Вы находитесь на странице: 1из 4

Critical Path: An Extended Definition

by Kevin Aguanno, PMP , MAPM

C ritical path is a term used in the field of project management to define a


sequence of tasks in a project wherein none of the tasks can be delayed
without affecting the final project end date. The sequence of tasks making
up the critical path starts with the first task in the project, and follows through to the
last task in the project. In effect, the timely completion of each task in the sequence
This article was the first of
several in a series of
extended definitions of
common project
management terms and
is critical to the timely completion of the project. techniques. The collected
set was to be used in a
Knowing the critical path on a project, the project manager can apply additional textbook for beginning
students of project
management techniques to the tasks in the critical path sequence to reduce the risk management.
of delays in the completion of those tasks and the overall project schedule. Critical
path is, therefore, a risk management technique. The publisher of the
textbook later canceled the
History of the Critical Path Technique project, returning the
copyrights of the articles to
The critical path concept evolved during the late 1950s on large defense research
their authors.
projects in the United States of America. Meredith and Mantel (336-7) present two
different project scheduling methods developing the concept of a critical path at the
same time:

! Critical Path Method. The Critical Path Method (CPM) was developed
by DuPont Inc. for use on construction-type projects with fixed project
end dates. CPM's main strength is the data it provides for making cost vs.
schedule tradeoff decisions. Today, the CPM is the most widely used
method for determining and managing the critical path on projects, and
is used in all industries.
! Program Evaluation and Review Technique. This method, known by
the acronym PERT, was developed in 1958 by the consulting firm Booz-
Allen Hamilton and the defense contractor Lockheed Corporation for
use on the Polaris missile/submarine project. PERT uses probabilistic
methods to assess the likelihood that a project will finish by a given date.

Duncan (1996) promotes both the CPM and PERT techniques for determining the
critical path on a project. His Guide to the Project Management Body of Knowledge
(PMBOK Guide) published by the Project Management Institute, has become a
defacto baseline standard for project management knowledge and competency
assessments. Duncan describes the critical path techniques as being tools that are
applicable to most projects most of the time, and that there is widespread
consensus about their value and usefulness (1).

2002 Kevin Aguanno. All rights reserved. h t t p : / / w w w. m m p u b s . c o m / a g u a n n o


2

Determining the Critical Path in a Project


The critical path identifies the sequence of tasks in which no single task can be
delayed without affecting the completion date of the sequence: in other words, a
sequence with no buffer (also called float). Figure 1 shows a traditional task
network diagram wherein the boxes represent tasks to be completed on a project.
The arrows connecting the boxes show the order in which the tasks must be
completed. For example, task B cannot start until task A has finished; this
dependency is shown with the arrow connecting the two tasks. Task D has two
arrows coming in to it; this means that both of the linked tasks (B and C) must be
complete before task D can start. The number in parentheses below each box
represents the number of days required to complete the task. A quick look at this
network diagram shows that there are three sequences of tasks (paths) that need
to be completed: the sequence A-B-D-E, the sequence A-C-D-E, and the sequence A-
C-E.
Beyond the PMP:
Advanced Project
Management Certification
B D Options.
by Kevin Aguanno.

(3) (4) Available for $39.95 at:


http://www.mmpubs.com/
A E aguanno/book2.html

(1) (1)
C

(1)

Figure 1: A sample project task network.

We can calculate the sequence with the longest duration by adding the numbers in
parentheses in each sequence. Figure 2 shows the calculations for the duration of
each sequence in the network. The sequence A-B-D-E has the longest duration at
nine days, making it the critical path. This means that any delay in a task in this
sequence will increase the total duration of the sequence and delay the final project
end date. On the other hand, if task C were delayed such that its actual duration
were now two days, task D would not have to start any later because it is also
dependent upon task B which would have not yet completed. Task C, therefore, is
not on the critical path.

Sequence
Sequence Calculation
Duration
A-B-D-E 1+3+4+1 9 days
A-C-D-E 1+1+4+1 7 days

A-C-E 1+1+1 3 days

Figure 2: Calculating sequence durations.

2002 Kevin Aguanno. All rights reserved. h t t p : / / w w w. m m p u b s . c o m / a g u a n n o


3

Limitations of the Critical Path Techniques


When a project manager provides extra attention to tasks on the critical path, it is
easy to lose sight of the risks inherent in the other tasks in the project. For example,
the completion of a task not on the critical path could be delayed so that its duration
becomes long enough to change the critical path of the project. Using our project
task network above, if the completion of task C required four days (instead of one
day), the task sequence A-C-D-E would be lengthened to a total of ten days, making
the sequence the new critical path on the project. Project managers should watch
for schedule risks in these non-critical tasks.

Another limitation of the critical path technique is that it highlights tasks at greatest
risk for causing schedule delays, but it does not identify the source of the schedule
risks. Alternate methods, such as the Critical Resource Path technique identified by
Aguanno (2002) calculate alternate critical paths that factor in the risks caused by
dependence on unique or constrained resources. 101 Ways to Reward Your
Project Team for $20 (or
less!)
An Alternate Approach to Critical Path Techniques by Kevin Aguanno.
Other approaches to determining and managing schedule risk have emerged in
recent years. For example, Goldratt developed the Critical Chain Method (1997) Available for $24.95 at:
based upon his Theory of Constraints (1990) that addresses the problems of http://www.mmpubs.com/
constrained scheduling and process aguanno/book1.html
optimization. Goldratt's Critical Chain
Method provides a practical means of Works Cited
scheduling project task sequences (taking
into account the common constraint of Aguanno, Kevin. Understanding the Critical Resource Path. Book of
Readings in Project Management. Hyderabad, India: Institute
relatively finite resource availability) to
of Chartered Financial Analysts of India - Center for
minimize risk in the project delivery Management Research, 2002.
schedule. Patrick (1999 and 2001) has
refined the practical implementation of - - -. Using the Critical Resource Path. Project Magazine 3.5 (2002). 13
Goldratt's method and is a driving force F e b r u a r y 2 0 0 3 < h t t p : / / w w w. p r o j e c t m a g a z i n e
.com/may02/critical1.html>.
behind its growing adoption in the
corporate world. - - -. Using the Critical Resource Path to Reduce Project Risk. Inside
Project Management 2.7 (2002): 1-4.
Duncan, William R., ed. A Guide to the Project Management Body of
Why Use the Critical Path Knowledge . Newton Square, Pennsylvania: Project
Techniques? Management Institute, 1996.
While there are significant limitations in Goldratt, Eliyahu M. Critical Chain. Great Barrington, Massachusetts:
using the critical path for schedule risk North River Press Publishing Corporation, 1997.
management, the critical path techniques - - -. Theory of Constraints. Great Barrington, Massachusetts: North
provide a quick means of determining the River Press Publishing Corporation, 1990.
task sequence that is likely the source of
the greatest schedule risk in the project. Meredith, Jack. R. and Mantel, Samuel J. Project Management: A
rd
Managerial Approach. 3 ed. New York: John Wiley & Sons,
Widespread adoption of the techniques,
1995.
and their support in most project
scheduling software packages, have lead Patrick, Francis S. "Critical Chain and Risk Management -- Protecting
to a growing understanding and Project Value from Uncertainty (Part 1)." Focused Performance
acceptance of critical path as a schedule Web Site Nov. 2001. 13 Feb. 2003 <http://www.
focusedperformance.com/articles/ccrisk.html>.
risk management technique among
executives. Critical path is a tool all - - -. "Critical Chain Scheduling and Buffer Management . . . Getting Out
project managers should have in their From Between Parkinson's Rock and Murphy's Hard Place."
toolbox. a Focused Performance Web Site Apr. 1999. 13 Feb. 2003
<http://www.focusedperformance.com/articles/ccpm.html>.

2002 Kevin Aguanno. All rights reserved. h t t p : / / w w w. m m p u b s . c o m / a g u a n n o


4
About the Author
As a Certified Senior Project Manager, Kevin Aguanno specializes in
managing complex software development projects. He has been
managing consulting, integration, and software development
projects in various industries since 1990.
Mr. Aguanno is certified by the Project Management Institute (PMI),
and is a member of both PMI and the Association for Project
Management (APM) in the United Kingdom.
Mr. Aguanno is the editor of Inside Project Management, an
element-K journal, and has written several books. His articles
appear regularly in various professional journals, and he speaks
internationally on project-management related issues.
Web site: http://www.mmpubs.com/aguanno

So, You Think Youre


Done? What to do after
the launch audio tape
by Kevin Aguanno.

Available for $12 at:


http://www.mmpubs.com/
aguanno/tape2.html

Agile Project Management


Using Scrum audio tape
by Kevin Aguanno.

Available for $12 at:


http://www.mmpubs.com/
aguanno/tape1.html

Planning a corporate event?

Kevin Aguanno is available to speak at your corporate or association functions on general


topics ranging from project management, goal setting, and rewarding for performance to
more specialized topics such as agile software development methods. To find out more, visit
www.mmpubs.com/aguanno/speaking.html or contact speakers@mmpubs.com.

2002 Kevin Aguanno. All rights reserved. h t t p : / / w w w. m m p u b s . c o m / a g u a n n o

Вам также может понравиться