Академический Документы
Профессиональный Документы
Культура Документы
Management
Guide on Economics
of Transformer Management
Part 1 Introduction
Part 2 Risk Management
Part 3 Spcification and Pourchasse
Part 4 Operation and maintenance
Part 5 - Repair vs. Replacement Decision Process
What is risk?
P1 C1 R1 =P1.C1
P3 C3 R3 =P3.C1
. . .
. . .
. . .
Likelihood/ Consequences/ Risk Level
Probability Loss of utility
CONSEQUENCES
15
High
10 criticality
given
med agitt
crit icalit
5
transf. with
0
of transf.
0, 3
-5
3, 7 Good
1
2,6
3
Antall
3,4
4,2
5,8
4,8
5,4
6
Global Technical
No.
Ge n e ral T e ch n ical
6,4
6,9
8,5
Low
7,5
C o n ditio n
7,8
8,4
Condition
9,2
10 12,2
10,8
Glo b al St rate g ic Im p act
11,6
Global Strategic Impact
12,4
13,2
14,8
Bad
High
Example of GSI and GTC mapping for a population of 900 transformers.
Economics of Transformer management Tutorial of CigreWG A2.20 19
L(x)
pL(x)
NO RISK
L(px)
AVERSION
px
x
RISK AVERSION
P( A | B) P( B)
P ( B | A) =
P ( A)
The Bayesian formula uses new information to revise
probabilities based on the old information, or in other words to
calculate future probability distributions based on previous
occurrences and new information, e.g. expert opinions.
0,90 0,02
P( S | +) = = 0,11
0,90 0,02 + 0,60 0,10 + 0,10 0,88
We introduce:
+1 = { First test is positive. }
+2 = { Second test is positive. }
0,60 0,10
P( L | +1) = = 0,36
0,90 0,02 + 0,60 0,10 + 0,10 0,88
0,10 0,88
P(N | +1) = = 0,53
0,90 0,02+ 0,60 0,10+ 0,10 0,88
Economics of Transformer management Tutorial of CigreWG A2.20 26
Bayesian decision method
independence of the tests
If we want to calculate the probability for the second
test result being positive, given the transformer is in a
serious bad shape, this second test is not dependent on
the result of the first test. We have:
P ( +2 | S I +1) = P ( +2 | S ) = P ( + | S ) = 0,90
P (+2 | L I +1) = P (+2 | L) = P (+ | L) = 0,60
P ( +2 | N I +1) = P (+2 | N ) = P (+ | N ) = 0,10
Economics of Transformer management Tutorial of CigreWG A2.20 27
0,90 0,11
P(S | +1I +2) = = 0,27
0,90 0,11+ 0,60 0,36 + 0,10 0,53
0,60 0,36
P ( L | +1 I + 2 ) = = 0,59
0,90 0,11 + 0,60 0,36 + 0,10 0,53
0,10 0,53
P ( N | +1 I + 2 ) = = 0,14
0,90 0,11 + 0,60 0,36 + 0,10 0,53
Economics of Transformer management Tutorial of CigreWG A2.20 28
Bayesian decision method
two decisions
D1 = { The transformer is moved immediately to the
factory for inspection and possibly repair. }
D2 = { Wait some time and see. }
Our power engineer assess the transformer and
tabulate the loss of utility:
Transformer condition:
S L N
Decision: D1 0 50.000 50.000
D2 200.000 25.000 0
Transformer condition:
S L N
Decision: D1 0 50.000 50.000
D2 200.000 25.000 0
D2 200.000 25.000 0
Transformer condition:
S L N
Decision: D1 0 50.000 50.000
D2 200.000 25.000 0
Transformer condition:
S L N
Decision: D1 0 50.000 50.000
D2 200.000 25.000 0
Transformer condition:
S L N
Decision: D1 0 50.000 50.000
D2 200.000 25.000 0
Spare Transformers
Spare Transformers
Example of calculation:
Group of 47 transformers
In most cases 2 transformer per substation
Failure rate (for costly failures) : 0.4% per year
Practically no option for load transfer
Repair time : 9 months
Loss of two transformers entail loss of 100MVA
load
Value to the community of lost load = $10
000/MWhr
Economics of Transformer management Tutorial of CigreWG A2.20 38
Spare Transformers
Spare Transformers
Probability of loss of station (N-2) during
transformer repair time of 9 months (0.75
year):
Reserve transformer fault: 0.03 x 0.75 = 0.023
Circuit breaker faults: 0.03 x 0.75 x 2 = 0.046
Isolator fault: 0.03 x 0.75 x 2 = 0.046
CT, bus, SA fault: 0.046 = 0.046
Weather, animals: 0.03 x 0.75 = 0.023
Total probability of a minor failure = 0.18
Spare Transformers
The cost of risk in each year: 0.03384 x $48m = $1.62
M$
m : mass,
S : rated power,
indexes 1 and 2 stand for transformer 1
and 2
Economics of Transformer management Tutorial of CigreWG A2.20 44
Specification and Purchase
Normal Y
ageing Terminate
result
N
Calculate risk of failure
under worst conditions
N Does
Carry out deferral outweigh
capital investment cost?
Y
Terminate
Terminate
Detectable
Percent: 30%
Percent: 70%
Percent: 90%
Proability: 0.0063
Detectable
Percent: 30%
Detectable
Failure Rate Proability: 0.003 Catastrophic
Percent: 60%
Percent: 1% Percent: 10%
Proability: 0.0042
Proability: 0.01 Not Detectable
Proability: 0.00028
Percent: 70% Not Detectable
Proability: 0.007 Percent: 40% Non-Catastrophic
Proability: 0.00252
Phase 1
Determination
of Risk
and Investments
Policy
Consider the Age and The cost of no-load and load losses are
Evaluate Total Loss of vital in making the repair /
Candidate Unit(s) replacement decision
Unit more than 35 to 40 years old, the
cost of no-load losses is often too high
Consider Obsolescence
to consider keeping the unit
and availability of
spare parts
Bushings A key factor is availability or
OLTC
Cooling System
obsolescence of spares parts
Ancillary Components replacement of parts by non-original
requires extra money and time
Consider Future
Failed transformers are often
Substation Loading
replaced by new larger units
Loading Enhancement
Relocation of Unit
Decide if NPV
Favours New or a Repair
Difference in Life
Capitalized losses
Cost of Capital
Depreciation Factors
Scope of On-Site
Refurbishment Life Extension
Estimate Costs
Materials
Labour
Tools / Equipment
Lease / Rental
Decide if NPV
of Life Extending Expenses
are Less than Capital
Deferment Saving
Cost of rebuilding CR
(or Cost of replacement)
For more
information
consult Cigre
Brochure 248