Work: Construciton and Upgradation of Road and other structures from Phulwaria ghat at Lalbakiya River to Bahar (Bahera)

Village in Sitamarhi District under INDO-NEPAL Border Road Project for the Year 2

Agreement No. 27/SBD/2012-13


Ageny: M/s Aarpee Infraprojects Pvt. Ltd. (M/s Rajesh Kumar Garg)
Programme of Work
Sl. No. of EXECUTION TIME
ACTIVITY UNIT QNTY
No. Days October-2013 November-2013 December-2013 January-2014 February-2014 March-2014 April-2014
1 Selection of Site for Casting Yard
Setting up Casting Yardincluding Cement Godown, Site
2 office, Site Lab i/c Fencing etc.
Job 1
3 Procurement of Shuttering material like MS Sheet,
Angle Iron, I Section, etc. Job 1
4 Fabrication of Shuttering
5 Pile Liner nos 6 01.09.13 to 21.06.14
6 Pile Cap
Size 900x1200 = 108.00 sqm
600x900 = 63.00 sqm sqm 208.80 01.10.13 to 31.10.13
300x1200 =21.60 sqm
300x900mm =16.20 sqm

7 Pier i/c Pier Cap set 1 01.10.13 to 31.10.13


8 Abutment i/c Cap set 1 01.10.13 to 31.10.13
9 I-Beams i/c intermediate cross Girders etc. set 3 15.11.13 to 14.12.13
10 Wing Wall, Retain Wall, Deck Slab, etc.
Size 900x1200 = 108.00 sqm
600x900 = 63.00 sqm
sqm 400.00 01.11.13 to 30.11.13
300x1200= 21.60 sqm
300x900mm= 16.20 sqm

11 Crash Barrier & Railing, Shuttering etc. = 5 mtr. Length set 1


12 Piling i/c setting out on ground, boring, using Bentonite
Slurry & Temporary liner, preparing Reinforcement
Cage i/c Cutting, Bending, Binding, Lowering the Cage
in the Bore hole, lowering tremmi pipe in the bore hole, nos 88
concreting & removal of Temp. Liner etc complete.

13 Piles of Abutment 'A1' (Bhangaha Side) - Rig No.1 nos 12 36 01.10.13 to 05.11.13
14 Pile of Pier P1 - Rig No.1 nos 16 36 06.11.13 to 11.12.13
15 Pile of Pier P2 - Rig No.1 nos 16 36 12.12.13 to 16.01.14
16 Pile of Abutment 'A2' - Rig No.2 nos 12 36 1.10.13 to 05.11.13
17 Pile of Pier P3 - Rig No.2 nos 16 36 06.11.13 to 11.12.13
18 Pile of Pier P4 - Rig No.2 nos 16 36 12.12.13 to 16.01.14
19 Pile Cap for Abutment A1 including from next day of
completion of Piling work i.e. S.No.5 no. 1 21 06.11.13 to 26.11.13
20 Breacking Pile head, Excavation upto founding level & P/L
PCC, levelling bed etc. complete.
21 Reinforcement i/c Cutting, binding& bending etc.
22 Shuttering i/c shuttering & proping etc.
23 Concreting i/c compaction, curing etc.
24 Deshuttering i/c shifting of material to the other location
25 Pile Cap for
Breacking Pier
Pile P1 Excavation upto founding level & P/L
head, no. 1 21 12.12.13 to 01.01.14
26 PCC, levelling bed etc. complete.
27 Reinforcement i/c Cutting, binding& bending etc.
28 Shuttering i/c shuttering & proping etc.
29 Concreting i/c compaction, curing etc.
30 Deshuttering i/c shifting of material to the other location
31 Pile Cap for Pier P2 21 17.01.14 to 06.02.14
Breacking Pile head, Excavation upto founding level & P/L
32 PCC, levelling bed etc. complete.
33 Reinforcement i/c Cutting, binding& bending etc. nos
34 Shuttering i/c shuttering & proping etc.
35 Concreting i/c compaction, curing etc. nos 1
36 Deshuttering i/c shifting of material to the other location nos 1
37 Pile Cap for
Breacking Abutment
Pile A2
head, Excavation upto founding level & P/L nos 1 21 06.11.13 to 26.11.13
38 PCC, levelling bed etc. complete. nos 1
39 Reinforcement i/c Cutting, binding& bending etc.
40 Shuttering i/c shuttering & proping etc.
41 Concreting i/c compaction, curing etc.
42 Deshuttering i/c shifting of material to the other location
43 Pile Cap for Pier P4 21 12.12.13 to 01.01.14
44 Breacking Pile head, Excavation upto founding level & P/L
PCC, levelling bed etc. complete.
45 Reinforcement i/c Cutting, binding& bending etc.
46 Shuttering i/c shuttering & proping etc.
47 Concreting i/c compaction, curing etc.
48 Deshuttering i/c shifting of material to the other location
49 Pile Cap for Pier P3 21 17.01.14 to 06.02.14
50 Breacking Pile head, Excavation upto founding level & P/L
PCC, levelling bed etc. complete.
51 Reinforcement i/c Cutting, binding& bending etc.
52 Shuttering i/c shuttering & proping etc.
53 Concreting i/c compaction, curing etc.
54 Deshuttering i/c shifting of material to the other location

55 Concreting of Abutment A1 including Cap 15 27.11.13 to 10.12.13


56 Reinforcement i/c Cutting, binding& bending etc.
57 Shuttering i/c shuttering & proping etc.
58 Concreting i/c compaction, curing etc.
59 Deshuttering i/c shifting of material to the other location
60 Concreting of Pier P1 including Cap 15 02.01.14 to 16.01.14
61 Reinforcement i/c Cutting, binding& bending etc.
62 Shuttering i/c shuttering & proping etc.
63 Concreting i/c compaction, curing etc.
64 Deshuttering i/c shifting of material to the other location
65 Concreting of Pier P2 including Cap 15 06.02.14 to 21.02.14
66 Reinforcement i/c Cutting, binding& bending etc.
67 Shuttering i/c shuttering & proping etc.
68 Concreting i/c compaction, curing etc.
69 Deshuttering i/c shifting of material to the other location
70 Concreting of Abutment A2 including Cap 15 27.11.13 to 10.12.13
71 Reinforcement i/c Cutting, binding& bending etc.
72 Shuttering i/c shuttering & proping etc.
73 Concreting i/c compaction, curing etc.
74 Deshuttering i/c shifting of material to the other location
75 Concreting of Pier P3 including Cap 15 02.01.14 to 16.01.14
76 Reinforcement i/c Cutting, binding& bending etc.
77 Shuttering i/c shuttering & proping etc.
78 Concreting i/c compaction, curing etc.
79 Deshuttering i/c shifting of material to the other location
80 Concreting of Pier P4 including Cap 15 07.02.14 to 21.02.14
81 Reinforcement i/c Cutting, binding& bending etc.
82 Shuttering i/c shuttering & proping etc.
83 Concreting i/c compaction, curing etc.
84 Deshuttering i/c shifting of material to the other location
85 Concreting of Bearing Pedastal i/c Centring,
Shuttering, Proping & Deshuttering etc complete. nos. 6
86 Abutment A1 no. 1 11.12.13
87 Pier P1 no. 1 13.01.14
88 Pier P2 no 1 22.02.14
89 Abutment A2 no. 1 11.12.13
90 Pier P4 no 1 17.01.14
91 Pier P3 no. 1 22.02.14
92
Pre-casting of I-Beam on Casting Bed i/c Prestressing,
Shifting to the stacking bed & erction thereof in nos 4
93 Span between Abutment A1- & Pier P1 including 45 01.12.13 to 14.01.14
94 Concreting i/c Shuttering, proping & reinforcement i/c
cutting, bending, binding etc.
95 Shifting of I-Beam from Casting Bed to Stacking Bed
96 Prestressing of I-Beam
97 Placing Elastomaric Bearings over Abutment & Pier
98 Erection of prestressed I-Beam in the respective Span
99 Span between Pier P1- & Pier P2 including 45 16.12.13 to 29.01.14
100 Concreting i/c Shuttering, proping & reinforcement i/c
cutting, bending, binding etc.
101 Shifting of I-Beam from Casting Bed to Stacking Bed
102 Prestressing of I-Beam
103 Placing Elastomaric Bearings over Abutment & Pier
104 Erection of prestressed I-Beam in the respective Span
105 Span between Abutment A2- & Pier P4 including 45 31.12.13 to 13.02.14
106 Concreting i/c Shuttering, proping & reinforcement i/c
cutting, bending, binding etc.
107 Shifting of I-Beam from Casting Bed to Stacking Bed
108 Prestressing of I-Beam
109 Placing Elastomaric Bearings over Abutment & Pie
110 Erection of prestressed I-Beam in the respective Span
111 Span between Pier P4- & Pier P3 including 45 16.01.14 to 01.03.14
112 Concreting i/c Shuttering, proping & reinforcement i/c
cutting, bending, binding etc.
113 Shifting of I-Beam from Casting Bed to Stacking Bed
114 Prestressing of I-Beam
115 Placing Elastomaric Bearings over Abutment & Pie
116 Erection of prestressed I-Beam in the respective Span
117 Span between Pier P3- & Pier P2 including 45 31.01.14 to 16.03.14
118 Concreting i/c Shuttering, proping & reinforcement i/c
cutting, bending, binding etc.
119 Shifting of I-Beam from Casting Bed to Stacking Bed
120 Prestressing of I-Beam
121 Placing Elastomaric Bearings over Abutment & Pie
122 Erection of prestressed I-Beam in the respective Span

123 Concreting of Intermediate Cross Girders nos 15 21 15.01.14 to 04.02.14


124 Between Span Abutment A1 & Pier P1 including
125 Reinforcement i/c Cutting, binding& bending etc.
126 Shuttering i/c shuttering & proping etc.
127 Concreting i/c compaction, curing etc.
128 Deshuttering i/c shifting of material to the other location
129 Between Span Pier P1 & Pier P2 including nos 15 21 30.01.14 to 19.02.14
130 Reinforcement i/c Cutting, binding& bending etc.
131 Shuttering i/c shuttering & proping etc.
132 Concreting i/c compaction, curing etc.
133 Deshuttering i/c shifting of material to the other location
134 Between Span Abutment A2 & Pier P4 including nos. 15 21 14.02.14 to 12.03.14
135 Reinforcement i/c Cutting, binding& bending etc.
136 Shuttering i/c shuttering & proping etc.
137 Concreting i/c compaction, curing etc.
138 Deshuttering i/c shifting of material to the other location
139 Between Span Pier P4 & Pier P3 including nos. 15 21 02.03.14 to 22.03.14
140 Reinforcement i/c Cutting, binding& bending etc.
141 Shuttering i/c shuttering & proping etc.
142 Concreting i/c compaction, curing etc.
143 Deshuttering i/c shifting of material to the other location
144 Between Span Pier P3 & Pier P2 including nos. 15 21 17.03.14 to 06.04.14
145 Reinforcement i/c Cutting, binding& bending etc.
146 Shuttering i/c shuttering & proping etc.
147 Concreting i/c compaction, curing etc.
148 Deshuttering i/c shifting of material to the other location
149 Deck Slab Concreting cum
150 Of Span between Abutment A1 & Pier P1 including 10 01.02.14 to 11.02.14
151 Reinforcement i/c Cutting, bending & binding etc.
152 Shuttering i/c shuttering & proping etc.
153 Concreting i/c compaction, curing etc.
154 Deshuttering i/c shifting of material to the other location
155 Of Span between Pier P1 & Pier P2 including cum 10 16.02.14 to 26.02.14
156 Reinforcement i/c Cutting, bending & binding etc.
157 Shuttering i/c shuttering & proping etc.
158 Concreting i/c compaction, curing etc.
159 Deshuttering i/c shifting of material to the other location
160 Of Span between Abutment A2 & Pier P4 including cum 10 09.03.14 to 19.03.14
161 Reinforcement i/c Cutting, bending & binding etc.
162 Shuttering i/c shuttering & proping etc.
163 Concreting i/c compaction, curing etc.
164 Deshuttering i/c shifting of material to the other location
165 Of Span between Pier P4 & Pier P3 including cum 10 19.03.14 to 29.03.14
166 Reinforcement i/c Cutting, bending & binding etc.
167 Shuttering i/c shuttering & proping etc.
168 Concreting i/c compaction, curing etc.
169 Deshuttering i/c shifting of material to the other location
170 Of Span between Pier P3 & Pier P2 including cum 10 03.04.14 to 13.04.14
171 Reinforcement i/c Cutting, bending & binding etc.
172 Shuttering i/c shuttering & proping etc.
173 Concreting i/c compaction, curing etc.
174 Deshuttering i/c shifting of material to the other location
175 Consolidation of Sub Grade i/c Levelling & Dressing
and placing PCC for Aproach Slab.
176 Bhangaha Side 10 01.03.14 to 13.03.14
177 Kanuali Side 10 15.04.14 to 25.04.14
178 Concreting of Approach slab i/c cutting, bending,
binding of Reinforcement, Providing & Placing Centring
& Shuttering i/c Proping & Deshuttering etc. as
required.

179 Bhangaha Side 7 14.03.14 to 21.03.14


180 Kanuali Side 7 26.04.14 to 02.05.14
181 Provding & Fixing Expansion Joint
182 Over Abutment A1 7 24.03.14 to 31.03.14
183 Over Pier P1 7 31.03.14 to 07.04.14
184 Over Abutment A2 7 05.05.14 to 12.05.14
185 Over Pier P4 7 12.05.14 to 19.05.14
186 Over Pier P3 7 19.05.14 to 26.05.14
187 Over Pier P2 7 26.05.14 to 02.06.14
188 Concreting of Crash Barrier & Footpath etc.
189 Unstream side Mtr. 180 50 01.03.14 to 19.04.14
190 Downstream side Mtr. 180 50 18.03.14 to 06.05.14
191 Bituminous work on Deck slab
192 DBC 5 01.06.14 to 05.06.14
193 Mastic 10 06.06.14 to 16.06.14
194 Misc. & Finishin Work
195 Rain water spout & down take pipe 15 01.05.14 to 15.05.14
196 GI Pipe Railing 15 26.04.14 to 10.05.14
197 Painting & Road Marking 4 17.06.14 to 20.06.14
198 Opening the Bridge for Traffic 1 21.06.14
DO-NEPAL Border Road Project for the Year 2012-13.

EXECUTION TIME
May-2014 June-2014 July-2014 July-2014 August-2014 September-2014 October-2014 November-2014 December-2014
Work: Construciton and Upgradation of Road and other structures from Phulwaria ghat at Lalbakiya River to Bahar (Bahera) Village in Sitamarhi District under INDO-NEPAL

Agreement No. 27/SBD/2012-13


Ageny: M/s Aarpee Infraprojects Pvt. Ltd. (M/s Rajesh Kumar Garg)
Programme of Work
Sl. EXECUTION
ACTIVITY UNIT QNTY
No. October-2013 November-2013 December-2013 January-2014 February-2014 March-2014 April-2014
1 Selection of Site for Casting Yard
Setting up Casting Yardincluding Cement Godown, Site
2 office, Site Lab i/c Fencing etc.
Job 1
3 Procurement of Shuttering material like MS Sheet,
Angle Iron, I Section, etc. Job 1
4 Fabrication of Shuttering
5 Pile Liner nos 6
6 Pile Cap
Size 900x1200 = 108.00 sqm
600x900 = 63.00 sqm sqm 208.80 01.10.13 to 31.10.13
300x1200 =21.60 sqm
300x900mm =16.20 sqm

7 Pier i/c Pier Cap set 1 01.10.13 to 31.10.13


8 Abutment i/c Cap set 1 01.10.13 to 31.10.13
9 I-Beams i/c intermediate cross Girders etc. set 3 15.11.13 to 14.12.13
10 Wing Wall, Retain Wall, Deck Slab, etc.
Size 900x1200 = 108.00 sqm
600x900 = 63.00 sqm
300x1200= 21.60 sqm
300x900mm= 16.20 sqn
sqm 400.00 01.11.13 to 30.11.13
11 Crash Barrier & Railing, Shuttering etc. = 5 mtr. Length set 1
12 Piling i/c setting out on ground, boring, using Bentonite
Slurry, Temporary liner, preparing Reinforcement Cage
i/c Cutting, Bending, Binding, Lowering the Case in the
Bore hole, concreting & Removal of Temp. Liner.

nos 88
13 Abutment 'A1' (Bhangaha Side) nos 12
14 Pile Cap Group Pier P1 nos 16
15 Pile Cap Group Pier P2 nos 16
16 Abutment 'A2' nos 12
17 Pile Cap Group Pier P3 nos 16
18 Pile Cap Group Pier P4 nos 16
19 Pile Cap for Abutment A1 no. 1
Excavation upto founding level & P/L PCC, levelling bed
etc. complete.
Reinforcement i/c Cutting, binding& bending etc.
Shuttering i/c shuttering & proping etc.
Concreting i/c compaction, curing etc.
Deshuttering i/c shifting of material to the other location
7 Pile Cap forupto
Excavation Abutment
founding A2level & P/L PCC, levelling bed nos 1
etc. complete. nos 1
Reinforcement i/c Cutting, binding& bending etc.
Shuttering i/c shuttering & proping etc.
Concreting i/c compaction, curing etc.
Deshuttering i/c shifting of material to the other location
8 Concreting of Abutment A1
Reinforcement i/c Cutting, binding& bending etc.
Shuttering i/c shuttering & proping etc.
Concreting i/c compaction, curing etc.
Deshuttering i/c shifting of material to the other location
9 Concreting of Abutment A2
Reinforcement i/c Cutting, binding& bending etc.
Shuttering i/c shuttering & proping etc.
Concreting i/c compaction, curing etc.
Deshuttering i/c shifting of material to the other location
Concreting of Bearing Pedastal i/c Centring, Shuttering
10 & Proping etc. nos. 6
Abutment A1 no. 1
Abutment A2 no. 1
11 Pre-casting of I-Beam on Casting Bed i/c Prestressing,
Shifting to the stacking bed & erction thereof in the
Span 'A1-A2' nos 4
Concreting i/c Shuttering, proping & reinforcement i/c
cutting, bending, binding etc.
Shifting of I-Beam from Casting Bed to Stacking Bed
Prestressing of I-Beam
Erection of prestressed I-Beam in the respective Span
12 Concreting of Intermediate Cross Girders of Span A1-
A2 nos 15
Reinforcement i/c Cutting, binding& bending etc.
Shuttering i/c shuttering & proping etc.
Concreting i/c compaction, curing etc.
Deshuttering i/c shifting of material to the other location
13 Deck Slab Concreting of Span A1-A2 cum
Reinforcement i/c Cutting, bending & binding etc.
Shuttering i/c shuttering & proping etc.
Concreting i/c compaction, curing etc.
Deshuttering i/c shifting of material to the other location
14 Concreting of Crash Barrier & Footpath
Unstream side Mtr. 180
Downstream side Mtr. 180
15 Bituminous work on Deck slab
DBC
Mastic
Fancing GI Pipe Railing
Painting & Road Marking
der INDO-NEPAL Border Road Project for the Year 2012-13.

EXECUTION TIME
May-2014 June-2014 July-2014 July-2014 August-2014 September-2014 October-2014 November-2014 December-2014
Work: Construciton and Upgradation of Road and other structures from Phulwaria ghat at Lalbakiya River to Bahar (Bahera) Village in Sitamarhi District under INDO-NEPAL
Agreement No. 27/SBD/2012-13
Ageny: M/s Aarpee Infraprojects Pvt. Ltd. (M/s Rajesh Kumar Garg)
Programme of Work
Sl. EXECUTION
ACTIVITY UNIT QNTY
No. October-2013 November-2013 December-2013 January-2014 February-2014 March-2014 April-2014
1 Selection of Site for Casting Yard
Setting up Casting Yard i.e. Cement Godown, Site
2 office, Site Lab i/c Fencing etc.
Job 1
3 Procurement of Shuttering material like MS Sheet,
Angle Iron, I Section, etc. Job 1
4 Fabrication of Shuttering
Pile Liner nos 4
Pile Cap (Size 900x1200, 600x900, 300x1200 &
300x900mm ) nos
Pier i/c Pier Cap set 1
Abutment i/c Cap set 1
I-Beams i/c intermediate cross Girders etc. set 3
Wing Wall, Retain Wall, Deck Slab, etc. (Size 900x1200,
600x900, 300x1200 & 300x900mm ) sqm 400.00
5 Piling i/c boring, using Bentonite Slurry, Temporary
liner, preparing Reinforcement Cage i/c Cutting,
Bending, Binding, Lowering the Case in the Bore hole,
concreting & Removal of Temp. Liner.

nos 88
Abutment 'A1' (Bhangaha Side) nos 12
Pile Cap Group Pier P1 nos 16
Pile Cap Group Pier P2 nos 16
Abutment 'A2' nos 12
Pile Cap Group Pier P3 nos 16
Pile Cap Group Pier P4 nos 16
6 Pile Cap for Abutment A1 no. 1
Excavation upto founding level & P/L PCC, levelling bed
etc. complete.
Reinforcement i/c Cutting, binding& bending etc.
Shuttering i/c shuttering & proping etc.
Concreting i/c compaction, curing etc.
Deshuttering i/c shifting of material to the other location
7 Pile Cap forupto
Excavation Abutment
founding A2level & P/L PCC, levelling bed nos 1
etc. complete. nos 1
Reinforcement i/c Cutting, binding& bending etc.
Shuttering i/c shuttering & proping etc.
Concreting i/c compaction, curing etc.
Deshuttering i/c shifting of material to the other location
8 Concreting of Abutment A1
Reinforcement i/c Cutting, binding& bending etc.
Shuttering i/c shuttering & proping etc.
Concreting i/c compaction, curing etc.
Deshuttering i/c shifting of material to the other location
9 Concreting of Abutment A2
Reinforcement i/c Cutting, binding& bending etc.
Shuttering i/c shuttering & proping etc.
Concreting i/c compaction, curing etc.
Deshuttering i/c shifting of material to the other location
Concreting of Bearing Pedastal i/c Centring, Shuttering
10 & Proping etc. nos. 6
Abutment A1 no. 1
Abutment A2 no. 1
11 Pre-casting of I-Beam on Casting Bed i/c Prestressing,
Shifting to the stacking bed & erction thereof in the
Span 'A1-A2' nos 4
Concreting i/c Shuttering, proping & reinforcement i/c
cutting, bending, binding etc.
Shifting of I-Beam from Casting Bed to Stacking Bed
Prestressing of I-Beam
Erection of prestressed I-Beam in the respective Span
12 Concreting of Intermediate Cross Girders of Span A1-
A2 nos 15
Reinforcement i/c Cutting, binding& bending etc.
Shuttering i/c shuttering & proping etc.
Concreting i/c compaction, curing etc.
Deshuttering i/c shifting of material to the other location
13 Deck Slab Concreting of Span A1-A2 cum
Reinforcement i/c Cutting, bending & binding etc.
Shuttering i/c shuttering & proping etc.
Concreting i/c compaction, curing etc.
Deshuttering i/c shifting of material to the other location
14 Concreting of Crash Barrier & Footpath
Unstream side Mtr. 180
Downstream side Mtr. 180
15 Bituminous work on Deck slab
DBC
Mastic
Fancing GI Pipe Railing
Painting & Road Marking
der INDO-NEPAL Border Road Project for the Year 2012-13.

EXECUTION TIME
May-2014 June-2014 July-2014 July-2014 August-2014 September-2014 October-2014 November-2014 December-2014