Академический Документы
Профессиональный Документы
Культура Документы
SPATSAElDCONSTRUCTION
COSTCONTROL
Hobert Smith
Chief SPATSEngineer, Planning
The H. K. Ferguson Company, Inc.
One Erieview Plaza
Cleveland, Ohio till&
Presented At
AMERICANASSOCIATIONOF COSTENGINEERS
LlTH~TIONdL~TING,CLEVELAND,OHIO
JULY 10-12, 1967
- 203 -
The need for an effective method of eontrolling non- No control system, including SPATS, can be self-
repetitive operations, such as those which typify the contained and function successfully. Each must draw
construction industry, has long been apparent. Devel- upon every facet of the organization for pertinent
opment of PERT, LESS, CPM, and several other information. As Figure II indicates, all functional
planning-scheduling and control methods did not provide areas of the organization contribute to the overall
an adaquate solution. Sequence Planning and rime effort.
scheduling - SPATS - a control technique developed by
The II. If. Ferguson Company does provide all the For ezample, the Project Engineer and Project Con-
elements necessary for total project control. Applied struction Manager provide duration, progress, man-
initially to the Companys construction operations, this power requirements, and similar data while material
system has been expanded to include engineering, pur- and equipment costs, delivery dates, and other related
chasing, expediting, safety, and labor relations activi- information is furnished by Purchasing. Similarily,
ties. SPATS is today effectively providing the manage- wage rates, jurisdictional agreements, and manpower
ment of our company and others with a meaningful tool availability figures are obtained from Labor Relations.
for total control.
Of special significance is the data received from the
But SPATS is just that - a tool, not a substitute for Estimating Department. This detailed information
effective management. It does not make decisions nor concerning direct labor costs and direct manpower
does it solve problems. But it provides the informa- requirements is used as the primary comparison fac-
tion necessary for valid decisions to be made and de- tor throughout a project.
fines problems in advance so corrective action can be
taken before schedules are jeopardized or excessive SPATS, in turn, provides a medium for the free inter-
costs incurred. change of data among these groups and acts as a co-
ordinator between them. But above all, it provides
SPATS, by incorporating, altering, and adding to the management with the information essential to making
methods of other planning and control systems, ac- sound judgements and decisions.
complishes its purpose through the collection and
dissemination of information. To a large degree, the The development and acceptance of planning and con-
nomenclature and network diagrams (Figure I) are trol systems has been ,influenced considerably by the
common to the other systems. use of data processing equipment. Although more
EARLY START
CRITICAL ACTIVITY
Figure I
- 204 -
sophisticated installations dc permit greater flexibility A thorough analysis of this data is made by the SPATS
and variations in programming, large units are not Engineering Department. All critical activities are
necessary for the computerization of any system, studied to determine if economical and practical ways
Presently, at Ferguson, an IBM 360-C computer with exist to reduce duration times and thus advance project
high speed printers, sorters, and other peripheral completion. Among these possibilities are increases
equipment is used for processing SPATS data. Row- in manpower, further overlapping of activities, and use
ever, less complex installations are satisfactory for of overtime.
projects of moderate size requiring only a modest
degree of data processing. The modified data is then reprocessed and a new LESS
Phase printout obtained (Printout I). Further analyses
Computer time required for SPATS is minimal; current- are made and additional reprocessing is done until it is
ly somewhat less than one percent of total available determined that the data represents a desirable, realis-
capacity is used for this purpose. At other times the tic, and economical schedule. Only then is the MAN-
equipment is utilized for engineering calculations, POWER Phase begun.
general accounting and statistical functions.
SOURCES OF
INFORMATION AND CONSULTATION
PAST - - LABOR
RECORDS - - RELATIONS
PROCUREMENT SAFETY
ESTIMATING
FIGURE II
The computer program for the SPATS system consists The MANPOWER Phase, a Ferguson innovation, com-
of two basic phases (Figure RI). The LESS Phase bines resource requirements and restrictions with the
provides least cost estimating and scheduling. This is LESS Phase output data. Manpower needs are introduc-
a tabular model of the project resulting from activity ed through the input data (Figure V), using composite
durations supplied in the input data (Figure IV). Event crews - forces comprised of craftsmen from more than
identification numbers and activity descriptions, craft one trade. For example, while the erection of struc-
designations, and manpower requirements are also in- tural steel is normally done by ironworkers, such items
cluded. as tank and vessel installation require work by boiler-
makers, pipefitters, and ironworkers. Therefore, a
The LESS Phase computer output provides early and composite crew, denoted TANK for computer purpo&
late start and finish times, total float, and free float es, may con&et of three boilermakers, two pipefitters,
for each activity. Manpower requirements and craft and one ironworker (rigger). The same is true of many
designations are also included, but only for reference other activities found on any project.
purposes. This data is in two forms; by calendar dates
and by project workday numbers. The initial output, an unrestricted Manpower Require-
- 205 -
SPATS
COMPUTER SYSTEM FL0 w CHU
Figure III
ments Summary (Printout II), is a day-by-day summa- lists (Printouts IV, V, & VI) are then compiled.
tion of manpower neededto follow the early start-early
finish LESS Phase schedule. At this point, unlimited The General Schedulepresents the activity sequencein
manpower and equipment resources are assumedto be a logical manner and within the limits imposed. It
available. provides preferred start and finish dates for each
activity and represents the most economical and prac-
A study in depth of this summary by the SPATS Engi- tical approach to the project under the prescribed con-
neering Group is made, considering such factors as the ditions .
daily direct labor work force, manpower availability on
a craft basis, and widely fluctuating manpower require- The General Scheduleis illustrated graphically on time-
ments. Construction equipment availability is also sn scale networks (Figure VI). These networks depict all
important factor. work to be performed by engineering, procurement, and
construction and provide a complete visual concept of
Limitations are then introduced to impose the necessary the project. It is here that interdependenciesof
restrictions. If, for instance, the unrestricted man- activities are clearly evident. Thus, the basis for pro-
power requirements indicate several peaks and valleys, ject control is established.
limitations can be applied to induce a leveling effect on
the total work force as well as individual crafts. For To exercise effective control over a project once it is
example, the availability of men in a specific craft is underway, a meansof measuring progress is required.
always an inherent limitation. If there are only twenty- SPATS fulfills this need through a system of periodic
five pipefitters available in a particular area, this is project monitoring. This is in the form of a written
the limit which must be used in manpower planning. discussion of progress achieved on each work area and
is accompaniedwith a Project Progress Chart (Figure
Restrictions are then incorporated and a revised Man- VII) that graphically illustrates current project status.
power Requirements SummarJireceived (Printout III).
If these restrictions do not result in an extension of the The Progress Chart, similar to the familiar construc-
project completion date and if the durations and man- tion bar chart, presents various elements of the project
power needsfor each activity are satisfaotory, the as logical parts of the whole. For instance, typical
MANPOWER Phaseprogram is continued. Manpower unite may include a process building, office building,
graphs, a general schedule, and craft responsibility general site work, storage facilities, and other items.
- 206 -
These are further divided into their component parts. From the network and General Schedule, all activities
The process building would probably include, from the encompassed within each unit or component part would
construction standpoint, foundations and slabs, struc- be grouped together and a duration span for that group
tural steel, equipment installation, process piping, and established. Using manpower requirements shown in
other general work categories. From the engineering the General Schedule, a total of the manpower needed
standpoint, components most likely would be presented for the unit is determined and its proportionate weight
on a discipline basis such as structural, mechanical, of the entire project expressed as a percentage of total
electrical, and so forth. direct labor. Separate figures are used for engineering
RESPONSIBLE
ACTIVITY DESCRIPTION
Figure lV
- 207 -
and construction. Cost Engineers, have long been attempting to accom-
plish. The Purchasing Department is provided with
Actual progress is then measured against the predeter- schedule information much sooner than in the past and
mined schedule. Percentage of work accomplished is expediting per_eonnel have a firm basis for discussions
determined by using a composite of information. Judge- with vendors about deliveries.
ments of experienced personnel associated with the
project are strongly considered, especially in the con- The effect of manpower leveling is of substantial bene-
struction phase where physical measurements of work fit to Labor Relations through reduced employment in-
completed are acertained. For engineering, the pri- terruptions resulting from sound predictions of the needs
mary source is the drawing schedule. Other sources of for specific crafts well in advance. This leads to a re-
project progress include manpower reports, periodic duction of unemployment insurance taxes.
construction reports, purchasing and expediting reports,
job condition statements, and other project data. By The Safety Department is able to study each activity
drawing upon all these sources, a full and accurate well in advance, determining types and degrees of haz-
measurement of project status is reached and areas of ards involved before construction begins. Using the
difficulty made apparent. This allows attention to be coding system pictured in Figure I! advance warnings
given to any problem areas and, therefore, permits are signalled and the appropriate precautions taken.
corrective action to be taken before the project schedule Recorded results today include lower accident rates
or cost is seriously affected. and a savings in insurance costs.
SPATS NETWORK
Figure VI
Full utilization of SPATS means more effective project At Ferguson, SPATS has proved to be an effective,
control from inception to completion. Advantages to practical control system that is based upon logic and
each group or department vary. Zn engineering, Fer- fact and, most importantly, results. Armed with
guson has learned that designing can be done to a sensible objectives, an accurate measurement of per-
schedule, an objective that many people, including formance, and a positive means to avoid difficulties,
management manages effectively with SPATS.
PROJECT PROGRESS CHART
Figure VII
- 209 -
TOT. FR.
TL. HD. DUR MP RESP DESCRIPTION OF ACTMTY E.START E.FIN. L.STAR!c L.FIN. FLT. FLT.
604 605 80 1 ELEF COMPPROCFSS
WIRF:LINE 3
604 618 80 1 ELEF COMFPROCESS
WIRELINE 1
250 0 CONSTRUCT
80 5 P+IF CONTINST DSGN
$08 609 20 5 P+IF COMPINST DSGN
609 653 10 1 AEi O.A. PLANTLGT DSGN
613 558 0 0 DUMMY
613 577 0 0 DUMMY
AB OWNERS APPROVAL
PUR PURFORSERVICEAREAEQPT
AB OWNERSAPPROVE
TO CONSTRUCTION
CONSTRUCTION
AB O.A. PW= 1
AB O.A. PW= 2
AB O.A. PWRACK
STARTSHOPDWGS LIST 3
SHOPDWGSCO!@LIST 3
Printout I
PROJ-ECTMANPOWER
REQUIREMENTS
SUMMARY
MANPOWER
AVAILABLE
999 999 999 999 999 999 999 999 999 999
PROJECT CRAFTCODES
DAY ARCF MECF EXXF STRF P+IF
0 4 8 7 10 2 0 0 0 0 0
5 0 3 2 3 2 0 0 0 0 0
10 0 5 2 2 2 0 0 0 0 0
15 0 2 2 2 2 0 0 0 0 0
30 1 4 2 3 2 0 0 0 0 0
40 1 2 2 3 2 0 0 0 0 0
Printout II
- 210 -
PROJECTMANPOWER
REQW SUMMARY
f
MANPOWER
AVAILABLE
110 60 999 999 250 85 165 999 999
PROJECT CRAFTCODES
DAY LAB OETD PF BM CF SUBS
0 0 0 0 0 0 0 0
67 6 0 2 0 0 0 14
91 14 2 2 0 0 0 40
99 24 6 3 0 0 1 40
106 24 6 3 0 0 1 28
109 24 9 3 0 0 1 86
119 28 13 5 0 0 1 86
Printout III
***~**~~++ik~~~*
* * CRAFTCODES LAB CARP Iw OETD PF BM ELF MW CF SUBS
<* PF CURVE *
* * MPAVAILABLE 110 60 999 999 250 85 165 999 999 999
*mm** -***MM
306 ----+----1----t
307 ----t----1----+
----+----l----+----2----+----3
----+----1----t----2----+----3
309 ----t ---- 1 ----t ---- 2 ---- + ---- 3
310 ----t----1----+----2----+----3
311 ----t----1----+----2----+-----3--+--+----
----t----1----+----2----+----3----+---- t
z:: ----+----1----t----2----+----3----+----
314 ----+----1----+----2----+-----3--+--t---- t
315 ----+----1----+----~----+----3----t--------t----3----+----
----+----1----+---- 4---- +---5----t
31.6 4 ----+----5----t
317 ----+----l----+----2----+----3----+---- ----+----5----+-
318 ----+----1-w--+---- 2----+----3----+---- k ----t---- 5 --m-t-
319 ----+----1----+----2----+-----3--+--t---- ----+----5----t---- ----+-
320 ----+----l----+----2----+----3----+---- t ----t----5---+---- z ----+-
Printout IV
- 211 -
* GEN. SCHEDULE * PAGE 570
-----e------------e-
GENERAL SCHEDULE
Printout V
ci . . _
Printout VI
- 212 -