Академический Документы
Профессиональный Документы
Культура Документы
(ATC)
EE 521 Analysis of Power Systems
Chen-Ching Liu
Washington
hi State University
i i
Available Transfer Capability (ATC)
Total Transfer
MW
A >B
A->B Capability (TTC)
TRM
Transmission
Reliability Margin
TRM Nonrecallable ATC measures the residual
ATC
Recallable transfer capability in the
Recallable ATC Nonrecallable
ATC physical transmission
Available
Transfer network for the purpose of
Recallable Capability
Scheduled Recallable further commercial activity
Reserved over existing transmission
Nonrecallable
R
Reserved d commitments.
i
Nonrecallable
Nonrecallable Reserved
Scheduled
Time
Operating Horizon Planning Horizon
NERC: Available Transfer Capability (ATC)
Area A
#1
#2
#1
#2
Thermal Limit: Thermal Limit:
2 x 1100 MW 2 x 1000 MW
#2
Area B
Thermall Limit:
Th Li it #1 Area C
2 x 1000 MW
Example
p [[2]]
1. Base case power flow.
Area A
#1
#2
#1
#2
100 MW
100 MW
100 MW
100 MW
100 MW
#2
Area B
100 MW
#1 Area C
Example
p [[2]]
2. Increase generation in area A and increase demand in area B by
the same amount.
Increase 667 MW #2
demand in Area B
area B by #1 Area C
667 MW
2834 MW.
Example
p [[2]]
3. Check the normal thermal, stability and voltage constraints.
4. Evaluate the first contingency event and ensure that the emergency operating
limits are met.
met
5. When the emergency limit is reached for a first contingency, the corresponding
(pre-contingency) transfer amount from area A to area B is the TTC.
Area A
#1
#2
#1 Fault on line #1
#2
917 MW 1000 MW
917 MW
500 MW #2
A B
Area
#1 Area C
500 MW
First Contingency Incremental Transfer Capability (FCITC)
First Contingency Total Transfer Capability (FCTTC)
ATC and TTC depends on system generation dispatch and system load level, power
transfers between areas, network topology, and the limits imposed on the
transmission network due to thermal, voltage and stability constraints