support this weight. The all-up weight will have ramifications
on the cost and on the seabed design of the foundations.
2.7. Dimensions
The size of the structure will be dictated by the work functions required to be
carried out and will be strongly affected by the requirements to keep the
topside weight to the minimum.
3. Construction Activity Monitoring System
At the same time as the Design Specification is drafted it is possible for the
QUALITY ASSURANCE (QA) function to be implemented. This can take the
form of an Activity Monitoring System that would compile: -
Full certification for the location of all components, normally by way of
as built drawings. This would normally include any concessions, repairs
and the actual location of J tube and temporary access holes.
Full material certification
Non-destructive Testing (NDT) and inspection certification, which would
include personnel qualifications.
4. Guidance On Design And Construction
With these engineering requirements in mind as the basic starting point design
and structural engineers will be able to obtain guidance as to what minimum
standards are acceptable to the appropriate authority or government body
whatever country they are operating in. As an example of these types of
guidance two different sets of national regulations will be illustrated.
Tuition Notes for 3.4U Course
Chapter 3
regulations lay down in broad terms the minimum standards for the design
and construction of offshore structures in offshore environments as indicated
below. The major difference between the US and the UK regulations at that
time was the fact that the US offered advise and cited recommended
practice but did not authorise certification authorities. Nor does it now.
4.3.1. Guidance From The US Regulations
US regulations are intended for use in the American offshore
environment, but, because they are based on good engineering practice,
in common with the old UK regulations, the guidance follows much the
same ground. This is not surprising, as the structures will have to
withstand very similar forces and loadings.
4.3.1.1. Planning
The US Guidance, which was given for this aspect of the design
function considers such items as: -
Function
The function for which the structure is intended such as drilling,
producing, storage, accommodation, or a combination of these.
The Location
Orientation
Water Depth
All of these factors being considered with a view o giving guidance as
to what parameters should be applied.
The environmental conditions are considered and designers are
specifically advised to make best use of all available statistical and
mathematical modelling data todevelop the description of
operating and extreme environmental conditions.
Operating Environmental Conditions
(Those conditions which are expected to occur frequently during
the life of the structure) are important both during the construction
and the life of a platform.
Extreme Conditions
(Those conditions which recur quite rarely during the life of the
structure) are important in formulating platform design loadings
Wind
Waves
Tides
Tuition Notes for 3.4U Course
Chapter 2
Currents
Ice
Earthquakes
Sea-floor Instability
Scour
Marine Fouling
As with the UK guidance loads are given full consideration and are
defined as: -
Dead Loads
Live Loads
Environmental Loads
Construction Loads
Dynamic Loads
5. Conclusion
It is obvious from the comparisons made here and from common engineering
experience that the engineering requirements for offshore structures anywhere
in the world will be similar. The only marked changes will be due to local
conditions either imposing greater loadings on the structure or perhaps the local
environment being more aggressive. The basic engineering will not change but
some components may have to be more massive or higher-grade materials may
be required to meet these local requirements.
6. Pipelines
Offshore pipelines are used to transport oil or gas from platform to loading
towers or to shore. They are fabricated from high-grade steel pipe (e.g.API-5LX)
which is bitumen wrapped for corrosion prevention and coated with a layer of
reinforced concrete to provide a weight coating which gives additional protection
as well.
The sizes normally vary from 50 mm (2) to 914 mm (36) and the wall thickness
normally varies according to the pressure rating required.
6.1. Pipeline Laying
The methods for laying pipe has evolved since the 1950s and utilises lay
barges on which standard 12 m lengths of pipe are welded together along
the centre of the specially designed and fitted out deck of the vessel.
Each joint is X-rayed and then coated with bitumen and
wrapped with a protective sheathing.
As new lengths of pipe are added the assembly is fed over the
stern and the barge is moved forward, usually by pulling on
anchors, which have been laid by an associated anchor-
handling vessel.
An alternative approach is laying pipe from a reel barge. The earliest
application of this technique occurred during World War II when a 76 mm
(3) diameter pipe was laid across the English Channel in Operation PLUTO
(Pipeline Under The Ocean). This early application utilised floating reels with
the pipeline being unwrapped from them as they were towed along.
The modern application requires the pipe to be prepared on land and then
wound onto the reel which is mounted on the stern of the reel laying vessel
which itself is moored at a specially designed pier. The vessel then proceeds
to the required site and lays the pipeline by un-reeling it over the stern as the
barge steams forward.
The welding and preparation work on land is carried out in a spooling
yard, where the pipe sections are supplied in 12 m (40 ft) lengths.
These are welded together to form stalks, usually about 518 m
(1700 ft) long. All the welds are X-rayed and coated and the stalks are
stowed in racks alongside the spooling dock.
Tuition Notes for 3.4U Course
Chapter 2
At the start of spooling, the first stalk is moved into the roller system.
The end is welded to a stub of pipe on the reel and is pulled onto the
reel. The second length is then welded to the end of the first, the weld
is X-rayed and coated and the procedure is then repeated for
subsequent stalks.
All welding and loading operations are performed at the shore facility
and therefore are less affected by weather conditions.
The major area of criticality is establishing and maintaining even
tightness of the wraps on the reel. This is to avoid potential
breakthrough of one wrap into another, which would cause damage to
the pipe.
The reeling and un-reeling of the pipe actually causes yielding of the
steel and the maximum diameter pipeline that can be laid is 600 mm
(24).
See Figure 1.2
Figure 1.2
MSV Norlift, laying the 10in pipeline,
between the Neptune and Mercury fields.
7. Offshore Oil Terminals
Large oil tankers are cheaper to run than small tankers. This philosophy of
building large tankers was reinforced in the 1950s when the Suez crisis forced
tankers from the Gulf to detour around the South of Africa in order to reach
Europe. As tanker sizes increased the number of ports that could handle
tankers decreased and public opinion was against allowing such tankers too
close to inhabited areas. Many solution were proposed to solve this problem of
shrinking docking facilities which included artificial harbours, artificial offshore
islands, multiple buoy mooring systems, tower mooring systems and Single
Point Mooring systems (SPMs).
Tuition Notes for 3.4U Course
Chapter 3
The SPM is the most widely used because of its relatively low operational cost,
reliability and flexibility. This configuration is illustrated in a later Chapter.
8. Future Trends
The future is likely to see continued development of current trends and
techniques in all areas of offshore engineering, with the probability of new
techniques being evolved to enable the exploitation of reserves which are
currently marginal or beyond the range of present day techniques.
8.1. Drilling
This is a branch of engineering, which has seen numerous developments
the results of which have made recovery of reserves more efficient and more
effective. Cost reduction and further development of marginal reserves will,
no doubt, cause a continuation of developments of the present techniques
and trends. There will surely be, for instance, increased use of: -
Horizontal Drilling
This enables more formation to be exposed to production and reduces
reservoir problems such as associated gas and water production. It is
useful for thin and tight, low permeability reservoirs. Fewer wells are
needed to achieve optimum reservoir production than with conventional
drilling. Figure 1.3 refers.
Figure 1.3
Diagram Of Bottomhole Assemblies
These Bottomhole Assemblies Are Designed For
Drilling A Straight Hole (Left) And A Directional Hole (Right)
Tuition Notes for 3.4U Course
Chapter 2
Figure 1.4
The Drill Floor Showing
The Drill String Being Broken Out
Tuition Notes for 3.4U Course
Chapter 3
Figure 1.5
The Derrick.
The Pyramidal Derrick Supports
The Crown Blocks And The Drillstring
Photo courtesy of Mark S. Ramsey
Figure 11.6
Photograph Of Crown Block
The Pulleys That Make Up The Crown Block
Allow The Cable To Hoist Heavy Loads.
Photo courtesy of Mark S. Ramsey
Tuition Notes for 3.4U Course
Chapter 2
Figure 1.7
Drawworks
The Drawworks Reels The Drilling Line In Or Out Over The Crown Blocks To
Raise Or Lower The Travelling Block (Shows The Spool-Like Drawworks
Without The Drilling Line
Photo courtesy of Mark S. Ramsey
Figure 11.8
Travelling Block
The Yellow Travelling Block Moves Up And Down In The Derrick, Suspended By
The Black Wire Rope, To Lift Or Lower The Drillstring Or Casing
Photo courtesy of the Petroleum Extension Service The University of Texas at Austin
Tuition Notes for 3.4U Course
Chapter 3
Figure 11.9
Breakout Cathead. The Breakout Cathead Allows The Driller To Make A
Connection Using The Power Of The Motor
Photo courtesy of the Petroleum Extension Service, The University of Texas at Austin
Figure 1.10
Spinning chain
The Spinning Chain (Centre Photograph) Turns Pipe Rapidly, But Is A
Dangerous Way To Screw Pipe Together Because Of Potential For Catching
And Damaging Clothing And Fingers. Mechanical Spinning Devices Are Now
Favoured Over Spinning Chains
Photo courtesy of the Petroleum Extension Service, The University of Texas at Austin
Tuition Notes for 3.4U Course
Chapter 2
Figure 1.11
Slips
The Rig Crew Sets Wedge-Like Pipe Slips (Near The Bottom Of This
Photograph) In The Rotary Table To Hold The Pipe While Another Component Is
Added To The Drillstring
Photo courtesy of the Petroleum Extension Service, The University of Texas at Austin.
Figure 1.12
Gannet Platform North Sea
Central Sector
Tender Assisted Operations
These operations also help to minimise the weight of the production
platform by providing most drilling support equipment on a floating
anchored, ship-shaped tender in calm waters or an anchored semi-
submersible unit for deeper or harsher environments.
Mobile Drilling Units
These are jack-up or semi-submersible rigs, depending on water and
they can be used to drill production wells (with well completion on the
seabed and production pipelines led to a nearby facility) where size and
economics of the reservoir do not justify the installation of a platform.
Tuition Notes for 3.4U Course
Chapter 2