Вы находитесь на странице: 1из 508

GENERAL

PRLIS-P
NAME OF WORK :- PACKAGE.NO: 1, EARTH WOR
INTAKE STRUCTURE AND TUNNEL FROM
CONSTRUCTION OF STAGE-1 PUMPING STATI
NARLAPUR (V), KOLLAPUR (M), MAHABUBNAGAR
S.NO
A
1
2
3
4
5
6
7
8
9
10
11
12
13
14

15

1
2

B
1
2

3
4
5
6
7
8
9
10
11

12
13
14
15
GENERAL ABSTRACT
PRLIS-PACKAGE-1
NAME OF WORK :- PACKAGE.NO: 1, EARTH WORK EXCAVATION OF APPROACH CHANNEL
INTAKE STRUCTURE AND TUNNEL FROM FORESHORE OF SRISAILAM RESER
CONSTRUCTION OF STAGE-1 PUMPING STATION NEAR ANJANGIRI BALANCING RE
NARLAPUR (V), KOLLAPUR (M), MAHABUBNAGAR (DISTRICT).
DESCRIPTION OF WORK
ABSTRACT FOR CIVIL ITEMS
CONSTRUCTION OF APPROACH CHANNEL
CONSTRUCTION OF INTAKE STRUCTURE INCLUDING GATES
CONSTRUCTION OF APPROACHTUNNEL
CONSTRUCTION OF SURGE POOL
CONSTRUCTION OF DRAFT TUBE TUNNEL
SUPPLY, FABRICATION AND ERECTION OF DRAFT TUBE GATES
CONSTRUCTION OF PUMP HOUSE
CONSTRUCTION OF DELIVERY MAINS
CONSTRUCTION OF DELIVERY CISTERN
CONSTRUCTION OF PERMANENT ACCESS TUNNEL
CONSTRUCTION OF BUS DUCT TUNNEL
CONSTRUCTION OF VENTILATION DUCT TUNNEL
CONSTRUCTION OF EMERGENCY EXIT TUNNEL
CONSTRUCTION OF ADIT TUNNELS

MISCELLANEOUS ITEMS SUCH AS CONSTRUCTION OF COMPOUND WALL


SUB-TOTAL OF CIVIL WORKS
ABSTRACT FOR E&M WORKS
E&M Equipment (8X145 MW)

Add O&M Charges on Total cost of E&M Equipment @1% per year for 5years
SUB-TOTAL of E&M WORKS
TOTAL ECV
L.S. PROVISIONS
Provision for VAT for Civil works @ 5.00%
Add Exice Duty @ 16.32% on E&M Equipment cost item 1 @ 16.32% on
Rs.20987001000
Provision for VAT for E&M works 12.50% on Rs.22036351050
Provision for Labour Cess @ 1.00%
Provision for NAC Charges @ 0.10%
Provision for Seignorage Charges
Provision for Preparation & Publication of Tenders LS
Provision for Quality Control Charges, material testing etc LS.
Provision for Electronic & Monitering Equipment LS.
Provision for Survey, Investigation and designs LS.
Provision for Ultrosonic testing and Radiography testing to Delivery mains,
Spiral casing and other tests etc. LS.

Provision for TRANSCO & GENCO Supervision and Vetting Charges LS.
Provision for sheds for office for Department staff LS.
Approach Roads to Pump house LS.
Provision for Consultation charges for Senior geologist and Photographic and
xerox and rounding off LS.
TOTAL OF B-L.S. PROVISIONS
GRAND TOTAL
or say in Crores
RAL ABSTRACT
IS-PACKAGE-1
WORK EXCAVATION OF APPROACH CHANNEL INCLUDING
M FORESHORE OF SRISAILAM RESERVOIR AND
ATION NEAR ANJANGIRI BALANCING RESERVOIR AT
GAR (DISTRICT).
AMOUNT (Rupees)

951263384
411,842,153
939,877,181
1,791,469,258
561,448,068
180,826,596
1,586,167,909
2,189,511,644
405,677,301
976,496,298
152,453,130
44,329,948
42,251,845
187,056,826

40,003,641
10,460,675,182

20,987,001,000

1,049,350,050
22,036,351,050
32,497,026,232

523,033,759

3,425,078,563
2,754,543,881
104,606,752
10,460,676
47,235,284
1,000,000
5,000,000
5,000,000
1,000,000

20,000,000

20,000,000
20,000,000
20,000,000

3,417,780
6,960,376,696
39,457,402,928
3945.74
PRLIS - PACKAGE NO -1
COMPARITIVE STATEMENT
PRLIS - (Package No-1) - Construction of stage -1 pumping station near Anjanagiri Reservoir and Design , supply , erection testing and commissioning of Electro Mechanical works s
of 145 MW each including all accessories and Earth work Excavation of approach channel from foreshore of Srisailam Reservoir including intake structure and tunnel at stage -1 pumping s

AS PER MODIFIED Difference


AS PER SANCTION WITH
S.No DESCRIPTION OF WORK PROPOSAL WITH
OPEN PH
UNDER GROUND PH

Excess Less
A WORK ITEMS
APPROACH CHANNEL a) Excavation of combined Approach channel of
1 78,494,344 78,494,344 -
PRLIS & MGKLIS from 0.00 to 0.400 Km -
b) Km 0.400 to 2.205 Km 754,174,456 941,057,356 186,882,900 -
2 CONSTRUCTION OF INTAKE STRUCTURE INCLUDING GATES 320,829,108 443,670,361 122,841,253 -
3 CONSTRUCTION OF APPROACH TUNNEL 160,216,117 934,312,716 774,096,599 -
4 CONSTRUCTION OF SURGE POOL 1,395,823,761 1,744,311,148 348,487,387 -
5 CONSTRUCTION OF DRAFT TUBE TUNNEL 561,448,068 561,448,068 - -

6 SUPPLY ,FABRICATION AND ERECTION OF DRAFT TUBE GATES 180,826,596 180,826,596 - -

7 CONSTRUCTION OF PUMP HOUSE 3,029,503,530 1,586,167,909 - 1,443,335,621

8 CONSTRUCTION OF DELIVERY MAINS 3,209,883,828 2,205,934,017 - 1,003,949,811


9 CONSTRUTION OF DELIVERY CISTERN 405,637,800 405,677,301 39,501 -
10 CONSTRUCTION OF CHUTE SPILLWAY CARRIER 128,651,141 - - 128,651,141
11 CONSTRUCTION OF PERMANENT ACCESS TUNNEL - 814,076,133 814,076,133 -
12 CONSTRUCTION OF BUS DUCT TUNNEL - 219,224,878 219,224,878 -
13 VENTILATIONDUCT TUNNEL - 56,776,791 56,776,791 -
14 CONSTRUCTION OF EMERGENCY EXIT TUNNEL - 60,159,291 60,159,291 -
15 CONSTRUCTION OF ADIT TUNNELS - 189,632,815 189,632,815 -

16 MISCELLANEOUS ITEMS SUCH AS CONSTRUCTION OF COMPOUND WALL 59,956,367 40,612,772 19,343,595

TOTAL OF CIVIL WORK ITEMS 10,206,950,772 10,462,382,496 2,850,711,892 2,595,280,168


Percentage over open pump house 2.50
B E&M WORKS
1 E&M Equipment (8x145 MW) 20,987,001,000 20,987,001,000 -

2 Add O&M Charges on Total cost of Equipment @1%per year for 5 yrs 1,049,350,050 1,049,350,050
-
TOTAL OF E&M WORKS 22,036,351,050 22,036,351,050 -
Total ECV 32,243,301,822 32,498,733,546 -
Percentage over open pump house 0.79
C L.S PROVISIONS -

1 PROVISION FOR VAT CHARGES FOR CIVIL WORKS @5.00% 510,347,539 523,119,125 12,771,586

2 Add Excise Duty @ 16.32 % on E&M Equipment cost item No 1 @ 16.32% 3,425,078,563 3,425,078,563 -

3 Provision for VAT for E&M works @12.50% 2,754,543,881 ### -


4 Provision for labour Welfare cess @1.00% 102,069,508 104,623,825 2,554,317
5 Provision for NAC charges for civil charges @0.10% 10,206,951 10,462,382 255,432
6 Provision for seignorage charges 47,235,284 47,235,284 - -

7 Provision for preparation & publication of tenders L.s 1,000,000 ### -

8 Provision for Quality control charges ,material Testing etc. ,L.S 5,000,000 ### -

9 Provision for Electronic Equipment LS 5,000,000 ### -


10 Provision for survey Investigation &Design Works LS 1,000,000 ### -

Add provision for ultra sonic Testing and Radio graphic testing for Delivery
11 20,000,000 ### -
Mains, spiral casing and others LS

12 Provision for TRANSCO & GENCO Supervision and vetting charges LS 20,000,000 ### -

13 Provision for Sheds for storage and office accomdation to the Dept .staff LS 20,000,000 ### -

14 Approach Road to pump House LS 20,000,000 ### -


Provision for consultation charges for senior Geologist and photographic
15 2,216,453 3,417,781 1,201,328
charges and rounded off LS
TOTAL L.S PROVISIONS: 6,943,698,178 6,960,480,841 16,782,663 -
-
Grand Total (A+B+C) 39,187,000,000 39,459,214,387 2,867,494,555 2,595,280,168

Or Say in Crores 3,918.70 3,945.92

PERCENTAGE OVER OPEN PUMP HOUSE TO UNDER GOROUND PUMP


0.69 % EXCESS
HOUSE:

D LAND ACQUISITION ( As per Agency proposals) -

1 Land required 150 Ac @ RS 5,00,000/Ac 75,000,000 75,000,000

2.a NPV value for forest department for 273 Ac @ RS 10 Lakhs/Ac 273,000,000 - 273,000,000

273 Ac Land to be given to Forest Dept. for compensatory afforestaton cost


b 136,500,000 - 136,500,000
@Rs 5 lakhs/Ac

150 Ac land required for dumping excavated rock muck out side forest area
c 75,000,000 - 75,000,000
@ Rs 5 lakhs

Sub - total for land acqusition 484,500,000 75,000,000 75,000,000 484,500,000

Grand total of A+B+C+D 39,671,500,000 39,534,214,387 2,942,494,555 3,079,780,168


Say in Cr 3,967.15 3,953.42 294.25 307.98
Difference in Cr Less -13.73
Percentage over open pump house to under ground pump house LESS -0.346
PACKAGE NO -1
ITIVE STATEMENT
nd commissioning of Electro Mechanical works such as Vertical - single stage -Francis Turbine pumps and Synchronous motor sets for 8 No.s
g intake structure and tunnel at stage -1 pumping station at Anjanagiri Reservoir at Narlapur (V), Kollapur (M),Mahabubnagar District.

Remarks

Same off take point MGKLIS utlised

The Varation is due to change in design, quantities and ground levels.


In the modified proposals length of Tunnels are increased.
The cost is increased due to under ground excavation.
This provision retained as it is same either for open PH or under ground PH.

This provision retained as it is same either for open PH or under ground PH.

The cost of under ground PH is decreased due to less quantity of excavation owing to reduced height
of pump house as practised in Package 6 of Kaaleshwaram Project as suggested by BHEL.
The Length of Delivery mains is reduced in the modified proposal.
This provision retained as it is same either for open PH or under ground PH.
This provision is not required in under ground proposals.
This provision is necessary for under ground proposals.
This provision is made as per Package-5 under ground proposal i.e. Lift-2.
This provision is made as per Package-5 under ground proposal i.e. Lift-2.
This provision is necessary for under ground proposals.
This provision is necessary for under ground proposals.

This provision retained as it is same either for open PH or under ground PH.

255,431,724
% Excess

This Provision is same either for open PH or under ground PH.

This Provision is same either for open PH or under ground PH.

25.54
% Excess
Increased due to increase in civil work items with under ground PH.

This provision retained as it is same either for open PH or under ground PH.

This provision retained as it is same either for open PH or under ground PH.
Increased due to increase in civil work items with under ground PH.
Increased due to increase in civil work items with under ground PH.
This provision retained as it is same either for open PH or under ground PH.

This provision retained as it is same either for open PH or under ground PH.

This provision retained as it is same either for open PH or under ground PH.

This provision retained as it is same either for open PH or under ground PH.
This provision retained as it is same either for open PH or under ground PH.

This provision retained as it is same either for open PH or under ground PH.

This provision retained as it is same either for open PH or under ground PH.

This provision retained as it is same either for open PH or under ground PH.

This provision retained as it is same either for open PH or under ground PH.

This provision retained as it is same either for open PH or under ground PH.

Increased due to increase in civil work items with under ground PH.

27.22

For Under Ground Proposals less Land acquisition is required. Hence 150 Acres land acquisition is
proposed for little open excavations and for Dumping Rock Muck etc.

This provision is required for making payment to Forest Department.

EquivalEnt Revenue land is to be given to Forest Department for Compensatory afforestation.

Forest Department will not allow to Dump excavated rock muck etc. Hence Non-Forest land is required
for dumping excavated Rock muck.

40.95
ABSTRACT OF EARTH WORK

FOR APPROACH CHANNEL

1. Combined canal from Km 0/0 to Km 0.400 383967

Deducting Existing MGKLIS approach Channel (-) 37000

total in cum 346967

2. Earth work in transition length of Approach channel

From Km 0.400 to 1.100 1260099.6

3. PR approach channel from km 1.10 to 2.056 2085818.0402

4. Approach channel Ramp portion from km 2.056 to 2.205 813,819.60

Total = 43, 62,559. 00 Cum 4,159,737.24

Rate of excavation (Through Rate) Rs 226.23per cum

Total value 4159737.23995

= 98, 69, 41,723 = 941057355.7938

Total value for excavation in Rupees 941057356


Excavation of combined approach channel

in Rupees 78494344

total value: 1,019,551,700.00

9.4E+008
ORK

NEL

383967 141467.702207297

37000 217287.456109909

52688.18

346967 411443.338317206

27476.3383172058

1260099.6

2085818.0402

813,819.60

4,159,737.24

s 226.23per cum

59737.23995 X 226.23

941057355.793889

356
44

019,551,700.00
Package I:

As per Previsous Sanctioned Estimate the EWE Quantity From Km.0.000 to Km

Quantities of earth work in transition portion of Approach channel from km 0.400 t


Distance between
two sections
Sl No Chainage Area
1 Km 0.400 1105.787
100
2 Km 0.500 1453.495
100
3 Km 0.600 1374.151
100
4 Km 0.700 1580.835
100
5 Km 0.800 2082.252
100
6 Km 0.900 1906.392
100
7 Km 1.000 2897.762
100
8 Km 1.100 1506.431

Estimate Quantities of earth work in PR Approach channel from


Distance between
Sl no Chainage Area in sq.m
two sections in m

1 1.100 1506.431
100
2 1.200 1751.018
100
3 1.300 1719.485
100
4 1.400 1848.972
100
6 1.500 2188.008
100
7 1.600 2119.843
100
8 1.700 2354.528
100
9 1.800 2586.213
100
10 1.900 2617.742
100
10 2.000 2744.933
56
11 2.056 2778.958

Total

Estimate for earth work in Approach channel Ramp portion from Km 2.056 to 2.205
Sl no chainage Area deduct due to
2.5mtrs bedwidth
reduced
1 Km 2.056 2778.958 0

2 Km 2.075 2965.909 76.4825

3 Km 2.100 4095.903 80.067

4 Km 2.125 5012.438 84.272

5 Km 2.150 6053.450 89.077

6 Km 2.175 7184.581 93.882

7 Km 2.205 10508.590 98.687


Km.0.000 to Km.0.400 383967

from km 0.400 to Km 1.100

Average Area Quality

1279.641 127,964.10

1413.823 141,382.30

1477.493 147,749.30

1831.5435 183,154.35

1994.322 199,432.20

2402.077 240,207.70

2202.0965 220,209.65

1260099.6

channel from Km 1.100 to 2.056

Average Area Quantity in Cum

1628.72445 162872.445

1735.25145 173525.145

1784.2285 178422.85

2018.49 201849

2153.9255 215392.55

2237.1855 223718.55
2470.3705 247037.05

2601.9776 260197.76

2681.33745 268133.75

2761.94545 154668.95

Total 2085818.0402

m 2.056 to 2.205
net area Distance between Average area Quality
two sections

2778.958
19 2834.192 53,849.65
2889.426
25 3452.63085 86,315.77
4015.8357
25 4472.00085 111,800.02
4928.166
25 5446.2695 136,156.74
5964.373
25 6527.53585 163,188.40
7090.6987
30 8750.30085 262,509.03
10409.903
Total 813,819.60
Total
ABSTRCT OF INTAKE STRUCTURE AT KM 2.185 FOR LIFT-1
Type Qty Unit
A INTAKE STRUCTURE
1 Earthwork Excavation
a Excavation for Structures- Mechanical MeansEarth work in
excavation in all kinds of soils of foundation of structures as
per drawing and technical pecification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom and
backfilling with approved material.Depth upto 3 m

All soils 12645.00 Cum


b Excavation in ordnary rock without blasting for foundations
of canal cross drainageand other appurtenant structures and
placing the excavated stuff neatly in specified dump area or
disposing off the same as directed etc., complete with initial
lead upto 50 m and initial lift upto 3 m.

HDR 16860.00 Cum


c Excavation in hard rock requiring blasting including boulders
above 0.6 m upto 1.2 m dia. for foundations of canal cross
drainage and other appurtenant structures and placing
theexcavated stuff neatly in specified dump area or disposing
off the same as directed etc.,complete with initial lead upto
HR
50 m and initial lift upto 3 m. 12645.00 Cum
2 Providing and laying insitu vibrated M-25 ( 28 days cube
compressive strength not less than 25 N /sq mm ) grade
cement concrete using 40 mm down size approved, clean,
hard, graded aggregates for foundation filling including cost
of all materials, machinery, labour, formwork,cleaning,
batching, mixing, placing in position, levelling, vibrating,
finishing, curing etc.,complete with initial lead upto 50 m and
all lifts.

M-25 for Foundations 2416.00 Cum


3 Providing and laying insitu vibrated M-30 ( 28 days cube
compressive strength not less than 30 N / sq mm ) grade
cement concrete using 20 mm down size approved, clean,
hard, graded aggregates for troughs including cost of all
materials, machinery, labour, formwork,scaffolding, cleaning,
batching, mixing, placing in position,levelling, vibrating,
finishing, curing etc., complete with initial lead upto 50 m
and all lifts.

RCC M-30 for piers, abutments, 32766.00 Cum


beams,slabs,columns and returns
4 Providing and laying insitu M- 35 ( 28 days cube compressive
strength not less than 35 N /sqmm ) grade cement concrete
using 20 mm down size approved, clean, hard,
gradedaggregates for wearing coat including cost of all
materials, machinery, labour, formwork,cleaning, batching,
mixing, placing in position in alternate panels, levelling,
compacting,finishing, curing, packing joints with asphalt
mortar etc., complete with initial lead upto 50 mand all lifts.

M-35 wearing coat 285.00 Cum


5 Providing, fabricating and placing in position reinforcement
steel bars for RCC works includingcleaning, straightening,
cutting, bending, hooking, lapping, welding wherever
required,tying with1.25 mm dia soft annealed steel wire,
including cost of all materials, machinery, labour
etc.,complete with initial lead upto 50 and all lifts.

Steel 882.00 MT
6 Providing and fixing 100 mm dia perforated PVC pipes
40 cm long for Weep holes including cost of all materials,
labour, drilling 8 mm dia holes etc. complete with allleads
and lifts.

Weep Holes 300.00 Nos


7 Shortcreting in two layers (each layer+38 mm thickness) for slabs 4050.00 Sqm
duly fixing chain weld wire mesh 100 x 100x5 mm in between the
two layers including cost and conveyance of all materials, labour
charges, all heads, lifts, centering, scaffolding, machine mixing,
laying concrete with shortcrete machine etc. complete as per
specification and as directed by Engineer-in-Charge

A Amount of Intake Structure


B Amount of Intake Gates
Grand Total :(A+B)
UCTURE AT KM 2.185 FOR LIFT-1 OF PRLIS
Rate Amount Remarks

IRR-CCDW-1-2

136.40 1724778.00

IRR-CCDW-1-4

161.50 2722890.00

IRR-CCDW-1-5

378.90 4791191.00

IRR-CCDW-2-3

5567.90 13452046.00

IRR-CCDW-2-27

7173.20 235037071.00
IRR-CCDW-2-26

5522.90 1574027.00

IRR-CCDW-2-1

50126.90 44211926.00

IRR-CAW-7-23

221.30 66390.00
1453.60 5887080.00

IRR-TAW-2-3

309467399.00
134209503.40
443676902
DETAILED ESTIMATE OF INTAKE STRUCTURE FOR LIFT-1 OF PRLIS
Sl. No. Description of work Nos L B

1 Earth work excavation

1 Returns @1-1 2 48.00 6.00


2 Returns @2-2 2 49.30 6.00
3 Returns @3-3 uk 2 5.00 4.40
4 Wing 6 20.00 3.00
5 U/s floor 3 10.00 20.50
6 CREST 3 15.00 16.50
7 D/S Sloped Portion 3 9.00 16.50

All soils 30% 12645.30


HDR 40% 16860.40
HR 30% 12645.30

2 Vibrated M 25 for foundation concrete

1 Returns @1-1 2 48.00 6.00


2 Returns @2-2 2 49.30 6.00
3 Returns @3-3 2 5.00 4.40
4 Wing 6 20.00 2.50
5 U/s floor 3 10.00 20.50
6 CREST 3 15.00 16.50
7 D/S Sloped Portion 3 9.00 16.50
8 Parapet wall 1 199.00 0.60

3 Vibrated M30 for Piers, abutments,beams, slabs,columns and returns

1 Returns @1-1 2 48.00 6.00


2 Returns @2-2 2 49.30 6.00
3 Returns @3-3 2 4.60 4.40
4 Wing 6 20.00 2.50
5 PIERS 6 20.00 2.50
6 Slab 3 10.50 10.35
7 Bel mouth slab 3 20.00 9.07
8 Columns 18 2.80 1.00
9 Beams 6 20.00 0.60
6 9.07 0.60
10 Trash structure beams 9 36.00 0.60
4 Wearing coat in M-35 over the floor

1 U/sfloor 3 10.00 20.50


2 Crest 3 17.00 16.50
3 D/S Floor 3 9.00 16.50

5 Steel

1 Piers upto 18.92m height 1 78288.52


2 Piers from 18.92m to 34m height 1 51202.90
3 piers distribution bars 1 90200.48
1 72586.00
4 Winghs reinforcement 1 111600.00
distribution 1 59500.00
5 Gate chamber 1 74830.00
distribution 1 34150.00
6 Bell mouth chamber 1 46930.00
distribution 1 29950.00
7 base slab reinforcement @218.84m 1 15333.13
distribution 1 15333.13
8 base slab reinforcement @238.76m 1 15333.13
distribution 1 15333.13
9 beams 1 17981.00
10 stirrups 1 1771.20
11 Anchor bars 1 5000.00

For Twin Tunnel


For Three Tunnel (Increased 20 %)
6 Weep holes 300 - -

7 Short creting 3 30
INTAKE STRUCTURE FOR LIFT-1 OF PRLIS
D QTY

10.60 6105.60
10.60 6270.96
8.60 378.40
8.60 3096.00
1.10 676.50
34.00 25245.00
0.85 378.68

42151.14
or say 42151.00 cum

12645.00 cum
16860.00 cum
12645.00 cum

0.60 345.60 cum


0.60 354.96 cum
0.60 26.40 cum
0.60 180.00 cum
1.10 676.50 cum
0.60 445.50 cum
0.60 267.30 cum
1.00 119.40
2415.66 cum
or say 2416.00 cum

13.00 7488.00 cum


13.00 7690.80 cum
8.60 348.12 cum
15.80 4740.00 cum
34.00 10200.00 cum
2.50 814.75 cum
0.30 163.33 cum
21.76 1096.70
0.75 54.00
0.75 24.50
0.75 145.80
32766.00 cum
or say 32766.00 cum
0.150 92.25 cum
0.150 126.23 cum
0.150 66.83 cum
285.30 cum
or say 285.00 cum

78288.52 kg
51202.90 kg
90200.48
72586.00
111600.00
59500.00
74830.00
34150.00
46930.00
29950.00
15333.13
15333.13
15333.13
15333.13
17981.00
1771.20
5000.00 kg
735322.62 kg
735 MT
882 MT
- 300 Nos

45 4050 Sqm
ABSTRACT
SERVICE GATES

Sl.no SSR-Ref

1 IRR-GAW-2-1

2 IRR-GAW-2-2
3 IRR-GAW-2-4

4 IRR-GAW-2-7
5 IRR-GAW-2-8

SAND BLASTING AND PAINTING


Sl.no SSR-Ref

6 IRR-GAW-3-1

7 IRR-GAW-3-2

8 IRR-GAW-3-3
9 IRR-GAW-3-4
ABSTRACT
SERVICE GATES
Quantity
Description of Item
in MT

VERTICAL LIFT GATES-EM PARTS


Design, fabrication, supply, erection and commissioning of
embedded parts consisting of sill beam, slide tracks, seal seats, guide
rails, dogging sets for storage of stoplog elements etc., with all
accessories for spillway stop log gates and other vertical lift elements
including cost of all materials,machinery, labour, etc., complete as per
567
specifications and approved drawings (without painting on sand-blasted
or mechanical cleaning surfaces which are added extra as perscedule
of rates under items in this chapter and add as applicable separately)
Drawing No. MD/CDO/GNCP/HR/1759,1760/94 (GNSS Project)Vent
Size:3.6 X 6.1 Mtr

Vertical lift gates and stop log gate elements (SLIDING


GATES)
Design, fabrication, supply, erection, testing and commissioning of
vertical lift gates and stoplog gate elements, consisting of skin
plate,horizontal and vertical girders, stiffeners, lifting pins, bronze
padded slide blocks/bearings, guide shoes,rubber seals, clamps etc.,
with all accessories including cost of all materials,machinery, labour,
seal fixing etc.,complete as per specifications and approved drawings
(without painting on sand-blasted or mechanical cleaning surfaces
which are added extra as perscedule of rates under items in this
chapter and add as applicable separately).
Drawing NO. CE/CDO/CL3/MRP/783/2002 (Spillway Stop log gate
Elements of Madduvalasa Project)
Vent Size: 12.624 X 0.50 M 16 Elements

218.45
MOVING GANTRY CRANE-CLASS II
fabrication, supply, erection, testing and commissioning of adequate
capacity Class- II type moving gantry crane consisting of rail mounted
gantry frame, top platform with hand railing, long / cross travel
arrangements, rope drums, gear systems, electric motors, electro-
magnetic brake system, cabin, control panel, wire rope, ladder,
motorised cable reeling drum etc., with all accessories for operating 30

spillway stop log gate elements and river sluice /canal sluice
emergency gates including cost of all materials, machinery, labour, etc.,
complete with all leads and lifts. (without painting on sand-blasted or
mechanical cleaning surfaces which are added extra as perscedule of
rates under items in this chapter and add as applicable separately)
VERTICAL LIFT GATES-ROPE DRUM HOIST UPTO 30 TON CAP.
POWER OPERATED
Design, fabrication, supply, erection, testing and commissioning of
adequate capacity rope drum hoist consisting of hoist platform, rope
drum, gear system, electric motor, electro-magnetic brake system, hand
operation assembly, control panel, wire rope, pulleys, ladder etc.,with all
accessories for operating river sluice / canal sluice service gate 120
including cost of all materials, machinery, labour, , complete as per
specifications and drawings with all leads and lifts (without painting on
sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under items in this chapter and add as
applicable separately)
HOIST BRIDGE/ WITH TRESSELS
Design, fabrication, supply, erection and commissioning of structural
steel hoist bridge consisting of columns, beams, bracings, stiffeners,
ties, chequered plate covering, hand railing, ladder etc., with all
accessories for supporting rope drum hoist for operating barrage gates
including cost of all materials, machinery, labour, welding, finishing,
6
etc., complete complete as per specifications and drawings with all
leads and lifts(without painting on sand-blasted or mechanical cleaning
surfaces which are added extra as perscedule of rates under items in
this chapter and add as applicable separately)
Drawing No. CE/CDO/VRSP/215,216/86-87 (Vengalaraya Sagar -
Gomukhi Project)

SAND BLASTING AND PAINTING


Description of Item Nos

Cleaning gates / hoists / embedded parts/lifting beams etc, to expose


fresh metal surface for painting by sand blasting method as per
specifications including cost of all materials, Labour, machinery, 470
scaffolding, etc., complete with initial lead for sand upto 1 km and all
lifts.

Painting of embedded metal parts and all types of gates, stoplogs,etc,


on sand blasted surfaces with one coat of inorganic zinc silicate (airless
spray preferred)70+/- 5 and two super coats with a total thickness of
470
300 microns (each 150+/- 5) of solventless coaltar epoxy paint each
coat 150 microns ( total 300 microns) cost of all materials, labour,
scaffolding etc., complete with all leads and all lifts

Painting of Lifting beams,cat walks and other similar structures-


painting hoist machinery, on sand blasted surfaces with two coats of
zinc phosphate primer (airless spray preferred) 40microns/coat and 470
twocoats of alkyd based micaccous iron oxide paint , 65 microns/coat
cost of all materials, labour, scaffolding etc., complete with all leads and
lifts
HOISTS:STRUCTURAL COMPONENTS--painting structurals on sand
blasted surfaces with two coats of zinc phosphate primer (airless spray 470
preferred) 40microns/coat and one coat 65+/-5 of alkyd based
micaccous iron oxide paint followed by two coats of synthetic enamel
paint 25 microns/coat cost of all materials, labour, scaffolding etc.,
complete with all leads and all lifts
Rate Amount

157753 89445951

128611 28095072.95
228410 6852300

70435 8452200
110270 661620

133507143.95

Rate Amount

360.12 169256.4

479 225130

346.6 162902
431.8 202946

760234.4
Total = 134267378.35
GATES
Sl.no SSR-Ref

1 IRR-GAW-2-1

2 IRR-GAW-2-2
3 IRR-GAW-2-4

4 IRR-GAW-2-7

5 IRR-GAW-2-8
SAND BLASTING AND PAINTING
Sl.no SSR-Ref

1 IRR-GAW-3-1

2 IRR-GAW-3-2

3 IRR-GAW-3-3

4 IRR-GAW-3-4
GATES
Description of Item Nos
VERTICAL LIFT GATES-EM PARTS
Design, fabrication, supply, erection and commissioning of
embedded parts consisting of sill beam, slide tracks, seal seats, guide
rails, dogging sets for storage of stoplog elements etc., with all
accessories for spillway stop log gates and other vertical lift elements
including cost of all materials,machinery, labour, etc., complete as per
specifications and approved drawings (without painting on sand-blasted
or mechanical cleaning surfaces which are added extra as perscedule
of rates under items in this chapter and add as applicable separately)
Drawing No. MD/CDO/GNCP/HR/1759,1760/94 (GNSS Project)Vent
Size:3.6 X 6.1 Mtr

EM parts 9
Vertical Service gates 9
Hoist Brigde 9
Total
Vertical lift gates and stop log gate elements (SLIDING
GATES)
Design, fabrication, supply, erection, testing and commissioning of
vertical lift gates and stoplog gate elements, consisting of skin
plate,horizontal and vertical girders, stiffeners, lifting pins, bronze
padded slide blocks/bearings, guide shoes,rubber seals, clamps etc.,
with all accessories including cost of all materials,machinery, labour,
seal fixing etc.,complete as per specifications and approved drawings
(without painting on sand-blasted or mechanical cleaning surfaces
which are added extra as perscedule of rates under items in this
chapter and add as applicable separately).
Drawing NO. CE/CDO/CL3/MRP/783/2002 (Spillway Stop log gate
Elements of Madduvalasa Project)
Vent Size: 12.624 X 0.50 M 16 Elements

EM parts 9
Stop Log Gates 1
Total
MOVING GANTRY CRANE-CLASS II
fabrication, supply, erection, testing and commissioning of adequate
capacity Class- II type moving gantry crane consisting of rail mounted
gantry frame, top platform with hand railing, long / cross travel
arrangements, rope drums, gear systems, electric motors, electro-
magnetic brake system, cabin, control panel, wire rope, ladder,
motorised cable reeling drum etc., with all accessories for operating 1

spillway stop log gate elements and river sluice /canal sluice
emergency gates including cost of all materials, machinery, labour, etc.,
complete with all leads and lifts. (without painting on sand-blasted or
mechanical cleaning surfaces which are added extra as perscedule of
rates under items in this chapter and add as applicable separately)
VERTICAL LIFT GATES-ROPE DRUM HOIST UPTO 30 TON CAP.
POWER OPERATED
Design, fabrication, supply, erection, testing and commissioning of
adequate capacity rope drum hoist consisting of hoist platform, rope
drum, gear system, electric motor, electro-magnetic brake system, hand
operation assembly, control panel, wire rope, pulleys, ladder etc.,with all
accessories for operating river sluice / canal sluice service gate 1
including cost of all materials, machinery, labour, , complete as per
specifications and drawings with all leads and lifts (without painting on
sand-blasted or mechanical cleaning surfaces which are added extra
as perscedule of rates under items in this chapter and add as
applicable separately)

HOIST BRIDGE/ WITH TRESSELS


Design, fabrication, supply, erection and commissioning of structural
steel hoist bridge consisting of columns, beams, bracings, stiffeners,
ties, chequered plate covering, hand railing, ladder etc., with all
accessories for supporting rope drum hoist for operating barrage gates
including cost of all materials, machinery, labour, welding, finishing,
1
etc., complete complete as per specifications and drawings with all
leads and lifts(without painting on sand-blasted or mechanical cleaning
surfaces which are added extra as perscedule of rates under items in
this chapter and add as applicable separately)
Drawing No. CE/CDO/VRSP/215,216/86-87 (Vengalaraya Sagar -
Gomukhi Project)
SAND BLASTING AND PAINTING
Description of Item Nos

Cleaning gates / hoists / embedded parts/lifting beams etc, to expose


fresh metal surface for painting by sand blasting method as per
specifications including cost of all materials, Labour, machinery, 1
scaffolding, etc., complete with initial lead for sand upto 1 km and all
lifts.

Painting of embedded metal parts and all types of gates, stoplogs,etc,


on sand blasted surfaces with one coat of inorganic zinc silicate (airless
spray preferred)70+/- 5 and two super coats with a total thickness of
1
300 microns (each 150+/- 5) of solventless coaltar epoxy paint each
coat 150 microns ( total 300 microns) cost of all materials, labour,
scaffolding etc., complete with all leads and all lifts

Painting of Lifting beams,cat walks and other similar structures-


painting hoist machinery, on sand blasted surfaces with two coats of
zinc phosphate primer (airless spray preferred) 40microns/coat and 1
twocoats of alkyd based micaccous iron oxide paint , 65 microns/coat
cost of all materials, labour, scaffolding etc., complete with all leads and
lifts

HOISTS:STRUCTURAL COMPONENTS--painting structurals on sand


blasted surfaces with two coats of zinc phosphate primer (airless spray 1
preferred) 40microns/coat and one coat 65+/-5 of alkyd based
micaccous iron oxide paint followed by two coats of synthetic enamel
paint 25 microns/coat cost of all materials, labour, scaffolding etc.,
complete with all leads and all lifts
Quantity in
Weight in MT
MT

2.7333333

10 90 8.25
45 405 34.017 7.2
8 72
= 567

12.05 108.45
110 110
= 218.45
30 30

120 120

6 6
Quantity in Quantity in
Sq.m Sq.m

470.25 470

470.25 470

470.25 470

470.25 470
43.2 70
27.075 0.6267361
43.871528
PRLIS - PACKAGE NO. 1

ABSTRACT OF APPROACH
PRLIS-(Package No.1)- Construction of Stage-1 pumping station near Anjanagiri Reserv

Electro Mechanical works such as Vertical- Single Stage-Francis Turbine Pumps and S

accessories and Earth work Excavation of approach channel from foreshore of Srisai

pumping station at Anjanagiri Reservoir at Narlapur (V), Kollapur (M), Mahabubnagar Dist
S.No Item Description

Excavation of tunnel in hard rock equiring blasting drilling, wedging


1 and chiselling as required with a lead of 5 Km and depositing the muck
as directed by the Engineer-in-Charge during the excution.

Shotcreting with CC (M20) for 50mm thick around the tunnel and adits
2
cross-section in weak zones(Anticipated 25% of the length)

PCC (M 10) concrete for backfilling the extra excavated portion around
3
the tunnel (200mm on either side).
4 PCC (M 20) around the Tunnel sction
Tunnel Bed & Kerb (500 mm thick)
Tunnel Arch (500 mm Thick)
RCC (M20) lining with 500mm thick around the tunnel at weak/faulty
5
zones in the tunnel.(Anticipated 25% of the length)
Tunnel Bed & Kerb (500 mm thick)
Tunnel Arch (500 mm Thick)

Reinforcement steel for RCC lining at weak/faulty zones in the tunnel.


6
(Anticipated 25% of the length)
Drilling grout holes of 10m long (equal to dia of tunnel) with 3m c/c
7
spacing in weak/faulty zone. (Anticipated 25% of the length)

Backfill cement grouting between rock and concrete lining with 3m c/c
8
spacing.

Providing weep holes (Drainage holes) with 75 mm dia G.I Pipe on


10
both side of the crown at 6m c/c staggered.

25mm dia bolts of 4m long @ 3m c/c spacing of intake tunnel and


11
adits.(for 3/4 th peimeter)
RCC (M20) lining of 500 mm thick for construction of entrance portal
12
section for tunnels
PRLIS - PACKAGE NO. 1

Reinforcement Steel for RCC lining at tunnels entrance portals (10mm


13
dia bars 200c/c in b/w).
Providing, fabricating and fixing in position permanent supports in
13
weak zone of one setup@250 m

Providing, fabricating and fixing in position temporarily structural steel


14
supports in weak zone of 4 Km supports between@250 m
PRLIS - PACKAGE NO. 1

TRACT OF APPROACH TUNNEL


ation near Anjanagiri Reservoir and Design, supply, erection testing and commissioning of

ancis Turbine Pumps and Synchronous motor sets for 8 No.s of 145 MW each including all

nel from foreshore of Srisailam Reservoir including intake structure and tunnel at Stage -1

apur (M), Mahabubnagar District.


Rate.Rs/
Item Code Quantity Unit Amount in Rupees
unit

IRR-TAW-1-3 262212.00 Cum 1827.00 479061324.00

IRR-TAW-2-3 17729.00 Sqm 1454.00 25777966.00

IRR-TAW-5-2
13985.00 Cum 5402.00 75546970.00

IRR-TAW-5-3 19776.00 Cum 6617.00 130857792.00


IRR-TAW-5-4 15008.00 Cum 6822.00 102384576.00

IRR-TAW-5-3 6373.00 Cum 6617.00 42170141.00


IRR-TAW-5-4 5003.00 Cum 6822.00 34130466.00

IRR-TAW-5-1
291.32 M.T 58504.00 17043444.00
IRR-TAW-6-1
8058.00 Rm 399.00 3215142.00

IRR-TAW-6-2
322.37 M.T 11171.00 3601173.00
IRR-TAW-6-3
876.00 Nos 366.00 320616.00

IRR-TAW-3-1
1752.00 Rm 1034.00 1811568.00
IRR-TAW-5-4
546.00 Cum 6822.00 3724812.00
PRLIS - PACKAGE NO. 1

IRR-TAW-5-1
6.32 M.T 58504.00 369979.00

IRR-TAW-3-3 48.00 M.T 85617.00 4109616.00

IRR-TAW-3-4 48.00 M.T 22068.00 1059264.00

TOTAL FOR THREE TUNNELS 925184849.00


PRLIS - PACKAGE NO. 1

DETAILED ESTIMATE OF APPRO


PRLIS-(Package No.1)- Construction of Stage-1 pumping station near Anjanagiri Reservoir and

works such as Vertical- Single Stage-Francis Turbine Pumps and Synchronous motor sets for 8

approach channel from foreshore of Srisailam Reservoir including intake structure and tunnel

(M), Mahabubnagar District.


SSR REF
S.No Item Description Nos

Excavation of tunnel and adits in hard rock equiring


blasting drilling, wedging and chiselling as required
1 with a lead of 5 Km and depositing the muck as
directed by the Engineer-in-Charge during the
excution.

Tunnel-9.2 m Dia Ch:3.081 to 2.205 m IRR-TAW-1-3


9.2+2*0.5+2*0.15=10.5 3
or Say

Shotcreting with CC (M20) for 50mm thick around


2 the tunnel and adits cross-section in weak
zones(Anticipated 25% of the length)

Tunnel 1

IRR-TAW-2-3 3

PCC (M 10) concrete for backfilling the extra


3 excavated portion around the tunnel (200mm on
either side).

Tunnel10.5-0.15=10.35(c/c) IRR-TAW-5-2 3

PCC (M 20) around the Tunnel section(75% of the


4
Length)
Tunnel Bed & Sides (500 mm Thick) IRR-TAW-5-3 3
Kerb 3
Tunnel Arch (500 mm Thick) IRR-TAW-5-4 3

RCC (M20) lining with 500mm thick around the


5 tunnel at weak/faulty zones in the tunnel.(Anticipated
25% of the length)

Tunnel Bed & sides (500 mm thick)


IRR-TAW-5-3 3

Tunnel Arch (500 mm Thick) IRR-TAW-5-4 3


PRLIS - PACKAGE NO. 1

Reinforcement steel for RCC lining at weak/faulty


6 IRR-TAW-5-1
zones in the tunnel.(Anticipated 25% of the length)

Main reinforcement outer side (20mmdia at


1096
200mmc/c)
Main reinforcement inner side (20mmdia at
1096
200mmc/c)
distribution reinforcement outer side (10mmdia at
60.4764
250mmc/c)
distribution reinforcement inner side (10mmdia at
59.032
250mmc/c)

Drilling grout holes of 9.20m long (equal to dia of


7 tunnel) with 3m c/c spacing in weak/faulty zone.
(Anticipated 25% of the length)

4 grout holes distributed at 900 along periphery of


IRR-TAW-6-1 3
Tunnel

Backfill cement grouting between rock and concrete


8 IRR-TAW-6-2 3
lining with 3m c/c spacing.

4 grout holes distributed at 900 along periphery of


Tunnel(equal to dia of tunnel)

Providing weep holes (Drainage holes) with 75 mm


9 dia G.I Pipe on both side of the crown at 6m c/c IRR-TAW-6-3 3
staggered.

25mm dia rock bolts of 4m long @ 3m c/c spacing of


10
intake tunnel and adits.(for 3/4 th peimeter)

Tunnel (1/3 rd length) Nos = 8 nos IRR-TAW-3-1 3

RCC (M20) lining of 500 mm thick for construction of


11 3
entrance portal section for tunnels

Reinforcement Steel for RCC lining at tunnels


12 IRR-TAW-5-1
entrance portals (10mm dia bars 200c/c in b/w).
longitidinal bars (outer) 50
longitidinal bars (inner) 50
distribution bars(Outer) 100.00
distribution bars(inner) 90.00
PRLIS - PACKAGE NO. 1

Providing, fabricating and fixing in position


13 permanent supports in weak zone of one setup@250 3
m
Assumed Steel for each setup

Providing, fabricating and fixing in position


14 temporarily structural steel supports in weak zone of 3
4 Km supports between@250 m

Assumed Steel for each setup


PRLIS - PACKAGE NO. 1

MATE OF APPROACH TUNNEL


iri Reservoir and Design, supply, erection testing and commissioning of Electro Mechanical

motor sets for 8 No.s of 145 MW each including all accessories and Earth work Excavation of

ture and tunnel at Stage -1 pumping station at Anjanagiri Reservoir at Narlapur (V), Kollapur

Dimensions
Quantity Remarks
L B D

###
0.905x10.5x10.5 #
876 99.78 262211.99 Cum
262212.00 Cum

###
219.0 (3.14x5.25)+(2x5.25)
#

219.0 26.985 17729.00 Sqm

876
#

876 5.322 13985.00 Cum

###
657 9.7 19119.00 Cum
876 0.250 657.00 Cum
657 7.615 15008.00 Cum

657 0.00 Cum

219 9.7 6373.00 Cum

219 7.615 5003.00 Cum


PRLIS - PACKAGE NO. 1

15.1191 40929.00 40.93

14.758 39952.00 39.95

219 8211.00 8.21

219 8015.00 8.02


TOTAL (for 1 No.) 97107.00 Kgs
(for 3 No's) 291321.00 Kgs
291.32 MT

292 9.2 8058.00 Rm

292 9.2 40kg/Rm 322.37 MT

292 876.00 Nos

2336 4 1752.00 Rm

10 18.211 546.00 Cum

15.00 0.62 kg/Rm 465.00


15.00 465.00
10.00 620.00
10.00 558.00
Total 2108.00 Kgs
For 3 No's Total 6324.00 Kgs
PRLIS - PACKAGE NO. 1

6.32 MT

4x4 48.00 MT

4x4 48.00 MT
PRRLIS -PACKEGE NO.1

ABSTRACT
PRLIS-(Package No.1)- Construction of Stage-1 pumping station n

Electro Mechanical works such as Vertical- Single Stage-Francis T

accessories and Earth work Excavation of approach channel from

pumping station at Anjanagiri Reservoir at Narlapur (V), Kollapur (M


S.NO ITEM CODE

1 IRR-TAW-1-5

2 IRR-TAW-1-3

3 IRR-TAW-1-4

4 IRR-TAW-1-6
PRRLIS -PACKEGE NO.1

5 IRR-TAW-3-4

6 IRR-TAW-3-3

7 IRR-TAW-6-1

8 IRR-TAW-6-2

9 IRR-TAW-3-1

10 IRR-TAW-2-2

IRR-TAW-2-3 (new4 -
11
2011-12)
PRRLIS -PACKEGE NO.1

12 IRR-TAW-5-3

13 IRR-TAW-5-4

14 IRR-TAW-5-1

15 IRR-CCDW-2-25
PRRLIS -PACKEGE NO.1

16 IRR-DAW-2-1A
PRRLIS -PACKEGE NO.1

ABSTRACT ESTIMATE OF SURGE POOL


)- Construction of Stage-1 pumping station near Anjanagiri Reservoir and Design, supply, erection tes

orks such as Vertical- Single Stage-Francis Turbine Pumps and Synchronous motor sets for 8 No.s of

th work Excavation of approach channel from foreshore of Srisailam Reservoir including intake struct

njanagiri Reservoir at Narlapur (V), Kollapur (M), Mahabubnagar District.


DESCRIPTION OF ITEM QUANTITY UNIT

Excavation for tunnel by heading and benching tunnelling methods


including excavation for supports in all types of soil / rock strata
requiring supports ( excluding cost of providing supports ) for roof
before benching including cost of all other materials, machinery,
40363 Cum
labour,scaling excavated surface, ventilation, lighting, drainage
removing and hauling excavated muck outside tunnel upto specified
dump area and all other ancillary operations etc., complete with initial
lead upto 1 km and all lifts for Surgepool Roof.

Excavation for tunnel by tunnelling methods in rock not requiring


supports including cost of all materials,machinery, labour, scaling
excavated surface, removing under-cuts, ventilation,lighting,
327335 Cum
drainage, removing and hauling the excavated muck outside tunnel
upto specified dump area and all other ancillary operations etc.,
complete with initial lead upto 1 km and all lifts.

Excavation for tunnel by tunnelling methods including excavation for


supports in all types of soil / rock strata requiring supports ( excluding
cost of providing supports ) including cost of all other materials,
machinery, labour, scaling excavated surface, ventilation, lighting, 140286 Cum
drainage,removing and hauling the excavated muck outside tunnel
upto specified dump area and all other ancillary operations etc.,
complete with initial lead upto 1 km and all lifts.

Removing and hauling muck overfallen due to natural causes such


as geological faults etc., out of tunnel including breaking large
fragments by blasting if necessary and disposing off the same in
50798 Cum
specified dump area or as directed including cost of all materials,
machinery,labour, ventilation, drainage, lighting and all other ancillary
operations etc., complete with initial lead upto 1 km and all lifts
PRRLIS -PACKEGE NO.1

Providing, fabricating and fixing in position temperary structural steel


supports as per details and dismantling the same before concreting
including cost of all materials, machinery, labour,cutting, bending, 100 MT
welding, grinding, ventilation, lighting, drainage and all other ancillary
operations etc.,complete with initial lead upto 1 km and all lifts.

Providing, fabricating and fixing in position permanent structural steel


supports as per details including cost of all materials, machinery,
labour, cutting, bending, welding, grinding, lighting,ventilation, 200 MT
drainage and all other ancillary operations etc., complete with initial
lead upto 1 km and all lifts.

Drilling 32 mm diameter grout holes in concrete / rock by percussion


drilling using jack hammer or stooper drills as directed to specified
depth for consolidation / contact grouting including cost of all 697 Rmt
materials, machinery, labour, cleaning holes, ventilation, lighting,
drainage and all other ancillary operations etc., complete.

Grouting cement slurry in grout holes under specified pressure for


consolidation / contact grouting including cost of all materials,
machinery, labour, redrilling wherever necessary,ventilation,lighting, 52.275 MT
drainage and other ancillary operations etc., complete with lead upto
1 km and all lifts.

Providing and fixing 25 mm diameter steel rock bolts with mechanical


/ wedge type anchorage including drilling 35 mm dia holes, providing
15 cm long 20 mm thick steel tapered wedge, 10 mm thick plate
washers and nuts, tightening bolt by torque wrench, cost of all 41414 Rmt
materials, machinery, labour, ventilation, lighting, drainage and all
other ancillary operations etc., complete with lead upto 1 km and all
lifts.

Providing 25 mm thick guniting to sides and arch of tunnel in cement


mortar
1 : 3 proportion by weight including cost of all materials, machinery, 30660 Sqm
labour, ventilation, lighting, drainage and all other ancillary operations
etc., complete with lead upto 1 km and all lifts.

Shortcreting in two layers (each layer+38 mm thickness) for slabs


duly fixing chain weld wire mesh 100 x 100x5 mm in between the two
layers including cost and conveyance of all materials, labour charges,
30660 Sqm
all heads, lifts, centering, scaffolding, machine mixing, laying
concrete with shortcrete machine etc. complete as per specification
and as directed by Engineer-in-Charge
PRRLIS -PACKEGE NO.1

Providing and laying insitu vibrated M-20 ( 28 days cube compressive


strength not less than 20 N / sqmm ) grade cement concrete using 40
mm and down size approved clean, hard,graded aggregates crushed
from tunnel muck for kerb and bed lining including cost of all
materials, machinery, labour, formwork, batching, mixing, conveying
upto placing point in agitator cars, placing in position, levelling, 6288 Cum
vibrating, finishing, curing, ventilation, lighting,drainage and all other
ancillary operations etc., complete with lead upto 1 km and all lifts.
( Cement content 330 kg / cum for use of super plasticiser(0.4% by
wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA :
0.40 cum)

Providing and laying insitu vibrated M-20 ( 28 days cube compressive


strength not less than 20 N / sqmm ) grade cement concrete using 40
mm and down size approved clean, hard,graded aggregates crushed
from tunnel muck for sides and arch lining including cost of all
materials, machinery, labour, formwork, batching, mixing, conveying
upto placing point in agitator cars, placing in position, levelling, 36792 Cum
vibrating, finishing, curing, ventilation, lighting,drainage and all other
ancillary operations etc., complete with lead upto 1 km and all lifts.
( Cement content 330 kg / cum for use of super plasticiser(0.4% by
wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA :
0.40 cum)

Providing, fabricating and placing in position reinforcement steel for


tunnel RCC works including cleaning, straightening, cutting, bending,
hooking, lapping / welding joints wherever required, tying with 1.25
3446.4 MT
mm dia.soft annealed steel wire, including cost of all materials,
labour,machinery, ventilation, lighting, drainage etc.,complete with
initial lead upto 1 km and all lifts.

Providing and laying insitu vibrated M-20 ( 28 days cube compressive


strength not less than 20 N / sq mm ) grade cement concrete using
20 mm down size approved, clean, hard, graded aggregates for
columns and beams including cost of all materials, labour,
14428.00 Cum
machinery,formwork, scaffolding, cleaning, batching, mixing, placing
in position, levelling, vibrating,finishing, curing etc.,complete with
initial lead upto 50 m and all lifts.CA : 0.80cum, Blending Ratio of
CA--65:35, FA : 0.45 cum))
PRRLIS -PACKEGE NO.1

Providing, fabricating and placing in position reinforcement steel for


RCC,below 36 dia rods overlaps and wastages wherever required,
tying with 1.25 mm diameter soft annealed steel wire, including cost 1299.00 MT
of all materials, machinery, labour etc., complete with initial lead upto
1 km and all lifts.overlaps and wastage as per NHAI-data

T
PRRLIS -PACKEGE NO.1

SURGE POOL
Reservoir and Design, supply, erection testing and commissioning of

and Synchronous motor sets for 8 No.s of 145 MW each including all

Srisailam Reservoir including intake structure and tunnel at Stage -1

r District.
RATE AMOUNT

1928.00 77819864.00

1827.00 598041045.00

1879.00 263597394.00

405.00 20573190.00
PRRLIS -PACKEGE NO.1

22068.00 2206800.00

85617.00 17123400.00

399.00 278103.00

11171.00 583964.00

1034.00 42822076.00

604.00 18518640.00

1454.00 44579640.00
PRRLIS -PACKEGE NO.1

6617.00 41607696.00

6822.00 250995024.00

58504.00 201628186.00

7204.00 103939312.00
PRRLIS -PACKEGE NO.1

46151.00 59950149.00

TOTAL 1744264483.00
PRRLIS -PACKAGE NO. 1
DETAILED ESTIMATE OF SURGE POOL
PRLIS-(Package No.1)- Construction of Stage-1 pumping station near Anjanagiri Reservoir and

Electro Mechanical works such as Vertical- Single Stage-Francis Turbine Pumps and Synchron

accessories and Earth work Excavation of approach channel from foreshore of Srisailam Res

pumping station at Anjanagiri Reservoir at Narlapur (V), Kollapur (M), Mahabubnagar District.
IRR-TAW-1-5 Excavation for tunnel by heading and benching tunnelling methods including exca
supports ( excluding cost of providing supports ) for roof before benching including c
excavated surface, ventilation, lighting, drainage removing and hauling excavated m
ancillary operations etc., complete with initial lead upto 1 km and all lifts for Surgepo

Surge pool Roof


Length= 246
Width= 23
Lining thickness 0.6
Length of Excavation= 247.20
Width of Excavation= 24.2
Roof Area =
108.3852 Sqm
Surge pool roof +292 to +286

Surge pool roof (extended portion) from +292 to + 286

IRR-TAW-1-3 Excavation for tunnel by tunnelling methods in rock not requiring supports including
surface, removing under-cuts, ventilation,lighting, drainage, removing and hauling th
area and all other ancillary operations etc., complete with initial lead upto 1 km and

Surge pool
Length of Surge pool= 246
Widht of surge pool= 23
Lining thickness 0.6
Length of Excavation= 247.20
Width of Excavation= 24.2
Rectangular portion from +286 to + 221
Rectangular portion

Rectangular portion +286 to +260

Assuming 70% of Qty does not require supports

IRR-TAW-1-4 Excavation for tunnel by tunnelling methods including excavation for supports in all
of providing supports ) including cost of all other materials, machinery, labour, scalin
drainage,removing and hauling the excavated muck outside tunnel upto specified d
with initial lead upto 1 km and all lifts.
PRRLIS -PACKAGE NO. 1
For the excavation in Surgepool of item no.4
Assuming remaining 30% length requires supports

IRR-TAW-1-6 Removing and hauling muck overfallen due to natural causes such as geological fa
blasting if necessary and disposing off the same in specified dump area or as direct
ventilation, drainage, lighting and all other ancillary operations etc., complete with in

Asuming Muck Overfallen is 10% of qty in item no.1 to 5


(40363+327335+140286)*X10%="

IRR-TAW-3-4 Providing, fabricating and fixing in position temperary structural steel supports as pe
including cost of all materials, machinery, labour,cutting, bending, welding, grinding,
operations etc.,complete with initial lead upto 1 km and all lifts.

The qty will be based on type of rock and dessign of supports

Provide

IRR-TAW-3-3 Providing, fabricating and fixing in position permanent structural steel supports as p
cutting, bending, welding, grinding, lighting,ventilation, drainage and all other ancilla
all lifts.

The qty will be based on type of rock and dessign of supports

Provide

IRR-TAW-6-1 Drilling 32 mm diameter grout holes in concrete / rock by percussion drilling u


depth for consolidation / contact grouting including cost of all materials, machinery,
other ancillary operations etc., complete.

Surge pool
Length of Surge pool= 246
Widht of surge pool= 23
Outer radius 3
Length of Excavation= 252.00
Width of Excavation= 29
Area of grouting= 252x29-246x23
No of Holes @ 10m c/c =
Length of each hole required be half the depth
Total length
Surge pool
Length of Surge pool= 124
Widht of surge pool= 23
Outer radius 3
Length of Excavation= 130.00
PRRLIS -PACKAGE NO. 1
Width of Excavation= 29
Area of grouting= 130x29-124x23
No of Holes @ 10m c/c =
Length of each hole required be half the depth
Total length
Total length
IRR-TAW-6-2 Grouting cement slurry in grout holes under specified pressure for consolidation / co
labour, redrilling wherever necessary,ventilation,lighting, drainage and other ancillar

Surge pool
Length of grouting =

Grout required per m length be


Total Qty in Kg
Total Qty in MT

IRR-TAW-3-1 Providing and fixing 25 mm diameter steel rock bolts with mechanical / wedge type
cm long 20 mm thick steel tapered wedge, 10 mm thick plate washers and nuts, tigh
machinery, labour, ventilation, lighting, drainage and all other ancillary operations et

Surge pool
Length of Surge pool= 246
Widht of surge pool= 23
Outer radius 0.6
Length of Excavation= 247.20
Width of Excavation= 24.2
Perimeter of roof =
Depth of Surge pool =
Area of Rock Bolting= =
No of Holes @ 3m c/c =
Length of rock bolt = 5
Total Length =
Surge pool
Length of Surge pool= 124
Widht of surge pool= 23
Outer radius 0.6
Length of Excavation= 125.20
Width of Excavation= 24.2
Perimeter of roof =
Depth of Surge pool =
Area of Rock Bolting= =
No of Holes @ 3m c/c =
Length of rock bolt = 5
Total Length =
Roof
Total Length
IRR-TAW-2-2 Providing 25 mm thick guniting to sides and arch of tunnel in cement mortar
1 : 3 proportion by weight including cost of all materials, machinery, labour, ventilatio
complete with lead upto 1 km and all lifts.
1 : 3 proportion by weight including cost of all materials, machinery, labour, ventilatio
complete with lead upto 1 km and all lifts.
PRRLIS -PACKAGE NO. 1

Surge pool
Length of Surge pool=
Widht of surge pool=
Outer radius 0.6
Length of Excavation= 247.20
Width of Excavation= 24.2
Perimeter of roof =
Depth of Surge pool =
Area = =
Let 50% of Area requires guniting
Surge pool
Length of Surge pool=
Widht of surge pool=
Outer radius 0.6
Length of Excavation= 125.20
Width of Excavation= 24.2
Perimeter of roof =
Depth of Surge pool =
Area = =
Let 50% of Area requires guniting

Total Guiniting

IRR-TAW-2-3 (new4
Shortcreting in two layers (each layer+38 mm thickness) for slabs duly fixing c
layers including cost and conveyance of all materials, labour charges, all heads, lifts
with shortcrete machine etc. complete as per specification and as directed by Engin

Surge pool
Length of Surge pool= 246
Widht of surge pool= 23
Outer radius 0.6
Length of Excavation= 247.20
Width of Excavation= 24.2
Perimeter of roof =
Depth of Surge pool =
Area = =
Let 50% of Area requires shotcreting
Surge pool
Length of Surge pool= 124
Widht of surge pool= 23
Outer radius 0.6
Length of Excavation= 125.20
Width of Excavation= 24.2
Perimeter of roof =
Depth of Surge pool =
Area = =
Let 50% of Area requires shotcreting
PRRLIS -PACKAGE NO. 1
Total Shotcrete quantity =
IRR-TAW-5-3 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not l
mm and down size approved clean, hard,graded aggregates crushed from tunnel m
machinery, labour, formwork, batching, mixing, conveying upto placing point in agita
curing, ventilation, lighting,drainage and all other ancillary operations etc., complete
cum for use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Rat

Surge pool
Length= 370
Widht= 23
Lining thickness 0.6
Length of Excavation= 371.20
Width of Excavation= 24.2
Foundation for bottom

IRR-TAW-5-4 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength no
mm and down size approved clean, hard,graded aggregates crushed from tunnel m
materials, machinery, labour, formwork, batching, mixing, conveying upto placing po
finishing, curing, ventilation, lighting,drainage and all other ancillary operations etc.,
( Cement content 330 kg / cum for use of super plasticiser(0.4% by wt. of cement),C
cum)

Surge pool
Length of Surge pool= 246
Widht of surge pool= 23
Outer radius 0.6
Length of Excavation= 247.20
Width of Excavation= 24.2
Perimeter of roof =
Depth of Surge pool =
Area of Lining= =

Qty of Lining

Surge pool
Length of Surge pool= 124
Widht of surge pool= 23
Outer radius 0.6
Length of Excavation= 125.20
Width of Excavation= 24.2
Perimeter of roof =
Depth of Surge pool =
Area of Lining= =

Qty of Lining
PRRLIS -PACKAGE NO. 1
Total lining

IRR-TAW-5-1 Providing, fabricating and placing in position reinforcement steel for tunnel RCC wo
hooking, lapping / welding joints wherever required, tying with 1.25 mm dia.soft ann
labour,machinery, ventilation, lighting, drainage etc.,complete with initial lead upto 1

Lining Qty =36792+6288


Qty of Reinforcement @80Kg/Cum

Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not l
mm down size approved, clean, hard, graded aggregates for columns and beams in
scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating,finishi
lifts.CA : 0.80cum, Blending Ratio of CA--65:35, FA : 0.45 cum))

Surge pool
Depth of Surge pool =
Piers for DT Gates and Trash rack
Breast wall

IRR-DAW-2-1A Providing, fabricating and placing in position reinforcement steel for RCC,below 36
with 1.25 mm diameter soft annealed steel wire, including cost of all materials, mac
all lifts.overlaps and wastage as per NHAI-data

Qty of Concrete =
QtyReinforcement @90Kg/cum
(14428)x 90 =
PRRLIS -PACKAGE NO. 1
ESTIMATE OF SURGE POOL
near Anjanagiri Reservoir and Design, supply, erection testing and commissioning of

Turbine Pumps and Synchronous motor sets for 8 No.s of 145 MW each including all

m foreshore of Srisailam Reservoir including intake structure and tunnel at Stage -1

M), Mahabubnagar District.


nnelling methods including excavation for supports in all types of soil / rock strata requiring
roof before benching including cost of all other materials, machinery, labour,scaling
moving and hauling excavated muck outside tunnel upto specified dump area and all other
pto 1 km and all lifts for Surgepool Roof.

(306m +2 x 25m )

###
=(246+ 2x0.6)
=(23+ 2x0.6)

247.20 x 108.3852 = 26792.82

125.20 x 108.3852 = 13569.83


40363.00
not requiring supports including cost of all materials,machinery, labour, scaling excavated
ainage, removing and hauling the excavated muck outside tunnel upto specified dump
e with initial lead upto 1 km and all lifts.

=(246+ 2x0.6)
=(23+ 2x0.6)

247.20 x 24.2 x 65 = 388845.6

125.20 x 24.2 x 26 = 78775.84


467621.44

0.7 x 467621.44 = 327335

ng excavation for supports in all types of soil / rock strata requiring supports ( excluding cost
terials, machinery, labour, scaling excavated surface, ventilation, lighting,
outside tunnel upto specified dump area and all other ancillary operations etc., complete
PRRLIS -PACKAGE NO. 1
###

0.3 x 467621.44 = 140286.432


140286

al causes such as geological faults etc., out of tunnel including breaking large fragments by
specified dump area or as directed including cost of all materials, machinery,labour,
operations etc., complete with initial lead upto 1 km and all lifts

50798

ry structural steel supports as per details and dismantling the same before concreting
ting, bending, welding, grinding, ventilation, lighting, drainage and all other ancillary
and all lifts.

100

nt structural steel supports as per details including cost of all materials, machinery, labour,
on, drainage and all other ancillary operations etc., complete with initial lead upto 1 km and

200

/ rock by percussion drilling using jack hammer or stooper drills as directed to specified
cost of all materials, machinery, labour, cleaning holes, ventilation, lighting, drainage and all

=(246+ 2x3)
=(23+ 2x3)
= 1650
1650 / (10x10) = 17 Nos
65 / 2= 32.5
= 553 Rmt

=(124+ 2x3)
PRRLIS -PACKAGE NO. 1
=(23+ 2x3)
= 918
918 / (10x10) = 9 Nos
32 / 2= 16
= 144 Rmt
= 697 m
d pressure for consolidation / contact grouting including cost of all materials, machinery,
ting, drainage and other ancillary operations etc., complete with lead upto 1 km and all lifts.

697
kg per rmt
75
52275
= 52.275 MT

s with mechanical / wedge type anchorage including drilling 35 mm dia holes, providing 15
hick plate washers and nuts, tightening bolt by torque wrench, cost of all materials,
d all other ancillary operations etc., complete with lead upto 1 km and all lifts.

=(246+ 2x0.6)
=(23+ 2x0.6)
35.72697333
=292-221 = 71
2x(247.2+24.2) x71+246x35.7269733333333 = 47327.63544
47327.63544 / (3 x3) = 5259 Nos
m
26295 Rmt

=(124+ 2x0.6)
=(23+ 2x0.6)
35.72697333
=292-260 = 32
2x(125.2+24.2) x32+124x35.7269733333333 = 13991.7446933
13991.74469 / (3 x3) = 1555 Nos
m
7775 Rmt
7343.677778
41414
h of tunnel in cement mortar
ials, machinery, labour, ventilation, lighting, drainage and all other ancillary operations etc.,
PRRLIS -PACKAGE NO. 1

246
23

=(246+ 2x0.6)
=(23+ 2x0.6)
35.72697333
=292-221 = 71 ###
2x(247.2+24.2) x71+246x35.7269733333333 = 47327.63544
23663.81772

124
23

=(124+ 2x0.6)
=(23+ 2x0.6)
35.72697333
=292-260 = 32 ###
2x(125.2+24.2) x32+124x35.7269733333333 = 13991.7446933
6995.87234667

30660

ickness) for slabs duly fixing chain weld wire mesh 100 x 100x5 mm in between the two
s, labour charges, all heads, lifts, centering, scaffolding, machine mixing, laying concrete
cation and as directed by Engineer-in-Charge

=(246+ 2x0.6)
=(23+ 2x0.6)
35.72697333
=292-221 = 71
2x(247.2+24.2) x71+246x35.7269733333333 = 47327.63544
23663.81772

=(124+ 2x0.6)
=(23+ 2x0.6)
35.72697333
=292-260 = 32
2x(125.2+24.2) x32+124x35.7269733333333 = 13991.7446933
6995.87234667
PRRLIS -PACKAGE NO. 1
30660
cube compressive strength not less than 20 N / sqmm ) grade cement concrete using 40
gregates crushed from tunnel muck for kerb and bed lining including cost of all materials,
eying upto placing point in agitator cars, placing in position, levelling, vibrating, finishing,
cillary operations etc., complete with lead upto 1 km and all lifts.( Cement content 330 kg /
ent),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

(361m +2 x 25m )

=(370+ 2x0.6)
=(23+ 2x0.6)
371.20 24.2 0.7 = 6288

s cube compressive strength not less than 20 N / sqmm ) grade cement concrete using 40
gregates crushed from tunnel muck for sides and arch lining including cost of all
ixing, conveying upto placing point in agitator cars, placing in position, levelling, vibrating,
l other ancillary operations etc., complete with lead upto 1 km and all lifts.
sticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40

=(246+ 2x0.6)
=(23+ 2x0.6)
35.72697333
=292-221 = 71 ###
2x(247.2+24.2) x71+296x35.7269733333333 = 47327.63544

47327.63544
47327.63544 x 0.6 = 28396.581264

=(124+ 2x0.6)
=(23+ 2x0.6)
35.72697333
=292-260 = 32 ###
2x(125.2+24.2) x32+174x35.7269733333333 = 13991.7446933

13991.7446933
13991.74469 x 0.6 = 8395.046816
PRRLIS -PACKAGE NO. 1
36792

cement steel for tunnel RCC works including cleaning, straightening, cutting, bending,
tying with 1.25 mm dia.soft annealed steel wire, including cost of all materials,
complete with initial lead upto 1 km and all lifts.

= 43080 Cum
= 3446.4 MT

cube compressive strength not less than 20 N / sq mm ) grade cement concrete using 20
gates for columns and beams including cost of all materials, labour, machinery,formwork,
osition, levelling, vibrating,finishing, curing etc.,complete with initial lead upto 50 m and all
: 0.45 cum))

=282-221 = 61
22 5 2 61 = 13420.00
10 6 0.3 56 1008.00
= 14428.00

cement steel for RCC,below 36 dia rods overlaps and wastages wherever required, tying
uding cost of all materials, machinery, labour etc., complete with initial lead upto 1 km and

14428.00 (Item no.17

1298520 Kg Say 1299.00 MT


PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

NAME OF WORK: PRLIS-STAGE1 -CONSTRUCTION OF DRAFT TUBE


ABSTRACT
ITEM
S.NO DESCRIPTION OF ITEM QUANTITY
CODE
1 IRR- Excavation for tunnel by tunnelling methods in rock not requiring 65025
TAW-1-3 supports including cost of all materials,machinery, labour, scaling
excavated surface, removing under-cuts, ventilation,lighting, drainage,
removing and hauling the excavated muck outside tunnel upto specified
dump area and all other ancillary operations etc., complete with initial lead
upto 1 km and all lifts.

2 IRR- Providing, fabricating and placing in position reinforcement steel for 3024
TAW-5-1 tunnel RCC works including cleaning, straightening, cutting, bending,
hooking, lapping / welding joints wherever required, tying with 1.25 mm
dia.soft annealed steel wire, including cost of all materials,
labour,machinery, ventilation, lighting, drainage etc.,complete with initial lead
upto 1 km and all lifts.

3 IRR- Providing and fixing 25 mm dia 3 m long cold twisted 12600


DAW-1- deformed steel dowel bars with one end driven into 45 to 50
13 mm diameter 1.50 m deep hole drilled in bed rock and other end
provided with L-bend for embedding in concrete / masonry of over
flow / non-over flow blocks and other appertenant works including
cost of drilling and cleaning hole, filling hole with cement mortar
1 : 1 proportion, driving anchor rod, cost of all materials,
machinery, labour etc., complete with initial lead upto 1 km and all
lifts.

4 IRR- Providing and laying insitu vibrated M-20 ( 28 days cube compressive 37800
TAW-5-4 strength not less than 20 N / sqmm ) grade cement concrete using 40 mm
and down size approved clean, hard,graded aggregates crushed from
tunnel muck for sides and arch lining including cost of all materials,
machinery, labour, formwork, batching, mixing, conveying upto placing point
in agitator cars, placing in position, levelling, vibrating, finishing, curing,
ventilation, lighting,drainage and all other ancillary operations etc., complete
with lead upto 1 km and all lifts.( Cement content 330 kg / cum for use of
super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of
CA--50:30:20, FA : 0.40 cum)

TOTAL

355787507.xlsx/A-DTT 91/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

N OF DRAFT TUBE TUNNEL

UNIT RATE AMOUNT

Cum 1798.84 116969571.00

MT 58503.88 176915733.00

Nos 868.38 10941588.00

Cum 6788.92 256621176.00

###

355787507.xlsx/A-DTT 92/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

NAME OF WORK: PRLIS-STAGE 1 -CONSTRUCTION OF DRAFT TUBE T


DETAILED ESTIMATE

1 IRR-TAW-1- Excavation for tunnel by tunnelling methods in rock not requiring supports including cost
3 materials,machinery, labour, scaling excavated surface, removing under-cuts, ventilation,lighting
removing and hauling the excavated muck outside tunnel upto specified dump area and all othe
operations etc., complete with initial lead upto 1 km and all lifts.

DRAFT TUBE TUNNELS 9X 100 x 8.5 x 8.5

2 IRR-TAW-5- Providing, fabricating and placing in position reinforcement steel for tunnel RCC works includ
1 straightening, cutting, bending, hooking, lapping / welding joints wherever required, tying with 1.2
annealed steel wire, including cost of all materials, labour,machinery, ventilation, lighting, draina
etc.,complete with initial lead upto 1 km and all lifts.

@ 80Kg per Cum 80 x 37800 = 3024000


Weight = 3024

3 IRR-DAW-1- Providing and fixing 25 mm dia 3 m long cold twisted deformed steel dowel b
13 end driven into 45 to 50 mm diameter 1.50 m deep hole drilled in bed rock and othe
provided with L-bend for embedding in concrete / masonry of over flow / non-over flo
other appertenant works including cost of drilling and cleaning hole, filling hole with
mortar 1 : 1 proportion, driving anchor rod, cost of all materials, machinery, labour e
with initial lead upto 1 km and all lifts.

DRAFT TUBE TUNNELS 9x 100 x 28 / 2

4 IRR-TAW-5- Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
4 grade cement concrete using 40 mm and down size approved clean, hard,graded aggregates cr
tunnel muck for sides and arch lining including cost of all materials, machinery, labour, formwo
mixing, conveying upto placing point in agitator cars, placing in position, levelling, vibrating, finis
ventilation, lighting,drainage and all other ancillary operations etc., complete with lead upto 1 km
( Cement content 330 kg / cum for use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum
Ratio of CA--50:30:20, FA : 0.40 cum)

DRAFT TUBE TUNNELS 9 X2x 100 x 8.5 X 1.5


9 X2x 100 x 5.5 X 1.5

355787507.xlsx/D-DTT 2/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

F DRAFT TUBE TUNNEL

pports including cost of all


uts, ventilation,lighting, drainage,
ump area and all other ancillary

= 65025
65025 Cum

nel RCC works including cleaning,


required, tying with 1.25 mm dia.soft
lation, lighting, drainage

Kg
MT

med steel dowel bars with one


n bed rock and other end
r flow / non-over flow blocks and
ole, filling hole with cement
machinery, labour etc., complete

= 12600
12600 Nos

strength not less than 20 N / sqmm )


,graded aggregates crushed from
hinery, labour, formwork, batching,
velling, vibrating, finishing, curing,
te with lead upto 1 km and all lifts.
cement),CA : 0.90cum, Blending

= 22950
= 14850
37800 Cum

355787507.xlsx/D-DTT 3/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

NAME OF WORK: PRLIS- SATGE1 -SUPPLY ,FABRICATION AND ERECTION OF DRAFT


ABSTRACT
S.NO DESCRIPTION OF ITEM QUANTITY
1 IRR- Design, fabrication, supply, erection, testing and commissioning of 1194
GAW-2- vertical lift gates and stoplog gate elements, consisting of skin plate,
2 horizontal and vertical girders, stiffeners, lifting pins, bronze padded slide
blocks/bearings, guide shoes,rubber seals, clamps etc., with all
accessories including cost of all materials,machinery, labour, seal fixing
etc.,complete as per specifications and approved drawings (without
painting on sand-blasted or mechanical cleaning surfaces which are
added extra as perscedule of rates under items in this chapter and add
as applicable separately)

2 IRR- Fabrication, supply, erection, testing and commissioning of adequate 100


GAW-2- capacity Class- II type moving gantry crane consisting of rail mounted
4 gantry frame, top platform with hand railing, long / cross travel
arrangements, rope drums, gear systems, electric motors, electro-
magnetic brake system, cabin, control panel, wire rope, ladder,
motorised cable reeling drum etc., with all accessories for operating
spillway stop log gate elements and river sluice /canal sluice emergency
gates including cost of all materials, machinery, labour, etc., complete
with all leads and lifts. .

3 IRR- Design, fabrication, supply, erection and commissioning of rail track 560
GAW-2- using 45 kg / m standard rails on spillway bridge for movement of gantry
5 crane for handling and operating spillway stoplog gate elements / river
sluice / canal sluice emergency gate including cost of all
materials,machinery, labour, complete as per specifications (without
painting on sand-blasted or mechanical cleaning surfaces which are
added extra as perscedule of rates under items in this chapter and add
as applicable separately)

4 IRR- Fabrication, supply, erection, testing and commissioning of automatic 2.5


GAW-2- lifting beam with all accessories for handling, lowering and lifting of
3 spillway stop log gate elements including cost of all materials, machinery,
labour, cutting, aligning, welding, finishing, etc., complete as per
specifications and drawings with all leads and lifts. (without painting on
sand-blasted or mechanical cleaning surfaces which are added extra as
perscedule of rates under items in this chapter and add as applicable
separately)

TOTAL

355787507.xlsx/A-DTG 4/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

AND ERECTION OF DRAFT TUBE GATES

UNIT RATE AMOUNT


MT 128611.00 153561534.00

MT 228410.00 22841000.00

Rmt 7305.23 4090929.00

MT 111044.26 277611.00

180771074.00
Say 180771074.00

355787507.xlsx/A-DTG 5/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

NAME OF WORK: PRLIS- SATGE1 -SUPPLY ,FABRICATION AND ERECTION OF DRAFT TUBE
DETAILED ESTIMATE
1 IRR-GAW-2- Design, fabrication, supply, erection, testing and commissioning of vertical lift gates and stoplo
2 elements, consisting of skin plate, horizontal and vertical girders, stiffeners, lifting pins, bronze p
slide blocks/bearings, guide shoes,rubber seals, clamps etc., with all accessories including cos
materials,machinery, labour, seal fixing etc.,complete as per specifications and approved draw
(without painting on sand-blasted or mechanical cleaning surfaces which are added extra as pe
of rates under items in this chapter and add as applicable separately)

Vertical lift gates for Draft


tube 9X 5.15 x 5.15 x 4.0 =
Trash rack gates for Draft
tube 9X 5.15 x 5.15 x 1.0 =

2 IRR-GAW-2- Fabrication, supply, erection, testing and commissioning of adequate capacity Class- II type m
4 gantry crane consisting of rail mounted gantry frame, top platform with hand railing, long / cros
arrangements, rope drums, gear systems, electric motors, electro-magnetic brake system, cabi
panel, wire rope, ladder, motorised cable reeling drum etc., with all accessories for operating sp
stop log gate elements and river sluice /canal sluice emergency gates including cost of all mate
machinery, labour, etc., complete with all leads and lifts.

Capacity of Crane = 100 MT

3 IRR-GAW-2- Design, fabrication, supply, erection and commissioning of rail track using 45 kg / m standard ra
5 spillway bridge for movement of gantry crane for handling and operating spillway stoplog gate
elements / river sluice / canal sluice emergency gate including cost of all materials,machinery, l
complete as per specifications (without painting on sand-blasted or mechanical cleaning surfac
are added extra as perscedule of rates under items in this chapter and add as applicable separ

Length of rail =

4 IRR-GAW-2- Fabrication, supply, erection, testing and commissioning of automatic lifting beam with all acce
5 for handling, lowering and lifting of spillway stop log gate elements including cost of all material
machinery, labour, cutting, aligning, welding, finishing, etc., complete as per specifications and
with all leads and lifts. (without painting on sand-blasted or mechanical cleaning surfaces which
added extra as perscedule of rates under items in this chapter and add as applicable separatel

Lifting Beam 5x 0.5 =

355787507.xlsx/D-DTG 2/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

TION OF DRAFT TUBE GATES

cal lift gates and stoplog gate


ners, lifting pins, bronze padded
ccessories including cost of all
ions and approved drawings
ch are added extra as perscedule

954.81

238.7025
1194 MT

capacity Class- II type moving


h hand railing, long / cross travel
netic brake system, cabin, control
essories for operating spillway
ncluding cost of all materials,

ng 45 kg / m standard rails on
g spillway stoplog gate
all materials,machinery, labour,
chanical cleaning surfaces which
add as applicable separately)

560 Rmt

ifting beam with all accessories


uding cost of all materials,
s per specifications and drawings
cleaning surfaces which are
as applicable separately)

2.5 MT

355787507.xlsx/D-DTG 3/508
PRRLIS - PACKAGE NO.1

ABSTR
PRLIS-(Package No.1)- Construction of Stage-1 pumping station

Electro Mechanical works such as Vertical- Single Stage-Francis

accessories and Earth work Excavation of approach channel fro

pumping station at Anjanagiri Reservoir at Narlapur (V), Kollapur (


S.NO ITEM CODE

1 IRR-TAW-1-5

2 IRR-TAW-1-3

3 IRR-TAW-1-4

4 IRR-TAW-1-6
PRRLIS - PACKAGE NO.1

5 IRR-TAW-3-4

6 IRR-TAW-3-3

7 IRR-TAW-6-1

8 IRR-TAW-6-2

9 IRR-TAW-3-1

10 IRR-TAW-2-2
PRRLIS - PACKAGE NO.1

IRR-TAW-2-3
11
(new4 - 2011-12)

12 IRR-TAW-5-3

13 IRR-TAW-5-4

14 IRR-TAW-5-1
PRRLIS - PACKAGE NO.1

15 IRR-DAW-2-4(B)

16

17

18

19
PRRLIS - PACKAGE NO.1

20

21
PRRLIS - PACKAGE NO.1

22

23

24
PRRLIS - PACKAGE NO.1

ABSTRACT OF PUMP HOUSE


o.1)- Construction of Stage-1 pumping station near Anjanagiri Reservoir and Design, supply, erection te

works such as Vertical- Single Stage-Francis Turbine Pumps and Synchronous motor sets for 8 No.s o

arth work Excavation of approach channel from foreshore of Srisailam Reservoir including intake stru

Anjanagiri Reservoir at Narlapur (V), Kollapur (M), Mahabubnagar District.


DESCRIPTION OF ITEM QUANTITY UNIT
Excavation for tunnel by heading and benching tunnelling methods
including excavation for supports in all types of soil / rock strata requiring
supports ( excluding cost of providing supports ) for roof before benching
including cost of all other materials, machinery, labour,scaling excavated
surface, ventilation, lighting, drainage removing and hauling excavated
muck outside tunnel upto specified dump area and all other ancillary 33105 Cum
operations etc., complete with initial lead upto 1 km and all lifts.

Excavation for tunnel by tunnelling methods in rock not requiring


supports including cost of all materials,machinery, labour, scaling
excavated surface, removing under-cuts, ventilation,lighting, drainage,
removing and hauling the excavated muck outside tunnel upto specified
dump area and all other ancillary operations etc., complete with initial 211943 Cum
lead upto 1 km and all lifts.

Excavation for tunnel by tunnelling methods including excavation for


supports in all types of soil / rock strata requiring supports ( excluding
cost of providing supports ) including cost of all other materials,
machinery, labour, scaling excavated surface, ventilation, lighting,
drainage,removing and hauling the excavated muck outside tunnel upto 90833 Cum
specified dump area and all other ancillary operations etc., complete
with initial lead upto 1 km and all lifts.

Removing and hauling muck overfallen due to natural causes such as


geological faults etc., out of tunnel including breaking large fragments by
blasting if necessary and disposing off the same in specified dump area
or as directed including cost of all materials, machinery,labour,
ventilation, drainage, lighting and all other ancillary operations etc., 33588 Cum
complete with initial lead upto 1 km and all lifts
PRRLIS - PACKAGE NO.1

Providing, fabricating and fixing in position temperary structural steel


supports as per details and dismantling the same before concreting
including cost of all materials, machinery, labour,cutting, bending,
welding, grinding, ventilation, lighting, drainage and all other ancillary 75 MT
operations etc.,complete with initial lead upto 1 km and all lifts.

Providing, fabricating and fixing in position permanent structural steel


supports as per details including cost of all materials, machinery, labour,
cutting, bending, welding, grinding, lighting,ventilation, drainage and all
other ancillary operations etc., complete with initial lead upto 1 km and 150 MT
all lifts.

Drilling 32 mm diameter grout holes in concrete / rock by percussion


drilling using jack hammer or stooper drills as directed to specified depth
for consolidation / contact grouting including cost of all materials,
machinery, labour, cleaning holes, ventilation, lighting, drainage and all 4270 Rmt
other ancillary operations etc., complete.

Grouting cement slurry in grout holes under specified pressure for


consolidation / contact grouting including cost of all materials,
machinery, labour, redrilling wherever necessary,ventilation,lighting,
drainage and other ancillary operations etc., complete with lead upto 1
321 MT
km and all lifts.

Providing and fixing 25 mm diameter steel rock bolts with mechanical /


wedge type anchorage including drilling 35 mm dia holes, providing 15
cm long 20 mm thick steel tapered wedge, 10 mm thick plate washers
and nuts, tightening bolt by torque wrench, cost of all materials,
machinery, labour, ventilation, lighting, drainage and all other ancillary
operations etc., complete with lead upto 1 km and all lifts. 26748 Rmt

Providing 25 mm thick guniting to sides and arch of tunnel in cement


mortar
1 : 3 proportion by weight including cost of all materials, machinery,
labour, ventilation, lighting, drainage and all other ancillary operations 19383 Sqm
etc., complete with lead upto 1 km and all lifts.
PRRLIS - PACKAGE NO.1

Shortcreting in two layers (each layer+38 mm thickness) for slabs duly


fixing chain weld wire mesh 100 x 100x5 mm in between the two layers
including cost and conveyance of all materials, labour charges, all
heads, lifts, centering, scaffolding, machine mixing, laying concrete with
shortcrete machine etc. complete as per specification and as directed by 22071 Sqm
Engineer-in-Charge

Providing and laying insitu vibrated M-20 ( 28 days cube compressive


strength not less than 20 N / sqmm ) grade cement concrete using 40
mm and down size approved clean, hard,graded aggregates crushed
from tunnel muck for kerb and bed lining including cost of all materials,
machinery, labour, formwork, batching, mixing, conveying upto placing
point in agitator cars, placing in position, levelling, vibrating, finishing,
curing, ventilation, lighting,drainage and all other ancillary operations
etc., complete with lead upto 1 km and all lifts.( Cement content 330 kg / 5301 Cum
cum for use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum,
Blending Ratio of CA--50:30:20, FA : 0.40 cum)

Providing and laying insitu vibrated M-20 ( 28 days cube compressive


strength not less than 20 N / sqmm ) grade cement concrete using 40
mm and down size approved clean, hard,graded aggregates crushed
from tunnel muck for sides and arch lining including cost of all materials,
machinery, labour, formwork, batching, mixing, conveying upto placing
point in agitator cars, placing in position, levelling, vibrating, finishing,
curing, ventilation, lighting,drainage and all other ancillary operations
etc., complete with lead upto 1 km and all lifts. 24655 Cum
( Cement content 330 kg / cum for use of super plasticiser(0.4% by wt.
of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40
cum)

Providing, fabricating and placing in position reinforcement steel for


tunnel RCC works including cleaning, straightening, cutting, bending,
hooking, lapping / welding joints wherever required, tying with 1.25 mm
dia.soft annealed steel wire, including cost of all materials,
labour,machinery, ventilation, lighting, drainage etc.,complete with initial 5417.57 MT
lead upto 1 km and all lifts.
PRRLIS - PACKAGE NO.1

Providing and laying insitu vibrated M-25 ( 28 days cube compressive


strength not less than 25 N / sq mm ) grade cement concrete using 20
mm down size approved, clean, hard, graded aggregates including cost
of all materials, machinery, labour, formwork, centering, scaffolding,
cleaning, batching, mixing, placing in position, levelling, vibrating,
finishing, curing etc.,complete for RCC works with initial lead upto 1 km
33568.3 Cum
and all lifts.( Cement content : 380 kg / cum with use of super
plasticiser,CA : 0.90 cum, blending ratio of CA--65:35, FA : 0.40 cum)

Brick Masonry in CM (1:6) with 2nd class Bricks traditional size 23 x


11 x 7 cms 82.00 Cum

Plastering with CM 2 coats, 20 mm thick, base coat in CM (1:6),


16mm thick and top coat in CM (1:4), 4mm thick with Dubara
sponze finishing. 713 Sqm

Painting to new walls with 2 coats of water proof cement paint of


apporved brand and shade over a base coat of approved cement
primer grade I making making 3 coats in all to give an even shade after
thourughly brushing the surface to remove all dirt and remains of loose
powdered materials, including cost and conveyance of all materials to 713 Sqm
work site and all operational, incidental, labour charges etc. complete for
finished item of work as per SS

Providing and fixing of Two shutter Sliding Windows made of


Galvanized Steel as per IS 513, D quality,galvanized as per IS 277
with powder coated with Pure polyester powder up to 50-60 microns
thick with total coated thickness of 0.8 mm for Outer Frame and 0.58mm
thickness for Sliding Shutter Section, the OuterFrame for Two
Tracks with Grill provision size of 90 mm x 50 mm and the Window
Shutter section of 58 mm x 36 mm and the outer Frame with two
integrated guide tracks of 12mm width and 24mm deep for provision to
slide the Shutter / sash frame and facilitates with a water drain
outlet component made of PVC and the shutter frame fitted with 5mm
thick plain float glass of reputed make and fixed with EPDM weathering
seal resistant accessories and handle made of Alumimium 1No. per
each shutter including installation of window system at site using anchor 288 Sqm
fasteners, Silicon sealant applied at the Outer frame corners inclusive of
conveyance of all materials accessories, labour charges, and erection at
site with complete finished item of work for Window with Two Sliding
Shutters and with Grill
PRRLIS - PACKAGE NO.1

Supplying and fixing of Unplasticised Poly Vinyl Chloride (UPVC)


sliding doors three track - two glass shutters sliding and one mesh
shutter sliding- 95 -Series duly manufactured using UPVC reinforced
profiles of (108 mm x 45 mm)/(95.50 mm x 60 mm) x 2.0 mm for outer
frames, (75 mm x 39 mm)/(66 mm x 42 mm) x 2.0 mm for sliding door
shutter frames capable of mounting single glazing system, structurally
reinforced with hot dip galvanized up to 50 microns of minimum
thickness of 1.2 mm prefabricated & welded through fusion welding the
window sash shall be fitted with 5 mm thick clear float glass of reputed
make and mesh shutter shall be made of (48.5 mm x 30 mm))/(50 mm x
26.5 mm) x2.0 mm uPVC profile section and fitted with nylon/polymer
mesh and rollers/pulley duly fixed with TPV Gaskets/ EPDM weathering
seal resistant accessories like clipping locking system made of 135 Sqm
aluminium 1 No., per set of sashes and the system is to be installed at
the site using anchor fasteners, silicon rubber sealant, easy glazing/
deglazing at site etc., including cost and conveyance of all materials,
accessories, labour charges for transportation, erection at site with
templates for casement sizing complete for finished item of work

Providing and fixing false ceiling consisting of


600mmX600mm, Solid PVC insulation panels having wall thickness
of 1mm thick plain PVC rigid foam sheet and EPS as defined in of
desired thickness depending on insulation required shall be insert in a
frame work made using anodized aluminium Tee section of sizes
1X1 (25X25mm, 19 gauge or 1mm thick) in square pattern of grid sizes
of 2X2 (600X600mm). The aluminium framework is supported from the
ceiling with the help of G.I. hook and G.I. wire/6mm.M.S. rods of
required sizes to maintain proper level etc. the aluminium framework is 7800 Sqm
supported on side wall with the use of aluminium 1X1 (25X25mm)
angles, complete as per direction of Engineer-in-Charge & drawing
PRRLIS - PACKAGE NO.1

Reinforced Brick Masonary walls of 11.5cm in CM(1:6) using 2nd


bricks having a crushing strength of not less than 35.00kg/cm2
and using two mild steel bars of 6m dia in every third layer of brick
masory, with free joints of the main block work including cost and
seignorage charges and conveyance of all materials and water from
approved sources to work site and all operational, incidental, labour
charges such as scaffolding mixing mortor constructing masonary
lift charges, curing etc. complete but excluding the cost of steel and its 339.135 Sqm
fabrication charges for finished item of work as per SS 509 .

Design, fabrication, supply, erection, testing of roof truss with all


accessories including cost of all materials,machinery, labour
etc.,complete as per specifications and approved drawings . 860 MT

Heavy duty industrial variety / tact porcelain vitrified tile of size 300 x 300
/ 200 x 100 mmand thickness between 12-15 mm 1st quality
conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to15) of any colour
and finish in all shades and designs, set over base coat of cement
mortar (1:8), 12 mm thick over CC bed already laid or RCC roof
slab, including neat cement slurry of honey like consistency spread
@ 3.3.kgs per sqm & jointed neatly with white cement paste to full
depth mixed with pigment of matching shade, including cost of all 7088.00 Sqm
materials like cement, sand water and tiles etc., complete, including
seigniorage charges, etc., complete for finished item of work, .
PRRLIS - PACKAGE NO.1

MP HOUSE
Reservoir and Design, supply, erection testing and commissioning of

and Synchronous motor sets for 8 No.s of 145 MW each including all

Srisailam Reservoir including intake structure and tunnel at Stage -1

ar District.
RATE AMOUNT

1928.00 63826440.00

1827.00 387219861.00

1879.00 170675207.00

405.00 13603140.00
PRRLIS - PACKAGE NO.1

22068.00 1655100.00

85617.00 12842550.00

399.00 1703730.00

11171.00 3585891.00

1034.00 27657432.00

604.00 11707332.00
PRRLIS - PACKAGE NO.1

1454.00 32091234.00

6617.00 35076717.00

6822.00 168196410.00

58504.00 316949311.00
PRRLIS - PACKAGE NO.1

7331.00 246088981.51

4479.00 367278.00

279.00 198927.00

145.60 199909

6681.00 1924128.00
PRRLIS - PACKAGE NO.1

8028.00 1083780.00

1534.00 11965200.00
PRRLIS - PACKAGE NO.1

4982.00 1689571

72055.00 61967300.00

1960.00 13892480.00

TOTAL 1586167909
PRRLIS -PACKAGE 1

DETAILED ESTIMATE OF PUMP HOUSE


PRLIS-(Package No.1)- Construction of Stage-1 pumping station near Anjanagiri Reservoir a
erection testing and commissioning of Electro Mechanical works such as Vertical- Single S
Pumps and Synchronous motor sets for 8 No.s of 145 MW each including all accessories and Ea
of approach channel from foreshore of Srisailam Reservoir including intake structure and tunnel
station at Anjanagiri Reservoir at Narlapur (V), Kollapur (M), Mahabubnagar District.

1 IRR-TAW-1-5 Excavation for tunnel by heading and benching tunnelling methods including excavation fo
soil / rock strata requiring supports ( excluding cost of providing supports ) for roof before be
all other materials, machinery, labour,scaling excavated surface, ventilation, lighting, drainag
excavated muck outside tunnel upto specified dump area and all other ancillary operations e
lead upto 1 km and all lifts.

PUMP HOUSE
Length= 336
Width= 25
Lining thickness 0.6 Roof= 264-259 = 5
Length of Excavation= 337.20 =(336+ 2x0.6)
Width of Excavation= 26.2 =(25+ 2x0.6)
Roof Area = 98.18 Sqm
PH Roof 337.20 x 98.175

2 IRR-TAW-1-3 Excavation for tunnel by tunnelling methods in rock not requiring supports including cost of a
labour, scaling excavated surface, removing under-cuts, ventilation,lighting, drainage, remov
excavated muck outside tunnel upto specified dump area and all other ancillary operations e
lead upto 1 km and all lifts.

PUMP HOUSE
Length l= 246
Width = 25
Lining thickness 0.6
Length of Excavation= 247.20 =(246+ 2x0.6)
Width of Excavation= 26.2 =(25+ 2x0.6)
Rectangular portion from +259 to 217.22
Rectangular portion 247.20 x 26.2 x 41.78
Service Bay and Control room
Length l= 90 (90=30+60)
Width = 25
Lining thickness 0.6
Length of Excavation= 91.20 =(90+ 2x0.6)
Width of Excavation= 26.2 =(25+ 2x0.6)
Rectangular portion from +259 to 241
Rectangular portion 91.20 x 26.2 x 18
Deduct:
Rock ledge between pumps
8X 15 X 8X 11.28

Assuming 70% of Qty does not require supports


PRRLIS -PACKAGE 1

0.7 x 302775.1392
3 IRR-TAW-1-4 Excavation for tunnel by tunnelling methods including excavation for supports in all types of
requiring supports ( excluding cost of providing supports ) including cost of all other material
scaling excavated surface, ventilation, lighting, drainage,removing and hauling the excavate
upto specified dump area and all other ancillary operations etc., complete with initial lead up

For the excavation in PH of item no.4


Assuming remaining 30% length requires supports
0.3 x 302775.1392

4 IRR-TAW-1-6 Removing and hauling muck overfallen due to natural causes such as geological faults etc.,
breaking large fragments by blasting if necessary and disposing off the same in specified du
including cost of all materials, machinery,labour, ventilation, drainage, lighting and all other a
complete with initial lead upto 1 km and all lifts

Asuming Muck Overfallen is 10% of qty in item no.1 to 5


(0+0+33105+211943+90833)x10%=

5 IRR-TAW-3-4 Providing, fabricating and fixing in position temperary structural steel supports as per details
same before concreting including cost of all materials, machinery, labour,cutting, bending, w
ventilation, lighting, drainage and all other ancillary operations etc.,complete with initial lead

The qty will be based on type of rock and dessign of supports


Provide

6 IRR-TAW-3-3 Providing, fabricating and fixing in position permanent structural steel supports as per details
materials, machinery, labour, cutting, bending, welding, grinding, lighting,ventilation, drainag
operations etc., complete with initial lead upto 1 km and all lifts.

The qty will be based on type of rock and dessign of supports


Provide

7 IRR-TAW-6-1 Drilling 32 mm diameter grout holes in concrete / rock by percussion drilling using jac
drills as directed to specified depth for consolidation / contact grouting including cost of all m
labour, cleaning holes, ventilation, lighting, drainage and all other ancillary operations etc., c

PUMP HOUSE
Length= 246
Width = 25
Outer radius 3
Length of Excavation= 252.00 =(246+ 2x3)
Width of Excavation= 31 =(25+ 2x3)
Area of grouting= 252x31-246x25 = 1662
No of Holes @ 3m c/c = 1662 / (3 x3) = 185
Length of each hole required be hlf the depth 41.78 / 2
Total length = 3864.65
service bay:
PRRLIS -PACKAGE 1

Length= 90
Width = 25
Outer radius 3
Length of Excavation= 96.00 =(90+ 2x3)
Width of Excavation= 31 =(25+ 2x3)
Area of grouting= 96x31-90x25 = 726
No of Holes @ 3m c/c = 726 / (3 x3) = 81
Length of each hole required be hlf the depth 10 / 2
Total length = 405
Total 4270
10 IRR-TAW-6-2 Grouting cement slurry in grout holes under specified pressure for consolidation / contact gr
all materials, machinery, labour, redrilling wherever necessary,ventilation,lighting, drainage a
operations etc., complete with lead upto 1 km and all lifts.

PUMP HOUSE
Length of grouting = 4270
Grout required per m length be 75 kg per rmt
Total Qty in Kg 320250
Total Qty in MT = 320.25

11 IRR-TAW-3-1 Providing and fixing 25 mm diameter steel rock bolts with mechanical / wedge type anchorag
mm dia holes, providing 15 cm long 20 mm thick steel tapered wedge, 10 mm thick plate wa
tightening bolt by torque wrench, cost of all materials, machinery, labour, ventilation, lighting,
ancillary operations etc., complete with lead upto 1 km and all lifts.

PUMP HOUSE
Length of PH= 246
Widht of PH= 25
Outer radius 0.6
Length of Excavation= 247.20 =(246+ 2x0.6)
Width of Excavation= 26.2 =(25+ 2x0.6)
Perimeter of roof = 38.8336667
Depth of Pump House = =259-217.22 = 41.78
Area of Rock Bolting= = 2x(247.2+26.2) x41.78+246x38.833666666666
No of Holes @ 3m c/c = 32398.386 / (3 x3) = 3600
Length of rock bolt = 6m
Total Length = 21600 Rmt
service bay:
Length of PH= 90
Widht of PH= 25
Outer radius 0.6
Length of Excavation= 91.20 =(90+ 2x0.6)
Width of Excavation= 26.2 =(25+ 2x0.6)
Perimeter of roof = 38.8336667
Depth of Pump House = =259-241 = 18
Area of Rock Bolting= = 2x(91.2+26.2) x18+90x38.8336666666667
No of Holes @ 3m c/c = 7721.43 / (3 x3) = 858
Length of rock bolt = 6m
Total Length = 5148 Rmt

Total 26748 Rmt


PRRLIS -PACKAGE 1

12 IRR-TAW-2-2 Providing 25 mm thick guniting to sides and arch of tunnel in cement mortar
1 : 3 proportion by weight including cost of all materials, machinery, labour, ventilation, lightin
other ancillary operations etc., complete with lead upto 1 km and all lifts.

PUMP HOUSE
Length of Pump house= 336
Widht of Pump house= 25
Outer radius 0.6
Length of Excavation= 337.20 =(336+ 2x0.6)
Width of Excavation= 26.2 =(25+ 2x0.6)
Perimeter of roof = 41
Depth of PH = =259-217.22 = 41.78
Area = = 2x(337.2+26.2) x41.78+336x41
Let 50% of Area requires guniting

13 IRR-TAW-2-3 (newShortcreting in two layers (each layer+38 mm thickness) for slabs duly fixing chain weld
100 x 100x5 mm in between the two layers including cost and conveyance of all materials, la
charges, all heads, lifts, centering, scaffolding, machine mixing, laying concrete with shortcre
etc. complete as per specification and as directed by Engineer-in-Charge

PUMP HOUSE
Length = 336
Widht = 25
Lining thickness 0.6
Length of Excavation= 337.20 =(336+ 2x0.6)
Width of Excavation= 26.2 =(25+ 2x0.6)
Perimeter of roof = 41
Depth of PH = =259-217.22 = 41.78
Area = = 2x(337.2+26.2) x41.78+336x41
Let 50% of Area requires shotcreting

14 IRR-TAW-5-3 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than
cement concrete using 40 mm and down size approved clean, hard,graded aggregates crus
for kerb and bed lining including cost of all materials, machinery, labour, formwork, batching,
placing point in agitator cars, placing in position, levelling, vibrating, finishing, curing, ventilat
and all other ancillary operations etc., complete with lead upto 1 km and all lifts.( Cement co
use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:2

PUMP HOUSE
Length= 336
Width= 25
Lining thickness 0.6
Length of Excavation= 337.20 =(336+ 2x0.6)
Width of Excavation= 26.2 =(25+ 2x0.6)
Foundation for bottom 337.20 26.2 0.6
PRRLIS -PACKAGE 1

15 IRR-TAW-5-4 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less tha
cement concrete using 40 mm and down size approved clean, hard,graded aggregates crus
for sides and arch lining including cost of all materials, machinery, labour, formwork, batch
upto placing point in agitator cars, placing in position, levelling, vibrating, finishing, curing, ve
lighting,drainage and all other ancillary operations etc., complete with lead upto 1 km and all
( Cement content 330 kg / cum for use of super plasticiser(0.4% by wt. of cement),CA : 0.90
CA--50:30:20, FA : 0.40 cum)

PUMP HOUSE
Length 246
Width= 25
Outer radius 0.6
Length of Excavation= 247.20 =(246+ 2x0.6)
Width of Excavation= 26.2 =(25+ 2x0.6)
Perimeter of roof = 42.7
Depth of PH = =259-217.22 -0.6 = 41.2
Area of Lining= = 2x(247.2+26.2) x41.18+246x42.7
Service bay and Control room
Length = 90
Width= 25
Outer radius 0.6
Length of Excavation= 91.20 =(90+ 2x0.6)
Width of Excavation= 26.2 =(25+ 2x0.6)
Perimeter of roof = 42.7
Depth = =259-241 = 18
Area of Lining= = 2x(91.2+26.2) x18+90x42.7

Qty of Lining 41090.824 x 0.6

16 IRR-TAW-5-1 Providing, fabricating and placing in position reinforcement steel for tunnel RCC works includ
straightening, cutting, bending, hooking, lapping / welding joints wherever required, tying wit
annealed steel wire, including cost of all materials, labour,machinery, ventilation, lighting, dra
initial lead upto 1 km and all lifts.

Lining Qty =24654+5301 = 29955 Cum


Qty of Reinforcement @80Kg/Cum = 2396.4 MT

Bottom Raft Foundation at 90kg/Cum 3021.12 MT

TOTAL 5418.00

Providing and laying insitu vibrated M-25 ( 28 days cube compressive strength not less tha
17 IRR-DAW-2-4(B) cement concrete using 20 mm down size approved, clean, hard, graded aggregates includin
machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing, placing in po
vibrating, finishing, curing etc.,complete for RCC works with initial lead upto 1 km and all lift
kg / cum with use of super plasticiser,CA : 0.90 cum, blending ratio of CA--65:35, FA : 0.40

For Foundation
PRRLIS -PACKAGE 1

From Level +217.22 to +231.690


1x 246 x 25 x 14.47
Deduct openings
Draft Tube 9x 9X X 52 /
pump dia 9X x(14^2-12^2)/4 x 7.5
Gallery 246 x X 3.5 2 /
246 x 3.5 X 3.5 /
Delivery pipe vents 1x 246 x 7.5 x 9.7
Dewatering Pits 2x 15 x 25 x 23
Gaps 9x 13 x 8x 9.5
Rock ledge between pumps
8X 15 X 8X 11.28

Slabs
@ Level +239.69, 2x 246 x 25 x 0.2
+236.345
Deduct Pump area 9x x(14^2-12^2)/4 x 0.2
Columns 34 x 1.2 x 1.2 x 26.71
Beams 33 x6 8x 0.45 x 0.6
40 x3 8x 0.45 x 0.6
Around Pump 10 x x(14^2-12^2)/4 x 4.5
For Annexes
Columns 7x 1.2 x 0.9 x 30
Beams 36 x 50 x 0.6 x 0.6
8x 22.4 x 0.6 x 0.9
Slabs@ service control 3x 30 x 26 x 0.2
rooms
Slab for Steps
6x 1x 20.4 x 1.2 x 0.3

18 BLD-CSTN-5-4 Brick Masonry in CM (1:6) with 2nd class Bricks traditional size 23 x 11

For Annexes 1 21.6 0.23 16.50

19 BLD-CSTN-6-10 Plastering with CM 2 coats, 20 mm thick, base coat in CM (1:6), 16mm thick and top
4mm thick with Dubara sponze finishing.

For Annexes 2 21.6 16.5

20 BLD-CSTN-12-5 Painting to new walls with 2 coats of water proof cement paint of apporved brand and
of approved cement primer grade I making making 3 coats in all to give an even shade after
surface to remove all dirt and remains of loose powdered materials, including cost and conv
work site and all operational, incidental, labour charges etc. complete for finished item of wo

For Annexes 2 21.6 16.5


PRRLIS -PACKAGE 1

21 Providing and fixing of Two shutter Sliding Windows made of Galvanized Steel as per IS
quality,galvanized as per IS 277 with powder coated with Pure polyester powder up to 50-60
coated thickness of 0.8 mm for Outer Frame and 0.58mm thickness for Sliding Shutter S
for Two Tracks with Grill provision size of 90 mm x 50 mm and the Window Shutter section o
the outer Frame with two integrated guide tracks of 12mm width and 24mm deep for provisio
sash frame and facilitates with a water drain outlet component made of PVC and the shu
5mm thick plain float glass of reputed make and fixed with EPDM weathering seal resistant a
TBSC-M.II-03 made of Alumimium 1No. per each shutter including installation of window system at site usi
Silicon sealant applied at the Outer frame corners inclusive of conveyance of all materials ac
charges, and erection at site with complete finished item of work for Window with Two Slidin

For Annexes 18 4 4

22 Supplying and fixing of Unplasticised Poly Vinyl Chloride (UPVC) sliding doors three
shutters sliding and one mesh shutter sliding- 95 -Series duly manufactured using UPVC r
(108 mm x 45 mm)/(95.50 mm x 60 mm) x 2.0 mm for outer frames, (75 mm x 39 mm)/(66 m
for sliding door shutter frames capable of mounting single glazing system, structurally reinfo
galvanized up to 50 microns of minimum thickness of 1.2 mm prefabricated & welded throu
window sash shall be fitted with 5 mm thick clear float glass of reputed make and mesh shut
(48.5 mm x 30 mm))/(50 mm x 26.5 mm) x2.0 mm uPVC profile section and fitted with nylon
rollers/pulley duly fixed with TPV Gaskets/ EPDM weathering seal resistant accessories like
system made of aluminium 1 No., per set of sashes and the system is to be installed at th
fasteners, silicon rubber sealant, easy glazing/ deglazing at site etc., including cost and con
materials, accessories, labour charges for transportation, erection at site with templates for c
complete for finished item of work

For Annexes 15 6 1.5 135


135 Sqm

23 TBSC-K.I-29 Providing and fixing false ceiling consisting of 600mmX600mm, Solid PVC insu
wall thickness of 1mm thick plain PVC rigid foam sheet and EPS as defined in of desired thic
insulation required shall be insert in a frame work made using anodized aluminium Tee sec
(25X25mm, 19 gauge or 1mm thick) in square pattern of grid sizes of 2X2 (600X600mm). T
framework is supported from the ceiling with the help of G.I. hook and G.I. wire/6mm.M.S
to maintain proper level etc. the aluminium framework is supported on side wall with the use
(25X25mm) angles, complete as per direction of Engineer-in-Charge & drawing

For floors
Slabs 6 50 26

24 BLD-CSTN-5-12 Reinforced Brick Masonary walls of 11.5cm in CM(1:6) using 2nd bricks having a crush
less than 35.00kg/cm2 and using two mild steel bars of 6m dia in every third layer of brick
of the main block work including cost and seignorage charges and conveyance of all
from approved sources to work site and all operational, incidental, labour charges such
mortor constructing masonary lift charges, curing etc. complete but excluding the cost of s
charges for finished item of work as per SS 509 .
PRRLIS -PACKAGE 1
Reinforced Brick Masonary walls of 11.5cm in CM(1:6) using 2nd bricks having a crush
less than 35.00kg/cm2 and using two mild steel bars of 6m dia in every third layer of brick
of the main block work including cost and seignorage charges and conveyance of all
from approved sources to work site and all operational, incidental, labour charges such
mortor constructing masonary lift charges, curing etc. complete but excluding the cost of s
charges for finished item of work as per SS 509 .

For toilet blocks in 5x3x2 6 0.115 3.3


Annexes 5x3x2 5 0.115 3.3
For Partition walls 20x3 15.5 0.115 2

25 Design, fabrication, supply, erection, testing of roof truss with all accessories including cost
materials,machinery, labour etc.,complete as per specifications and approved drawings .

Length - 120m, span of truss - 25m


Quantity = 110 tons.
Length - 321m, span of truss - 25m
Quantity =550 tons
Gantry girder designed for 75 ton crane capacity.
Length of gantry girder considered on each side is 140m.
Span of gantry girder - 25m.
Quantity of gantry girder = 200 tons
Total Quantity of structural steel

26 Heavy duty industrial variety / tact porcelain vitrified tile of size 300 x 300 / 200 x 100 mmand
12-15 mm 1st quality conforming to IS:13711, IS:13712, IS:13630 (Parts 1 to15) of an
shades and designs, set over base coat of cement mortar (1:8), 12 mm thick over CC
RCC roof slab, including neat cement slurry of honey like consistency spread @ 3.3.kgs
neatly with white cement paste to full depth mixed with pigment of matching shade, i
materials like cement, sand water and tiles etc., complete, including seigniorage charges,
finished item of work, .

For Annexes(50% area control pa 0.5 21.6 26


For Pump House 1 321 26
Deduct Pump area 10 (14^2)/4
PRRLIS -PACKAGE 1

STIMATE OF PUMP HOUSE


umping station near Anjanagiri Reservoir and Design, supply,
echanical works such as Vertical- Single Stage-Francis Turbine
45 MW each including all accessories and Earth work Excavation
servoir including intake structure and tunnel at Stage -1 pumping
ur (M), Mahabubnagar District.
#
benching tunnelling methods including excavation for supports in all types of
cluding cost of providing supports ) for roof before benching including cost of
caling excavated surface, ventilation, lighting, drainage removing and hauling
pecified dump area and all other ancillary operations etc., complete with initial

###

= 33104.61 ###
33105 Cum
hods in rock not requiring supports including cost of all materials,machinery,
oving under-cuts, ventilation,lighting, drainage, removing and hauling the
pecified dump area and all other ancillary operations etc., complete with initial

41.78 = 270594.0192

###
#
18 = 43009.92 ###

-10828.80 ###
302775.1392 #
PRRLIS -PACKAGE 1

302775.1392 = 211943 Cum


hods including excavation for supports in all types of soil / rock strata
roviding supports ) including cost of all other materials, machinery, labour,
lighting, drainage,removing and hauling the excavated muck outside tunnel
ancillary operations etc., complete with initial lead upto 1 km and all lifts.

###

302775.1392 = 90832.54176
90833 Cum

due to natural causes such as geological faults etc., out of tunnel including
necessary and disposing off the same in specified dump area or as directed
ry,labour, ventilation, drainage, lighting and all other ancillary operations etc.,
d all lifts

33588 Cum

tion temperary structural steel supports as per details and dismantling the
of all materials, machinery, labour,cutting, bending, welding, grinding,
her ancillary operations etc.,complete with initial lead upto 1 km and all lifts.

75 MT

tion permanent structural steel supports as per details including cost of all
ending, welding, grinding, lighting,ventilation, drainage and all other ancillary
ad upto 1 km and all lifts.

150 MT

in concrete / rock by percussion drilling using jack hammer or stooper


consolidation / contact grouting including cost of all materials, machinery,
ing, drainage and all other ancillary operations etc., complete.

###

185 Nos
= 20.89
Rmt
PRRLIS -PACKAGE 1

###

81 Nos
= 5
Rmt

nder specified pressure for consolidation / contact grouting including cost of


ng wherever necessary,ventilation,lighting, drainage and other ancillary
o 1 km and all lifts.

MT

teel rock bolts with mechanical / wedge type anchorage including drilling 35
mm thick steel tapered wedge, 10 mm thick plate washers and nuts,
of all materials, machinery, labour, ventilation, lighting, drainage and all other
lead upto 1 km and all lifts.

2x(247.2+26.2) x41.78+246x38.833666666666 = 32398.386 Sqm


3600 Nos

Servicebay
= 7721.43 Sqm
858 Nos
PRRLIS -PACKAGE 1

des and arch of tunnel in cement mortar


st of all materials, machinery, labour, ventilation, lighting, drainage and all
e with lead upto 1 km and all lifts.

= 38765.704
19383 Sqm

er+38 mm thickness) for slabs duly fixing chain weld wire mesh
yers including cost and conveyance of all materials, labour
folding, machine mixing, laying concrete with shortcrete machine
as directed by Engineer-in-Charge

= 44141.704
22071 Sqm

20 ( 28 days cube compressive strength not less than 20 N / sqmm ) grade


wn size approved clean, hard,graded aggregates crushed from tunnel muck
f all materials, machinery, labour, formwork, batching, mixing, conveying upto
position, levelling, vibrating, finishing, curing, ventilation, lighting,drainage
complete with lead upto 1 km and all lifts.( Cement content 330 kg / cum for
cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

0.6 = 5301 Cum


PRRLIS -PACKAGE 1

M-20 ( 28 days cube compressive strength not less than 20 N / sqmm ) grade
wn size approved clean, hard,graded aggregates crushed from tunnel muck
st of all materials, machinery, labour, formwork, batching, mixing, conveying
ing in position, levelling, vibrating, finishing, curing, ventilation,
operations etc., complete with lead upto 1 km and all lifts.
of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of

42.72576

= 33021.424 Sqm

Service bay level


= 8069.4
41090.824 Sqm
= 24654 Cum

sition reinforcement steel for tunnel RCC works including cleaning,


g, lapping / welding joints wherever required, tying with 1.25 mm dia.soft
ll materials, labour,machinery, ventilation, lighting, drainage etc.,complete with

M-25 ( 28 days cube compressive strength not less than 25 N / sq mm ) grade


ize approved, clean, hard, graded aggregates including cost of all materials,
, scaffolding, cleaning, batching, mixing, placing in position, levelling,
e for RCC works with initial lead upto 1 km and all lifts.( Cement content : 380
CA : 0.90 cum, blending ratio of CA--65:35, FA : 0.40 cum)
PRRLIS -PACKAGE 1

14.47 = 88990.50 #

4= -1590.43
= -2756.75
8= -2366.80
2= -1506.75
= -17896.50
23 = -17250.00
= -8892.00

-10828.80 ###
##
#
0.2 = 2460.00

= -110.27
26.71 = 1307.72
0.6 = 427.68 ###
0.6 = 259.20
= 1837.83

= 226.80
= 648.00
= 96.77
0.2 = 468.00

###
0.3 = 44.06 #
33568.00 Cum
###
(1:6) with 2nd class Bricks traditional size 23 x 11 x 7 cms
###
16.50 81.972
82
thick, base coat in CM (1:6), 16mm thick and top coat in CM (1:4),
ing.

712.8
713
water proof cement paint of apporved brand and shade over a base coat
king making 3 coats in all to give an even shade after thourughly brushing the
of loose powdered materials, including cost and conveyance of all materials to
, labour charges etc. complete for finished item of work as per SS

16.5 712.8
713 Sqm
PRRLIS -PACKAGE 1

ding Windows made of Galvanized Steel as per IS 513, D


owder coated with Pure polyester powder up to 50-60 microns thick with total
Frame and 0.58mm thickness for Sliding Shutter Section, the OuterFrame
of 90 mm x 50 mm and the Window Shutter section of 58 mm x 36 mm and
ide tracks of 12mm width and 24mm deep for provision to slide the Shutter /
ater drain outlet component made of PVC and the shutter frame fitted with
make and fixed with EPDM weathering seal resistant accessories and handle
tter including installation of window system at site using anchor fasteners,
me corners inclusive of conveyance of all materials accessories, labour
plete finished item of work for Window with Two Sliding Shutters and with Grill

288
288 Sqm

sed Poly Vinyl Chloride (UPVC) sliding doors three track - two glass
sliding- 95 -Series duly manufactured using UPVC reinforced profiles of
m) x 2.0 mm for outer frames, (75 mm x 39 mm)/(66 mm x 42 mm) x 2.0 mm
of mounting single glazing system, structurally reinforced with hot dip
m thickness of 1.2 mm prefabricated & welded through fusion welding the
hick clear float glass of reputed make and mesh shutter shall be made of
m) x2.0 mm uPVC profile section and fitted with nylon/polymer mesh and
ets/ EPDM weathering seal resistant accessories like clipping locking
er set of sashes and the system is to be installed at the site using anchor
y glazing/ deglazing at site etc., including cost and conveyance of all
for transportation, erection at site with templates for casement sizing

g consisting of 600mmX600mm, Solid PVC insulation panels having


rigid foam sheet and EPS as defined in of desired thickness depending on
rame work made using anodized aluminium Tee section of sizes 1X1
square pattern of grid sizes of 2X2 (600X600mm). The aluminium
g with the help of G.I. hook and G.I. wire/6mm.M.S. rods of required sizes
ium framework is supported on side wall with the use of aluminium 1X1
rection of Engineer-in-Charge & drawing

7800
7800

Sqm

5cm in CM(1:6) using 2nd bricks having a crushing strength of not


o mild steel bars of 6m dia in every third layer of brick masory, with free joints
st and seignorage charges and conveyance of all materials and water
nd all operational, incidental, labour charges such as scaffolding mixing
arges, curing etc. complete but excluding the cost of steel and its fabrication
er SS 509 .
PRRLIS -PACKAGE 1

3.3 68.31
3.3 56.925
2 213.9
339

sting of roof truss with all accessories including cost of all


ete as per specifications and approved drawings .

= 860 MT

elain vitrified tile of size 300 x 300 / 200 x 100 mmand thickness between
g to IS:13711, IS:13712, IS:13630 (Parts 1 to15) of any colour and finish in all
oat of cement mortar (1:8), 12 mm thick over CC bed already laid or
nt slurry of honey like consistency spread @ 3.3.kgs per sqm & jointed
ll depth mixed with pigment of matching shade, including cost of all
nd tiles etc., complete, including seigniorage charges, etc., complete for

= 280.8
= 8346
-1539
7087 Sqm
PRRLIS - PACKAGE NO. 1

ABSTRACT OF DELIVERY MAIN


PRLIS-(Package No.1)- Construction of Stage-1 pumping station near Anjanagiri Reservo

commissioning of Electro Mechanical works such as Vertical- Single Stage-Francis Turbine Pu

145 MW each including all accessories and Earth work Excavation of approach channel fr

intake structure and tunnel at Stage -1 pumping station at Anjanagiri Reservoir at Narlapur (V),
S.NO ITEM CODE DESCRIPTION OF ITEM
Earth work in excavation in all kinds of soils of
foundation of structures as per drawing and technical
specification, including setting out, construction of
shoring and bracing, and other deleterious matter,
1 IRR-DAW-1-1 dressing of sides and bottom and backfilling with
approved material.removal of stumps Depth upto 3 m

Excavation for foundation in ordinary rock (including


HDR) without blasting including boulders above 0.3 m
upto 0.6 m dia for dam, spillway, intake structure and
other appurtenant works and placing the excavated
2 IRR-DAW-1-2 material neatly in dump area or disposing off the same as
directed etc., complete with all leads and lifts.

Excavation for foundation in hard rock of all toughness by


blasting including boulders above 1.2 m dia. for dam,
spillway, intake structure and other appurtenant works
and placing the excavated rock neatly in dump area or
3 IRR-DAW-1-4a stack yard including levelling as directed etc., complete
with all leads and lifts.

Excavation for vertical / inclined shaft in all types of soft /


hard rock including cost of all materials, machinery,
labour, shoring, strutting, scaling excavated surface,
ventilation, lighting,drainage, removing and hauling
4 IRR-TAW-1-2 excavated muck outside shaft upto specified dump area
and all other ancillary operations etc., complete with all
leads and lifts.
PRRLIS - PACKAGE NO. 1

Providing, fabricating and placing in position


reinforcement steel for tunnel RCC works including
cleaning, straightening, cutting, bending, hooking,
lapping / welding joints wherever required, tying with 1.25
mm dia.soft annealed steel wire, including cost of all
5 IRR-TAW-5-1 materials, labour,machinery, ventilation, lighting, drainage
etc.,complete with all leads and lifts.

Providing and laying insitu vibrated M-20 ( 28 days


cube compressive strength not less than20 N / sq mm )
grade cement concrete using 40 mm down size
approved, clean, hard, graded aggregates for anchor
blocks including cost of all materials,machinery, labour,
formwork, scaffolding, cleaning, batching, mixing, placing
in position,levelling, vibrating, finishing, curing etc.,
complete with all leads and lifts.(Cement content: 320
6 IRR-CCDW-2-20 kg / cum with use of super plasticiser(0.4% by wt. of
cement),CA : 0.90cum, Blending Ratio of CA--50:30:20,
FA : 0.40 cum)

Providing, fabricating and placing in position


reinforcement steel for RCC,below 36 dia rods
overlaps and wastages wherever required, tying with 1.25
mm diameter soft annealed steel wire, including cost of
all materials, machinery, labour etc., complete all leads
7 IRR-DAW-2-1A and lifts.overlaps and wastage Lap jointing considered for
bars upto 36 mm diameter.
PRRLIS - PACKAGE NO. 1

Providing and laying insitu vibrated M-20 ( 28 days


cube compressive strength not less than 20 N / sqmm )
grade cement concrete using 40 mm and down size
approved clean, hard,graded aggregates crushed from
tunnel muck for sides and arch lining including cost of
all materials, machinery, labour, formwork, batching,
mixing, conveying upto placing point in agitator cars,
placing in position, levelling, vibrating, finishing, curing,
ventilation, lighting,drainage and all other ancillary
8 IRR-TAW-5-4 operations etc., complete with lead upto 1 km and all lifts.
( Cement content 330 kg / cum for use of super
plasticiser(0.4% by wt. of cement),CA : 0.90cum,
Blending Ratio of CA--50:30:20, FA : 0.40 cum)

Design, fabrication, supply, erection, testing and


commissioning of delivery mains with all accessories
including cost of all materials,machinery, labour
9 etc.,complete as per specifications and approved
drawings

Cleaning delivery lines to expose fresh metal surface for


painting by sand blasting method as per specifications
including cost of all materials, labour, machinery,
10 scaffolding, etc., complete with leads and lifts.

painting of steel liner on sand blasted surfaces with one


coat of inorganic zinc silicate and three super coats of
solventless coaltar epoxy brown paint paint each coat
11 cost of all materials, labour, scaffolding etc., complete
with all leads and all lifts
PRRLIS - PACKAGE NO. 1

Providing and fixing 25 mm dia 3 m long cold twisted


deformed steel dowel bars with one end driven into 45 to
50 mm diameter 1.50 m deep hole drilled in bed rock and
other end provided with L-bend for embedding in
concrete / masonry of over flow / non-over flow blocks
and other appertenant works including cost of drilling and
cleaning hole, filling hole with cement mortar 1 : 1
12 IRR-DAW-1-13 proportion, driving anchor rod, cost of all materials,
machinery, labour etc., complete with all leads and lifts.
PRRLIS - PACKAGE NO. 1

TRACT OF DELIVERY MAIN


station near Anjanagiri Reservoir and Design, supply, erection testing and

l- Single Stage-Francis Turbine Pumps and Synchronous motor sets for 8 No.s of

xcavation of approach channel from foreshore of Srisailam Reservoir including

janagiri Reservoir at Narlapur (V), Kollapur (M), Mahabubnagar District.


QUANTITY UNIT RATE AMOUNT
2373 Cum 160.00 379680.00

2373 Cum 199.00 472227.00

1187 Cum 472.00 560264.00

136993 Cum 2356.00 322755508.00


PRRLIS - PACKAGE NO. 1

2222.64 MT 58504.00 130033331.00

16928 Cum 6066.00 102685248.00

1354 MT 46151.00 62488454.00


PRRLIS - PACKAGE NO. 1

27783.00 Cum 6822.00 189535626.00

15088 MT 81595.00 1231105360.00

87368.00 Sqm 368.00 32151424.00

92740.00 Sqm 1437.00 133267380.00


PRRLIS - PACKAGE NO. 1

405 Nos 866.00 350730.00

2205785232.00
TOTAL 2205785232.00
PRRLIS PACKAGE NO 1

DETAILED ESTIMATE OF DELIVERY M


PRLIS-(Package No.1)- Construction of Stage-1 pumping station near Anjanagiri Reservoir a

Electro Mechanical works such as Vertical- Single Stage-Francis Turbine Pumps and Synch

accessories and Earth work Excavation of approach channel from foreshore of Srisailam

pumping station at Anjanagiri Reservoir at Narlapur (V), Kollapur (M), Mahabubnagar District.
1(a) IRR-DAW-1-1 Earth work in excavation in all kinds of soils of foundation of structures as pe
construction of shoring and bracing, and other deleterious matter, dressing of
of stumps Depth upto 3 m

Area at Deeper section (160+1.5*13.2)*13


1 x (0+2703.36)/2
Consider All soils 40% 5933.4
(b) IRR-DAW-1-2 Excavation for foundation in ordinary rock (including HDR) without blasting inc
intake structure and other appurtenant works and placing the excavated mate
etc., complete with initial lead upto 1 km and all lifts.

Area at Deeper section (160+1.5*13.2)*13


1 x (0+2703.36)/2
Consider HDR 40% 5933.4
IRR-DAW-1-4a Excavation for foundation in hard rock of all toughness by blasting including bo
other appurtenant works and placing the excavated rock neatly in dump area o
initial lead upto 1 km and all lifts.

Area at Deeper section (160+1.5*13.2)*13


1 x (0+2703.36)/2
Consider HR 20% 5933.4
2 IRR-TAW-1-2 Excavation for vertical / inclined shaft in all types of soft / hard rock including c
excavated surface, ventilation, lighting,drainage, removing and hauling excava
ancillary operations etc., complete with initial lead upto 1 km and all lifts.

DELIVERY MAINS 9X 618

618= 160+170+188+62+38(inclinations)
3 IRR-TAW-5-1 Providing, fabricating and placing in position reinforcement steel for tunnel RC
hooking, lapping / welding joints wherever required, tying with 1.25 mm dia.so
labour,machinery, ventilation, lighting, drainage etc.,complete with initial lead u

80Kg per Cum 27783.0


Weight
PRRLIS PACKAGE NO 1

4 IRR-CCDW-2-20 Providing and laying insitu vibrated M-20 ( 28 days cube compressive streng
mm down size approved, clean, hard, graded aggregates for ANCHOR BLOC
scaffolding, cleaning, batching, mixing, placing in position,levelling, vibrating, f
lifts.(Cement content: 320 kg / cum with use of super plasticiser(0.4% by wt. o
0.40 cum)

Anchor blocks
At bend 1x 108
(-) Delivery Mains area 9x 15
tunnel portal
2x 9
9x 1.2

5 IRR-DAW-2-1A Providing, fabricating and placing in position reinforcement steel for RCC,b
tying with 1.25 mm diameter soft annealed steel wire, including cost of all mat
and all lifts.overlaps and wastage Lap jointing considered for bars upto 36 mm

80Kg per Cum 16928

6 IRR-TAW-5-4 Providing and laying insitu vibrated M-20 ( 28 days cube compressive streng
mm and down size approved clean, hard,graded aggregates crushed from tun
machinery, labour, formwork, batching, mixing, conveying upto placing point in
curing, ventilation, lighting,drainage and all other ancillary operations etc., com
cum for use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blendin

DELIVERY MAINS
9X 618 x /4

7 Design, fabrication, supply, erection, testing and commissioning of delivery ma


labour etc.,complete as per specifications and approved drawings

DELIVERY MAINS
9X 618 x

Weight 1922.00 x 7.85

8 Cleaning delivery lines to expose fresh metal surface for painting by sand blas
labour, machinery, scaffolding, etc., complete with initial lead for sand upto 1 k

DELIVERY MAINS
PRRLIS PACKAGE NO 1

9X 618 x

9 painting of steel liner on sand blasted surfaces with one coat of inorganic zinc
brown paint paint each coat cost of all materials, labour, scaffolding etc., com

DELIVERY MAINS Interior Surface


9X 618 x
Exterior Surface
9X 38 x

10 IRR-DAW-1-13 Providing and fixing 25 mm dia 3 m long cold twisted deformed steel dow
deep hole drilled in bed rock and other end provided with L-bend for embeddin
other appertenant works including cost of drilling and cleaning hole, filling hole
all materials, machinery, labour etc., complete with initial lead upto 1 km and a

Anchor blocks 1x 108


PRRLIS PACKAGE NO 1

OF DELIVERY MAIN
giri Reservoir and Design, supply, erection testing and commissioning of

mps and Synchronous motor sets for 8 No.s of 145 MW each including all

e of Srisailam Reservoir including intake structure and tunnel at Stage -1

nagar District.
structures as per drawing and technical specification, including setting out,
atter, dressing of sides and bottom and backfilling with approved material.removal

160+1.5*13.2)*13.2 = 2373.36
0+2703.36)/2 x 5 = 5933.4 Cum
x 0.4 = 2373 Cum
thout blasting including boulders above 0.3 m upto 0.6 m dia for dam, spillway,
e excavated material neatly in dump area or disposing off the same as directed

160+1.5*13.2)*13.2 = 2373.36
0+2703.36)/2 x 5 = 5933.4 Cum
x 0.4 = 2373 Cum
sting including boulders above 1.2 m dia. for dam, spillway, intake structure and
tly in dump area or stack yard including levelling as directed etc., complete with

160+1.5*13.2)*13.2 = 2373.36
0+2703.36)/2 x 5 = 5933.4 Cum
x 0.2 = 1187 Cum
d rock including cost of all materials, machinery, labour, shoring, strutting, scaling
nd hauling excavated muck outside shaft upto specified dump area and all other
and all lifts.

2
x /4 x 5.6 = 136992.540579849
136993 Cum
nclinations)
eel for tunnel RCC works including cleaning, straightening, cutting, bending,
h 1.25 mm dia.soft annealed steel wire, including cost of all materials,
with initial lead upto 1 km and all lifts.

27783.0 x 80 = 2222640 Kg
= 2222.64 MT
PRRLIS PACKAGE NO 1

ompressive strength not less than20 N / sq mm ) grade cement concrete using 40


ANCHOR BLOCKS including cost of all materials,machinery, labour, formwork,
elling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all
ser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA :

x 15 x 12 = 19440
x 52 / 4= -2651

x 2.5 x 1.2 = 54
x /2 x 5 = 84.82
16928 Cum

t steel for RCC,below 36 dia rods overlaps and wastages wherever required,
ng cost of all materials, machinery, labour etc., complete with initial lead upto 1 km
bars upto 36 mm diameter.

16928 x 0.08 = 1354.2


1354 MT

ompressive strength not less than 20 N / sqmm ) grade cement concrete using 40
crushed from tunnel muck for sides and arch lining including cost of all materials,
o placing point in agitator cars, placing in position, levelling, vibrating, finishing,
erations etc., complete with lead upto 1 km and all lifts.( Cement content 330 kg /
0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

x (5.62-52) = 27783.00 Cum

ng of delivery mains with all accessories including cost of all materials,machinery,


wings

x 5.0 x 0.022 = 1922.00 Cum

MT/cum = 15088 MT

ting by sand blasting method as per specifications including cost of all materials,
for sand upto 1 km and all lifts.
PRRLIS PACKAGE NO 1

x 5.0 = 87368.00 Sqm

of inorganic zinc silicate and three super coats of solventless coaltar epoxy
folding etc., complete with all leads and all lifts

x 5.0 = 87367.6916963322 Sqm

x 5.0 = 5372.12 Sqm


92740.00 Sqm

ormed steel dowel bars with one end driven into 45 to 50 mm diameter 1.50 m
end for embedding in concrete / masonry of over flow / non-over flow blocks and
g hole, filling hole with cement mortar 1 : 1 proportion, driving anchor rod, cost of
d upto 1 km and all lifts.

x 15 / 4= 405
405 Nos
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

Name of Work: PRLIS- SATGE1 -CONSTRUCTION OF DELIVERY CISTERN

(Formation of Bund in cistern area is not covered in this estimate)


S.NO DESCRIPTION OF ITEM
1 IRR- Excavation in all kinds of soil including boulders upto 0.30 m dia. for
CCDW-1- foundations of canal cross drainage and other appurtenant structures and
1 placing the excavated stuff neatly in specified dump area or disposing off the
same as directed etc., complete with initial lead upto 50 m and initial lift upto
3 m.

2 IRR- Excavation in ordnary rock without blasting for foundations of canal cross
CCDW-1- drainage and other appurtenant structures and placing the excavated stuff
4 neatly in specified dump area or disposing off the same as directed etc.,
complete with initial lead upto 50 m and initial lift upto 3 m.

3 IRR- Excavation in hard rock of all toughness by blasting including boulders


CCDW-1- above 1.2 m dia. For foundations of canal cross drainage and other
6 appurtenant structures and placing the excavated rock neatly in specified
dump area or stack yard as directed etc., complete with initial lead upto 50
m and initial lift upto 3 m.

4 IRR- Providing and laying insitu vibrated M-15 ( 28 days cube compressive
DAW-2-6 strength not less than 15 N / sq mm ) grade cement concrete using 40 mm
down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for plain concrete works with initial lead upto 1 km and all lifts.
( Cement content : 260 kg / cum with use of super plasticiser,CA : 0.90 cum,
Blending Ratio of CA -- 50:30:20, FA : 0.40 cum)

5 IRR- Providing and fixing 25 mm dia 3 m long cold twisted deformed steel dowel
DAW-1- bars with one end driven into 45 to 50 mm diameter 1.50 m deep hole drilled
13 in bed rock and other end provided with L-bend for embedding in concrete /
masonry of over flow / non-over flow blocks and other appertenant works
including cost of drilling and cleaning hole, filling hole with cement mortar 1 :
1 proportion, driving anchor rod, cost of all materials, machinery, labour etc.,
complete with initial lead upto 1 km and all lifts.

6 IRR- Providing and laying insitu vibrated M-20 ( 28 days cube compressive
CCDW- strength not less than20 N / sq mm ) grade cement concrete using 40 mm
2-20 down size approved, clean, hard, graded aggregates for cantiliver /
counterfort retaining walls including cost of all materials,machinery,
labour, formwork, scaffolding, cleaning, batching, mixing, placing in
position,levelling, vibrating, finishing, curing etc., complete with initial lead
upto 50 m and all lifts.(Cement content: 320 kg / cum with use of super
plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--
50:30:20, FA : 0.40 cum)

7 IRR- Providing, fabricating and placing in position reinforcement steel for


DAW-2- RCC,below 36 dia rods overlaps and wastages wherever required, tying
1A with 1.25 mm diameter soft annealed steel wire, including cost of all
materials, machinery, labour etc., complete with initial lead upto 1 km and all
355787507.xlsx/A-DC
lifts.overlaps and wastage Lap jointing considered for bars upto 36 mm 52/508
diameter.
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

7 IRR- Providing, fabricating and placing in position reinforcement steel for


S.NO DAW-2- RCC,below
DESCRIPTION 36 dia
OFrods
ITEMoverlaps and wastages wherever required, tying
1A with 1.25 mm diameter soft annealed steel wire, including cost of all
materials, machinery, labour etc., complete with initial lead upto 1 km and all
lifts.overlaps and wastage Lap jointing considered for bars upto 36 mm
diameter.

8 IRR- Providing and laying insitu vibrated M-20 ( 28 days cube compressive
DAW-2-4 strength not less than 20 N / sq mm ) grade cement concrete using 40 mm
down size approved, clean, hard, graded aggregates including cost of all
materials, machinery, labour, formwork, centering, scaffolding, cleaning,
batching, mixing, placing in position, levelling, vibrating, finishing, curing
etc.,complete for RCC works of gallery, sluice, spillway crest, spillway d / s
face, energy dissipating structures, training walls, piers, abutments and such
other locations with initial lead upto 1 km and all lifts.

TOTAL

355787507.xlsx/A-DC 53/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

STRUCTION OF DELIVERY CISTERN

a is not covered in this estimate)


QUANTITY UNIT RATE AMOUNT
9800 Cum 132.00 1293600.00

9800 Cum 159.00 158200.00

29400.00 Cum 568.07 16701258.00

12426 Cum 4577.00 56873802.00

1100 Nos 866.00 952600.00

38487 Cum 6066.00 233462142.00

1925 MT 46151.00 88840675.00

355787507.xlsx/A-DC 54/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

1925 MT 46151.00 88840675.00


QUANTITY UNIT RATE AMOUNT

1456 Cum 5079.00 7395024.00

405677301.00

355787507.xlsx/A-DC 55/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

Name of Work: PRLIS- SATGE1 -CONSTRUCTION OF DELIVERY CISTERN


DETAILED ESTIMATE
1 IRR- Excavation in all kinds of soil including boulders upto 0.30 m dia. for foundations of canal cross drai
CCDW-1- and other appurtenant structures and placing the excavated stuff neatly in specified dump area or d
1 off the same as directed etc., complete with initial lead upto 50 m and initial lift upto 3 m.

Qty as per Statement =

2 IRR- Excavation in ordnary rock without blasting for foundations of canal cross drainage and other appu
CCDW-1- structures and placing the excavated stuff neatly in specified dump area or disposing off the same a
4 directed etc., complete with initial lead upto 50 m and initial lift upto 3 m.

Qty as per Statement = 9800.0 Cum

3 IRR- Excavation in hard rock of all toughness by blasting including boulders above 1.2 m dia. For founda
CCDW-1- canal cross drainage and other appurtenant structures and placing the excavated rock neatly in spe
5 dump area or stack yard as directed etc., complete with initial lead upto 50 m and initial lift upto 3 m

Qty as per Statement = 29399.91

4 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strength not less than 15 N / s
grade cement concrete using 40 mm down size approved, clean, hard, graded aggregates including
all materials, machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing, placing
position, levelling, vibrating, finishing, curing etc.,complete for plain concrete works with initial lead u
km and all lifts. ( Cement content : 260 kg / cum with use of super plasticiser,CA : 0.90 cum, Blendin
of CA -- 50:30:20, FA : 0.40 cum)

Qty as per Statement = 12426.192

5 IRR- Providing and fixing 25 mm dia 3 m long cold twisted deformed steel dowel bars with one end
DAW-1- into 45 to 50 mm diameter 1.50 m deep hole drilled in bed rock and other end provided with L-bend
13 embedding in concrete / masonry of over flow / non-over flow blocks and other appertenant works in
cost of drilling and cleaning hole, filling hole with cement mortar 1 : 1 proportion, driving anchor rod,
all materials, machinery, labour etc., complete with initial lead upto 1 km and all lifts.

Qty as per Statement =

6 IRR- Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than20 N
CCDW-2- mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded aggregates for
20 cantiliver / counterfort retaining walls including cost of all materials,machinery, labour, formwork,
scaffolding, cleaning, batching, mixing, placing in position,levelling, vibrating, finishing, curing etc., c
with initial lead upto 50 m and all lifts.(Cement content: 320 kg / cum with use of super plasticiser(0.
wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

Qty as per Statement


7 IRR- Providing, fabricating and placing in position reinforcement steel for RCC,below 36 dia rods
DAW-2- overlaps and wastages wherever required, tying with 1.25 mm diameter soft annealed steel wire,
1A including cost of all materials, machinery, labour etc., complete with initial lead upto 1 km and all
lifts.overlaps and wastage Lap jointing considered for bars upto 36 mm diameter.

355787507.xlsx/D-DC 3/508
IRR- Providing, fabricating and placing in position
PRLISreinforcement
Stage-1 P.Ssteel
DPRfor Volume-3C,
RCC,below 36Part-IV
dia rods
DAW-2- overlaps and wastages wherever required, tying with 1.25 mm diameter soft annealed steel wire,
1A including cost of all materials, machinery, labour etc., complete with initial lead upto 1 km and all
lifts.overlaps and wastage Lap jointing considered for bars upto 36 mm diameter.

Qty as per Statement =

8 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less than 20 N /
sq mm ) grade cement concrete using 40 mm down size approved, clean, hard, graded
aggregates including cost of all materials, machinery, labour, formwork, centering, scaffolding,
cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc.,complete
for RCC works of gallery, sluice, spillway crest, spillway d / s face, energy dissipating structures,
training walls, piers, abutments and such other locations with initial lead upto 1 km and all lifts.

Qty as per Statement =

355787507.xlsx/D-DC 4/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

DELIVERY CISTERN

for foundations of canal cross drainage


neatly in specified dump area or disposing
and initial lift upto 3 m.

9799.96875
9800.0 Cum
nal cross drainage and other appurtenant
mp area or disposing off the same as
to 3 m.

Cum

ulders above 1.2 m dia. For foundations of


g the excavated rock neatly in specified
d upto 50 m and initial lift upto 3 m.

Cum

ssive strength not less than 15 N / sq mm )


hard, graded aggregates including cost of
cleaning, batching, mixing, placing in
in concrete works with initial lead upto 1
r plasticiser,CA : 0.90 cum, Blending Ratio

Cum

ed steel dowel bars with one end driven


nd other end provided with L-bend for
cks and other appertenant works including
: 1 proportion, driving anchor rod, cost of
o 1 km and all lifts.

1100 Nos

essive strength not less than20 N / sq


clean, hard, graded aggregates for
erials,machinery, labour, formwork,
g, vibrating, finishing, curing etc., complete
um with use of super plasticiser(0.4% by
: 0.40 cum)

38486.58853 Cum
eel for RCC,below 36 dia rods
ameter soft annealed steel wire,
ith initial lead upto 1 km and all
6 mm diameter.

355787507.xlsx/D-DC 5/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

1925 MT

ssive strength not less than 20 N /


d, clean, hard, graded
mwork, centering, scaffolding,
finishing, curing etc.,complete
, energy dissipating structures,
al lead upto 1 km and all lifts.

1456 Cum

355787507.xlsx/D-DC 6/508
PRRLIS - PACKAGE NO. 1

ABSTRACT OF PERMANENT ACCESS TUN

PRLIS-(Package No.1)- Construction of Stage-1 pumping station near Anjanagiri Rese

commissioning of Electro Mechanical works such as Vertical- Single Stage-Francis Turbine

145 MW each including all accessories and Earth work Excavation of approach channel from

structure and tunnel at Stage -1 pumping station at Anjanagiri Reservoir at Narlapur (V), Koll

S.NO ITEM CODE DESCRIPTION OF ITEM

Excavation in ordinary rock (including HDR) without blasting


including boulders above 0.30 m upto 0.6 m dia. For canals,
seating of embankment, filter drain / catch water drains etc.,
including dressing of bed and sides to required level and
1 IRR-DAW-1-3
profile, cost of all materials, machinery, labour, placing the
excavated soft rock neatly in dump area or for formation of
service road as directed etc.,complete with lead upto 1 km
and all lifts.

Excavation for vertical / inclined shaft in all types of soft / hard


rock including cost of all materials, machinery, labour, shoring,
strutting, scaling excavated surface, ventilation,
2 IRR-TAW-1-2 lighting,drainage, removing and hauling excavated muck
outside shaft upto specified dump area and all other ancillary
operations etc., complete with initial lead upto 1 km and all
lifts.

Excavation for tunnel by tunnelling methods in rock not


requiring supports including cost of all materials,machinery,
labour, scaling excavated surface, removing under-cuts,
3 IRR-TAW-1-3 ventilation,lighting, drainage, removing and hauling the
excavated muck outside tunnel upto specified dump area and
all other ancillary operations etc., complete with initial lead
upto 1 km and all lifts. (PAT)
PRRLIS - PACKAGE NO. 1

Excavation for tunnel by tunnelling methods including


excavation for supports in all types of soil / rock strata
requiring supports ( excluding cost of providing supports )
including cost of all other materials, machinery, labour, scaling
4 IRR-TAW-1-4
excavated surface, ventilation, lighting, drainage,removing
and hauling the excavated muck outside tunnel upto specified
dump area and all other ancillary operations etc., complete
with initial lead upto 1 km and all lifts.

Removing and hauling muck overfallen due to natural causes


such as geological faults etc., out of tunnel including breaking
large fragments by blasting if necessary and disposing off the
3 IRR-TAW-1-6 same in specified dump area or as directed including cost of
all materials, machinery,labour, ventilation, drainage, lighting
and all other ancillary operations etc., complete with initial
lead upto 1 km and all lifts

Providing, fabricating and fixing in position temperary


structural steel supports as per details and dismantling the
same before concreting including cost of all materials,
4 IRR-TAW-3-4
machinery, labour,cutting, bending, welding, grinding,
ventilation, lighting, drainage and all other ancillary operations
etc.,complete with initial lead upto 1 km and all lifts.

Providing, fabricating and fixing in position permanent


structural steel supports as per details including cost of all
materials, machinery, labour, cutting, bending, welding,
5 IRR-TAW-3-3
grinding, lighting,ventilation, drainage and all other ancillary
operations etc., complete with initial lead upto 1 km and all
lifts.

Grouting cement slurry in grout holes under specified pressure


for consolidation / contact grouting including cost of all
6 IRR-TAW-6-2 materials, machinery, labour, redrilling wherever
necessary,ventilation,lighting, drainage and other ancillary
operations etc., complete with lead upto 1 km and all lifts.
PRRLIS - PACKAGE NO. 1

Drilling 32 mm diameter grout holes in concrete / rock by


percussion drilling using jack hammer or stooper drills as
directed to specified depth for consolidation / contact grouting
7 IRR-TAW-6-1
including cost of all materials, machinery, labour, cleaning
holes, ventilation, lighting, drainage and all other ancillary
operations etc., complete.

Providing and fixing 25 mm diameter steel rock bolts with


mechanical / wedge type anchorage including drilling 35 mm
dia holes, providing 15 cm long 20 mm thick steel tapered
8 IRR-TAW-3-1 wedge, 10 mm thick plate washers and nuts, tightening bolt by
torque wrench, cost of all materials, machinery, labour,
ventilation, lighting, drainage and all other ancillary operations
etc., complete with lead upto 1 km and all lifts.

Providing 25 mm thick guniting to sides and arch of tunnel in


cement mortar
1 : 3 proportion by weight including cost of all materials,
9 IRR-TAW-2-2
machinery, labour, ventilation, lighting, drainage and all other
ancillary operations etc., complete with lead upto 1 km and all
lifts.

Shortcreting in two layers (each layer+38 mm thickness) for


slabs duly fixing chain weld wire mesh 100 x 100x5 mm in
between the two layers including cost and conveyance of all
IRR-TAW-2-3
10 materials, labour charges, all heads, lifts, centering,
(new4 - 2011-12)
scaffolding, machine mixing, laying concrete with shortcrete
machine etc. complete as per specification and as directed by
Engineer-in-Charge

Providing and laying insitu vibrated M-20 ( 28 days cube


compressive strength not less than 20 N / sqmm ) grade
cement concrete using 40 mm and down size approved clean,
hard,graded aggregates crushed from tunnel muck for kerb
and bed lining including cost of all materials, machinery,
labour, formwork, batching, mixing, conveying upto placing
11 IRR-TAW-5-3
point in agitator cars, placing in position, levelling, vibrating,
finishing, curing, ventilation, lighting,drainage and all other
ancillary operations etc., complete with lead upto 1 km and all
lifts.( Cement content 330 kg / cum for use of super
plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending
Ratio of CA--50:30:20, FA : 0.40 cum)
PRRLIS - PACKAGE NO. 1

Providing and laying insitu vibrated M-20 ( 28 days cube


compressive strength not less than 20 N / sqmm ) grade
cement concrete using 40 mm and down size approved clean,
hard,graded aggregates crushed from tunnel muck for sides
and arch lining including cost of all materials, machinery,
labour, formwork, batching, mixing, conveying upto placing
[ IRR-TAW-5-4 point in agitator cars, placing in position, levelling, vibrating,
finishing, curing, ventilation, lighting,drainage and all other
ancillary operations etc., complete with lead upto 1 km and all
lifts.
( Cement content 330 kg / cum for use of super
plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending
Ratio of CA--50:30:20, FA : 0.40 cum)

Providing, fabricating and placing in position reinforcement


steel for tunnel RCC works including cleaning, straightening,
cutting, bending, hooking, lapping / welding joints wherever
13 IRR-TAW-5-1 required, tying with 1.25 mm dia.soft annealed steel wire,
including cost of all materials, labour,machinery, ventilation,
lighting, drainage etc.,complete with initial lead upto 1 km and
all lifts.
PRRLIS - PACKAGE NO. 1

OF PERMANENT ACCESS TUNNEL

ng station near Anjanagiri Reservoir and Design, supply, erection testing and

cal- Single Stage-Francis Turbine Pumps and Synchronous motor sets for 8 No.s of

cavation of approach channel from foreshore of Srisailam Reservoir including intake

giri Reservoir at Narlapur (V), Kollapur (M), Mahabubnagar District.

QUANTITY UNIT RATE AMOUNT

98590 Cum 281.00 27703790.00

0 Cum 2356.00 0.00

147517 Cum 1827.00 269513559.00


PRRLIS - PACKAGE NO. 1

63222 Cum 1879.00 118794138.00

21074 Cum 405.00 8534970.00

50 MT 22068.00 1103400.00

100 MT 85617.00 8561700.00

27.72 MT 11171.00 309660


PRRLIS - PACKAGE NO. 1

310.65 Rmt 399.00 123949.35

42219 Rmt 1034.00 43654446.00

18553 Sqm 604.00 11206012.00

37105 Sqm 1454.00 53950670.00

9927 Cum 6617.00 65686959.00


PRRLIS - PACKAGE NO. 1

30040 Cum 6822.00 204932880.00

0 MT 58504.00 0.00

TOTAL 814076133.00
PRRLIS - PACKAGE NO. 1

DETAILED ESTIMATE OF PERMANENT ACCESS T

1 IRR-DAW-1-3 Excavation in ordinary rock (including HDR) without blasting including boulders abo
embankment, filter drain / catch water drains etc., including dressing of bed and side
machinery, labour, placing the excavated soft rock neatly in dump area or for format
upto 1 km and all lifts.

For approach L = 264 m

IRR-TAW-1-2 Excavation for vertical / inclined shaft in all types of soft / hard rock including cost of
scaling excavated surface, ventilation, lighting,drainage, removing and hauling exca
all other ancillary operations etc., complete with initial lead upto 1 km and all lifts.

0x 1791.789 x
Outer dia =10 +2x0.5+2x0.1+2x0.1 11.4 m

2 IRR-TAW-1-3 Excavation for tunnel by tunnelling methods in rock not requiring supports including
surface, removing under-cuts, ventilation,lighting, drainage, removing and hauling th
area and all other ancillary operations etc., complete with initial lead upto 1 km and

PERMANENT ACCESS TUNNELS


10m dia -1 nos 1x 1791.789 x

Assuming 70% of Qty does not require supports


0.7 x

3 IRR-TAW-1-4 Excavation for tunnel by tunnelling methods including excavation for supports in all
cost of providing supports ) including cost of all other materials, machinery, labour, s
drainage,removing and hauling the excavated muck outside tunnel upto specified du
with initial lead upto 1 km and all lifts.

For the excavation in PAT of item no.2


Assuming remaining 30% length requires supports
0.3 x

4 IRR-TAW-1-6 Removing and hauling muck overfallen due to natural causes such as geological fau
by blasting if necessary and disposing off the same in specified dump area or as dir
ventilation, drainage, lighting and all other ancillary operations etc., complete with in
PRRLIS - PACKAGE NO. 1
Removing and hauling muck overfallen due to natural causes such as geological fau
by blasting if necessary and disposing off the same in specified dump area or as dir
ventilation, drainage, lighting and all other ancillary operations etc., complete with in

Asuming Muck Overfallen is 10% of qty in item no.1 to 5

5 IRR-TAW-3-4 Providing, fabricating and fixing in position temperary structural steel supports as
including cost of all materials, machinery, labour,cutting, bending, welding, grinding,
operations etc.,complete with initial lead upto 1 km and all lifts.

This qty will be based on type of rock and dessign of supports

6 IRR-TAW-3-3 Providing, fabricating and fixing in position permanent structural steel supports a
labour, cutting, bending, welding, grinding, lighting,ventilation, drainage and all othe
1 km and all lifts.

This qty will be based on type of rock and dessign of supports

7 IRR-TAW-6-1 Drilling 32 mm diameter grout holes in concrete / rock by percussion drilling usin

depth for consolidation / contact grouting including cost of all materials, machinery,

all other ancillary operations etc., complete.


Length of PAT = 1791.8
Widht of PAT= 11.4
Outer radius 3
Length of Excavation= 1797.79 =(1791.789+ 2x3)
Width of Excavation= 17.4 =(11.4+ 2x3)
Area of grouting= 1797.789x17.4-1791.789x11=
No of Holes @ 10m c/c = 10855.134 /
Length of each hole required be half the depth
Total length = 310.6

8 IRR-TAW-6-2 Grouting cement slurry in grout holes under specified pressure for consolidation
machinery, labour, redrilling wherever necessary,ventilation,lighting, drainage and ot
km and all lifts.

Length of PAT= 1791.8


Widht of PAT= 11.4
Outer radius 3
Length of Excavation= 1794.789
Width of Excavation= 14.4
Area of grouting= 5418.567
PRRLIS - PACKAGE NO. 1

No of Holes @ 10m c/c 54.18567 Say 55 Nos


Length of each hole required be half the depth
Total length 396 For each PAT
396 Rmt
Grout required per m length be
Total Qty in Kg 70/kg 27720
Total Qty in MT 27.72

9 IRR-TAW-3-1 Providing and fixing 25 mm diameter steel rock bolts with mechanical / wedge type
15 cm long 20 mm thick steel tapered wedge, 10 mm thick plate washers and nuts,
machinery, labour, ventilation, lighting, drainage and all other ancillary operations et

PERMANENT ACCESS TUNNELS


Area for bolting 1x 1791.8 X
No of Holes @ 2m c/c = 56290.712 /
Length of rock bolt = 3m
Total Length = 42219 Rmt

10 IRR-TAW-2-2 Providing 25 mm thick guniting to sides and arch of tunnel in cement mortar
1 : 3 proportion by weight including cost of all materials, machinery, labour, ventilatio
etc., complete with lead upto 1 km and all lifts.

PERMANENT ACCESS TUNNELS 1x 1791.789 X


1x 1791.789 X

Let 25% of Area requires guniting


11 Shortcreting in two layers (each layer+38 mm thickness) for slabs duly fixing ch
IRR-TAW-2-3 (new4 between the two layers including cost and conveyance of all materials, labour charg
- 2011-12) machine mixing, laying concrete with shortcrete machine etc. complete as per spec
Charge

PERMANENT ACCESS TUNNELS 1x 1791.789 X


1x 1791.789 X

Let 50% of Area requires shotcreting

12 IRR-TAW-5-3 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not l
mm and down size approved clean, hard,graded aggregates crushed from tunnel m
machinery, labour, formwork, batching, mixing, conveying upto placing point in agita
curing, ventilation, lighting,drainage and all other ancillary operations etc., complete
kg / cum for use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending

for bottom lining 1x 1791.789 x


for kerb lining 2x 1791.789 x
PRRLIS - PACKAGE NO. 1

13 IRR-TAW-5-4 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength no
40 mm and down size approved clean, hard,graded aggregates crushed from tunne
materials, machinery, labour, formwork, batching, mixing, conveying upto placing po
finishing, curing, ventilation, lighting,drainage and all other ancillary operations etc.,
( Cement content 330 kg / cum for use of super plasticiser(0.4% by wt. of cement),C
cum)

PERMANENT ACCESS TUNNELS


1 1791.789 x 0.3927 (11.4^2-10.0^2)
2 1791.789 x 0.5 x
Qty of Lining

14 IRR-TAW-5-1 Providing, fabricating and placing in position reinforcement steel for tunnel RCC wo
hooking, lapping / welding joints wherever required, tying with 1.25 mm dia.soft ann
labour,machinery, ventilation, lighting, drainage etc.,complete with initial lead upto 1

Lining Qty =30039.865787388+9926.51106 =


Qty of Reinforcement @80Kg/Cum =
PRRLIS - PACKAGE NO. 1

E OF PERMANENT ACCESS TUNNEL

blasting including boulders above 0.30 m upto 0.6 m dia. For canals, seating of
ncluding dressing of bed and sides to required level and profile, cost of all materials,
neatly in dump area or for formation of service road as directed etc.,complete with lead

= 98590 Cum

soft / hard rock including cost of all materials, machinery, labour, shoring, strutting,
nage, removing and hauling excavated muck outside shaft upto specified dump area and
al lead upto 1 km and all lifts.

2
0.905 x 11.4 = 0
0 Cum

not requiring supports including cost of all materials,machinery, labour, scaling excavated
rainage, removing and hauling the excavated muck outside tunnel upto specified dump
e with initial lead upto 1 km and all lifts.

2
0.905 x 11.4 = 210739.1131
210739.1131

210739.1130882 = 147517.3792 Cum

ng excavation for supports in all types of soil / rock strata requiring supports ( excluding
er materials, machinery, labour, scaling excavated surface, ventilation, lighting,
k outside tunnel upto specified dump area and all other ancillary operations etc., complete

210739.1130882 = 63221.73393
63221.73393 Cum

ral causes such as geological faults etc., out of tunnel including breaking large fragments
in specified dump area or as directed including cost of all materials, machinery,labour,
operations etc., complete with initial lead upto 1 km and all lifts
PRRLIS - PACKAGE NO. 1

21073.91131 Cum

ary structural steel supports as per details and dismantling the same before concreting
ting, bending, welding, grinding, ventilation, lighting, drainage and all other ancillary
and all lifts.

Provide 50.0 MT

ent structural steel supports as per details including cost of all materials, machinery,
ventilation, drainage and all other ancillary operations etc., complete with initial lead upto

Provide 100 MT

rock by percussion drilling using jack hammer or stooper drills as directed to specified

cost of all materials, machinery, labour, cleaning holes, ventilation, lighting, drainage and

10855.134
(10x10) = 109 Nos
5.7 / 2= 2.85
310.65 Rmt

cified pressure for consolidation / contact grouting including cost of all materials,
ntilation,lighting, drainage and other ancillary operations etc., complete with lead upto 1
PRRLIS - PACKAGE NO. 1

55
7.2

s with mechanical / wedge type anchorage including drilling 35 mm dia holes, providing
m thick plate washers and nuts, tightening bolt by torque wrench, cost of all materials,
d all other ancillary operations etc., complete with lead upto 1 km and all lifts.

x 10.0 = 56290.71159
(2 x2) = 14073 Nos

h of tunnel in cement mortar


rials, machinery, labour, ventilation, lighting, drainage and all other ancillary operations

x 10.00 = 56290.71159
10.00 = 17917.89
74208.60159
18552.1504 Sqm
ickness) for slabs duly fixing chain weld wire mesh 100 x 100x5 mm in
nce of all materials, labour charges, all heads, lifts, centering, scaffolding,
chine etc. complete as per specification and as directed by Engineer-in-

x 10 = 56290.71159
10 = 17917.89
74208.60159
37104.3008 Sqm

cube compressive strength not less than 20 N / sqmm ) grade cement concrete using 40
ggregates crushed from tunnel muck for kerb and bed lining including cost of all materials,
veying upto placing point in agitator cars, placing in position, levelling, vibrating, finishing,
ncillary operations etc., complete with lead upto 1 km and all lifts.( Cement content 330
cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

0.5 x 10.0 = 8958.945


0.45 x 0.6 = 967.56606
PRRLIS - PACKAGE NO. 1

9926.51106 Cum

ys cube compressive strength not less than 20 N / sqmm ) grade cement concrete using
d aggregates crushed from tunnel muck for sides and arch lining including cost of all
mixing, conveying upto placing point in agitator cars, placing in position, levelling, vibrating,
ll other ancillary operations etc., complete with lead upto 1 km and all lifts.
sticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40

(11.4^2-10.0^2) = 21080.9
5.00 = 8958.945
= 30039.9 Cum

cement steel for tunnel RCC works including cleaning, straightening, cutting, bending,
tying with 1.25 mm dia.soft annealed steel wire, including cost of all materials,
,complete with initial lead upto 1 km and all lifts.

39966.37685 Cum
3197.3101 MT
PRRLIS STAGE2 PS AT YEDULACIVIL AND HYDROMECHANICAL WORKS

Name of Work: PRRLIS- STAGE2 -CONSTRUCTION OF BUS D

ABSTRACT

S.NO ITEM CODE DESCRIPTION OF ITEM

Excavation for vertical / inclined shaft in all types of soft / hard


rock including cost of all materials, machinery, labour,
shoring, strutting, scaling excavated surface, ventilation,
1 IRR-TAW-1-2 lighting,drainage, removing and hauling excavated muck
outside shaft upto specified dump area and all other ancillary
operations etc., complete with initial lead upto 1 km and all
lifts.

Providing, fabricating and placing in position reinforcement


steel for tunnel RCC works including cleaning,
straightening, cutting, bending, hooking, lapping / welding
2 IRR-TAW-5-1 joints wherever required, tying with 1.25 mm dia.soft
annealed steel wire, including cost of all materials,
labour,machinery, ventilation, lighting, drainage etc.,complete
with initial lead upto 1 km and all lifts.

Providing and laying insitu vibrated M-20 ( 28 days cube


compressive strength not less than 20 N / sqmm ) grade
cement concrete using 40 mm and down size approved
clean, hard,graded aggregates crushed from tunnel muck for
sides and arch lining including cost of all materials,
machinery, labour, formwork, batching, mixing, conveying
3 IRR-TAW-5-4 upto placing point in agitator cars, placing in position,
levelling, vibrating, finishing, curing, ventilation,
lighting,drainage and all other ancillary operations etc.,
complete with lead upto 1 km and all lifts.( Cement content
330 kg / cum for use of super plasticiser(0.4% by wt. of
cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA :
0.40 cum)

355787507.xlsx 23
PRRLIS STAGE2 PS AT YEDULACIVIL AND HYDROMECHANICAL WORKS

Providing and fixing 25 mm diameter steel rock bolts with


mechanical / wedge type anchorage including drilling 35 mm
dia holes, providing 15 cm long 20 mm thick steel tapered
4 wedge, 10 mm thick plate washers and nuts, tightening bolt
by torque wrench, cost of all materials, machinery, labour,
ventilation, lighting, drainage and all other ancillary operations
etc., complete with lead upto 1 km and all lifts.

Providing and fixing 25 mm dia 3 m long cold twisted


deformed steel dowel bars with one end driven into 45 to 50
mm diameter 1.50 m deep hole drilled in bed rock and other
end provided with L-bend for embedding in concrete /
5 IRR-DAW-1-13 masonry of over flow / non-over flow blocks and other
appertenant works including cost of drilling and cleaning hole,
filling hole with cement mortar 1 : 1 proportion, driving anchor
rod, cost of all materials, machinery, labour etc., complete
with initial lead upto 1 km and all lifts.

355787507.xlsx 24
PRRLIS STAGE2 PS AT YEDULACIVIL AND HYDROMECHANICAL WORKS

TRUCTION OF BUS DUCT TUNNEL

CT

QUANTITY UNIT RATE AMOUNT

55215 Cum 2356.00 130086540.00

758 MT 58503.00 44345274.00

6319.00 Cum 6822.00 43108218.00

355787507.xlsx 25
PRRLIS STAGE2 PS AT YEDULACIVIL AND HYDROMECHANICAL WORKS

1194.00 Rmt 1034.00 1234596

487 Nos 866.00 412261.35

219186889.35
TOTAL 219186889.00

355787507.xlsx 26
PRRLIS PACKAGE NO 1

Name of Work: PRRLIS- STAGE2 -CONSTRUCTION OF BUS DUCT TUN

DETAILED ESTIMATE
1 Excavation for vertical / inclined shaft in all types of soft / hard rock including cost of all m
labour, shoring, strutting, scaling excavated surface, ventilation, lighting,drainage, removi
IRR-TAW- excavated muck outside shaft upto specified dump area and all other ancillary operations
1-2 initial lead upto 1 km and all lifts.

Bus Ducts 5X 112.005 x /4

4x 26 0.785
For Horizontal tunnel perpendicular to the Pumphouse
5x 5x 0.79

2 Providing, fabricating and placing in position reinforcement steel for tunnel RCC works in
straightening, cutting, bending, hooking, lapping / welding joints wherever required, tying
IRR-TAW- annealed steel wire, including cost of all materials, labour,machinery, ventilation, lighting,
5-1 with initial lead upto 1 km and all lifts.

120 Kg per Cum 6319.00 x


Weight = 758

3 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not less
grade cement concrete using 40 mm and down size approved clean, hard,graded aggreg
tunnel muck for sides and arch lining including cost of all materials, machinery, labour, fo
mixing, conveying upto placing point in agitator cars, placing in position, levelling, vibratin
ventilation, lighting,drainage and all other ancillary operations etc., complete with lead up
IRR-TAW- ( Cement content 330 kg / cum for use of super plasticiser(0.4% by wt. of cement),CA : 0
5-4 of CA--50:30:20, FA : 0.40 cum)

Bus Ducts
5X 112.0 x /4 x (10.12-9.52)

4x 26 0.79 x (10.12-9.52)
4X 5X 0.79 X (10.12-9.52)

4 Providing and fixing 25 mm diameter steel rock bolts with mechanical / wedge type ancho
dia holes, providing 15 cm long 20 mm thick steel tapered wedge, 10 mm thick plate was
IRR-TAW- torque wrench, cost of all materials, machinery, labour, ventilation, lighting, drainage and
3-1 etc., complete with lead upto 1 km and all lifts.
Providing and fixing 25 mm diameter steel rock bolts with mechanical / wedge type ancho
dia holes, providing 15 cm long 20 mm thick steel taperedPRRLIS
wedge,PACKAGE NO plate
10 mm thick 1 was
IRR-TAW- torque wrench, cost of all materials, machinery, labour, ventilation, lighting, drainage and
3-1 etc., complete with lead upto 1 km and all lifts.

Length of busduct tunnel= 138.005


Width of busduct tunnel= 10.1
Outer radius 3
Width of Rock Bolting= 25.957

Area of Rock Bolting= 3582.195785


No of Holes @ 3m c/c 398.02175389 Nos 1194 Rm
Length of rock bolt 1194.00 Rmt

5 Providing and fixing 25 mm dia 3 m long cold twisted deformed steel dowel bars wit
to 50 mm diameter 1.50 m deep hole drilled in bed rock and other end provided with L-be
concrete / masonry of over flow / non-over flow blocks and other appertenant works inclu
IRR-DAW- cleaning hole, filling hole with cement mortar 1 : 1 proportion, driving anchor rod, cost of
1-13 labour etc., complete with initial lead upto 1 km and all lifts.

Length of busduct tunnel= 138.005


Width of busduct tunnel= 10.1
Outer radius 3
Perimeter of Rock Bolting= 31.714
Length of rock bolt
Total Length 4376.69057
No of Holes @ 3m c/c 486.29895222 Say 487 Nos
Number of Anchor Rods 487 No's
PRRLIS PACKAGE NO 1

E2 -CONSTRUCTION OF BUS DUCT TUNNEL

LED ESTIMATE
pes of soft / hard rock including cost of all materials, machinery,
surface, ventilation, lighting,drainage, removing and hauling
dump area and all other ancillary operations etc., complete with ###

x 10.1 2 = 44868.34

x 10.1 2 8332.32

x 10.1 2 = 2014.70

Total 55215 Cum

reinforcement steel for tunnel RCC works including cleaning,


ping / welding joints wherever required, tying with 1.25 mm dia.soft ###
erials, labour,machinery, ventilation, lighting, drainage etc.,complete

120 = 758280 Kg
MT

28 days cube compressive strength not less than 20 N / sqmm )


wn size approved clean, hard,graded aggregates crushed from #
ng cost of all materials, machinery, labour, formwork, batching, #
tor cars, placing in position, levelling, vibrating, finishing, curing, ###
cillary operations etc., complete with lead upto 1 km and all lifts.
per plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio

(10.12-9.52) = 5172.55 Cum

(10.12-9.52) 960.57 Cum


(10.12-9.52) = 185.81

Total 6319.00 Cum

ck bolts with mechanical / wedge type anchorage including drilling 35 mm


steel tapered wedge, 10 mm thick plate washers and nuts, tightening bolt by
ry, labour, ventilation, lighting, drainage and all other ancillary operations
s.
PRRLIS PACKAGE NO 1

old twisted deformed steel dowel bars with one end driven into 45
in bed rock and other end provided with L-bend for embedding in
ow blocks and other appertenant works including cost of drilling and
1 : 1 proportion, driving anchor rod, cost of all materials, machinery,
km and all lifts.
PRRLIS - PACKAGE NO. 1

ABSTRACT OF VENTILATION DUCT TUNNEL


PRLIS-(Package No.1)- Construction of Stage-1 pumping station near Anjanagiri Reservoi
commissioning of Electro Mechanical works such as Vertical- Single Stage-Francis Turbine
No.s of 145 MW each including all accessories and Earth work Excavation of approach cha
including intake structure and tunnel at Stage -1 pumping station at Anjanagiri Reservoir a
District.
S.NO ITEM CODE DESCRIPTION OF ITEM

Excavation for vertical / inclined shaft in all types of soft / hard


rock including cost of all materials, machinery, labour,
shoring, strutting, scaling excavated surface, ventilation,
1 IRR-TAW-1-2 lighting,drainage, removing and hauling excavated muck
outside shaft upto specified dump area and all other ancillary
operations etc., complete with initial lead upto 1 km and all
lifts.

Providing, fabricating and placing in position reinforcement


steel for tunnel RCC works including cleaning,
straightening, cutting, bending, hooking, lapping / welding
2 IRR-TAW-5-1 joints wherever required, tying with 1.25 mm dia.soft
annealed steel wire, including cost of all materials,
labour,machinery, ventilation, lighting, drainage etc.,complete
with initial lead upto 1 km and all lifts.

Providing and laying insitu vibrated M-20 ( 28 days cube


compressive strength not less than 20 N / sqmm ) grade
cement concrete using 40 mm and down size approved
clean, hard,graded aggregates crushed from tunnel muck for
sides and arch lining including cost of all materials,
machinery, labour, formwork, batching, mixing, conveying
3 IRR-TAW-5-4 upto placing point in agitator cars, placing in position,
levelling, vibrating, finishing, curing, ventilation,
lighting,drainage and all other ancillary operations etc.,
complete with lead upto 1 km and all lifts.( Cement content
330 kg / cum for use of super plasticiser(0.4% by wt. of
cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA :
0.40 cum)
PRRLIS - PACKAGE NO. 1

CT OF VENTILATION DUCT TUNNEL


ping station near Anjanagiri Reservoir and Design, supply, erection testing and
Vertical- Single Stage-Francis Turbine Pumps and Synchronous motor sets for 8
arth work Excavation of approach channel from foreshore of Srisailam Reservoir
ping station at Anjanagiri Reservoir at Narlapur (V), Kollapur (M), Mahabubnagar

QUANTITY UNIT RATE AMOUNT

13654 Cum 2356.00 32168824.00

213 MT 58504.00 12461352.00

1777 Cum 6822.00 12122694.00

56752870.00
TOTAL 56752870.00
PRRLIS - PACKAGE NO.1

DETAILED ESTIMATE OF VENTILATION DUCT TUNNEL


PRLIS-(Package No.1)- Construction of Stage-1 pumping station near Anjanagiri Reservoir and De
and commissioning of Electro Mechanical works such as Vertical- Single Stage-Francis Turbine Pu
sets for 8 No.s of 145 MW each including all accessories and Earth work Excavation of approa
Srisailam Reservoir including intake structure and tunnel at Stage -1 pumping station at Anjana
Kollapur (M), Mahabubnagar District.

1 Excavation for vertical / inclined shaft in all types of soft / hard rock including cost
labour, shoring, strutting, scaling excavated surface, ventilation, lighting,drainage
excavated muck outside shaft upto specified dump area and all other ancillary op
IRR-TAW-1-2 initial lead upto 1 km and all lifts.

Ventelation Ducts 2X 102 x 0.905 x 8.6 2


Cum

2 Providing, fabricating and placing in position reinforcement steel for tunnel RCC w
straightening, cutting, bending, hooking, lapping / welding joints wherever require
annealed steel wire, including cost of all materials, labour,machinery, ventilation,
IRR-TAW-5-1 with initial lead upto 1 km and all lifts.

120 Kg per Cum 1777 x 120


Weight = 213 MT
3 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength
grade cement concrete using 40 mm and down size approved clean, hard,graded
tunnel muck for sides and arch lining including cost of all materials, machinery, la
mixing, conveying upto placing point in agitator cars, placing in position, levelling
ventilation, lighting,drainage and all other ancillary operations etc., complete with
IRR-TAW-5-4 ( Cement content 330 kg / cum for use of super plasticiser(0.4% by wt. of cement
of CA--50:30:20, FA : 0.40 cum)

Ventelation Ducts

2 102 x /8 x (8.62-82)
2 102 x 0.3 x 8.0
4 102 x 0.3 x 4.0
PRRLIS - PACKAGE NO.1

E OF VENTILATION DUCT TUNNEL


station near Anjanagiri Reservoir and Design, supply, erection testing
Vertical- Single Stage-Francis Turbine Pumps and Synchronous motor
s and Earth work Excavation of approach channel from foreshore of
el at Stage -1 pumping station at Anjanagiri Reservoir at Narlapur (V),

t in all types of soft / hard rock including cost of all materials, machinery,
avated surface, ventilation, lighting,drainage, removing and hauling
pecified dump area and all other ancillary operations etc., complete with

= 13654.4952
13654

position reinforcement steel for tunnel RCC works including cleaning,


ng, lapping / welding joints wherever required, tying with 1.25 mm dia.soft
all materials, labour,machinery, ventilation, lighting, drainage etc.,complete
.

= 213240

M-20 ( 28 days cube compressive strength not less than 20 N / sqmm )


and down size approved clean, hard,graded aggregates crushed from
including cost of all materials, machinery, labour, formwork, batching,
in agitator cars, placing in position, levelling, vibrating, finishing, curing,
other ancillary operations etc., complete with lead upto 1 km and all lifts.
se of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending Ratio

= 797.90
= 489.60
= 489.60
= 1777.0
Cum
PRRLIS -PACKAGE NO. 1

ABSTRACT OF EMERGENCY EXIT TUNNEL


PRLIS-(Package No.1)- Construction of Stage-1 pumping station near Anjanagiri Reser

commissioning of Electro Mechanical works such as Vertical- Single Stage-Francis Turbine P

145 MW each including all accessories and Earth work Excavation of approach channel from

structure and tunnel at Stage -1 pumping station at Anjanagiri Reservoir at Narlapur (V), Kolla
S.NO ITEM CODE DESCRIPTION OF ITEM

Excavation for vertical / inclined shaft in all types of soft / hard


rock including cost of all materials, machinery, labour, shoring,
strutting, scaling excavated surface, ventilation,
1 IRR-TAW-1-2
lighting,drainage, removing and hauling excavated muck
outside shaft upto specified dump area and all other ancillary
operations etc., complete with initial lead upto 1 km and all lifts.

Providing, fabricating and placing in position reinforcement


steel for tunnel RCC works including cleaning, straightening,
cutting, bending, hooking, lapping / welding joints wherever
2 IRR-TAW-5-1
required, tying with 1.25 mm dia.soft annealed steel wire,
including cost of all materials, labour,machinery, ventilation,
lighting, drainage etc.,complete with all leads and lifts.

Providing and laying insitu vibrated M-20 ( 28 days cube


compressive strength not less than 20 N / sqmm ) grade
cement concrete using 40 mm and down size approved clean,
hard,graded aggregates crushed from tunnel muck for tunnel
floor bed including cost of all materials, machinery, labour,
formwork, batching, mixing, conveying upto placing point in
3 IRR-TAW-5-4
agitator cars, placing in position, levelling, vibrating, finishing,
curing, ventilation, lighting,drainage and all other ancillary
operations etc., complete with lead upto 1 km and all lifts.
( Cement content 330 kg / cum for use of super
plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending
Ratio of CA--50:30:20, FA : 0.40 cum)
PRRLIS -PACKAGE NO. 1

ENCY EXIT TUNNELS


ar Anjanagiri Reservoir and Design, supply, erection testing and

age-Francis Turbine Pumps and Synchronous motor sets for 8 No.s of

proach channel from foreshore of Srisailam Reservoir including intake

at Narlapur (V), Kollapur (M), Mahabubnagar District.


QUANTITY UNIT RATE AMOUNT

13654 Cum 2356.00 32168824.00

243 MT 58504.00 14216472.00

2022 Cum 6822 13794084

Total 60179380.00
PRRLIS - PACKAGE NO. 1

DETAILED ESTIMATE OF EMERGENCY EXIT TUNNELS


PRLIS-(Package No.1)- Construction of Stage-1 pumping station near Anjanagiri Reservoir and

testing and commissioning of Electro Mechanical works such as Vertical- Single Stage-Franc

Synchronous motor sets for 8 No.s of 145 MW each including all accessories and Earth work

channel from foreshore of Srisailam Reservoir including intake structure and tunnel at Stage

Anjanagiri Reservoir at Narlapur (V), Kollapur (M), Mahabubnagar Distric

1 Excavation for vertical / inclined shaft in all types of soft / hard rock including cost of a
machinery, labour, shoring, strutting, scaling excavated surface, ventilation, lighting,dr
removing and hauling excavated muck outside shaft upto specified dump area and al
IRR-TAW-1-3
operations etc., complete with initial lead upto 1 km and all lifts.

1 X 204 x 0.905 x 8.6


Emergency exit tunnels
slope 1in2

2 Providing, fabricating and placing in position reinforcement steel for tunnel RCC work
cleaning, straightening, cutting, bending, hooking, lapping / welding joints wherever re
with 1.25 mm dia.soft annealed steel wire, including cost of all materials, labour,mach
IRR-TAW-5-1 ventilation, lighting, drainage etc.,complete with initial lead upto 1 km and all lifts.

120 Kg per Cum 2022 x 120


Weight = 243 MT

3 Providing and laying insitu vibrated M-20 ( 28 days cube compressive strength not l
sqmm ) grade cement concrete using 40 mm and down size approved clean, hard,gra
crushed from tunnel muck for floor bed including cost of all materials, machinery, labo
batching, mixing, conveying upto placing point in agitator cars, placing in position, lev
finishing, curing, ventilation, lighting,drainage and all other ancillary operations etc., c
IRR-TAW-5-4 lead upto 1 km and all lifts.( Cement content 330 kg / cum for use of super plasticiser
cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

Emergency exit tunnels

1 204 x /8 x (8.62-82)
2 204 x 0.3 x 8.0
1 204 x 0.3 x 4.0
PRRLIS - PACKAGE NO. 1

E OF EMERGENCY EXIT TUNNELS


mping station near Anjanagiri Reservoir and Design, supply, erection

works such as Vertical- Single Stage-Francis Turbine Pumps and

h including all accessories and Earth work Excavation of approach

cluding intake structure and tunnel at Stage -1 pumping station at

pur (V), Kollapur (M), Mahabubnagar District.

n all types of soft / hard rock including cost of all materials,


aling excavated surface, ventilation, lighting,drainage,
outside shaft upto specified dump area and all other ancillary
d upto 1 km and all lifts.

2
= 13654.4952
Cum 13654

sition reinforcement steel for tunnel RCC works including


g, hooking, lapping / welding joints wherever required, tying
ire, including cost of all materials, labour,machinery,
lete with initial lead upto 1 km and all lifts.

= 242640
Kg

M-20 ( 28 days cube compressive strength not less than 20 N /


0 mm and down size approved clean, hard,graded aggregates
including cost of all materials, machinery, labour, formwork,
g point in agitator cars, placing in position, levelling, vibrating,
ainage and all other ancillary operations etc., complete with
ntent 330 kg / cum for use of super plasticiser(0.4% by wt. of
of CA--50:30:20, FA : 0.40 cum)

= 797.90
= 979.20
= 244.80
= 2022.0
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

Name of Work: PRLIS- SATGE1 -CONSTRUCTION OF COMPOUND WALL


ABSTRACT ESTIMATE
ITEM
S.NO
CODE DESCRIPTION OF ITEM QUANTITY
1 BLD- Earth work excavation for foundations and depositing on bank for all 5150
CSTN-2- lifts and with an initial lead of 10m including all operational, incidental,
1 labour charges such as shoring ,sheeting, planking, strutting, etc.
complete for finished item of work including seigniorage excluding
dewatering charges etc as per SS - 20 B (APSS 308).

2 BLD- Providing and filling of earth filling including breaking clods, spreading in 728
CSTN-2- layers of 10 to 15 cm, watering,etc. complete with all leads and lifts and as
9 directed by Engineer-in-Charge

3 BLD- Providing and laying Plain Cement concrete (1:4:8) using 40 mm down 3996
CSTN-3- size approved, clean, hard, graded aggregates including manufactured
5 sand obtained from rock spoil (Spoil Bank) including cost of all materials,
machinery, labour, cleaning bed, batching, mixing, conveying and laying,
levelling, compacting, finishing, curing,etc.,complete with lead all leads and
lifts as per approved drawing and as directed by Engineer-in-charge

1635.00

Providing and constructing RR masonry using approved rubble stones obtained


from rock spoil (Spoil Bank) in cement mortar 1 : 8 proportion including cost of
all materials, machinery, labour, scaffolding, ramps, cleaning, packing mortar,
wedging stone chips, curing etc., complete with lead all leads and lifts as per
4 approved drawing and as directed by Engineer-in-charge.
5 BLD- Providing and constructing coursed rubble stone masonry using approved 338.00
CSTN-6- rubble stones obtained from rock spoil (Spoil Bank) in cement mortar 1 : 6
6 proportion including cost of all materials, machinery, labour, scaffolding,
ramps, cleaning, packing mortar, wedging stone chips, curing etc.,
complete with lead all leads and lifts as per approved drawing and as
directed by Engineer-in-charge

6 BLD- Brick masonry cm (1:6) using 2nd class Bricks traditional size 23 x 11 x 7 2319.00
CSTN-5- cms cost of all materials,labour and all operations, mixing cement mortar,
4 curing etc., complete for finished item of work with lead all leads and lifts
as per approved drawing and as directed by Engineer-in-charge

355787507.xlsx/A-C Wall 39/508


PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

7 BLD- RCC M- 20 Nominal mix (Cement:fine aggregate: coarse aggregate) 477.00


CSTN-3- corresponding to Table 9 of IS 456 using 20mm size graded machine
13 crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine
aggregate (sand) coarse aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on all materials including all
operational, incidental and labour charges such as machine mixing,
laying concrete, curing etc.,complete but excluding cost of steel and its
fabrication charges for finished item of work, but excluding centering,
shuttering.

8 BLD- Supplying, fitting and placing HYSD bar reinforcement in foundation 24.00
CSTN-4- complete as per drawings and technical specifications for Bars below 36
1 mm dia including over laps and wastage, where they are not welded

9 BLD- Plastering with CM 2 coats, 20 mm thick, base coat in CM (1:6), 15270.00


CSTN-8- 16mm thick and top coat in CM (1:4), 4mm thick with Dubara sponze
9 finishing. complete with lead all leads and lifts as per approved drawing
and as directed by Engineer-in-charge .

10 BLD- Painting to new walls with 2 coats of water proof cement paint of 16000.00
CSTN- apporved brand and shade over a base coat of approved cement primer
12-5 grade I making making 3 coats in all to give an even shade after
thourughly brushing the surface to remove all dirt and remains of loose
powdered materials, including cost and conveyance of all materials to work
site and all operational, incidental, labour charges etc. complete for
finished item of work as per SS 912

TOTAL

355787507.xlsx/A-C Wall 40/508


PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

ON OF COMPOUND WALL
E
UNIT RATE AMOUNT in Rs
Cum 128.20 660230.00

Cum 300.20 218546.00

Cum 3218.90 12862724.00

Cum 2887.59 4721210.00

Cum 2986.58 1009464.00

Cum 4469.20 10364075.00

355787507.xlsx/A-C Wall 41/508


PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

Cum 6279.70 2995417.00

MT 51319.90 1231678.00

Sqm 276.40 4220628.00

10Sqm 1455.50 2328800.00

40612772.00

355787507.xlsx/A-C Wall 42/508


PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

Name of Work: PRLIS- SATGE1 -CONSTRUCTION OF COMPOUND WALL


DETAILED ESTIMATE
1 Earth work excavation for foundations and depositing on bank for all lifts and with an initial
lead of 10m including all operational, incidental, labour charges such as shoring ,sheeting,
planking, strutting, etc. complete for finished item of work including seigniorage excluding
dewatering charges etc as per SS - 20 B (APSS 308).

Ordinary Soil-Manual Means-Upto 3 m depth


For Construction of Compound wall 2244 0.75 1.5 2524.5
734 0.75 1.5 825.75
For formation of Internal drains 1500 0.75 1.5 1687.5
For Construction of Parking sheds 100 0.75 1.5 112.5
5150
2 Earth filling (ordinary soil)
Back filling in Compound wall foundation 2244 0.4 0.6 538.56
734 0.4 0.6 176.16
100 0.3 0.45 13.5
728
3 Plain Cement concrete (1:4:8) using 40 mm
metal with concrete mixture. All works upto plinth
level.

For Construction of Compound wall 2244 1 0.75 1683


734 1 0.75 550.5
For formation of Internal drains 1500 1.5 0.75 1687.5
For Construction of Parking sheds 100 1 0.75 75
3996
4 RR Masonry in CM(1:8)

For Construction of Compound wall basement 2244 0.6 0.9 1211.76


734 0.6 0.9 396.36
For Construction of Parking sheds 100 0.45 0.6 27
1635.00
5 CRS Masonry in CM (1:6) 2nd Sort
For Construction of Compound wall Front side 375 0.6 1.5 338

6 Brick Masonry in CM (1:6) with 2nd class


Bricks traditional size
For Construction 23 x 11 x 7wall
of Compound cms 2244 0.3 2.5 1683
734 0.3 2.5 550.5
For formation of Internal drains 100 0.45 0.9 40.5
For Construction of Parking sheds 100 0.45 1 45
2319.00
7 RCC M- 20 Nominal mix (Cement:fine aggregate: coarse aggregate) corresponding to Table 9 of
IS 456 using 20mm size graded machine crushed hard granite metal (coarse aggregate) from
approved quarry including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including Seigniorage charges, sales & other
taxes on all materials including all operational, incidental and labour charges such as machine
mixing, laying concrete, curing etc.,complete but excluding cost of steel and its fabrication charges
for finished item of work, but excluding centering, shuttering.for Lintels

For foundation to columns 225 x 0.3 1.5 0.60 167.4


For plinth beams 2244 0.3 0.3 201.96
734 0.3 0.3 66.06
For columns 225 x 0.3 0.3 2.50 41.85

355787507.xlsx/D-C Wall 2/508


PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

477.00
8 Supplying, fitting and placing HYSD bar reinforcement in foundation complete as
per drawings and technical specifications for Bars below 36 mm dia including over
laps and wastage, where they are not welded

For foundation to columns 477.00 50 Kg/Cum 23850


23850.00
24.00
9 Plastering with CM 2 coats, 20 mm thick, base coat in CM (1:6), 16mm thick and top coat in
CM (1:4), 4mm thick with Dubara sponze finishing.

Compound wall 4488 2.5 11220


1468 2.5 3670
For formation of Internal drains 200 0.9 180
For Construction of Parking sheds 200 1 200
15270
10 Painting to new walls with 2 coats of water proof cement paint of apporved brand and shade over
a base coat of approved cement primer grade I making making 3 coats in all to give an even shade
after thourughly brushing the surface to remove all dirt and remains of loose powdered materials,
including cost and conveyance of all materials to work site and all operational, incidental, labour
charges etc. complete for finished item of work as per SS 912

Compound wall 4488 2.5 11220


1468 2.5 3670
Add Miscellaneous items 1110
16000

355787507.xlsx/D-C Wall 3/508


PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

UND WALL

Cum

Cum

Cum

Cum

Cum

355787507.xlsx/D-C Wall 4/508


PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

Cum

MT

Sqm

Sqm

355787507.xlsx/D-C Wall 5/508


PRLIS - PACKAGE NO.1

DETAILED ESTIMATE OF ADIT TUNNELS


PRLIS-(Package No.1)- Construction of Stage-1 pumping station near Anjanagiri Reservoir and Design, supply, erection testing and comm

Vertical- Single Stage-Francis Turbine Pumps and Synchronous motor sets for 8 No.s of 145 MW each including all accessories and Ear

foreshore of Srisailam Reservoir including intake structure and tunnel at Stage -1 pumping station at Anjanagiri Reservoir at Narlapur (V), K
Dimensions
S.No Item Description Unit Nos
L Area
ADIT TUNNEL
Excavation of adit Tunnels (D-shaped Tunnel with 8m
1 Cum 1 584.898 62.345
dia) - from PAT to approach tunnels -Adit-1

Excavation of adit Tunnels (D-shaped Tunnel with 8m


2 Cum 1 342.372 62.345
dia) - from PAT to Surge pool -Adit-2

Excavation of adit Tunnels (D-shaped Tunnel with 8m


3 Cum 1 196 62.345
dia) - from PAT to PUMP House Roof -Adit-3

Excavation of adit Tunnels (D-shaped Tunnel with 8m


4 dia) - from PAT to Delivery mains& Pumphouse bottom Cum 1 576.0 62.345
-Adit - 4
PRLIS - PACKAGE NO.1
PRLIS - PACKAGE NO.1

NNELS
pply, erection testing and commissioning of Electro Mechanical works such as

luding all accessories and Earth work Excavation of approach channel from

agiri Reservoir at Narlapur (V), Kollapur (M), Mahabubnagar District.

Quantity Rate Amount Remarks

L=465.898+59.2+59.
36465.47 1790 65273191.3
2 = 584.898 M

21345.18 1790 38207872.2 L=292.372+50 M

12219.62 1790 21873119.8 L=196 M

35909.85 1790 64278631.5 L=27X8+359.986 M

Total: 189632815.00
PRLIS - PACKAGE NO.1
Excavation for Structures- Mechanical Means
IRR- Earth work in excavation in all kinds of soils of foundation of structures as per
CCDW-1-2 technical specification, including setting out, construction of shoring and bracing,
and other deleterious matter, dressing of sides and bottom and backfilling with a
Depth upto 3 m
Unit = cum
Taking output = 240 cum
A. Materials:
Sl No Description

NIL

B. Machinery:
Sl No Description

1 Hydraulic excavator 1.0 cum


bucket capacity
Fuel/ Energy charges
Total in Rs.

C. Labour:
Sl No Description

1 work inspector
2 Mazdoor
3 crew for excavator
Total in Rs.
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Abstract
a) Material
b) Machinery
c) Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Add Lead 2Km for dumping into the dumpyard

Rate per cum

Excavation in ordnary rock without blasting for foundations of canal cross dr


IRR- and other appurtenant structures and placing the excavated stuff neatly in specifi
CCDW-1-4 area or disposing off the same as directed etc., complete with initial
lead upto 50 m and initial lift upto 3 m.
( Data adopted from MORTH)
Mechanical Means
Unit = cum
Taking output = 180 cum
A. Materials:
Sl No Description

NIL

B. Machinery:
Sl No Description

1.0 Hydraulic excavator 1.0 cum bucket


capacity
Fuel/ Energy charges
Total in Rs.

C. Labour:
Sl No Description

1 work inspector
2 Mazdoor
3 crew for excavator
Total in Rs.

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Abstract
a) Material
b) Machinery
c) Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
Add Lead 2Km for dumping into the dumpyard
Total cost for
Rate per cum

Excavation in hard rock requiring blasting including boulders


IRR- foundations of canal cross drainage and other appurtenant structures and placing
CCDW-1-5 excavated stuff neatly in specified dump area or disposing off the same as directe
complete with initial lead upto 50 m and initial lift upto 3 m.

Drilling and Blasting :


Depth of drilling per hole
Effective depth of pull
Grid spacing of holes
Area covered by one hole ( 1.50 x 1.80 )
Consider 100 cum excavation for analysis.
Area for 100 cum SR requiring blasting for 1.3 m pull ( 100 / 1.3 ) :
Nos. of holes for 77 sqm area
Depth of drilling ( 29 x 1.5 )
Rate of drilling in soft rock per hour
Time required for drilling with 2 jack hammers
Deploy 1 air compressor 8.5 cmm capacity and 2 jack hammers for 3 hours.
Quantity of Explosive at 0.20 kg / cum
Electric detonators at 1 per hole
Detonating fuse coil
Cost of drill rod
4028.00
Life of drill rod for drilling in soft rock requiring blasting
Use rate of drill rod per m drilling
Length of air hose for drilling per jack hammer
Cost of 50 m air175.00
Life of air hose
Use rate of air hose per hr
Disposal of blasted soft rock :
Deploy 6 crowbarman and 3 stone breakers for loosening blasted material.
Deploy 50 mazdoors for disposal.

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars

1 Use rate of drill rod 1.6 m length


Reconditioning charges @
2 Use rate of air hose 2 Nos.
3 Explosive small dia ( Kelvex-220 )
4 Electric detonators
5 Detonating fuse coil
6 Sundries
Total cost of Materials

B. MACHINERY:
Sl No Description

1 Air compressor 8.5 cmm ( diesel )


Fuel / Energy charges
2 Jack hammers 2 Nos.
Fuel / Energy charges
Total hire charges of Machinery

C. LABOUR:
Sl No Description

1 Crew for Air compressor


2 Crew for Jack hammer
3 work inspector
4 Blaster
5 Helper blaster
6 Crowbarman
7 Stone breaker
8 mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)


Add Lead 2Km for dumping into the dumpyard
Total cost for
Rate per cum

Modified by us
IRR- Providing and laying insitu vibrated M-25 ( 28 days cube compressive strength
CCDW-2-3 concrete using 40 mm down size approved, clean, hard, graded aggregates for fo
machinery, labour, formwork,cleaning, batching, mixing, placing in position, level
initial lead upto 50 m and all lifts.

(Cement content: 400 kg / cum with use of super plasticiser(0.4% by wt.


CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.45 cum)
Data RATE ANALYSIS
A. MATERIALS:
Sl No Particulars

1 Cement for mix


Cement for incidentals @ 3 kg / cum
2 Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
3 Fine aggregate (Un-Screened)
4 Super Plasticizer
5 Use rate of shuttering for 40 uses
Scaffolding @ of shuttering
6 Sundries
Total cost of Materials

B. MACHINERY:
Sl No Description

1 Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
2 5 hp pump ( diesel )
Fuel / Energy charges
3 Water tanker 8000 ltr
Fuel / Energy charges
4 Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

C. LABOUR:
Sl No Description

1 Crew for Concrete mixer


2 Crew for Pump
3 Crew for Water tanker
4 Crew for Needle vibrator
5 work inspector
6 Mason Class-I
7 mazdoor
for batching materials
for loading mortar pans
for laying
for conveying concrete
for cleaning/ washing/ curing
8 Labour cost for shuttering
Labour cost for scaffolding @
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)


Total cost for
Add Lead Charges for Sand @ 4Km
Add Lead Charges for Metal @ 4 Km
Rate per cum
Rate per cum

9 Modified by us
Providing and laying insitu vibrated M-30 ( 28 days cube compressive strength
IRR- concrete using 20 mm down size approved, clean, hard, graded aggregates for tr
CCDW-2- labour, formwork,scaffolding, cleaning, batching, mixing, placing in position,levell
27 initial lead upto 50 m and all lifts.

Note: If water is to be brought from other place add only lead charges @ 500 l
(Cement content: 407 kg / cum with use of super plasticiser(0.4% by wt.
CA : 0.90cum, Blending Ratio of CA--65:35, FA : 0.46 cum)
DATA: RATE ANALYSIS
A. MATERIALS:
Sl No Particulars

1 Cement for mix


Cement for incidentals @ 5 kg / cum
2 Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
3 Fine aggregate (Un-Screened)
4 Super Plasticizer
5 Use rate of shuttering for 40 uses
Scaffolding @ of shuttering
6 Sundries
Total cost of Materials

B. MACHINERY:
Sl No Description

1 Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
2 5 hp pump ( diesel )
Fuel / Energy charges
3 Needle vibrator 40 mm dia ( diesel )
Fuel / Energy charges
Total hire charges of Machinery

C. LABOUR:
Sl No Description

1 Crew for Concrete mixer


2 Crew for Pump
3 Crew for Needle vibrator
4 Mason Class-I
5 work inspector
6 mazdoor
for batching materials
for loading mortar pans
for laying
for conveying concrete
for cleaning/ washing/ curing
7 Labour cost for shuttering
Labour cost for scaffolding @
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)


Total cost for
Add Lead Charges for Sand @4Km
Add Lead Charges for Metal @4Km
Rate per cum
Rate per cum

10 Modified by us
IRR- Providing and laying insitu M- 35 ( 28 days cube compressive strength not less
CCDW-2- sqmm ) grade cement concrete using 20 mm down size
26 aggregates for wearing coat including cost of all materials, machinery, labour, f
cleaning, batching, mixing, placing in position in alternate panels, levelling, comp
finishing, curing, packing joints with asphalt mortar etc., complete
and all lifts.
Note: If water is to be brought from other place add only lead charges @ 500 l
(Cement content: 422 kg / cum with use of super plasticiser(0.4% by wt.
CA : 0.90cum, Blending Ratio of CA--65:35, FA : 0.45 cum)

DATA: Requirement of materials :


For 1 cum CC :- Coarse aggregates : 0.80 cum Blending ratio : 65
Fine aggregate : 0.45 cum Cement content : 330 kg Super plasticizer
Average output of 300/200 ltr mixer : 50 x 13 x 8 / 330
Formwork & scaffolding :
Shuttering at 0.5 sqm / cum of concrete considered for wearing coat.
Use rate of shuttering for 40 uses ( Annexure-A Item-IRR-CCDW-2-3 )
Labour for shuttering ( Annexure-B Item-IRR-CCDW-2-3 )
No scaffolding required for wearing coat concrete laying.
Labour for concreting :
Requirement of labour for concreting same as in item IRR-CCDW-2-4 with 1 mason
finishing and packing joints with asphalt mortar.

DATA: RATE ANALYSIS


A. MATERIALS:
Sl No Particulars

1 Cement for mix


Cement for incidentals @ 5 kg / cum
2 Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
3 Fine aggregate (Un-Screened)
4 Super Plasticizer
5 Use rate of shuttering
6 Sundries ( asphalt mortar etc )
Total cost of Materials

B. MACHINERY:
Sl No Description

1 Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
2 5 hp pump ( diesel )
Fuel / Energy charges
3 Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

C. LABOUR:
Sl No Description

1 Crew for Concrete mixer


2 Crew for Pump
3 Crew for Needle vibrator
4 Mason Class-I
5 work inspector
6 mazdoor
for batching materials
for loading mortar pans
for laying
for conveying concrete
for cleaning/ washing/ curing
7 Labour cost for shuttering
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C


Total cost for
Add Lead Charges for Sand @4Km
Add Lead Charges for Metal @4Km

Rate per cum

11
Providing, fabricating and placing in position reinforcement steel bars for R
IRR- cleaning, straightening, cutting, bending, hooking, lapping, welding wherever req
CCDW-2-1 1.25 mm dia soft annealed steel wire, including cost of all materials, machinery, l
complete with initial lead upto 50 and all lifts.

Lap jointing considered assuming all reinforcement below 36 mm dia.


Quantity of binding wire per tonne
Wastage of steel
Cleaning,straightening
Marking, cutting, bending & stacking
Fixing & tying with binding wire
Checking / correcting & misc.

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars

1 Rein.Steel with 5 % wastage


2 Binding wire 1.25 mm dia
3 Sundries ( chairs / spacers etc )
Total cost of Materials

B. MACHINERY:
Sl No Description

1 Nil

Total hire charges of Machinery

C. LABOUR:
Sl No Description

1 work inspector
2 Bar bender
3 mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C


Add Lead Charges for 12 kms
Total cost for
Rate per kg

12
Providing and fixing 100 mm dia perforated PVC pipes 40 cm long for Wee
IRR-CAW- including cost of all materials, labour, drilling 8 mm dia holes etc. complete with
7-23 leads and lifts.

Consider 10 Nos 100 mm dia PVC pipes 40 cm long each

RATE ANALYSIS
A. MATERIALS:
Sl.No Particulars
1 PVC pipe 100 mm dia 10 Nos
Total cost of Materials

B. MACHINERY
Sl.No Description
1 Nill

Total hire chargs of Machinery

C. LABOUR

Sl.No Particulars
1 Pipe fitter
2 Mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)


Add Lead 12 Km
Total cost for
Rate per No.

13
Shortcreting in two layers (each layer+38 mm thickness) for slabs
IRR-TAW- 100 x 100x5 mm in between the two layers including cost and conveyance of all
2-3 labour charges, all heads, lifts, centering, scaffolding, machine mixing,
laying concrete with shortcrete machine etc. complete
directed by Engineer-in-Charge

Thickness of guniting
Mortar mix proportion by weight
Water to cement ratio by weight
Unit weight of mortar 1 : 2.44:1.1 proportion by weight in kg / cum
Cement per cum of mortar
Sand per cum of mortar
Coarse Aggregate per cum of mortar
During guniting a portion of the mortar mix is wasted due to rebounding of mainly
The extend of rebound varies from 20 to 25 percent. In view of very rich mix the e
rebound is considered at 20 percent for analysis.
For 76 mm thick guniting the rate of progress will be 4 to 5 sqm per hour.
For analysis rate of progress is considered at 4.5 sqm per hour.
For shift of 8 hours the progress will be 36 sqm.
Quantity of mortar for 36 sqm with 20 % rebound ( 36 x 1.2 x 0.076 ) :
Add for filling crevices / joints in exposed rock etc @ 5%
Total quantity of mortar for 36 sqm
Quantity of cement for 36 sqm
Quantity of sand for 36 sqm
Quantity of Coarse Aggregate for 36 sqm
Deploy Guniting equipment with accessories for 8 hours.
Deploy 8.5 cmm air compressor for 8 hours.
Deploy Drilling jumbo for 4 hours during guniting of arch portion.
Use rate of materials :
Cost of grout hose 25 m @ Rs: / m
Life of grout hose
Use rate of grout hose per hour ( cost / life )
Cost of water hose 25 m @ Rs: 110.00 / m
Life of water hose
Use rate of water hose per hour ( cost / life )
Cost of guniting nozzle @ Rs: / m
Life of guniting nozzle
Use rate of guniting nozzle per hour ( cost / life )
Chain linked weld mesh/ fabric 100 x 100 x 5 mm size, @ 3kg per sqm, for 36 sqm

RATE ANALYSIS
A. MATERIALS:
Sl No Particulars

1 Cement
2 Sand (Screened)
3 Coarse aggregate 10-4.75 mm size
4 Use rate of grout hose 20 m
5 Use rate of water hose 20 m
6 Use rate of guniting nozzle
7 Welded steel wire fabric 100 x 100 x 5 m
8 Sundries
Total cost of Materials

B. MACHINERY:
Sl No Description

1 Guniting equipment
Fuel / Energy charges
2 Air compressor 8.5 cmm ( ele )
Fuel / Energy charges
3 Pump 10 hp ( ele )
Fuel / Energy charges
4 Drilling jumbo
Fuel / Energy charges
5 Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No Description

1 Crew for Guniting equipment


2 Crew for Air compressor
3 Crew for pump
4 Crew for Drilling jumbo
5 Mason Cl I
6 mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Add for Air and Water line @


Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

D.Add for contractor's profit and overheads on (A+B+C+other percentages)


Seinorage for FA
Seinorage
Lead Chargesfor CA
for 4 Km for FA /
Mansandufactured
Lead Charges for 4 1 Km for CA
Cement (including Loading
and Unloading Charges)
Total cost for
Rate per sqm
( Data adopted from MORTH)
s of foundation of structures as per drawing and
construction of shoring and bracing, removal of stumps
es and bottom and backfilling with approved material.

Unit 240.00 cum

Unit Quantity Rate Amount


in Rs. in Rs.
0.00 0.00 0.00

Unit Quantity Rate Amount


in Rs. in Rs.
hour 6.00 1706.60 10239.60

hour 6.00 893.90 5363.40


15603.00

Unit Quantity Rate Amount


in Rs. in Rs.
day 0.32 400.00 128.00
day 8.00 310.00 2480.00
hour 6.00 221.00 1326.00
3934.00
16.40
13.615% 2.20
tor's profit) 18.60

Rs 0.00
Rs 15603.00
Rs 3934.00
Rs 19537.00
n (A+B+C) 13.615% Rs: 2659.96255
240.00 cum Rs: 22196.96
240.00 43.90 10536.00
32732.96
(A+B+C+D)/240.0 Rs. 136.39
Say Rs. 136.40

ng for foundations of canal cross drainage


the excavated stuff neatly in specified dump
., complete with initial
Unit: 180.00 cum

Unit Quantity Rate Amount


in Rs. in Rs.
0.00 0.00 0.00

Unit Quantity Rate Amount


in Rs. in Rs.
hour 6.00 1706.60 10239.60

hour 6.00 893.90 5363.40


15603.00

Unit Quantity Rate Amount


in Rs. in Rs.
day 0.24 400.00 96.00
day 6.00 310.00 1860.00
hour 6.00 221.00 1326.00
3282.00

18.20
13.615% 2.50
tor's profit) 20.70

Rs 0.00
Rs 15603.00
Rs 3282.00
Rs 18885.00
n (A+B+C) 13.615% Rs: 2571.19275
180.00 42.30 7614.00
180.00 cum Rs: 29070.19
(A+B+C+D)/180.0 Rs. 161.50
Say Rs. 161.50

including boulders above 0.6 m upto 1.2 m dia. for


appurtenant structures and placing the
or disposing off the same as directed etc.,
nitial lift upto 3 m.

: 1.50 m
: 1.30 m
: 2.7 m
: 2.70 sqm
m pull ( 100 / 1.3 ) : : 77 sqm
( 77 / 2.7 ) : 29 Nos.
: 43.5 m
: 10 m
say : 2.2 hours
d 2 jack hammers for 3 hours.
: 20.00 kg
: 29 Nos.
: 70 Rm
/ Each Rs: 4028.00
g blasting : 200.00 m
( cost / life ) Rs: 20.14
: 50.00 m
/ Rm Rs: 175.00
: 800 hours
( cost / life ) Rs: 0.22

or loosening blasted material.

UNIT : 100 cum

Unit Quantity Rate Amount


in Rs. in Rs.
Rm 43.50 20.75 902.63
10% 90.26
Hour 6.00 0.23 1.39
kg 20.00 70.00 1400.00
Nos 29.00 13.00 377.00
Rm 70.00 11.00 770.00
LS 0.50 20.00 10.00
Rs: 3551.28

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 3.00 275.60 826.80
Hour 3.00 914.20 2742.60
Hour 6.00 19.80 118.80
Hour 6.00 0.00 0.00
Rs: 3688.20

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 3.00 195.90 587.70
Hour 6.00 306.20 1837.20
Day 1.00 400.00 400.00
Day 0.50 480.00 240.00
Day 0.50 370.00 185.00
Day 6.00 370.00 2220.00
Day 3.00 370.00 1110.00
Day 51.00 310.00 15810.00
Rs: 22389.90
223.90
13.615% 30.50
tor's profit) 254.40

Rs: 3551.28
Rs: 3688.20
Rs: 22389.90
Total Rs: 29629.38
n (A+B+C) 13.615% Rs: 4034.04
100.00 42.30 4230.00
100.00 cum Rs: 37893.42
(A+B+C+D)/100.0 Rs. 378.93
Say Rs. 378.90

28 days cube compressive strength not less than 15 N /sq mm ) grade cement
ean, hard, graded aggregates for foundation filling including cost of all materials,
ng, mixing, placing in position, levelling, vibrating, finishing, curing etc.,complete with

of super plasticiser(0.4% by wt. of cement),


30:20, FA : 0.45 cum)
UNIT : 15.38 cum

Unit Quantity Rate Amount


in Rs. in Rs.
kg 6152.00 5.65 34758.80
kg 46.14 5.65 260.69
cum 6.92 980.00 6782.58
cum 4.15 1045.00 4339.47
cum 2.77 710.00 1965.56
cum 6.92 392.00 2713.03
kg 16.00 95.00 1519.54
sqm 15.38 225.53 3468.64
10% 346.86
LS 0.50 20.00 10.00
Rs: 56165.18

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 8.00 53.50 428.00
Hour 8.00 81.30 650.40
Hour 0.50 10.20 5.10
Hour 0.50 81.30 40.65
Hour 1.00 402.50 402.50
Hour 1.00 307.20 307.20
Hour 8.00 7.60 60.80
Hour 8.00 20.60 164.80
Rs: 2059.45

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 8.00 204.10 1632.80
Hour 0.50 103.60 51.80
Hour 1.00 165.80 165.80
Hour 8.00 146.90 1175.20
Day 1.00 400.00 400.00
Day 1.00 415.00 415.00

Day 11.00 310.00 3410.00


Day 4.00 310.00 1240.00
Day 3.00 310.00 930.00
Day 15.38 310.00 4767.80
Day 1.00 310.00 310.00
sqm 15.38 79.80 1227.32
10% 122.73
Rs: 15848.46
1030.46
13.615% 140.30
tor's profit) 1170.80

Rs: 56165.18
Rs: 2059.45
Rs: 15848.46
Total Rs: 74073.08
n (A+B+C) 13.615% Rs: 10085.05
15.38 cum Rs: 84158.13
71.10 6.92 Rs. 492.08
71.10 13.84 Rs. 984.17
(A+B+C+D)/15.38 Rs. 85634.38
Rs. 5567.91
Say Rs. 5567.90

28 days cube compressive strength not less than 30 N / sq mm ) grade cement


ean, hard, graded aggregates for troughs including cost of all materials, machinery,
ng, mixing, placing in position,levelling, vibrating, finishing, curing etc., complete with

e add only lead charges @ 500 ltr / cum. to the data


of super plasticiser(0.4% by wt. of cement),
35, FA : 0.46 cum)
UNIT : 15.76 cum
Unit Quantity Rate Amount
in Rs. in Rs.
kg 6414.32 5.65 36240.91
kg 78.80 5.65 445.22
cum 9.22 1045.00 9634.48
cum 4.96 710.00 3524.72
cum 7.25 392.00 2841.84
kg 20.80 95.00 1976.30
sqm 70.92 225.53 15994.52
25% 3998.63
LS 0.50 20.00 10.00
Rs: 74666.63

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 8.00 53.50 428.00
Hour 8.00 81.30 650.40
Hour 0.50 10.20 5.10
Hour 0.50 81.30 40.65
Hour 8.00 7.60 60.80
Hour 8.00 20.60 164.80
Rs: 1349.75

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 8.00 204.10 1632.80
Hour 0.50 103.60 51.80
Hour 8.00 146.90 1175.20
Day 1.00 415.00 415.00
Day 1.00 400.00 400.00

Day 11.00 310.00 3410.00


Day 4.00 310.00 1240.00
Day 5.00 310.00 1550.00
Day 15.76 310.00 4885.60
Day 1.00 310.00 310.00
sqm 70.92 79.80 5659.42
25% 1414.85
Rs: 22144.67
1405.12
13.615% 191.30
tor's profit) 1596.40

Rs: 74666.63
Rs: 1349.75
Rs: 22144.67
Total Rs: 98161.05
n (A+B+C) 13.615% Rs: 13364.6265559
15.76 cum Rs: 111525.67
71.10 7.25 Rs. 515.45
71.10 14.18 Rs. 1008.48
(A+B+C+D)/15.76 Rs. 113049.60
Rs. 7173.20
Say Rs. 7173.20

cube compressive strength not less than 20 N /


down size approved, clean, hard, graded
of all materials, machinery, labour, formwork,
in alternate panels, levelling, compacting,
mortar etc., complete with initial lead upto 50 m

e add only lead charges @ 500 ltr / cum. to the data


of super plasticiser(0.4% by wt. of cement),
35, FA : 0.45 cum)

cum Blending ratio : 65 :35


t : 330 kg Super plasticizer : 1.32 kg
x 8 / 330 15.76 cum per day

dered for wearing coat.


A Item-IRR-CCDW-2-3 ) Rs: 225.53 / sqm
CCDW-2-3 ) Rs: 79.80 / sqm
rete laying.

in item IRR-CCDW-2-4 with 1 mason and 1.5 mazdoor extra for

UNIT : 15.76 cum

Unit Quantity Rate Amount


in Rs. in Rs.
kg 6650.72 5.65 37576.57
kg 78.80 5.65 445.22
cum 9.22 1045.00 9634.48
cum 4.96 710.00 3524.72
cum 7.09 392.00 2780.06
kg 20.80 95.00 1976.30
sqm 7.88 225.53 1777.17
LS 5.00 20.00 100.00
Rs: 57814.53

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 8.00 53.50 428.00
Hour 8.00 81.30 650.40
Hour 0.50 10.20 5.10
Hour 0.50 81.30 40.65
Hour 8.00 7.60 60.80
Hour 8.00 20.60 164.80
Rs: 1349.75

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 8.00 204.10 1632.80
Hour 0.50 103.60 51.80
Hour 8.00 146.90 1175.20
Day 2.00 415.00 830.00
Day 1.00 400.00 400.00

Day 11.00 310.00 3410.00


Day 4.00 310.00 1240.00
Day 4.00 310.00 1240.00
Day 15.76 310.00 4885.60
Day 2.00 310.00 620.00
sqm 7.88 79.80 628.82
Rs: 16114.22
1022.48
13.62% 139.20
tor's profit) 1161.70

Rs: 57814.53
Rs: 1349.75
Rs: 16114.22
Total Rs: 75278.50
13.615% Rs: 10249.1683904
15.76 cum Rs: 85527.67
71.10 7.09 Rs. 504.24
71.10 14.18 Rs. 1008.48
87040.40
(A+B+C+D)/15.76 Rs. 5522.87
Say Rs. 5522.90

n reinforcement steel bars for RCC works including


king, lapping, welding wherever required,tying with
ng cost of all materials, machinery, labour etc.,

ment below 36 mm dia.


: 8 kg
: 5 percent
: 1 Bar benders & 2 mazdoors
: 2 Bar benders & 4 mazdoors
: 2 Bar benders & 4 mazdoors
: 1 Bar benders & 1 mazdoors

UNIT : 1000.00 kg

Unit Quantity Rate Amount


in Rs. in Rs.
kg 1050.00 35.00 36750.00
kg 8.00 70.00 560.00
LS 3.00 20.00 60.00
Rs: 37370.00

Unit Quantity Rate Amount


in Rs. in Rs.
0.00 0.00 0.00
0.00 0.00 0.00
Rs: 0.00

Unit Quantity Rate Amount


in Rs. in Rs.
Day 1.00 400.00 400.00
Day 6.00 490.00 2940.00
Day 11.00 310.00 3410.00
Rs: 6750.00
6.80
13.615% 0.90
tor's profit) 7.70

Rs: 37370.00
Rs: 0.00
Rs: 6750.00
Total Rs: 44120.00
13.615% Rs: 6006.938
1000.00 106.90 Rs: 0
1000.00 kg Rs: 50126.94
(A+B+C+D)/1000.0 Rs. 50.13
Say/MT Rs. 50126.90

d PVC pipes 40 cm long for Weep holes


8 mm dia holes etc. complete with all

m long each

UNIT: 10 Nos.
Unit Qty Rate in Rs Amount in Rs.
Rm 10.00 175.00 1750.00
Rs. 1750.00

Unit Quantity Rate in Rs. Amount in Rs.


0.00 0.00
0.00 0.00

Rs. 0.00

Unit Qty Rate in Rs Amount in Rs.


Day 0.25 480.00 120.00
Day 0.25 310.00 77.50
Rs. 197.50
19.80
13.62% 2.70
tor's profit) 22.50

Rs. 1750.00
Rs. 0.00
Rs. 197.50
Total Rs: 1947.50
n (A+B+C) 13.615% Rs: 265.15
10.00 106.80 0.00
10.00 Nos. Rs: 2212.65
(A+B+C+D)/10.0 Rs. 221.27
Say Rs. 221.30

8 mm thickness) for slabs duly fixing chain weld wire mesh


ncluding cost and conveyance of all materials,
ffolding, machine mixing,
complete as per specification and as

: 76 mm
: 1:2.44:1.1
: 0.35
by weight in kg / cum : 2300
: 450 kg
: 0.7 cum
0.3 cum
wasted due to rebounding of mainly sand particles.
ercent. In view of very rich mix the extent of
will be 4 to 5 sqm per hour.
4.5 sqm per hour.

und ( 36 x 1.2 x 0.076 ) : : 3.2832 cum


etc @ 5% : 0.16416 cum
: 3.44 cum
: 1548 kg
: 2.41 cum
: 1.03 cum
or 8 hours.

ing of arch portion.

175.00 Rs: 4375.00


: 800 hours
Rs: 5.47
219.00 Rs: 5475.00
: 800 hours
Rs: 6.84
700.00 Rs: 700.00
: 200 hours
Rs: 3.50
mm size, @ 3kg per sqm, for 36 sqm 108.00

UNIT : 36.00 sqm

Unit Quantity Rate Amount


in Rs. in Rs.
kg 1548.00 5.65 8746.20
cum 2.41 392.00 944.72
cum 1.03 710.00 731.30
Hour 8.00 5.78 46.24
Hour 8.00 5.78 46.28
Hour 8.00 3.50 28.00
kg 108.00 165.00 17820.00
LS 2.00 20.00 40.00
Rs: 28402.74

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 8.00 110.10 880.80
Hour 8.00 0.00 0.00
Hour 8.00 170.80 1366.40
Hour 8.00 433.10 3464.80
Hour 1.00 6.70 6.70
Hour 1.00 77.00 77.00
Hour 4.00 368.40 1473.60
Hour 4.00 43.90 175.60
LS 2.00 20.00 40.00
Rs: 7484.90

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 8.00 204.10 1632.80
Hour 8.00 153.10 1224.80
Hour 1.00 77.70 77.70
Hour 4.00 163.30 653.20
Day 1.00 415.00 415.00
Day 6.00 310.00 1860.00
Rs: 5863.50
162.88
0.14 21.40
tor's profit) 174.00

Rs: 28402.74
Rs: 7484.90
Rs: 5863.50
Total Rs: 41751.14
1.00% Rs: 417.51
4.50% Rs: 1878.80
1.60% Rs: 668.02
2.50% Rs: 1043.78
Total Rs: 45759.25
n (A+B+C+other percentages) 13.62% Rs: 6230.12
2.41 40 0.00
1.03 cum @ 75 0.00
2.41 cum @ 39.80 95.918
1.03 cum @ 40.90 42.127
1.55 tonne @ 129.70 200.7756
36.00 sqm Rs: 52328.19
(A+B+C+D)/36.0 Rs: 1453.57
Say Rs. 1453.60
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

NAME OF WORK: PRLIS- SATGE1


1 IRR-DAW- Excavation for foundation in all kinds of soil including boulders upto 0.30 m
1-1 other appurtenant works and placing the excavated soil neatly in dump are
complete with initial lead upto 1 km and all lifts.

A. MATERIALS:
Sl No Particulars

B. MACHINERY:
Sl No Description

1 Shovel 0.85 cum capacity


Fuel / Energy charges
2 Dumpers 5 cum capacity 6 Nos
Fuel / Energy charges
3 Tipper 5 cum capacity 1 No
Fuel / Energy charges

C. LABOUR:
Sl No Description

1 Crew for Shovel


2 Crew for Dumper
3 Crew for Tipper
4 work inspector
5 mazdoor

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

D.Add for contractor's profit and overheads on (A+B+C)


E. Add Lead charges for 2Km
Total cost for
Rate per

2 IRR-DAW- Excavation for foundation in ordinary rock (including HDR) without blas
1-2 dia for dam, spillway, intake structure and other appurtenant works and p
area or disposing off the same as directed etc., complete with initial lead u

A. MATERIALS:

355787507.xlsx/DATA 34/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

Sl No Particulars

1 NIL

B. MACHINERY:
Sl No Description

1 Shovel 0.85 cum capacity


Fuel / Energy charges
2 Dumpers 5 cum capacity( 4 Nos)
Fuel / Energy charges
3 Tipper 5 cum capacity( 1 No)
Fuel / Energy charges

C. LABOUR:
Sl No Description

1 Crew for Shovel


2 Crew for Dumper
3 Crew for Tipper
4 work inspector
5 Crowbarman
6 mazdoor

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

D.Add for contractor's profit and overheads on (A+B+C)


E. Add Lead charges for 2Km
Total cost for
Rate per

355787507.xlsx/DATA 35/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

3 IRR-DAW-1- Excavation for foundation in hard rock (including F&F rock) requiring
3 1.2 m dia. for dam, spillway, intake structure and other appurtenant works
dump area or disposing off the same as directed etc., complete with initial

A. MATERIALS:
Sl No Description

1 Use rate of 1.5 m drill rod


Reconditioning charges @
2 Use rate of air hose 4 Nos.
3 Explosive small dia
4 Electric detonators
5 Fuse coil
6 Sundries

B. MACHINERY:
Sl No Description

1 Shovel 0.85 cum capacity


Fuel / Energy charges
2 Dumpers 5 cum capacity 4 Nos.
Fuel / Energy charges
3 Tipper 5 cum capacity 1 No
Fuel / Energy charges
4 Air compressor 8.5 cmm ( ele ) 2 Nos
Fuel / Energy charges
5 Jack hammers 4 Nos.
Fuel / Energy charges

C. LABOUR:
Sl No

1 Crew for Shovel


2 Crew for Dumper
3 Crew for Tipper
4 Crew for Air compressor
5 Crew for Jack hammer
6 work inspector
7 Blaster
8 Helper blaster
9 Crowbarman
10 Stone breaker
11 mazdoor

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

355787507.xlsx/DATA 36/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

D.Add for contractor's profit and overheads on (A+B+C)


E. Add Lead charges for 2Km
Total cost for
Rate per

4 IRR-DAW-1- Excavation for foundation in hard rock of all toughness by blasting includin
4 (a) intake structure and other appurtenant works and placing the excavated ro
levelling as directed etc., complete with initial lead upto 1 km and all lifts.

DATA:

A. MATERIALS:
Sl No

1 Use rate of drill rod 1.5 m long


Reconditioning charges @
2 Use rate of air hose 4 Nos.
3 Explosive small dia
4 Ordinary detonators
5 Electric detonators
6 Fuse coil
7 Sundries

B. MACHINERY:
Sl No

1 Shovel 0.85 cum capacity


Fuel / Energy charges
2 Dumpers 5 cum capacity 3 Nos.
Fuel / Energy charges
3 Tipper 5 cum capacity 1 No
Fuel / Energy charges
4 Angle dozer 90 hp
Fuel / Energy charges
5 Air compressor 8.5 cmm (ele) 2 Nos.
Fuel / Energy charges
6 Jack hammers 4 Nos.
Fuel / Energy charges

C. LABOUR:
Sl No

1 Crew for Shovel

355787507.xlsx/DATA 37/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

2 Crew for Dumper


3 Crew for Tipper
4 Crew for Dozer
5 Crew for Air compressor
6 Crew for Jack hammer
7 work inspector
8 Blaster
9 Helper blaster
10 Crowbarman
11 Stone breaker
12 mazdoor

labour component/unit qty

355787507.xlsx/DATA 38/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

Add contractor's profit and overhead charges


labour component/unit qty (including contractor's profit)
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

D.Add for contractor's profit and overheads on (A+B+C)


E. Add Lead charges for 2Km
Total cost for
Rate per

5 IRR-DAW-1- Excavation for foundation in hard rock of all toughness including boulde
6 blasting and controlling fly-rock by muffling arrangements for dam, spillwa
structures etc., including dressing sides and bed to required level / profile,
in dump area or other place as directed etc., complete with lead upto 1 km
( c)
DATA:
A. MATERIALS:
Sl No

1 Use rate of drill rod 1.5 m length


Reconditioning charges @
2 Use rate of 50 m air hose 4 Nos.
3 Explosive small dia.
4 Ordinary detonators
5 Electric delay detonators
6 Fuse coil
7 Sundries

B. MACHINERY:
Sl No

1 Shovel 0.85 cum capacity


Fuel / Energy charges
2 Angle dozer 90 hp
Fuel / Energy charges
3 Dumpers 5 cum capacity 3 Nos.
Fuel / Energy charges
4 Air compressor 8.5 cmm ( ele ) 2 Nos
Fuel / Energy charges
5 Jack hammers 4 Nos.
Fuel / Energy charges

C. LABOUR:
Sl No

1 Crew for Shovel

355787507.xlsx/DATA 39/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

2 Crew for Angle dozer


3 Crew for Dumper
4 Crew for Air compressor
5 Crew for Jack hammer
6 work inspector
7 Blaster
8 Helper blaster
9 Crowbarman
10 Stone breaker
11 mazdoor

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

D.Add for contractor's profit and overheads on (A+B+C)


E. Add Lead charges for 2Km
Total cost for
Rate per

355787507.xlsx/DATA 40/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

6 IRR-TAW-1-3 Excavation for tunnel by tunnelling methods in rock not requiring


materials,machinery, labour, scaling excavated surface, removing under-cu
hauling the excavated muck outside tunnel upto specified dump area and
initial lead upto 1 km and all lifts.

DATA: RATE ANALYSIS


A. MATERIALS:
Sl No Particulars

1 Small dia explosive


2 Delay detonators
3 Electric detonators
4 Detonating fuse coil
5 Use rate of drill rod 2.5 m long
Reconditioning charges @
6 Use rate of air hose
7 Use rate of water hose
8 Sundries( paint / template etc )
Total cost of Materials

B. MACHINERY:
Sl No Description

1 Drilling jumbo
Fuel / Energy charges
2 Air compressor 15 cmm ( ele )
Fuel / Energy charges
3 Jack hammer ( 4 x 6.5 hrs )
Fuel / Energy charges
4 Pusher leg
Fuel / Energy charges
5 Convey mucker
Fuel / Energy charges
6 Dumper ( 2 x 6 hrs )
Fuel / Energy charges
7 Pump 10 hp ( ele )
Fuel / Energy charges
8 Ventilation fans 20 hp
Fuel / Energy charges
9 Sundries(explosive van / magazine )
Total hire charges of Machinery

C. LABOUR:
Sl No Description

1 Crew for Drilling jumbo


2 Crew for Air compressor
3 Crew for Jack hammer
4 Crew for Convey mucker
5 Crew for Dumper
6 Crew for Pump
355787507.xlsx/DATA 41/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

7 Crew for ventilation fans


8 Surveyor
9 Foreman
10 Fitter / Mechanic
11 Blaster ( Licensed )
12 Helper blasting
13 Hammerman
14 work inspector 1 in each shift
15 Khalasi for mucking shift 4 Nos
16 mazdoor
for mucking shift 8 Nos
for other 2 shifts 1 No each shift
for cleaning & miscellaneous
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Add for Air and Water line @


Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

D.Add for contractor's profit and overheads on (A+B+C+other percentages


E. Add Lead charges for 2Km
Total cost for
Rate pecum

355787507.xlsx/DATA 42/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

7 IRR-DAW-1- Preparing foundation bed for masonry or concrete by benching, stepp


7 chiselling and disposing off the same as directed and ,complete with initial
with air and water jet etc.
A. MATERIALS:
Sl No

1 NIL

B. MACHINERY:
Sl No

1 Air compressor 8.5 cmm ( ele )


Fuel / Energy charges
2 Pump 5 hp ( ele )
Fuel / Energy charges

C. LABOUR:
Sl No

1 Crew for Air compressor


2 Crew for Pump
3 Stone breaker
4 mazdoor
5 Crowbar man

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
Rate per

8 IRR-DAW-1- Drilling 45 to 50 mm dia holes vertical or inclined upto 10 degrees to ve


9 drilling using waggon drill or any other suitable equipment including cost o
through partially set grout wherever required etc., complete.for drilling up

A. MATERIALS:
Sl No

1 Use rate of cross bit 50 mm dia


2 Use rate of 50 mm dia air hose 50 m
3 Use rate of extension rod 4.5 m

355787507.xlsx/DATA 43/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

B. MACHINERY:
Sl No

1 Waggon drill
Fuel / Energy charges
2 Air compressor 8.5 cmm ( ele )
Fuel / Energy charges
3 Sundries

C. LABOUR:
Sl No

1 Crew for Waggon drill


2 Crew for Air compressor
3 mazdoor

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
Rate per
Upto 6 m from surface
Beyond 6 m upto 12 m from surface :
Upto 6 m from surface
Add for redrilling through partially set grout / additional
extension rods / reduction in rate of drilling etc @
Beyond 6 m upto 12 m from surface
Beyond 12 m upto 18 m from surface :
For 6 m to 12 m from surface
Add for redrilling through partially set grout / additional
extension rods / reduction in rate of drilling etc @
Beyond 12 m upto 18 m from surface
Beyond 18 m upto 24 m from surface
For 12 m to 18 m from surface
Add for redrilling through partially set grout / additional
extension rods / reduction in rate of drilling etc @
Beyond 18 m upto 24 m from surface
Beyond 24 m upto 30 m from surface
For 18 m to 24 m from surface
Add for redrilling through partially set grout / additional
extension rods / reduction in rate of drilling etc @ :
Beyond 24 m upto 30 m from surface
Beyond 30 m upto 36 m from surface
For 24 m to 30 m from surface
Add for redrilling through partially set grout / additional
355787507.xlsx/DATA 44/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

extension rods / reduction in rate of drilling etc @


Beyond 30 m upto 36 m from surface
Beyond 36 m upto 42 m from surface
For 30 m to 36 m from surface
Add for redrilling through partially set grout / additional
extension rods / reduction in rate of drilling etc @
Beyond 36 m upto 42 m from surface
Beyond 42 m upto 48 m from surface
For 36 m to 42 m from surface
Add for redrilling through partially set grout / additional
extension rods / reduction in rate of drilling etc @
Beyond 42 m upto 48 m from surface

9 IRR-DAW-1- Flushing grout holes of all sizes with water and air jets alternative
10 water intake observations after flushing, cost of all materials, machinery, l

A. MATERIALS:
Sl No

1 Use rate of air hose 2 Nos x 8 hrs


2 Use rate of water hose 2 Nos x 8 hrs
3 Sundries

B. MACHINERY:
Sl No

1 Air compressor 8.5 cmm ( ele )


Fuel / Energy charges
2 Pump 5 hp ( ele )
Fuel / Energy charges
3 Sundries

C. LABOUR:
Sl No

1 Crew for Air compressor


2 Crew for Pump
3 mazdoor

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

D.Add for contractor's profit and overheads on (A+B+C)


Total cost for
Rate per
355787507.xlsx/DATA 45/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

10 Consolidation grouting with neat cement grout mix of suitable consi


IRR-DAW-1- drilled holes by stage grouting method including cost of all materials, mac
11 etc.,complete with initial lead upto 1 km and all lifts.
(a)
A. MATERIALS:
Sl No

1 Cement
2 Use rate of 50 m pressure hose
3 Sundries ( packer assembly etc )

B. MACHINERY:
Sl No

1 Grouting equipment
Fuel / Energy charges
2 Pump 5 hp ( ele )
Fuel / Energy charges

355787507.xlsx/DATA 46/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

3 Sundries

C. LABOUR:
Sl No

1 Crew for Grout pump


2 Crew for Pump
3 mazdoor ( cement handling)

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

D.Add for contractor's profit and overheads on (A+B+C)


Lead Charges for 1 Km for Cement 1.05 Tonne @ (including
Loading and Unloading Charges)
Total cost for
Rate per Cum

11 IRR-DAW-1- Providing and fixing 25 mm dia 3 m long cold twisted deformed steel dowe
13 diameter 1.50 m deep hole drilled in bed rock and other end provided with
over flow / non-over flow blocks and other appertenant works including cos
cement mortar 1 : 1 proportion, driving anchor rod, cost of all materials, m
upto 1 km and all lifts.Consider 25 anchor rods for analysis.

A. MATERIALS:
Sl No

1 Use rate of drill bit 50 mm dia


2 Use rate of air hose 50 m
3 Anchor rod 25 mm dia
4 Cement
5 Sand ( screened )/Manufactured sand

B. MACHINERY:
Sl No

1 Air compressor 8.5 cmm ( ele )


Fuel / Energy charges
2 Waggon drill
Fuel / Energy charges

C. LABOUR:
Sl No

355787507.xlsx/DATA 47/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

1 Crew for Air compressor


2 Crew for Waggon drill
3 Bar bender
4 Mason Cl- II
5 mazdoor

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

355787507.xlsx/DATA 48/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

D.Add for contractor's profit and overheads on (A+B+C)


Lead Charges for 4 Km for FA /
Manufactured sand

Lead Charges for 1Km for Cement (including Loading and


Unloading Charges)

Lead Charges for 1Km for Steel (including Loading and


Unloading Charges)
Total cost for
Rate per

12 IRR-DAW-2- Providing, fabricating and placing in position reinforcement steel for


1A wherever required, tying with 1.25 mm diameter soft annealed steel wire,
etc., complete with initial lead upto 1 km and all lifts.overlaps and wastage

A. MATERIALS:
Sl No

1 Rein.Steel with 5 % wastage


2 Binding wire 1.25 mm dia

B. MACHINERY:
Sl No

C. LABOUR:
Sl No

1 Bar bender
2 mazdoor

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
A.MATERIAL
B.MACHINERY
C. LABOUR
Total
D.Add for contractor's profit and overheads on A+B+C
Lead Charges for 1Km for Steel (including Loading and
Unloading Charges)
Total cost for

13 IRR-TAW-3-1 Providing and fixing 25 mm diameter steel rock bolts with mechanical / we
holes, providing 15 cm long 20 mm thick steel tapered wedge, 10 mm thic
355787507.xlsx/DATA
torque wrench, cost of all materials, machinery, labour, ventilation, 49/508
lighting
complete with lead upto 1 km and all lifts.
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

IRR-TAW-3-1 Providing and fixing 25 mm diameter steel rock bolts with mechanical / we
holes, providing 15 cm long 20 mm thick steel tapered wedge, 10 mm thic
torque wrench, cost of all materials, machinery, labour, ventilation, lighting
complete with lead upto 1 km and all lifts.

DATA: RATE ANALYSIS


A. MATERIALS:
Sl No Particulars

1 Rein.Steel with 5 % wastage


2 Steel plate for washers
Steel plate for wedges
3 M S Nuts for bolts
4 Use rate of drill rod
Reconditioning charges @
5 Use rate of air hose 4 Nos
6 Use rate of water hose 4 Nos
7 Sundries ( gas for cutting / heating etc )
Total cost of Materials
B. MACHINERY:
Sl No Description

1 Air compressor 15 cmm ( ele )


Fuel / Energy charges
2 Pump 10 hp ( ele )
Fuel / Energy charges
3 Jack hammer
Fuel / Energy charges
4 Pusher leg
Fuel / Energy charges
5 Drilling jumbo
Fuel / Energy charges
6 Sundries ( lathe, blower etc )
Total hire charges of Machinery
C. LABOUR:
Sl No Description

1 Crew for Air compressor


2 Crew for pump
3 Crew for Jack hammer
4 Crew for Drilling jumbo
5 Fitter
6 Gas cutter
7 Turner
8 Blacksmith
9 Khalasi ( 2 x 0.5 )
10 Hammerman
11 mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
355787507.xlsx/DATA 50/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Add for Air and Water line @


Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

D.Add for contractor's profit and overheads on (A+B+C+other


percentages)

Lead Charges for 1Km for Steel (including Loading and


Unloading Charges)
Total cost for
Rate peRm

14 IRR-DAW-2- Providing and laying insitu vibrated M-15 ( 28 days cube compressive s
5 cement concrete using 40 mm down size approved, clean, hard, graded ag
machinery, labour, formwork, centering, scaffolding, cleaning, batching, m
finishing, curing etc.,complete for plain concrete works with initial lead upt
cum with use of super plasticiser,CA : 0.90 cum, Blending Ratio of CA -- 50

A. MATERIALS:
Sl No

1 Cement for mix


Cement for incidentals @ 3 kg
2 Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
3 Fine aggregate (Un-Screened )/Mfg.Sand
4 Super plasticizer
5 Use rate of shuttering
6 Use rate of scaffolding @

B. MACHINERY:
Sl No

1 Concrete mixer 300 / 200 ltr ( ele )


Fuel / Energy charges
2 10 hp pump ( ele )
Fuel / Energy charges
3 Needle vibrator 40 mm dia ( ele )
Fuel / Energy charges

355787507.xlsx/DATA 51/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

C. LABOUR:
Sl No

1 Crew for Concrete mixer


2 Crew for Pump
3 Crew for Needle vibrator
4 Mason Class-I
5 mazdoor
for batching cement ( cement handling
for batching other materials
for loading mortar pans
for laying
for conveying concrete
for cleaning / washing / curing
6 Labour cost of shuttering
7 Labour cost of scaffolding @

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

D.Add for contractor's profit and overheads on (A+B+C)


Lead Charges for 4 Km for FA /
Manufactured sand
Lead Charges for 4Km for CA
Lead Charges for 1Km for Cement (including Loading and
Unloading Charges)
Total cost for
Rate per

15 IRR-TAW-5-4 Providing and laying insitu vibrated M-20 ( 28 days cube compressive s
cement concrete using 40 mm and down size approved clean, hard,graded
including cost of all materials, machinery, labour, formwork, batching, mix
placing in position, levelling, vibrating, finishing, curing, ventilation, lightin
complete with lead upto 1 km and all lifts.( Cement content 330 kg / cum f
cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

A. MATERIALS:
Sl No Particulars

1 Cement 43 Gr
Cement for incidentals @ 1 kg / cum
2 Fine aggregate (Un-Screened )/Mfg.sand
3 Coarse aggregate 40-20 mm

355787507.xlsx/DATA 52/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

Coarse aggregate 20-10 mm


Coarse aggregate 10-4.75 mm
4 Super plasticiser
5 Use rate of end shuttering
6 Use rate of steel gantry
7 Sundries ( placer pipe etc )
Total cost of Materials
B. MACHINERY:
Sl No Description

1 Air compressor ( Ele ) 8.5 cmm


Fuel / Energy charges @ 75 % load
2 Batching plant 2 x 1.00 cum
Fuel / Energy charges
3 Agitator car 2 cum ( 2 Nos )
Fuel / Energy charges
4 Concrete placer pump
Fuel / Energy charges
5 Needle Vibrator / Shutter vibrator
Fuel / Energy charges
6 Pump 10 hp ( Ele )
Fuel / Energy charges
7 Sundries
Total hire charges of Machinery

355787507.xlsx/DATA 53/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

C. LABOUR:
Sl No Description

1 Crew charges for Air compressor


2 Crew charges for Batching plant
3 Crew charges for Agitator car
4 Crew charges for placer pump
5 Crew charges for vibrator
6 Crew charges for Pump
7 For scaling & cleaning
Stone chiseller Cl II
mazdoor
8 For dismantling / Laying track
Surveyer
Fitter shuttering
Helper shuttering 2 x 0.5
Khalasi 6 x 0.5
mazdoor 2 x 0.5
9 For Moving / Positioning gantry
Surveyer
Foreman
Fitter shuttering
Helper shuttering 2 x 0.5
Khalasi 6 x 0.5
mazdoor 2 x 0.5
10 For loading cement to BP bin
mazdoor
11 For miscellaneous works of BP
mazdoor
12 For Erection/Dismantling bulk head
13 For Laying concrete by placer
Masom Cl I
mazdoor
work inspector
14 For wetting C.A / Curing etc
mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
D.Add
for
ABSTRACT:
contrac
A. Cost of Materials
tor's
B. Hire charges of Machinery
profit
C. Cost of Labour
and
overhe
Add
ads onfor Air and Water line @
Add
(A+B+ for Ventilation @
Add for Lighting @
C+othe
Add
r for Ele sub-station / Demand charges @
percent
ages)

355787507.xlsx/DATA 54/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

Lead Charges for 4 Km for FA /Manufactured sand


Lead Charges for 4 Km for CA
Lead Charges for 1Km for Cement
Total cost for
Rate pecum

16 IRR-CCDW- Providing and laying insitu vibrated M-15 ( 28 days cube compressive s
2-21 cement concrete using 40 mm down size approved, clean, hard, graded ag
150 to 80 mm upto 15 percent for gravity type retaining walls / piers / abu
machinery,labour, formwork, scaffolding, cleaning, batching, mixing, placin
etc.,complete with initial lead upto 50 m and all lifts. (Cement content: 260
wt. of cement),CA : 0.765cum, Blending Ratio of CA--50:30:20, FA : 0.34 cu

DATA: RATE ANALYSIS


A. MATERIALS:
Sl No Particulars

1 Cement for mix


Cement for incidentals @ 4 kg / cum
2 Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
3 Plums of size 150 to 80 mm
4 Fine aggregate (Un-Screened)
5 Super Plasticizer
Use rate of shuttering for 40 uses
6 Scaffolding @ of shuttering
Total cost of Materials
B. MACHINERY:
Sl No Description

1 Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges
2 5 hp pump ( diesel )
Fuel / Energy charges
3 Needle vibrator 60 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery
C. LABOUR:
Sl No Description

1 Crew for Concrete mixer


2 Crew for Pump
3 Crew for Needle vibrator
4 Mason Class-I
5 work inspector
6 mazdoor
for batching materials
for loading mortar pans

355787507.xlsx/DATA 55/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

for laying
for placing plums
for conveying concrete
for conveying plums
for cleaning/ washing/ curing
7 Labour for shuttering
Labour for scaffolding @
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)


Lead Charges for 4Km for FA /Mfg.sand
Lead Charges for 4 Km for CA
Lead Charges for 1 Km for Cement
Total cost for
Rate pecum

17 IRR-CCDW- Providing and laying insitu vibrated M-20 ( 28 days cube compressive s
2-25 cement concrete using 20 mm down size approved, clean, hard, graded ag
of all materials, labour, machinery,formwork, scaffolding, cleaning, batchin
vibrating,finishing, curing etc.,complete with initial lead upto 50 m and all
FA : 0.45 cum))

DATA: Requirement of materials :


DATA: RATE ANALYSIS
A. MATERIALS:
Sl No Particulars

1 Cement for mix


Cement for incidentals @ 5 kg / cum
2 Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
3 Fine aggregate (Un-Screened)/Mfg.sand
4 Super Plasticizer
5 Use rate of shuttering
Scaffolding @ of shuttering
6 Sundries
Total cost of Materials

B. MACHINERY:
Sl No Description

1 Concrete mixer 300/200 ltr ( diesel )


Fuel / Energy charges

355787507.xlsx/DATA 56/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

2 5 hp pump ( diesel )
Fuel / Energy charges
3 Needle vibrator 40 mm dia ( petrol )
Fuel / Energy charges
Total hire charges of Machinery

C. LABOUR:
Sl No Description

1 Crew for Concrete mixer


2 Crew for Pump
3 Crew for Needle vibrator
4 Mason Class-I
5 work inspector
6 mazdoor
for batching materials
for loading mortar pans
for laying
for conveying concrete
for cleaning/ washing/ curing
7 Labour cost for shuttering
Labour cost for scaffolding @
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)


Lead Charges for 4 Km for FA /Mfg.sand
Lead Charges for 4 Km for CA
Lead Charges for 1Km for Cement
Total cost for
Rate pecum

18 Shortcreting in two layers (each layer+38 mm thickness) for slabs


mm in between the two layers including cost and conveyance of all materi
IRR-TAW-2-3 scaffolding, machine mixing, laying concrete with shortcrete machine etc.
(new4 - Engineer-in-Charge
2011-12)
Data RATE ANALYSIS
A. MATERIALS:
Sl No Particulars

1 Cement
2 Sand (Screened)/Mfg.sand

355787507.xlsx/DATA 57/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

3 Coarse aggregate 10-4.75 mm size


4 Use rate of grout hose 20 m
5 Use rate of water hose 20 m
6 Use rate of guniting nozzle
7 Welded steel wire fabric 100 x 100 x 5 mm
8 Sundries
Total cost of Materials

355787507.xlsx/DATA 58/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

B. MACHINERY:
Sl No Description

1 Guniting equipment
Fuel / Energy charges
2 Air compressor 8.5 cmm ( ele )
Fuel / Energy charges
3 Pump 10 hp ( ele )
Fuel / Energy charges
4 Drilling jumbo
Fuel / Energy charges
5 Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No Description

1 Crew for Guniting equipment


2 Crew for Air compressor
3 Crew for pump
4 Crew for Drilling jumbo
5 Mason Cl I
6 mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Add for Air and Water line @


Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

D.Add for contractor's profit and overheads on (A+B+C+other percentages


Lead Charges for 4 Km for FA /Mfg.sand
Lead Charges for 4 Km for CA
Lead Charges for 1Km for Cement (including Loading and
Unloading Charges)
Total cost for
Rate pesqm

19 IRR-TAW-2-1 Dewatering tunnel by pumping out water collected by natural drai


wherever necessary, cost of all materials, machinery, labour, drainage, ligh
etc., complete.

355787507.xlsx/DATA 59/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

DATA RATE ANALYSIS


A. MATERIALS:
Sl No Particulars

1 Use rate of G.I.pipe 100 mm dia


2 Sundries
Total cost of Materials

355787507.xlsx/DATA 60/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

B. MACHINERY:
Sl No Description

1 Electric pump 20 hp
2 Fuel / Energy charges
3 Sundries(Starter/Switches ete)
Total hire charges of Machinery

C. LABOUR:
Sl No Description

1 Crew charges for Pump


2 Laying & dismantling pipe
3 mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Add for Air and Water line @


Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

D.Add for contractor's profit and overheads on (A+B+C+other percentages


Total cost for
Rate peKwhr

20 IRR-DAW-1- Excavation for foundation in hard rock of all toughness including boulders
5 and controlling fly-rock by muffling arrangements for dam, spillway, intake
including placing and levelling the excavated rock neatly in dump area or o
upto upto 1 km and all lifts.

A. MATERIALS:
Sl No

1 Use rate of drill rod 1.5 m length


Reconditioning charges @
2 Use rate of 50 m air hose 4 Nos.
3 Use rate of chain link wire mesh
4 Use rate of sand bag
5 Explosive small dia.
6 Ordinary detonators
7 Electric delay detonators
8 Fuse coil
355787507.xlsx/DATA 61/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

9 Sundries

B. MACHINERY:
Sl No

1 Shovel 0.85 cum capacity


Fuel / Energy charges
2 Angle dozer 90 hp
Fuel / Energy charges
3 Dumpers 5 cum capacity 3 Nos.
Fuel / Energy charges
4 Tipper 5 cum capacity 1 No
Fuel / Energy charges
5 Air compressor 8.5 cmm ( ele ) 2 Nos
Fuel / Energy charges
6 Jack hammers 4 Nos.
Fuel / Energy charges

355787507.xlsx/DATA 62/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

C. LABOUR:
Sl No

1 Crew for Shovel


2 Crew for Angle dozer
3 Crew for Dumper
4 Crew for Tipper
5 Crew for Air compressor
6 Crew for Jack hammer
7 work inspector
8 Blaster
9 Helper blaster
10 Crowbarman
11 Stone breaker
13 mazdoor

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

D.Add for contractor's profit and overheads on (A+B+C)


E. Add Lead charges for 2Km
Total cost for
Rate per

1 IRR-TAW-1-3 Excavation for tunnel by tunnelling methods in rock not requiring


materials,machinery, labour, scaling excavated surface, removing under-cu
hauling the excavated muck outside tunnel upto specified dump area and
initial lead upto 1 km and all lifts.

355787507.xlsx/DATA 63/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

ORK: PRLIS- SATGE1


uding boulders upto 0.30 m diameter for dam, spillway, intake structure and
ted soil neatly in dump area or disposing off the same as directed etc.,

UNIT 880 cum


Unit Quantity Rate Amount
in Rs. in Rs
0.00 0.00 0.00
0.00 0.00 0.00
Rs: 0.00

Unit Quantity Rate Amount


in Rs. in Rs
Hour 8.00 1706.60 13652.80
Hour 8.00 893.90 7151.20
Hour 48.00 580.70 27873.60
Hour 48.00 409.60 19660.80
Hour 8.00 446.70 3573.60
Hour 8.00 307.20 2457.60
Rs: 74369.60

Unit Quantity Rate Amount


in Rs. in Rs
Hour 8.00 221.00 1768.00
Hour 48.00 212.20 10185.60
Hour 8.00 165.80 1326.40
Day 1.00 400.00 400.00
Day 16.00 310.00 4960.00
Total cost of Labour Rs: 18640.00
21.20
13.615% 2.89
24.09

Rs: 0.00
Rs: 74369.60
Rs: 18640.00
Total Rs: 93009.60
A+B+C) 13.615% Rs. 12663.26
880.00 12.6 11088.00
880.00 cum Rs: 116760.86
(A+B+C+D)/880 Rs: 132.68
Say Rs: 132.70

luding HDR) without blasting including boulders above 0.3 m upto 0.6 m
appurtenant works and placing the excavated material neatly in dump
omplete with initial lead upto 1 km and all lifts.

UNIT : 520 cum

355787507.xlsx/DATA 64/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

Unit Quantity Rate Amount


in Rs. in Rs.
0.00 0.00 0.00
0.00 0.00 0.00
Total cost of Materials Rs: 0.00

Unit Quantity Rate Amount


in Rs. in Rs
Hour 8.00 1706.60 13652.80
Hour 8.00 893.90 7151.20
Hour 32.00 580.70 18582.40
Hour 32.00 409.60 13107.20
Hour 8.00 446.70 3573.60
Hour 8.00 307.20 2457.60
Rs: 58524.80

Unit Quantity Rate Amount


in Rs. in Rs
Hour 8.00 221.00 1768.00
Hour 32.00 212.20 6790.40
Hour 8.00 165.80 1326.40
Day 1.00 400.00 400.00
Day 2.50 370.00 925.00
Day 10.00 310.00 3100.00
Total cost of Labour Rs. 14309.80
27.50
13.615% 3.74
31.24

Rs: 0.00
Rs: 58524.80
Rs: 14309.80
Total Rs: 72834.60
A+B+C) 13.615% Rs. 9916.43
520.00 12.6 6552.00
520.00 cum Rs: 89303.03
(A+B+C+D)/520 Rs: 171.74
Say Rs: 171.70

355787507.xlsx/DATA 65/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

ng F&F rock) requiring blasting including boulders above 0.6 m upto


d other appurtenant works and placing the excavated material neatly in
etc., complete with initial lead upto 1 km and all lifts.

UNIT : 520.00 cum.


Unit Quantity Rate Amount
in Rs. in Rs
Rm 216.00 20.75 4482.00
10% 448.20
Hour 26.00 11.56 300.63
kg 104.00 70.00 7280.00
Nos 154.00 13.00 2002.00
Rm 320.00 11.00 3520.00
LS 5.00 20.00 100.00
Rs. 18132.83

Unit Quantity Rate Amount


in Rs. in Rs
Hour 8.00 1706.60 13652.80
Hour 8.00 893.90 7151.20
Hour 32.00 580.70 18582.40
Hour 32.00 409.60 13107.20
Hour 8.00 446.70 3573.60
Hour 8.00 307.20 2457.60
Hour 13.00 170.80 2220.40
Hour 13.00 433.10 5630.30
Hour 26.00 19.80 514.80
Hour 26.00 0.00 0.00
Rs: 66890.30

Unit Quantity Rate Amount


in Rs. in Rs
Hour 8.00 221.00 1768.00
Hour 32.00 212.20 6790.40
Hour 8.00 165.80 1326.40
Hour 13.00 153.10 1990.30
Hour 26.00 306.20 7961.20
Day 1.00 400.00 400.00
Day 1.00 480.00 480.00
Day 1.00 370.00 370.00
Day 2.50 370.00 925.00
Day 1.00 370.00 370.00
Day 10.00 310.00 3100.00
Total cost of Labour Rs. 25481.30
49.00
13.615% 6.67
55.67

355787507.xlsx/DATA 66/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

Rs: 18132.83
Rs: 66890.30
Rs: 25481.30
Total Rs: 110504.43
A+B+C) 13.615% Rs. 15045.18
520.00 12.1 6292.00
520.00 cum. Rs: 131841.61
(A+B+C+D)/520 Rs: 253.54
Say Rs: 253.50

hness by blasting including boulders above 1.2 m dia. for dam, spillway,
d placing the excavated rock neatly in dump area or stack yard including
ad upto 1 km and all lifts.

RATE ANALYSIS
UNIT
320.00 cum
Unit Quantity Rate Amount
in Rs. in Rs
Rm 310.00 27.67 8576.67
10% 857.67
Hour 48.00 11.56 555.00
kg 95.00 70.00 6650.00
Nos 10.00 7.00 70.00
Nos 333.00 13.00 4329.00
Rm 450.00 11.00 4950.00
LS 5.00 20.00 100.00
Rs: 26088.34

Unit Quantity Rate Amount


in Rs. in Rs
Hour 8.00 1706.60 13652.80
Hour 8.00 893.90 7151.20
Hour 24.00 580.70 13936.80
Hour 24.00 409.60 9830.40
Hour 4.00 446.70 1786.80
Hour 4.00 307.20 1228.80
Hour 1.00 1715.50 1715.50
Hour 1.00 625.30 625.30
Hour 24.00 170.80 4099.20
Hour 24.00 433.10 10394.40
Hour 48.00 19.80 950.40
Hour 48.00 0.00 0.00
Rs. 65371.60

Unit Quantity Rate Amount


in Rs. in Rs
Hour 8.00 221.00 1768.00

355787507.xlsx/DATA 67/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

Hour 24.00 212.20 5092.80


Hour 4.00 165.80 663.20
Hour 1.00 221.00 221.00
Hour 24.00 153.10 3674.40
Hour 48.00 306.20 14697.60
Day 1.00 400.00 400.00
Day 1.00 480.00 480.00
Day 1.00 370.00 370.00
Day 1.00 370.00 370.00
Day 2.00 370.00 740.00
Day 6.00 310.00 1860.00
Rs. 30337.00
94.80

355787507.xlsx/DATA 68/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

13.615% 12.91
107.71

Rs: 26088.34
Rs: 65371.60
Rs: 30337.00
Total Rs: 121796.94
A+B+C) 13.615% Rs. 16582.65
320.00 12.1 3872.00
320.00 cum Rs: 142251.59
(A+B+C+D)/320 Rs: 444.54
Say Rs: 444.50

ughness including boulders above 1.2 m dia. by line drilling and smooth
ngements for dam, spillway, intake structure and other appurtenant
to required level / profile, placing and levelling the excavated rock neatly
mplete with lead upto 1 km and all lifts.

UNIT :
40.00 cum
Unit Quantity Rate Amount
in Rs. in Rs
Rm 138.00 27.67 3818.00
10% 381.80
Hour 22.00 11.56 254.38
kg 10.50 70.00 735.00
Nos 2.00 7.00 14.00
Nos 76.00 23.00 1748.00
Rm 140.00 11.00 1540.00
LS 2.00 20.00 40.00
Rs. 8531.18

Unit Quantity Rate Amount


in Rs. in Rs
Hour 1.00 1706.60 1706.60
Hour 1.00 893.90 893.90
Hour 0.25 1715.50 428.88
Hour 0.25 625.30 156.33
Hour 3.00 580.70 1742.10
Hour 3.00 409.60 1228.80
Hour 11.00 170.80 1878.80
Hour 11.00 433.10 4764.10
Hour 22.00 19.80 435.60
Hour 22.00 0.00 0.00
Rs: 13235.11

Unit Quantity Rate Amount


in Rs. in Rs
Hour 1.00 221.00 221.00

355787507.xlsx/DATA 69/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

Hour 0.25 221.00 55.25


Hour 3.00 212.20 636.60
Hour 11.00 153.10 1684.10
Hour 22.00 306.20 6736.40
Day 0.50 400.00 200.00
Day 0.50 480.00 240.00
Day 0.50 370.00 185.00
Day 0.50 370.00 185.00
Day 0.50 370.00 185.00
Day 2.00 310.00 620.00
Rs. 10948.35
273.70
13.615% 37.26
310.96

Rs: 8531.18
Rs: 13235.11
Rs: 10948.35
Total Rs: 32714.64
A+B+C) 13.615% Rs. 4454.1
40.00 12.1 484.00
40.00 cum Rs: 37652.74
(A+B+C+D)/40 Rs: 941.32
Say Rs: 941.30

355787507.xlsx/DATA 70/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

ds in rock not requiring supports including cost of all


surface, removing under-cuts, ventilation,lighting, drainage, removing and
specified dump area and all other ancillary operations etc., complete with

UNIT : 48.60 cum

Unit Quantity Rate Amount


in Rs. in Rs.
kg 54.00 70.00 3780.00
Nos 68.00 23.00 1564.00
Nos 10.00 13.00 130.00
Rm 50.00 11.00 550.00
Rm 150.00 42.67 6400.00
10% 640.00
Hour 24.00 5.78 138.75
Hour 24.00 5.78 138.75
LS 2.00 20.00 40.00
Rs: 13381.50

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 10.00 368.40 3684.00
Hour 10.00 43.90 439.00
Hour 6.50 138.80 902.20
Hour 6.50 962.30 6254.95
Hour 26.00 19.80 514.80
Hour 26.00 0.00 0.00
Hour 26.00 12.70 330.20
Hour 26.00 0.00 0.00
Hour 6.00 822.80 4936.80
Hour 6.00 267.90 1607.40
Hour 12.00 580.70 6968.40
Hour 12.00 409.60 4915.20
Hour 6.50 6.70 43.55
Hour 6.50 77.00 500.50
Hour 2.00 11.50 23.00
Hour 2.00 154.00 308.00
LS 2.00 20.00 40.00
Rs: 31468.00

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 10.00 163.30 1633.00
Hour 6.50 163.30 1061.45
Hour 26.00 306.20 7961.20
Hour 6.00 163.30 979.80
Hour 12.00 212.20 2546.40
Hour 6.50 77.70 505.05
355787507.xlsx/DATA 71/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

Hour 2.00 26.80 53.60


Day 0.50 590.00 295.00
Day 1.00 480.00 480.00
Day 2.00 415.00 830.00
Day 1.00 480.00 480.00
Day 2.00 370.00 740.00
Day 2.00 370.00 740.00
Day 3.00 400.00 1200.00
Day 4.00 415.00 1660.00

Day 8.00 310.00 2480.00


Day 2.00 310.00 620.00
Day 2.00 310.00 620.00
Rs: 24885.50
512.00
13.62% 69.71
581.71

Rs: 13381.50
Rs: 31468.00
Rs: 24885.50
Total Rs: 69735.00
1.00% Rs: 697.35
4.50% Rs: 3138.08
1.60% Rs: 1115.76
2.50% Rs: 1743.38
Total Rs: 76429.56
A+B+C+other percentages) 13.615% Rs: 10405.88
48.60 12.1 588.06
48.60 cum Rs: 87423.50
(A+B+C+D)/48.60 Rs: 1798.84
Say Rs: 1798.80

355787507.xlsx/DATA 72/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

ncrete by benching, stepping, removing all loose material by wedging /


and ,complete with initial lead upto 50 m and all lifts.cleaning the surface

UNIT: 100.00 sqm


Unit Quantity Rate Amount
in Rs. in Rs
0.00 0.00 0.00
0.00 0.00 0.00
Total cost of Materials Rs. 0.00

Unit Quantity Rate Amount


in Rs. in Rs
Hour 1.00 170.80 170.80
Hour 1.00 433.10 433.10
Hour 1.00 3.00 3.00
Hour 1.00 38.50 38.50
Rs. 645.40

Unit Quantity Rate Amount


in Rs. in Rs
Hour 1.00 153.10 153.10
Hour 1.00 77.70 77.70
Day 2.00 370.00 740.00
Day 2.50 310.00 775.00
Day 2.00 370.00 740.00
Rs: 2485.80
24.90
13.615% 3.39
28.29

Rs: 0.00
Rs: 645.40
Rs: 2485.80
Total Rs: 3131.20
A+B+C) 13.615% Rs. 426.31
100.00 sqm Rs: 3557.51
(A+B+C+D)/100 Rs: 35.60
Say Rs: 35.60

ned upto 10 degrees to vertical in rock /masonry/ concrete by percussion


equipment including cost of all materials,machinery, labour, redrilling
c., complete.for drilling upto 6 m depth from surface.

UNIT: 96.00 Rm
Unit Quantity Rate Amount
in Rs. in Rs
Rm 96.00 62.50 6000.00
Hour 8.00 18.63 149.00
Rm 96.00 6.68 641.09
Rs. 6790.09

355787507.xlsx/DATA 73/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

Unit Quantity Rate Amount


in Rs. in Rs
Hour 8.00 188.50 1508.00
Hour 8.00 0.00 0.00
Hour 8.00 170.80 1366.40
Hour 8.00 433.10 3464.80
LS 2.00 20.00 40.00
Rs: 6379.20

Unit Quantity Rate Amount


in Rs. in Rs
Hour 8.00 265.20 2121.60
Hour 8.00 153.10 1224.80
Day 2.00 310.00 620.00
Rs: 3966.40
41.30
13.615% 5.62
46.92

Rs: 6790.09
Rs: 6379.20
Rs: 3966.40
Total Rs: 17135.69
A+B+C) 13.615% Rs. 2333.02
96.00 Rm Rs: 19468.71
(A+B+C+D)/96 Rs: 202.80
202.80

Rate per Rm Rs: 202.80

10% Rs: 20.28


Rate / Rm Rs: 223.10

Rate per Rm Rs: 223.10

10% Rs: 22.31


Rate / Rm Rs: 245.40
:
Rate per Rm Rs: 245.40

10% Rs: 24.54


Rate / Rm Rs: 269.90
:
Rate per Rm Rs: 269.90

10% Rs 26.99
Rate / Rm Rs: 296.90
:
Rate per Rm Rs: 296.90

355787507.xlsx/DATA 74/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

10% Rs: 29.69


Rate / Rm Rs: 326.60
:
Rate per Rm Rs: 326.60

10% Rs: 32.66


Rate / Rm Rs: 359.30

Rate per Rm Rs: 359.30

10% Rs: 35.93


Rate per Rm Rs: 395.20
Say Rs: 395.20

and air jets alternatively for an average period of 30 minutes including


all materials, machinery, labour etc., complete.

UNIT : 192.00 Rm.


Unit Quantity Rate Amount
in Rs. in Rs
Hour 16.00 11.56 184.96
Hour 16.00 11.56 184.96
LS 2.00 20.00 40.00
Rs: 409.92

Unit Quantity Rate Amount


in Rs. in Rs
Hour 8.00 170.80 1366.40
Hour 8.00 433.10 3464.80
Hour 8.00 3.00 24.00
Hour 8.00 38.50 308.00
LS 2.00 20.00 40.00
Rs: 5203.20

Unit Quantity Rate Amount


in Rs. in Rs
Hour 8.00 153.10 1224.80
Hour 8.00 77.70 621.60
Day 4.00 310.00 1240.00
Rs: 3086.40
16.10
13.615% 2.19
18.29

Rs: 409.92
Rs: 5203.20
Rs: 3086.40
Total Rs: 8699.52
A+B+C) 13.615% Rs. 1184.44
192.00 Rm. Rs: 9883.96
(A+B+C+D)/192 Rs: 51.50
355787507.xlsx/DATA 75/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

Say Rs: 51.50

rout mix of suitable consistency under specified pressure as directed in


cost of all materials, machinery, labour, redrilling if necessary
lifts.

UNIT : 1.05 tonne


Unit Quantity Rate Amount
in Rs. in Rs
tonne 1.05 5650.00 5932.50
Hour 8.00 11.56 92.48
LS 3.00 20.00 60.00
Rs: 6084.98

Unit Quantity Rate Amount


in Rs. in Rs
Hour 8.00 24.90 199.20
Hour 8.00 38.50 308.00
Hour 2.00 3.00 6.00
Hour 2.00 38.50 77.00

355787507.xlsx/DATA 76/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

LS 2.00 20.00 40.00


Rs: 630.20

Unit Quantity Rate Amount


in Rs. in Rs
Hour 8.00 244.90 1959.20
Hour 2.00 77.70 155.40
Day 2.00 310.00 620.00
Rs: 2734.60
2604.40
13.615% 354.60
2959.00

Rs: 6084.98
Rs: 630.20
Rs: 2734.60
Total Rs: 9449.78
A+B+C) 13.615% Rs. 1286.59

1.05 129.70 Rs/Tonne 136.185


1.05 tonne Rs: 10872.56
(A+B+C+D)/1.05 Rs: 10354.81
Say Rs: 10354.80

isted deformed steel dowel bars with one end driven into 45 to 50 mm
nd other end provided with L-bend for embedding in concrete / masonry of
tenant works including cost of drilling and cleaning hole, filling hole with
od, cost of all materials, machinery, labour etc., complete with initial lead
or analysis.

UNIT: 25 Nos.
Unit Quantity Rate Amount
in Rs. in Rs
Rm 37.50 62.50 2343.75
Hour 4.00 18.63 74.52
kg 303.22 35.00 10612.70
kg 75.00 5.65 423.75
cum 0.05 392.00 19.60
Rs: 13474.32

Unit Quantity Rate Amount


in Rs. in Rs
Hour 4.00 170.80 683.20
Hour 4.00 433.10 1732.40
Hour 4.00 188.50 754.00
Hour 4.00 0.00 0.00
Rs: 3169.60

Unit Quantity Rate Amount

355787507.xlsx/DATA 77/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

in Rs. in Rs
Hour 4.00 153.10 612.40
Hour 4.00 265.20 1060.80
Day 0.50 490.00 245.00
Day 0.50 370.00 185.00
Day 1.00 310.00 310.00
Rs: 2413.20
89.70 96.528
13.615% 12.21
101.91

355787507.xlsx/DATA 78/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

Rs: 13474.32
Rs: 3169.60
Rs: 2413.20
Total Rs: 19057.12
A+B+C) 13.615% Rs. 2594.63

0.05 cum @ 39.80 1.99

0.08 tonne @ 129.70 9.73

0.30 tonne @ 151.50 45.94


25.00 Nos. Rs: 21709.41
(A+B+C+D)/25 Rs: 868.38
Say Rs: 868.40

einforcement steel for RCC,below 36 dia rods overlaps and wastages


soft annealed steel wire, including cost of all materials, machinery, labour
lifts.overlaps and wastage as per NHAI-data

UNIT : 1.00 tonne


Unit Quantity Rate Amount
in Rs. in Rs
tonne 1.05 35000.00 36750.00
kg 9.00 70.00 630.00
Rs: 37380.00

Unit Quantity Rate Amount


in Rs. in Rs
Rs: 0.00

Unit Quantity Rate Amount


in Rs. in Rs
Day 2.00 490.00 980.00
Day 6.84 310.00 2120.40
3100.40
3100.40
13.615% 422.10
3522.50
Rs: 37380.00
Rs: 0.00
Rs: 3100.40
Rs: 40480.40
13.615% Rs: 5511.40646

151.50 Rs/Tonne Rs: 159.075


1.00 tonne Rs: 46150.88
Say Rs: 46150.90

bolts with mechanical / wedge type anchorage including drilling 35 mm dia


apered wedge, 10 mm thick plate washers and nuts, tightening bolt by
355787507.xlsx/DATA
labour, ventilation, lighting, drainage and all other ancillary operations etc., 79/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

20.00 Rm

Unit Quantity Rate Amount


in Rs. in Rs.
kg 86.91 35.00 3041.98
kg 65.94 39.50 2604.63
kg 6.18 39.50 244.18
kg 4.00 90.00 360.00
Rm 20.00 42.67 853.33
10% 85.33
Hour 6.00 5.78 34.69
Hour 6.00 5.78 34.69
LS 5.00 20.00 100.00
Rs: 7358.84

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 1.50 138.80 208.20
Hour 1.50 962.30 1443.45
Hour 1.00 6.70 6.70
Hour 1.00 77.00 77.00
Hour 6.00 19.80 118.80
Hour 6.00 0.00 0.00
Hour 6.00 12.70 76.20
Hour 6.00 0.00 0.00
Hour 4.00 368.40 1473.60
Hour 4.00 43.90 175.60
LS 5.00 20.00 100.00
Rs: 3679.55

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 1.50 163.30 244.95
Hour 1.00 77.70 77.70
Hour 6.00 306.20 1837.20
Hour 4.00 163.30 653.20
Day 0.50 415.00 207.50
Day 1.00 415.00 415.00
Day 1.00 480.00 480.00
Day 1.00 415.00 415.00
Day 1.00 415.00 415.00
Day 0.50 370.00 185.00
Day 2.00 310.00 620.00
Rs: 5550.55
277.5
13.615% 37.78
315.28
355787507.xlsx/DATA 80/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

Rs: 7358.84
Rs: 3679.55
Rs: 5550.55
Total Rs: 16588.94
1.00% Rs: 165.89
4.50% Rs: 746.50
1.60% Rs: 265.42
2.50% Rs: 414.72
Total Rs: 18181.47

13.615% Rs: 2475.41

0.16 tonne @ 151.50 24.09


20.00 Rm Rs: 20680.97
(A+B+C+D)/20.0 Rs: 1034.05
Say Rs: 1034.00

8 days cube compressive strength not less than 15 N / sq mm ) grade


ed, clean, hard, graded aggregates including cost of all materials,
ing, cleaning, batching, mixing, placing in position, levelling, vibrating,
works with initial lead upto 1 km and all lifts. ( Cement content : 260 kg /
Blending Ratio of CA -- 50:30:20, FA : 0.40 cum)

UNIT : 14.00 cum


Unit Quantity Rate Amount
in Rs. in Rs
kg 3640.00 5.65 20566.00
kg 42.00 5.65 237.30
cum 6.3 980.00 6174.00
cum 3.78 1045.00 3950.10
cum 2.52 710.00 1789.20
cum 5.6 392.00 2195.20
kg 14.56 95.00 1383.20
sqm 14.00 217.39 3043.46
15% 456.52
Rs: 39794.98

Unit Quantity Rate Amount


in Rs. in Rs
Hour 8.0 51.70 413.60
Hour 8.0 38.50 308.00
Hour 1.0 6.70 6.70
Hour 1.0 77.00 77.00
Hour 8.0 8.00 64.00
Hour 8.0 7.70 61.60
Rs: 930.90

355787507.xlsx/DATA 81/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

Unit Quantity Rate Amount


in Rs. in Rs
Hour 8.00 204.10 1632.80
Hour 1.00 77.70 77.70
Hour 8.00 146.90 1175.20
Day 1.00 415.00 415.00

Day 2.00 310.00 620.00


Day 9.00 310.00 2790.00
Day 4.00 310.00 1240.00
Day 3.00 310.00 930.00
Day 14.00 310.00 4340.00
Day 1.00 310.00 310.00
sqm 14.00 79.80 1117.20
15% 167.58
Rs: 14815.48
1058.20
13.615% 144.07
1202.27

Rs: 39794.98
Rs: 930.90
Rs: 14815.48
Total Rs: 55541.36
A+B+C) 13.615% Rs. 7561.95602785

5.60 cum @ 39.80 222.88


12.60 cum @ 40.90 515.34

3.68 tonne @ 129.70 477.56


14.00 cum Rs: 64319.10
(A+B+C+D)/14 Rs: 4594.22
Say Rs: 4594.20

8 days cube compressive strength not less than 20 N / sqmm ) grade


proved clean, hard,graded aggregates crushed from muck for sides lining
, formwork, batching, mixing, conveying upto placing point in agitator cars,
curing, ventilation, lighting,drainage and all other ancillary operations etc.,
ent content 330 kg / cum for use of super plasticiser(0.4% by wt. of
30:20, FA : 0.40 cum)

UNIT : 48.00 cum


Unit Quantity Rate Amount
in Rs. in Rs.
kg 15840.00 5.65 89496.00
kg 48.00 5.65 271.20
cum 19.20 392.00 7526.40
cum 21.60 980.00 21168.00

355787507.xlsx/DATA 82/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

cum 12.96 1045.00 13543.20


cum 8.64 710.00 6134.40
kg 63.36 95.00 6019.20
sqm 6.00 155.53 933.17
sqm 100.00 79.80 7980.00
LS 5.00 20.00 100.00
Rs: 153171.57

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 16.00 170.80 2732.80
Hour 12.00 433.10 5197.20
Hour 12.00 405.40 4864.80
Hour 12.00 346.40 4156.80
Hour 32.00 758.40 24268.80
Hour 32.00 893.90 28604.80
Hour 16.00 102.00 1632.00
Hour 16.00 2.00 32.00
Hour 8.00 8.00 64.00
Hour 8.00 7.70 61.60
Hour 8.00 6.70 53.60
Hour 8.00 77.00 616.00
LS 5.00 20.00 100.00
Rs: 72384.40

355787507.xlsx/DATA 83/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 16.00 153.10 2449.60
Hour 16.00 318.20 5091.20
Hour 32.00 265.20 8486.40
Hour 16.00 16.80 268.80
Hour 8.00 146.90 1175.20
Hour 8.00 77.70 621.60

Day 0.50 370.00 185.00


Day 1.00 310.00 310.00

Day 0.50 590.00 295.00


Day 0.50 370.00 185.00
Day 1.00 370.00 370.00
Day 3.00 415.00 1245.00
Day 1.00 310.00 310.00

Day 0.50 590.00 295.00


Day 0.50 480.00 240.00
Day 0.50 370.00 185.00
Day 1.00 370.00 370.00
Day 3.00 415.00 1245.00
Day 1.00 310.00 310.00

Day 5.00 310.00 1550.00

Day 2.00 310.00 620.00


sqm 6.00 79.80 478.80

Day 3.00 415.00 1245.00


Day 9.00 310.00 2790.00
Day 3.00 400.00 1200.00

Day 3.00 310.00 930.00


Rs: 32451.60
676.10
13.615% 92.05
768.15

Rs: 153171.57
Rs: 72384.40
Rs: 32451.60
Total Rs: 258007.57
1.00% Rs: 2580.08
4.50% Rs: 11610.34
1.60% Rs: 4128.12
2.50% Rs: 6450.19
Total Rs: 282776.30
13.615% Rs: 38499.99

355787507.xlsx/DATA 84/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

19.20 cum @ 39.80 764.16


43.20 cum @ 40.90 1766.88
15.89 tonne @ 129.70 2060.6736
48.00 cum Rs: 325868.00
(A+B+C+D)/48.0 Rs: 6788.92
Say Rs: 6788.90

8 days cube compressive strength not less than 15 N / sq mm ) grade


ed, clean, hard, graded aggregates with placing and sinking plums of size
etaining walls / piers / abutments etc., including cost of all materials,
g, batching, mixing, placing in position, levelling, vibrating,finishing, curing
lifts. (Cement content: 260 kg / cum with use of super plasticiser(0.4% by
CA--50:30:20, FA : 0.34 cum, plums of size 150 to 80 mm : 0.25cum )

UNIT : 18.09 cum

Unit Quantity Rate Amount


in Rs. in Rs.
kg 4703.40 5.65 26574.21
kg 72.36 5.65 408.83
cum 6.92 980.00 6781.04
cum 4.15 1045.00 4338.48
cum 2.77 710.00 1965.12
cum 4.52 470.00 2125.58
cum 6.15 392.00 2411.04
kg 18.81 95.00 1787.29
sqm 49.75 225.53 11219.50
30% 3365.85
Rs: 60976.93

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 8.00 53.50 428.00
Hour 8.00 81.30 650.40
Hour 0.50 10.20 5.10
Hour 0.50 81.30 40.65
Hour 8.00 8.20 65.60
Hour 8.00 30.80 246.40
Rs: 1436.15

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 8.00 204.10 1632.80
Hour 0.50 103.60 51.80
Hour 8.00 146.90 1175.20
Day 1.00 415.00 415.00
Day 1.00 400.00 400.00

Day 11.00 310.00 3410.00


Day 4.00 310.00 1240.00

355787507.xlsx/DATA 85/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

Day 5.00 310.00 1550.00


Day 2.00 310.00 620.00
Day 15.38 310.00 4767.80
Day 2.00 310.00 620.00
Day 1.00 310.00 310.00
sqm 49.75 79.80 3969.85
30% 1190.96
Rs: 21353.41
1180.40
13.615% 160.71
1341.11

Rs: 60976.93
Rs: 1436.15
Rs: 21353.41
Total Rs: 83766.49
13.615% Rs: 11404.81
6.15 cum @ 71.10 437.30766
18.36 cum @ 71.10 1305.491985
4.78 tonne @ 106.80 0
18.09 cum Rs: 96914.10
(A+B+C+D)/18.09 Rs. 5357.30
Say Rs: 5357.30

8 days cube compressive strength not less than 20 N / sq mm ) grade


ed, clean, hard, graded aggregates for columns and beams including cost
affolding, cleaning, batching, mixing, placing in position, levelling,
ial lead upto 50 m and all lifts.CA : 0.80cum, Blending Ratio of CA--65:35,

UNIT : 15.76 cum

Unit Quantity Rate Amount


in Rs. in Rs.
kg 5200.80 5.65 29384.52
kg 78.80 5.65 445.22
cum 8.20 1045.00 8563.98
cum 4.41 710.00 3133.09
cum 7.09 392.00 2780.06
kg 20.80 95.00 1976.30
sqm 78.80 225.53 17771.69
50% 8885.84
LS 1.00 20.00 20.00
Rs: 72960.71

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 8.00 53.50 428.00
Hour 8.00 81.30 650.40

355787507.xlsx/DATA 86/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

Hour 0.50 10.20 5.10


Hour 0.50 81.30 40.65
Hour 8.00 7.60 60.80
Hour 8.00 20.60 164.80
Rs: 1349.75

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 8.00 204.10 1632.80
Hour 0.50 103.60 51.80
Hour 8.00 146.90 1175.20
Day 1.00 415.00 415.00
Day 1.00 400.00 400.00

Day 11.00 310.00 3410.00


Day 4.00 310.00 1240.00
Day 3.00 310.00 930.00
Day 15.76 310.00 4885.60
Day 1.00 310.00 310.00
sqm 78.80 79.80 6288.24
50% 3144.12
Rs: 23882.76
1515.40
13.615% 206.32
1721.72

Rs: 72960.71
Rs: 1349.75
Rs: 23882.76
Total Rs: 98193.22
13.615% Rs: 13369.00660347
7.09 cum @ 71.10 504.2412
12.61 cum @ 71.10 896.4288
5.28 tonne @ 106.80 0
15.76 cum Rs: 112962.89
(A+B+C+D)/15.76 Rs. 7167.70
Say Rs: 7167.70

mm thickness) for slabs duly fixing chain weld wire mesh 100 x 100x5
d conveyance of all materials, labour charges, all heads, lifts, centering,
h shortcrete machine etc. complete as per specification and as directed by

UNIT : 36.00 sqm

Unit Quantity Rate Amount


in Rs. in Rs.
kg 1548.00 5.65 8746.20
cum 2.41 392.00 944.72

355787507.xlsx/DATA 87/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

cum 1.03 710.00 731.30


Hour 8.00 5.78 46.25
Hour 8.00 5.78 46.25
Hour 8.00 3.50 28.00
kg 108.00 165.00 17820.00
LS 2.00 20.00 40.00
Rs: 28402.72

355787507.xlsx/DATA 88/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 8.00 110.10 880.80
Hour 8.00 0.00 0.00
Hour 8.00 170.80 1366.40
Hour 8.00 433.10 3464.80
Hour 1.00 6.70 6.70
Hour 1.00 77.00 77.00
Hour 4.00 368.40 1473.60
Hour 4.00 43.90 175.60
LS 2.00 20.00 40.00
Rs: 7484.90

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 8.00 204.10 1632.80
Hour 8.00 153.10 1224.80
Hour 1.00 77.70 77.70
Hour 4.00 163.30 653.20
Day 1.00 415.00 415.00
Day 6.00 310.00 1860.00
Rs: 5863.50
162.90
13.615% 22.20
185.10

Rs: 28402.72
Rs: 7484.90
Rs: 5863.50
Total Rs: 41751.12
1.00% Rs: 417.51
4.50% Rs: 1878.80
1.60% Rs: 668.02
2.50% Rs: 1043.78
Total Rs: 45759.23
A+B+C+other percentages) 13.615% Rs: 6230.12
2.41 cum @ 39.80 95.918
1.03 cum @ 40.90 42.127

1.55 tonne @ 129.70 200.78


36.00 sqm Rs: 52328.17
(A+B+C+D)/36.0 Rs: 1453.57
Say Rs: 1453.60

ollected by natural drainage inside tunnel including providing sump


nery, labour, drainage, lighting,ventilation and all other ancillary operations

355787507.xlsx/DATA 89/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

UNIT : 15.00 Kwhr

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 1.00 4.67 4.67
LS 0.10 20.00 2.00
Rs: 6.67

355787507.xlsx/DATA 90/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 1.00 12.30 12.30
Hour 1.00 154.00 154.00
LS 0.10 20.00 2.00
Rs: 168.30

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 1.00 77.70 77.70
LS 0.05 20.00 1.00
Day 0.10 310.00 31.00
Rs: 109.70
7.30
13.615% 0.99
8.29

Rs: 6.67
Rs: 168.30
Rs: 109.70
Total Rs: 284.67
1.00% Rs: 2.85
4.50% Rs: 12.81
1.60% Rs: 4.55
2.50% Rs: 7.12
Total Rs: 311.99
A+B+C+other percentages) 13.615% Rs: 42.48
15.00 Kwhr Rs: 354.47
(A+B+C+D)/15.0 Rs: 23.60
Say Rs: 23.60

hness including boulders above 1.2 m dia. by controlled blasting method


ts for dam, spillway, intake structure and other appurtenant structures etc.,
ck neatly in dump area or other place as directed etc., complete with lead

UNIT 480.00 cum


Unit Quantity Rate Amount
in Rs. in Rs
Rm 464.00 27.67 12837.33
10% 1283.73
Hour 70.00 11.56 809.38
sqm 715.00 67.38 48173.13
Nos 580.00 81.70 47386.00
kg 149.00 70.00 10430.00
Nos 23.00 7.00 161.00
Nos 500.00 23.00 11500.00
Rm 700.00 11.00 7700.00
355787507.xlsx/DATA 91/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

LS 10.00 20.00 200.00


Rs: 140480.57

Unit Quantity Rate Amount


in Rs. in Rs
Hour 12.00 1706.60 20479.20
Hour 12.00 893.90 10726.80
Hour 2.00 1715.50 3431.00
Hour 2.00 625.30 1250.60
Hour 36.00 580.70 20905.20
Hour 36.00 409.60 14745.60
Hour 4.00 446.70 1786.80
Hour 4.00 307.20 1228.80
Hour 35.00 170.80 5978.00
Hour 35.00 433.10 15158.50
Hour 70.00 19.80 1386.00
Hour 70.00 0.00 0.00
Rs: 97076.50

355787507.xlsx/DATA 92/508
PRLIS Stage-1 P.S DPR Volume-3C, Part-IV

Unit Quantity Rate Amount


in Rs. in Rs
Hour 12.00 221.00 2652.00
Hour 2.00 221.00 442.00
Hour 36.00 212.20 7639.20
Hour 4.00 165.80 663.20
Hour 35.00 153.10 5358.50
Hour 70.00 306.20 21434.00
Day 4.50 400.00 1800.00
Day 1.50 480.00 720.00
Day 3.00 370.00 1110.00
Day 2.50 370.00 925.00
Day 2.50 370.00 925.00
Day 20.00 310.00 6200.00
Total cost of Labour Rs. 49868.90
103.90
13.615% 14.15
118.05

Rs: 140480.57
Rs: 97076.50
Rs: 49868.90
Total Rs: 287425.97
A+B+C) 13.615% Rs. 39133.05
480.00 12.1 5808.00
480.00 cum Rs: 332367.02
(A+B+C+D)/480 Rs: 692.43
Say Rs: 692.40

ds in rock not requiring supports including cost of all


surface, removing under-cuts, ventilation,lighting, drainage, removing and
specified dump area and all other ancillary operations etc., complete with

355787507.xlsx/DATA 93/508
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

NAME OF WORK :- ESTIMATE OF PUMPING STATION CIVIL COMPONENT WORKS OF STAGE


MAHABUBNAGAR DIS

DATA

1 IRR-TAW-1-1 Excavation for adit by tunnelling methods in all types of rock including co
drainage, removing and hauling the excavated muck outside adit upto specifi
and all lifts.

DATA:
A. MATERIALS:
Sl No

1
2
3
4
5

6
7
8

B. MACHINERY:
Sl No

C. LABOUR:
Sl No

355787507.xlsx 6
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Add for Air and Water line @


Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

D.Add for contractor's profit and overheads on (A+B+C+other percentages)

E. Add lead charges 4KM


Total cost for
Rate per

2 IRR-TAW-1-2 Excavation for vertical / inclined shaft in all types of soft / hard rock
surface, ventilation, lighting,drainage, removing and hauling excavated muck
with initial lead upto 1 km and all lifts.

DATA
A. MATERIALS:

355787507.xlsx 7
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Sl No

1
2
3
4
5
6
7
8
9
10

B. MACHINERY:
Sl No

C. LABOUR:
Sl No

1
2
3
4
5
6
7
8
9
10
11
12
13

355787507.xlsx 8
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
14

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Add for Air and Water line @


Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

D.Add for contractor's profit and overheads on (A+B+C+other percentages)


E. Add lead charges of 4 KM
Total cost for
Rate per

3 IRR-TAW-1-3 Excavation for tunnel by tunnelling methods in rock not requiring suppo
under-cuts, ventilation,lighting, drainage, removing and hauling the excavated
complete with initial lead upto 1 km and all lifts.

A. MATERIALS:
Sl No

1
2
3
4
5

6
7
8

B. MACHINERY:
Sl No

355787507.xlsx 9
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

C. LABOUR:
Sl No

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery

355787507.xlsx 10
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
C. Cost of Labour

Add for Air and Water line @


Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

D.Add for contractor's profit and overheads on (A+B+C+other percentages)


E. Add lead charges of 4KM
Total cost for
Rate per

4 IRR-TAW-1-4 Excavation for tunnel by tunnelling methods including excavation for supports
including cost of all other materials, machinery, labour, scaling excavated surf
tunnel upto specified dump area and all other ancillary operations etc., compl

DATA:
A. MATERIALS:
Sl No

1
2
3
4
5

6
7
8

B. MACHINERY:
Sl No

355787507.xlsx 11
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

C. LABOUR:
Sl No

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Add for Air and Water line @


Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

D.Add for contractor's profit and overheads on (A+B+C+other percentages)


E. Add lead charges of 4KM
Total cost for
Rate per

355787507.xlsx 12
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
5 IRR-TAW-1-5 Excavation for tunnel by heading and benching tunnelling methods including
cost of providing supports ) for roof before benching including cost of all other
removing and hauling excavated muck outside tunnel upto specified dump ar

DATA:
A. MATERIALS:
Sl No

1
2
3
4
5

6
7
8

B. MACHINERY:
Sl No

C. LABOUR:
Sl No

1
2
355787507.xlsx 13
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
3
4
5
6
7
8
9
10
11
12
13
14
15

16

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Add for Air and Water line @


Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

D.Add for contractor's profit and overheads on (A+B+C+other percentages)

E. Add lead charges of 4KM


Total cost for
Rate per

6 IRR-TAW-1-6 Removing and hauling muck overfallen due to natural causes such as geol
and disposing off the same in specified dump area or as directed including co
operations etc., complete with initial lead upto 1 km and all lifts.

DATA
A. MATERIALS:
Sl No

355787507.xlsx 14
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
1

2
3
4
5
6
7

B. MACHINERY:
Sl No

C. LABOUR:
Sl No

1
2
3
4
5
6
7
8

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Add for Air and Water line @

355787507.xlsx 15
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

D.Add for contractor's profit and overheads on (A+B+C+other percentages)


E. Add lead charges of 4KM
Total cost for
Rate per

7 IRR-TAW-2-1 Dewatering tunnel by pumping out water collected by natural drainage i


machinery, labour, drainage, lighting,ventilation and all other ancillary operatio

DATA
A. MATERIALS:
Sl No

1
2

B. MACHINERY:
Sl No

1
2
3

C. LABOUR:
Sl No

1
2
3

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Add for Air and Water line @


Add for Ventilation @
Add for Lighting @

355787507.xlsx 16
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Add for Ele sub-station / Demand charges @

D.Add for contractor's profit and overheads on (A+B+C+other percentages)


Total cost for
Rate per

8 IRR-TAW-2-2 Providing 25 mm thick guniting to sides and arch of tunnel in ceme


ventilation, lighting, drainage and all other ancillary operations etc., complete

DATA:
A. MATERIALS:
Sl No

1
2
3
4
5
6

B. MACHINERY:
Sl No

C. LABOUR:
Sl No

1
2
3
4
5
6

labour component/unit qty


Add contractor's profit and overhead charges

355787507.xlsx 17
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Add for Air and Water line @


Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

D.Add for contractor's profit and overheads


on (A+B+C+other
F.Lead Charges forpercentages)
Cement (including
Loading and Unloading
Lead Charges for FA 6KM Charges)
Total cost for
Rate per

9 IRR-TAW-2-3
(new4 - 2011-12) Shortcreting in two layers (each layer+38 mm thickness) for slabs duly fi
conveyance of all materials, labour charges, all heads, lifts, centering, scaffol
specification and as directed by Engineer-in-Charge

Data
A. MATERIALS:
Sl No

1
2
3
4
5
6
7
8

B. MACHINERY:
Sl No

355787507.xlsx 18
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

C. LABOUR:
Sl No

1
2
3
4
5
6

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Add for Air and Water line @


Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

D.Add for contractor's profit and overheads


on (A+B+C+other
G.Lead Charges forpercentages)
Cement (including
Loading and Unloading
Lead Charges for FA 6KM Charges)
Total cost for
Rate per

10 IRR-TAW-3-1 Providing and fixing 25 mm diameter steel rock bolts with mechanical
thick steel tapered wedge, 10 mm thick plate washers and nuts, tightening bo
and all other ancillary operations etc., complete with lead upto 1 km and all lif

DATA:
A. MATERIALS:
Sl No

1
2

3
4

355787507.xlsx 19
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
5
6
7

B. MACHINERY:
Sl No

C. LABOUR:
Sl No

1
2
3
4
5
6
7
8
9
10
11

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Add for Air and Water line @


Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

355787507.xlsx 20
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

D.Add for contractor's profit and overheads


on (A+B+C+other
E.Lead Charges forpercentages)
Steel (including
Loading
Total costand
for Unloading Charges)
Rate per

11 IRR-TAW-3-3 Providing, fabricating and fixing in position permanent structural steel sup
welding, grinding, lighting,ventilation, drainage and all other ancillary operatio

Data
A. MATERIALS:
Sl No

1
2
3
4

B. MACHINERY:
Sl No

C. LABOUR:
Sl No

1
2
3

355787507.xlsx 21
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Add for Air and Water line @


Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

D.Add for contractor's profit and overheads


on (A+B+C+other
E.Lead percentages)
Charges for 1Km for Steel
(including Loading
Total cost for and Unloading Charges)
Rate per

12 IRR-TAW-3-4 Providing, fabricating and fixing in position temperary structural steel sup
materials, machinery, labour,cutting, bending, welding, grinding, ventilation, lig
and all lifts.

DATA
A. MATERIALS (for 20 uses):
Sl No

1
2
3
4

355787507.xlsx 22
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

B. MACHINERY (for fabrication):


Sl No

B. MACHINERY (for erection and dismantling):


Sl No

C. LABOUR ( for fabrication ):


Sl No

1
2

C. LABOUR ( for erection ):


Sl No

355787507.xlsx 23
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
2

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery for fabrication
C. Hire charges of Machinery for erection and dismantling
D. Cost of Labour for fabrication
E. Cost of Labour for erection and dismantling

Add for Air and Water line @


Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @

D.Add for contractor's profit and overheads


on (A+B+C+other
Lead percentages)
Charges for Steel (including Loading
and Unloading
Total cost for Charges)
Rate per

13 IRR-TAW-5-1 Providing, fabricating and placing in position reinforcement steel for tunnel RC
joints wherever required, tying with 1.25 mm dia.soft annealed steel wire, incl
with initial lead upto 1 km and all lifts.

DATA
A. MATERIALS:
Sl No

1
2
3

B. MACHINERY:
Sl No

355787507.xlsx 24
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
1

C. LABOUR:
Sl No

1
2

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

355787507.xlsx 25
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Add for Air and Water line @


Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @
D.Add for contractor's profit and overheads
on (A+B+C+other
E.Lead Charges forpercentages)
Steel (including
Loading and Unloading Charges)
Total cost for
Rate per

Providing and laying insitu vibrated M-10 ( 28 days cube compressive streng
10 N / sq mm ) grade cement concrete using 40 mm down size approved, cl
14 IRR-TAW-5-2 graded aggregates crushed from tunnel excavated muck for filling and level
in bed due to geological faults etc., including cost of all materials, machine
bed, batching, mixing, conveying and laying, levelling, compacting, finishing,
ventilation, drainage etc., complete with initial lead upto 1 km and all lifts.
content : 220 kg / cum, CA : 0.90cum, Blending Ratio of CA--50:30:20, FA
Superplasticizer 0.4% by wt. of cement)

DATA
A. MATERIALS:
Sl No Particulars

1 Cement for mix


2 Coarse aggregate 40-20 mm
Coarse aggregate 20-10 mm
Coarse aggregate 10 mm below
3 Fine aggregate (Un-Screened )
4 Super Plasticizer
5 Sundries
Total cost of Materials

B. MACHINERY:
Sl No Description

1 Batching plant 2 x 1 cum


Fuel / Energy charges
2 Agitator car 2 cum
Fuel / Energy charges
3 10 hp pump ( ele )
Fuel / Energy charges
4 Needle vibrator 40 mm dia
Fuel / Energy charges

355787507.xlsx 26
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
5 Sundries
Total hire charges of Machinery

C. LABOUR:
Sl No Description

1 Crew for Batching plant


2 Crew for Agitator car
3 Crew for Pump
4 Crew for Needle vibrator
5 Mason Class-I
6 work inspector
7 mazdoor
for cleaning bed
for loading material bin ( Cement )
for miscellaneous works at BP
for laying concrete
for conveying laying concrete
for cleaning bed
for washing CA / curing
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Add for Air and Water line @

355787507.xlsx 27
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @
D.Add for contractor's profit and overheads
on (A+B+C+other percentages)
Lead Charges for 1 Km for FA
1 Kmfor
Lead Charges for 1Km forCement
CA
(including Loading and Unloading Charges)
Total cost for
Rate per
Add Lead Charges for Sand
Deduct initial lead charges
Add Lead Charges for Metal
Deduct initial lead charges
Rate per

15 IRR-TAW-5-3 Providing and laying insitu vibrated M-20 ( 28 days cube compressive stre
approved clean, hard,graded aggregates crushed from tunnel muck for kerb a
mixing, conveying upto placing point in agitator cars, placing in position, level
operations etc., complete with lead upto 1 km and all lifts.( Cement content 33
Ratio of CA--50:30:20, FA : 0.40 cum)

DATA
A. MATERIALS:
Sl No

2
3

4
5
6

B. MACHINERY:
Sl No

355787507.xlsx 28
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
4

C. LABOUR:
Sl No

1
2
3
4
5

10

labour component/unit qty

355787507.xlsx 29
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Add for Air and Water line @


Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @
D.Add for contractor's profit and overheads
on (A+B+C+other
G.Lead Charges forpercentages)
Cement (including
Loading and Unloading Charges)
Lead Charges for FA 6KM
Lead Charges for CA 6KM
Total cost for
Rate per

16 IRR-TAW-5-4 Providing and laying insitu vibrated M-20 ( 28 days cube compressive st
approved clean, hard,graded aggregates crushed from tunnel muck for sid
mixing, conveying upto placing point in agitator cars, placing in position, l
operations etc., complete with lead upto 1 km and all lifts.( Cement content
Ratio of CA-

DATA:
A. MATERIALS:
Sl No

2
3

4
5
6
7

B. MACHINERY:
Sl No

355787507.xlsx 30
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
2

C. LABOUR:
Sl No

1
2
3
4
5
6
7

355787507.xlsx 31
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

10

11

12
13

14

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Add for Air and Water line @


Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @
D.Add for contractor's profit and overheads
on (A+B+C+other
G.Lead Charges forpercentages)
Cement (including
Loading and Unloading Charges)
Lead Charges for FA 6KM
Lead Charges for CA 6KM
Total cost for
Rate per

17 Providing and laying insitu vibrated M-25 ( 28 days cube compressive stren
approved, clean, hard, graded aggregates including cost of all materials, mac
position, levelling, vibrating, finishing, curing etc.,complete for RCC works of g
walls, piers, abutments and such other locations with initial lead upto 1 km an
IRR-DAW-2-4(B) blending ratio of CA--65:35, FA : 0.45 cum)

355787507.xlsx 32
IRR-DAW-2-4(B) blending ratio of CA--65:35, FA : 0.45 cum)
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

DATA:
DATA:
A. MATERIALS:
Sl No

4
5
6
7

B. MACHINERY:
Sl No

C. LABOUR:
Sl No

1
2
3
4
5
6
7

355787507.xlsx 33
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

10

11

12
13

14

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Add for Air and Water line @


Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @
D.Add for contractor's profit and overheads
on (A+B+C+other
Lead percentages)
Charges for Cement (including
Loading and Unloading Charges)
Lead Charges for FA 6KM
Lead Charges for CA 6KM
Total cost for
Rate per

18 IRR-TAW-6-1 Drilling 32 mm diameter grout holes in concrete / rock by percussion


consolidation / contact grouting including cost of all materials, machinery, labo
complete.

DATA:
A. MATERIALS:
Sl No

355787507.xlsx 34
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

2
3
4

B. MACHINERY:
Sl No

C. LABOUR:
Sl No

1
2
3
4
5

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Add for Air and Water line @


Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @
D.Add for contractor's profit and overheads
on (A+B+C+other percentages)
Total cost for
Rate per

19 IRR-TAW-6-2 Grouting cement slurry in grout holes under specified pressure for conso
redrilling wherever necessary,ventilation,lighting, drainage and othe
355787507.xlsx 35
IRR-TAW-6-2 Grouting cement slurry in grout
PRLISholes under
Stage-2 P.S specified for conso
pressure Part-IV
DPR Volume-3C,
redrilling wherever necessary,ventilation,lighting, drainage and othe

DATA: In contact zones, perticularly in crown portion, the grout intake will be heavy d
packing of concrete during placement of concrete by placer pump.
The average grout intake in the contact zone is considered at 75 kg per metre
zone the grout intake may vary from 25 kg per metre to 50 kg per metre depe
extent of opening of joints in rock during / after excavation.
The average gruot intake for consilidation /contact grouting is considered at 5
The average progress of grouting per shift is considered at 1500 kg.
Deploy Grout pump with accessories for 8 hours.
Deploy Drilling jumbo for 2 hours during grouting of top holes.
Deploy 10 hp pump for 2 hours for pumping water to storage tank.
Cost of grout hose 50 m @ Rs:
Life of grout hose
Use rate of grout hose per hour
Cost of water hose 50 m @ Rs:
Life of water hose
Use rate of water hose per hour

DATA:

A. MATERIALS:
Sl No

1
2
3
4

B. MACHINERY:
Sl No

C. LABOUR:
Sl No

1
2

355787507.xlsx 36
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
3
4

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Add for Air and Water line @


Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @
D.Add for contractor's profit and overheads
on (A+B+C+other
Lead percentages)
Charges for 1Km for Cement
(including Loading and Unloading Charges)
Total cost for
Rate per

20 IRR-TAW-6-3 Drilling 75 mm diameter drainage holes vertical or inclined in rock / con


equipment including cost of all materials, machinery, labour, ventilation, lightin

DATA
A. MATERIALS:
Sl No

1
2
3
4

B. MACHINERY:
Sl No

355787507.xlsx 37
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
C. LABOUR:
Sl No

1
2
3
4

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Add for Air and Water line @


Add for Ventilation @
Add for Lighting @
Add for Ele sub-station / Demand charges @
D.Add for contractor's profit and overheads
on (A+B+C+other percentages)
Total cost for
Rate per rmt

21 IRR-DAW-1-1
Excavation for foundation in all kinds of soil including boulders upto 0.30 m
and placing the excavated soil neatly in dump area or disposing off
A. MATERIALS:
Sl No

B. MACHINERY:
Sl No

C. LABOUR:
Sl No

355787507.xlsx 38
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
2
3
4
5

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads
on (A+B+C)
E. Add Lead charges for 4Km
Total cost for
Rate per

22 IRR-DAW-1-2 Excavation for foundation in ordinary rock (including HDR) without bl


and other appurtenant works and placing the excavated material neatly in du
and all lifts.

A. MATERIALS:
Sl No

B. MACHINERY:
Sl No

C. LABOUR:
Sl No

1
2
3
4
5
6

labour component/unit qty


Add contractor's profit and overhead charges

355787507.xlsx 39
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
labour component/unit qty (including contractor's profit)
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads
on (A+B+C)
E. Add Lead charges for 4Km
Total cost for
Rate per

23 IRR-DAW-1-3 Excavation for foundation in hard rock (including F&F rock) requir
structure and other appurtenant works and placing the excavated material n
upto

A. MATERIALS:
Sl No

2
3
4
5
6

B. MACHINERY:
Sl No

C. LABOUR:
Sl No

1
2
3
4
5
355787507.xlsx 40
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
6
7
8
9
10
11

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads
on (A+B+C)
E. Add Lead charges for 4Km
Total cost for
Rate per

24 IRR-DAW-1-4 (a) Excavation for foundation in hard rock of all toughness by blasting including b
and placing the excavated rock neatly in dump area or stack yard including le

DATA:

A. MATERIALS:
Sl No

2
3
4
5
6
7

B. MACHINERY:
Sl No

355787507.xlsx 41
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
4

C. LABOUR:
Sl No

1
2
3
4
5
6
7
8
9
10
11
12

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D.Add for contractor's profit and overheads
on (A+B+C)
E. Add Lead charges for 4Km
Total cost for
Rate per

25 IRR-DAW-1-13 Providing and fixing 25 mm dia 3 m long cold twisted deforme


deep hole drilled in bed rock and other end provided with L-bend for
other appertenant works including cost of drilling and cleaning hole,
materials, machinery, labour etc., complete with initial lead upto 1 k

DATA:

A. MATERIALS:
Sl No

355787507.xlsx 42
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
2
3
4
5

B. MACHINERY:
Sl No

355787507.xlsx 43
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

C. LABOUR:
Sl No

1
2
3
4
5

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

D.Add for contractor's profit and overheads on (A+B+C)


Lead Charges for 1Km for Cement

Lead Charges for 1Km for Steel


Total cost for
Rate per

26 IRR-DAW-2-1A Providing, fabricating and placing in position reinforcement steel for


with 1.25 mm diameter soft annealed steel wire, including cost of al
all lifts.overlaps and wastage as per NHAI-data
A. MATERIALS:
Sl No

1
2

B. MACHINERY:
Sl No

C. LABOUR:
Sl No

1
2

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

355787507.xlsx 44
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
A.MATERIAL
B.MACHINERY
C. LABOUR
Total
D.Add for contractor's profit and overheads on A+B+C
E.Lead Charges for Steel (including
Loading
Total costand
for Unloading Charges)

27 IRR-DAW-2-4 Providing and laying insitu vibrated M-20 ( 28 days cube compressive stren
approved, clean, hard, graded aggregates including cost of all materials, mac
position, levelling, vibrating, finishing, curing etc.,complete for RCC works of g
walls, piers, abutments and such other locations with initial lead upto 1 km an

( Cement content : 310 kg / cum with use of super plasticiser,CA : 0.90 c

DATA:

A. MATERIALS:
Sl No

1
2

3
4
5
6

B. MACHINERY:
Sl No

355787507.xlsx 45
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

C. LABOUR:
Sl No

1
2
3
4
5
6
7
8
9

10
11

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

Add for aggregate conveyor system @


Add for electric sub-station / Demand charges @
Add for trestle bridge for tower crane track @

D.Add for contractor's profit and overheads on (A+B+C+other percentages)


Lead Charges for 6 Km for FA
Lead Charges for 6 Km for CA
Lead Charges for 1 Km for Cement
(including Loading and Unloading Charges)
Total cost for
Rate per

28 IRR-DAW-2-6 Providing and laying insitu vibrated M-15 ( 28 days cube compressive strengt
clean, hard, graded aggregates including cost of all materials, machinery, lab
levelling, vibrating, finishing, curing etc.,complete for plain concrete works wit
plasticiser,CA : 0.90 cum, Blending Ratio of CA -- 50:30:20, FA : 0.40 cum)

DATA:
A. MATERIALS:
Sl No

355787507.xlsx 46
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

4
5
6

B. MACHINERY:
Sl No

C. LABOUR:
Sl No

1
2
3
4
5

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

D.Add for contractor's profit and overheads


on (A+B+C)
Lead Charges for 6 Km for FA
Lead Charges for 6 Km for CA and Plums

355787507.xlsx 47
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Lead Charges for 1Km for Cement
Total cost for
Rate per

29 IRR-GAW-2-2 Design, fabrication, supply, erection, testing and commissioning of vertical


girders, stiffeners, lifting pins, bronze padded slide blocks/bearings, guide sho
materials,machinery, labour, seal fixing etc.,complete as per specifications an
which are added extra as perscedule of rates under items in this chapter and

Drawing NO. CE/CDO/CL3/MRP/783/2002 (Spillway Stop log gate Elemen


of Madduvalasa Project)

Use rate of materials :


Cost of welding set @ Rs:
Life of welding set
Use rate of welding set per hour
Cost of gas cutting set @ Rs:
Life of gas cutting set
Use rate of gas cutting set per hr
DATA:
A. MATERIALS:
Sl No

5
6
7
8
9
10
11

B. MACHINERY:
Sl No

3
355787507.xlsx 48
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

C. LABOUR:
Sl No

1
2
3
4
5
6
7
8
9
10
11
12

Add towards highly skilled labour charges @ 30% on total cost of labour

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @

F. Add for contractor's profit and overheads on (A+B+C+D+E)


Add 2 leads
Add lead charges for fabricated parts Rs.
Unloading charges of fabricated parts Rs
Total cost for

30 IRR-GAW-2-4 Fabrication, supply, erection, testing and commissioning of adequate capa


platform with hand railing, long / cross travel arrangements, rope drums, gear
ladder, motorised cable reeling drum etc., with all accessories for operating s
cost of all materials, machinery, labour, etc., complete with all leads and lifts.
355787507.xlsx 49
IRR-GAW-2-4 Fabrication, supply, erection, testing and commissioning of adequate capa
platform with hand railing, long / cross travel arrangements, rope drums, gear
ladder, motorised cable reeling drum
PRLIS etc., with
Stage-2 P.Sall
DPRaccessories for operating
Volume-3C, Part-IV s
cost of all materials, machinery, labour, etc., complete with all leads and lifts.

DATA:
A. MATERIALS:
Sl No

6
7
8
9
10

11

12
13
14
15
16
17
18
19
20

B. MACHINERY:
Sl No

355787507.xlsx 50
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

C. LABOUR:
Sl No

1
2
3
4
5
6
7
8
9
10
11

Add towards highly skilled labour charges @ 30% on total cost of labour

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @

F. Add for contractor's profit and overheads on (A+B+C+D+E)


Add 2 leads
Add lead charges for fabricated parts Rs.
Unloading charges of fabricated parts Rs
Total cost for

31 IRR-GAW-2-5 Design, fabrication, supply, erection and commissioning of rail track using
operating spillway stoplog gate elements / river sluice / canal sluice emergen
(without painting on sand-blasted or mechanical cleaning surfaces which are
separately)

355787507.xlsx 51
operating spillway stoplog gate elements / river sluice / canal sluice emergen
(without painting on sand-blasted or mechanical cleaning surfaces which are
separately) PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

DATA: Rail track for moving gantry crane consists of 45 kg / m standard rails fixed by
bolting to anchors embedded in concrete at intervals. The width of track shall
requirement of gantry long travel specifications.
Consider track length of 200 m for rate analysis.
Actual weight of materials as per data
1 Requirement of materials : as per fabrication drawings
a. Structural steel conforming to IS : 2062 :
Structural steel angles / beams / channels / bars with 2.5 % wastage
Structural steel plates / flats with 2.5 % wastage
b. Bolt / Nut / Washer conforming to IS : 1363 :
MS bolts and nuts with 2.5 % wastage
c. Standard Rails 45 kg / m with 2.5 % wastage
d. Welding electrodes :
Welding electrodes for stitch welding at 10 % of total with 2.5 % wastage
Welding electrodes for run welding at 90 % of total with 2.5 % wastage
2 Cutting :
Total length of cutting assuming cutting for 2 sides
For cutting structural steel sections to required sizes gas cutting is assumed.
Length of steel to be cut by using gas cutting torch manually
Time for gas cutting manually assuming average cutting progress of 2 m / hou
Acetelyne gas @ 0.6 cum / hour ( 111 x 0.60 )
Oxygen gas @ 1.8 cum / hour ( 111 x 1.80 )
Use of gas cutting torch with 50 min / hr working ( 111 x 60 / 50 )
3 Welding :
Length of welding
For stich welding @ 2 hrs usage / shift & @ 15 electrodes / hr

For run welding @ 6 hrs usage / shift & @ 15 electrodes / hr

Deploy welding transformer for 193 hours.


Fuel / Energy charges @ 25 % hrs for stitch welding & @ 75 % hrs for run we

4 Requirement of other machinery :


For drilling holes for anchor bolts 50 hours use of drilling machine considered
For grinding edges of parts requiring finishing 8 hours use of grinding machin
For handling and erection mobile derric crane for 4 hours considered.
5 Requirement of work force :
Work component

Cutting sections 133 hours


Drilling holes for anchors / supports
Erection /stitch welding anchors 48 hours
Erection of rails & fixing clamps
Run welding 145 hours
Finishing / checking / cleaning
Total :
6 Excise duty on supply :
355787507.xlsx 52
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Excise duty is applicable on supply of fabricated parts. The cost of materials i
taxes/ duties. Therefore, for purpose of rate analysis 75 percent of total cost e
of materials ( assuming 25 % erection cost ) is considered for assessing excis
7 Use rate of materials :
Cost of welding set @R
Life of welding set
Use rate of welding set per hour
Cost of gas cutting set @ Rs
Life of gas cutting set
Use rate of gas cutting set per hr
DATA:
A. MATERIALS:
Sl No

1
2
3
4
5
6
7
8
9
10

B. MACHINERY:
Sl No

C. LABOUR:
Sl No

1
2
3
4
5
6
7
8

355787507.xlsx 53
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
9

Add towards highly skilled labour charges @ 30% on total cost of labour

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @

F. Add for contractor's profit and overheads on (A+B+C+D+E)


Add 2 leads
Add lead charges for fabricated parts Rs.
Unloading charges of fabricated parts Rs
Total cost for

32 IRR-GAW-2-3 Fabrication, supply, erection, testing and commissioning of automatic lifti


elements including cost of all materials, machinery, labour, cutting, aligning, w
(without painting on sand-blasted or mechanical cleaning surfaces which a

DATA: Automatic lifting beam for lifting spillway stop log elements consists of fabrica
lifting bracket and automatic engaging / dis-engaging type hooks for under wa
de-hooking of gate element. Lifting beam is an independent attachment to mo

The actual weight of stoplog element lifting beam as per data sheet

1 Requirement of materials :
a. Structural steel conforming to IS : 2062 :
Structural steel angles / beams / channels / bars with 2.5 % wastage
Structural steel plates / flats with 2.5 % wastage
b. Alloy steel components conforming to IS : 1570 :
Lifting pins
c. Alluminium / Bronze alloy components conforming to IS : 305 :
Bronze Bush
d. Forged steel components conforming to IS : 2004 :
Lifting hooks
e. Bolts / Nuts / Washers conforming to IS : 1363 :
MS bolts / nuts / washers with 2.5 % wastage
MS pipe 100 mm dia
f. Welding electrodes :
Welding electrodes for stitch welding at 10 % of total with 2.5 % wastage
Welding electrodes ( LH ) for run welding at 90 % of total with 2.5 % wastage

355787507.xlsx 54
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
2 Cutting :
Length of cutting assuming cutting for 2 sides
Add for variations ( cutting for more than 2 sides / odd shapes etc ) at 10 %

For cutting structural steel sections to required sizes gas cutting is assumed.
Length of steel to be cut by using gas manually
Length of steel to be cut by gas using pug cutting machine
Time for gas cutting manually assuming average cutting progress of 2 m / hou
Time for gas cutting by pug cutting machine at ( av ) 3 m / hour
Acetelyne gas @ 0.6 cum / hour ( 70 x 0.60 )
Oxygen gas @ 1.8 cum / hour ( 70 x 1.80 )
Use of gas cutting torch with 50 min / hr working ( 20 x 60 / 50 )
Use of pug cutting machine with 50 min / hr working ( 50 x 60 / 50 )
3 Welding :
Length of welding
For stich welding @ 2 hrs usage / shift & @ 15 electrodes / hr
( 175 / 15 ) x 8 / 2
For run welding @ 6 hrs usage / shift & @ 15 electrodes / hr
( 1575 / 15 ) x 8 / 6

Deploy welding transformer for 187 hours.


Fuel / Energy charges @ 25 % hrs for stitch welding & @ 75 % hrs for run we
( 47 x 0.25 + 140 x 0.75 )
5 Requirement of other machinery :
For handling during fabrication mobile derric crane for 4 hours and stationery
8 hours considered.
For drilling holes for pins / guide shoes 2 hours use of drilling machine consid
For grinding and finishing weld joints 2 hours use of grinding machine conside

6 Requirement of work force :


Work component

Cutting sections 84 hours


Drilling holes for pins / bolts fixing
Fabricating by stitch welding 47 hours
Run welding 140 hours
Finishing / guide shoe fixing / checking
Total :
7 Excise duty on supply :
Excise duty is applicable on supply of fabricated parts. The cost of materials i
taxes/ duties. Therefore, for purpose of rate analysis 75 percent of total cost e
of materials ( assuming 25 % erection cost ) is considered for assessing excis
8 Use rate of materials :
Cost of welding set @ Rs:
Life of welding set
Use rate of welding set per hour
Cost of gas cutting set @ Rs:
Life of gas cutting set
Use rate of gas cutting set per hr

355787507.xlsx 55
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

DATA:
A. MATERIALS:
Sl No

5
6

7
8
9
10
11
12
13

B. MACHINERY:
Sl No

355787507.xlsx 56
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
C. LABOUR:
Sl No

1
2
3
4
5
6
7
8
9

Add towards highly skilled labour charges @ 30% on total cost of labour

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @

F. Add for contractor's profit and overheads on (A+B+C+D+E)


Add 2 leads
Add lead charges for fabricated parts Rs.
Unloading charges of fabricated parts Rs
Total cost for

33 IRR-CCDW-1-1 Earth work in excavation in all kinds of soils of foundation of structures as p


bracing, removal of stumps and other deleterious matter, dressin

Taking output = 240 cum


A. Materials:
Sl No

B. Machinery:
Sl No

355787507.xlsx 57
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

C. Labour:
Sl No

1
2
3

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Abstract
a) Material
b) Machinery
c) Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
E. Add Lead charges for 4Km
Total cost for
Rate per

Excavation for Structures- Mechanical Means


34 Earth work in excavation in all kinds of soils of foundation of str
IRR-CCDW-1-2 technical specification, including setting out, construction of shorin
and other deleterious matter, dressing of sides and bottom and ba
Depth upto 3 m
Unit = cum
DATA: Taking output = 240 cum

355787507.xlsx 58
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
A. Materials:
Sl No

B. Machinery:
Sl No

C. Labour:
Sl No

1
2
3

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

Abstract
a) Material
b) Machinery
c) Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
E. Add Lead charges for 4Km
Total cost for
Rate per

35 IRR-CCDW-1-4 Excavation in ordnary rock without blasting for foundations of canal cross
specified dump area or disposing off the same as directed etc., complete with

DATA: Taking output = 180 cum


A. Materials:
Sl No

355787507.xlsx 59
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

B. Machinery:

Sl No

1.0

C. Labour:
Sl No

1
2
3

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
Abstract
a) Material
b) Machinery
c) Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
E. Add Lead charges for 4Km

355787507.xlsx 60
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Total cost for
Rate per
36 IRR-CCDW-1-5 Excavation in hard rock requiring blasting including boulders above 0.6 m
structures and placing the excavated stuff neatly in specified dump area or di
upto 3 m.

DATA:
A. MATERIALS:
Sl No

2
3
4
5
6

B. MACHINERY:
Sl No

C. LABOUR:
Sl No

1
2
3
4
5
6
7
8

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)


E. Add Lead charges for 4Km
Total cost for
Rate per

355787507.xlsx 61
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

37 IRR-CCDW-2-20 Providing and laying insitu vibrated M-20 ( 28 days cube compressive stren
approved, clean, hard, graded aggregates for cantiliver / counterfort retain
cleaning, batching, mixing, placing in position,levelling, vibrating, finishing, cu
with use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum, Blending R

Note: If water is to be brought from other place add only lead charges @ 500 ltr / cu
DATA: Requirement of materials :
For 1 cum CC :- Coarse aggregates : 0.90 cum Blending ratio
Fine aggregate : 0.40 cum Cement content : 320 kg Super plastic
Average output of 300/200 ltr mixer : 50 x 13 x 8 / 320
Formwork & scaffolding :
Shuttering at 3.25 sqm / cum of concrete considered for counterfort walls.
Use rate of shuttering for 40 uses ( Annexure-A Item-IRR-CCDW-2-3 )
Cost of scaffolding materials considered @ : 25 % of shut
Labour for shuttering ( Annexure-B Item-IRR-CCDW-2-3 )
Labour for erecting & dismantling scaffolding : 25 % of labo

355787507.xlsx 62
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Labour for concreting :
Requirement of labour for concreting same as in item IRR-CCDW-2-3 with av
involved for counterfort wall works.
DATA:
A. MATERIALS:
Sl No

3
4
5

B. MACHINERY:
Sl No

C. LABOUR:
Sl No

1
2
3
4
5
6

355787507.xlsx 63
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)


Lead Charges for FA 6KM
Lead Charges forforCA 6KM (including
Cement
Loading and Unloading Charges)
Total cost for
Rate per

38 IRR-CCDW-2-25 Providing and laying insitu vibrated M-20 ( 28 days cube compressive stre
approved, clean, hard, graded aggregates for columns and beams including c
placing in position, levelling, vibrating,finishing, curing etc.,complete with initia

DATA: Requirement of materials :


DATA:
A. MATERIALS:
Sl No

3
4
5

B. MACHINERY:
Sl No

355787507.xlsx 64
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

355787507.xlsx 65
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
C. LABOUR:
Sl No

1
2
3
4
5
6

labour component/unit qty


Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)


Lead Charges for Cement
Lead Charges for FA 6KM
Lead Charges for CA 6KM
Total cost for
Rate per

39 Brick Masonry in
CM
Unit =(1:6)
1cumwith 2nd
class Bricks
A. MATERIALS:
traditional size 23 x
Cement
11 x 7 cms
Bricks traditional size 23 x 11 x 7 cms 2nd
class
Fine aggregate (Sand)

B. LABOUR:
Mason 1 class
Mason 2 class
Mazdoor (unskilled)
Total
Total
Grand Total

355787507.xlsx 66
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Add profit
C. LEAD CHARGES OF MATERIALS:
Cement
Bricks traditional size 23 x 11 x 7 cms 2nd
class
Lead for Fine aggregate (Sand)
Rate per Cum
Say

355787507.xlsx 67
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
40 Design, fabrication, supply, erection of roof truss with all accessories including cost of all material
approved drawings
A. Cost of MS Angles/Channel/Beams
B. Fabrication Charges 24000/MT

E. Add for transportation upto work site @

F. Add for contractor's profit and overheads on (A+B+C+D+E)

Add lead charges for fabricated parts Rs.


Unloading charges of fabricated parts Rs
Total cost for

Design, fabrication, supply, erection, testing and commissioning of delivery mains with all accesso
41
and approved drawings

A. Cost of MS Plates per MT


B. Fabrication Charges 24000/MT

E. Add for transportation upto work site @

F. Add for contractor's profit and overheads on


Spiders
Weight of Spiders Required
Anchoring
Add Fabrication Charges Rs.24000/MT
Deduct Scrap Spider Cost
Scrap value taken 50% of Initial Cost

Net Cost of the Spiders =


Cost of Spiders and Hooks per MT
(Weight of Pipe per Metre=2.71 MT)

Add 1 km lead charges for fabricated parts Rs.


Unloading charges of fabricated parts Rs
Total cost for

42 IRR-GAW-3-1 Cleaning delivery lines to expose fresh metal surface for painting by sand b
scaffolding, etc., complete with initial lead for sand upto 1 km and all lifts.
DATA:
A. MATERIALS:
Sl No

1
2
3
4

355787507.xlsx 68
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

B. MACHINERY:
Sl No

C. LABOUR:
Sl No

1
2
3

355787507.xlsx 69
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)
ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @

F. Add for contractor's profit and overheads on (A+B+C+D+E)


Lead Charges for FA 6KM
Total cost for

42 IRR-GAW-3-2 painting of steel liner on sand blasted surfaces with one coat of inorganic z
300 microns (each 150+/- 5) of solventless coaltar epoxy brown paint paint e
complete with all leads and all lifts

A. MATERIALS:
Sl No

1
2
3
4

B. MACHINERY:
Sl No

2
3

C. LABOUR:
Sl No

1
2
3

355787507.xlsx 70
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

D. Add for excise duty


(on 75 percent cost excluding cost of materials)
E. Add for transportation upto work site @
F. Add for contractor's profit and overheads
on (A+B+C+D+E)
Total cost for

43 IRR-CAW-1-9 Excavation in hard rock by blasting including boulders


(a) embankment etc., including levelling bed by removing all projections
cost of all materials, machinery, labour, placing the excavated rock neatly in a
area and levelling the same as directed etc.,complete with

DATA:

Sl No

355787507.xlsx 71
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

5
6
7
8
9
10
11
12

Sl No

Sl No

1
2
3
4
5
6
7
8
9
10
11
12

355787507.xlsx 72
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
D. Add for contractor's profit and overheads
on (A+B+C)
Total cost for
Rate per Cum

Add Lead Charges for dumping of soil


Deduct initial 1 km lead for dumping of soil
Rate per Cum

Excavation in all kinds of soil including boulders upto 0.3 m diamete


44 IRR-CAW-1-1 dressing bed and sides to required level and profile, cost of all materials, mac
service road / embankment as directed etc.,complete with initial lead upto 1 k

DATA:
A. MATERIALS:
Sl No particulars

1 NIL

Total cost of Materials

B. MACHINERY:
Sl No Description

1 Shovel 0.85 cum capacity


Fuel / Energy charges
2 Tippers 5 cum capacity 6 Nos
Fuel / Energy charges
Total hire charges of Machinery

C. LABOUR:
Sl No Description

1 Crew for Shovel


2 Crew for Tipper
3 work inspector
4 mazdoor
Total cost of Labour
labour component/unit qty

355787507.xlsx 73
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour
Total
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per

embankment, filter drain / catch water drains etc., including dressin


45 IRR-CAW-1-3
machinery, labour, placing the excavated soft rock neatly in dump a
DATA:
A. MATERIALS:
Sl No particulars

1 NIL
Total cost of Materials

B. MACHINERY:
Sl No Description

1 Shovel 0.85 cum capacity


Fuel / Energy charges
2 Tippers 5 cum capacity 5 Nos
Fuel / Energy charges
Total hire charges of Machinery

C. LABOUR:
Sl No Description

1 Crew for Shovel


2 Crew for Tipper
3 work inspector
4 Crowbarman
5 mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery
C. Cost of Labour

355787507.xlsx 74
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
D. Add for contractor's profit and overheads on (A+B+C)
Total cost for
Rate per

Excavation in hard rock (including F&F rock) requiring blasting in


46 IRR-CAW-1-5 drain / catch water drains etc., including dressing bed and sides to required le
dump area or for formation of service road as directed etc., complete with lea

DATA:
A. MATERIALS:

355787507.xlsx 75
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Sl No particulars

1 Use rate of drill rod 1.5 m length


Reconditioning charges @ 10%
2 Use rate of 50 m air hose 2 Nos

3 Explosive small dia ( Kelvex-220 )


4 Ordinary detonators
5 Electric detonators
6 Fuse coil
7 Sundries
Total cost of Materials

B. MACHINERY:
Sl No Description

1 Shovel 0.85 cum capacity


Fuel / Energy charges
2 Tippers 5 cum capacity 5 Nos.
Fuel / Energy charges

3 Air compressor 8.5 cmm ( diesel )


Fuel / Energy charges
4 Jack hammers 3 Nos.
Fuel / Energy charges
Total hire charges of Machinery

C. LABOUR:
Sl No Description

1 Crew for Shovel


2 Crew for Tipper
3 Crew for Air compressor
4 Crew for Jack hammer
5 work inspector
6 Blaster
7 Helper blaster
8 Crowbarman
9 Stone breaker
10 mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery

355787507.xlsx 76
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
C. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)


Total cost for
Rate per

47 IRR-CAW-1-9 Excavation in hard rock by blasting including boulders above 1.2 m dia. for canal
embankment etc., including levelling bed by removing all projections by hammering
cost of all materials, machinery, labour, placing the excavated rock neatly in approve
area and levelling the same as directed etc.,complete with all leads and lifts,as per d
directed by Engineer-in-Charge.
DATA: RATE ANALYSIS
A. MATERIALS:
Sl No particulars

1 Use rate of T.C bit 100 mm dia

2 Use rate of Extension rod with coupling sleeve

3 Use rate of Jack hammer drill rod 1.5 m


reconditioning charges @

4 Use rate of 50 m air hose for waggon drill

Use rate of 25 m air hose for JH 2 Nos


5 High strength ANFO booster
6 ANFO
7 Diesel oil
8 Explosive small dia ( Kelvex-220 )

355787507.xlsx 77
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
9 Ordinary detonators
10 D-cord
11 Detonating fuse coil
12 Sundries
Total cost of Materials

B. MACHINERY:
Sl No Description

1 Tippers 5 cum capacity


Fuel / Energy charges
2 Shovel 0.85 cum capacity
Fuel / Energy charges
3 Angle dozer
Fuel / Energy charges
4 Air compressor 8.5 cmm ( diesel )
Fuel / Energy charges
5 Waggon drill
Fuel / Energy charges
6 Jack hammer
Fuel / Energy charges

Total hire charges of Machinery

C. LABOUR:
Sl No Description

1 Crew for Tipper


2 Crew for Shovel
3 Crew for Dozer
4 Crew for Air compressor
5 Crew for Waggon drill
6 Crew for Jack hammer
7 work inspector
8 Blaster
9 Helper blaster
10 Stone chiseller Cl - II
11 Stone breaker
12 mazdoor
Total cost of Labour
labour component/unit qty
Add contractor's profit and overhead charges
labour component/unit qty (including contractor's profit)

ABSTRACT:
A. Cost of Materials
B. Hire charges of Machinery

355787507.xlsx 78
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
C. Cost of Labour

D. Add for contractor's profit and overheads on (A+B+C)


Total cost for
Rate per

Add Lead Charges for dumping of soil


Deduct initial 1 km lead for dumping of soil
Rate per Cum

355787507.xlsx 79
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

L COMPONENT WORKS OF STAGE-II AT YEDULA FOR PALAMURU-RANGA REDDY LIFT IRRIGATION SCH
MAHABUBNAGAR DISTRICT

DATA

thods in all types of rock including cost of all materials,machinery, labour, scaling excavated surface, ventilation
cavated muck outside adit upto specified dump area and all other ancillary operations etc., complete with initial lea

RATE ANALYSIS UNIT : 38.50

Particulars Unit Quantity Rate


in Rs.
Small dia explosive kg 40.00 70.00
Delay detonators Nos 54.00 23.00
Electric detonators Nos 5.00 13.00
Detonating fuse coil Rm 50.00 11.00
Use rate of drill rod 2.5 m long Rm 119.00 42.67
Reconditioning charges @ 10%
Use rate of air hose Hour 20.00 5.78
Use rate of water hose Hour 20.00 5.78
Sundries( paint / template etc ) LS 2.00 20.00
Total cost of Materials Rs:

Description Unit Quantity Rate


in Rs.
Drilling jumbo Hour 8.00 368.40
Fuel / Energy charges Hour 8.00 43.90
Air compressor 15 cmm ( ele ) Hour 5.00 138.80
Fuel / Energy charges Hour 5.00 962.30
Jack hammer ( 4 x 5 hrs ) Hour 20.00 19.80
Fuel / Energy charges Hour 20.00 0.00
Pusher leg Hour 20.00 12.70
Fuel / Energy charges Hour 20.00 0.00
Convey mucker Hour 6.50 822.80
Fuel / Energy charges Hour 6.50 267.90
Dumper ( 1 x 6.5 hrs ) Hour 6.50 580.70
Fuel / Energy charges Hour 6.50 409.60
Pump 10 hp ( ele ) Hour 5.00 6.70
Fuel / Energy charges Hour 5.00 77.00
Ventilation fans 20 hp Hour 1.00 11.50
Fuel / Energy charges Hour 1.00 154.00
Sundries(explosive van / magazine ) LS 2.00 20.00
Total hire charges of Machinery Rs:

Description Unit Quantity Rate

355787507.xlsx 80
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
in Rs.
Crew for Drilling jumbo Hour 8.00 163.30
Crew for Air compressor Hour 5.00 163.30
Crew for Jack hammer Hour 20.00 306.20
Crew for Convey mucker Hour 6.50 163.30
Crew for Dumper Hour 6.50 212.20
Crew for Pump Hour 5.00 77.70
Crew for ventilation fans Hour 1.00 26.80
Surveyor Day 0.50 590.00
Foreman Day 1.00 480.00
Fitter / Mechanic Day 2.00 415.00
Blaster ( Licensed ) Day 1.00 480.00
Helper blasting Day 2.00 370.00
Hammerman Day 2.00 370.00
work inspector 1 in each shift Day 3.00 400.00
Khalasi for mucking shift 4 Nos Day 4.00 415.00
mazdoor
for mucking shift 4 Nos Day 4.00 310.00
for other 2 shifts 1 No each shift Day 2.00 310.00
for cleaning & miscellaneous Day 2.00 310.00
Total cost of Labour Rs:
519.70
harges 13.62% 70.80
ontractor's profit) 590.50

Rs:
Rs:
Rs:
Total Rs:
1.00% Rs:
4.50% Rs:
1.60% Rs:
ges @ 2.50% Rs:
Total Rs:
eads on (A+B+C+other percentages) 13.615% Rs:

38.50 @RS/Cum 39.8


38.50 cum Rs:
cum (A+B+C+D)/38.50 Rs:

shaft in all types of soft / hard rock including cost of all materials, machinery, labour, shoring, strutting, scaling
emoving and hauling excavated muck outside shaft upto specified dump area and all other ancillary operations et

RATE ANALYSIS UNIT : 30.00

355787507.xlsx 81
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Particulars Unit Quantity Rate
in Rs.
Small dia explosive kg 32.00 70.00
Electric detonator Nos 65.00 13.00
Detonating fuse coil Rm 50.00 11.00
Use rate of drill rod 1.6 m long Rm 95.00 27.67
Reconditioning charges @ 10%
Use rate of air hose Hour 18.00 23.13
Use rate of water hose Hour 16.00 23.13
Use rate of rail track Shift 3.00 130.01
Use rate of mucking bucket Hour 24.00 22.20
Sundries( paint / template etc ) LS 2.00 20.00
Total cost of Materials Rs:

Description Unit Quantity Rate


in Rs.
Air compressor 15 cmm ( ele ) Hour 4.50 138.80
Fuel / Energy charges Hour 4.50 962.30
Jack hammer ( 4 x 4 hrs ) Hour 16.00 19.80
Fuel / Energy charges Hour 16.00 0.00
Pump 10 hp ( ele ) Hour 4.00 6.70
Fuel / Energy charges Hour 4.00 77.00
Pump 20 hp electric Hour 2.00 12.30
Fuel / Energy charges Hour 2.00 154.00
Winch 35 hp electric Hour 28.00 129.40
Fuel / Energy charges Hour 28.00 188.60
Tipping tub 1.5 cum Hour 24.00 64.20
Fuel / Energy charges Hour 24.00 0.00
Sundries(explosive van / magazine ) LS 2.00 20.00
Total hire charges of Machinery Rs:

Description Unit Quantity Rate


in Rs.
Crew for Air compressor Hour 4.50 163.30
Crew for Jack hammer Hour 16.00 306.20
Crew for Pump 10 hp Hour 4.00 77.70
Crew for Pump 20 hp Hour 2.00 77.70
Crew for Winch Hour 28.00 244.90
Surveyor Day 0.50 590.00
Foreman Day 4.00 480.00
Fitter / Mechanic Day 2.00 415.00
Blaster ( Licensed ) Day 1.00 480.00
Helper blasting Day 2.00 370.00
Hammerman 1 No. in each shift Day 3.00 370.00
work inspector 1 in each shift Day 4.00 400.00
Khalasi for mucking 2 Nos in each shift Day 6.00 415.00

355787507.xlsx 82
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
mazdoor
for mucking 8 Nos in each shift Day 24.00 310.00
for other 2 shifts 1 No / shift Day 2.00 310.00
for cleaning & miscellaneous Day 2.00 310.00
Total cost of Labour Rs:
1036.70
harges 13.615% 141.10
ontractor's profit) 1177.80

Rs:
Rs:
Rs:
Total Rs:
1.00% Rs:
4.50% Rs:
1.60% Rs:
ges @ 2.50% Rs:
Total Rs:
eads on (A+B+C+other percentages) 13.615% Rs:
30.00 @RS/Cum 39.80
30.00 cum Rs:
cum (A+B+C+D)/30.0 Rs:

methods in rock not requiring supports including cost of all materials,machinery, labour, scaling excavated surf
e, removing and hauling the excavated muck outside tunnel upto specified dump area and all other ancillary oper
d all lifts.

RATE ANALYSIS UNIT : 48.60

Particulars Unit Quantity Rate


in Rs.
Small dia explosive kg 54.00 70.00
Delay detonators Nos 68.00 23.00
Electric detonators Nos 10.00 13.00
Detonating fuse coil Rm 50.00 11.00
Use rate of drill rod 2.5 m long Rm 150.00 42.67
Reconditioning charges @ 10%
Use rate of air hose Hour 24.00 5.78
Use rate of water hose Hour 24.00 5.78
Sundries( paint / template etc ) LS 2.00 20.00
Total cost of Materials Rs:

Description Unit Quantity Rate


in Rs.
Drilling jumbo Hour 10.00 368.40

355787507.xlsx 83
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Fuel / Energy charges Hour 10.00 43.90
Air compressor 15 cmm ( ele ) Hour 6.50 138.80
Fuel / Energy charges Hour 6.50 962.30
Jack hammer ( 4 x 6.5 hrs ) Hour 26.00 19.80
Fuel / Energy charges Hour 26.00 0.00
Pusher leg Hour 26.00 12.70
Fuel / Energy charges Hour 26.00 0.00
Convey mucker Hour 6.00 822.80
Fuel / Energy charges Hour 6.00 267.90
Dumper ( 2 x 6 hrs ) Hour 12.00 580.70
Fuel / Energy charges Hour 12.00 409.60
Pump 10 hp ( ele ) Hour 6.50 6.70
Fuel / Energy charges Hour 6.50 77.00
Ventilation fans 20 hp Hour 2.00 11.50
Fuel / Energy charges Hour 2.00 154.00
Sundries(explosive van / magazine ) LS 2.00 20.00
Total hire charges of Machinery Rs:

Description Unit Quantity Rate


in Rs.
Crew for Drilling jumbo Hour 10.00 163.30
Crew for Air compressor Hour 6.50 163.30
Crew for Jack hammer Hour 26.00 306.20
Crew for Convey mucker Hour 6.00 163.30
Crew for Dumper Hour 12.00 212.20
Crew for Pump Hour 6.50 77.70
Crew for ventilation fans Hour 2.00 26.80
Surveyor Day 0.50 590.00
Foreman Day 1.00 480.00
Fitter / Mechanic Day 2.00 415.00
Blaster ( Licensed ) Day 1.00 480.00
Helper blasting Day 2.00 370.00
Hammerman Day 2.00 370.00
work inspector 1 in each shift Day 3.00 400.00
Khalasi for mucking shift 4 Nos Day 4.00 415.00
mazdoor
for mucking shift 8 Nos Day 8.00 310.00
for other 2 shifts 1 No each shift Day 2.00 310.00
for cleaning & miscellaneous Day 2.00 310.00
Total cost of Labour Rs:
512.00
harges 13.615% 69.70
ontractor's profit) 581.70

Rs:
Rs:

355787507.xlsx 84
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Rs:
Total Rs:
1.00% Rs:
4.50% Rs:
1.60% Rs:
ges @ 2.50% Rs:
Total Rs:
eads on (A+B+C+other percentages) 13.615% Rs:
48.60 @RS/Cum 39.80
48.60 cum Rs:
cum (A+B+C+D)/48.60 Rs:

hods including excavation for supports in all types of soil / rock strata requiring supports ( excluding cost of provid
chinery, labour, scaling excavated surface, ventilation, lighting, drainage,removing and hauling the excavated mu
l other ancillary operations etc., complete with initial lead upto 1 km and all lifts.

RATE ANALYSIS UNIT : 46.00

Particulars Unit Quantity Rate


in Rs.
Small dia explosive kg 41.00 70.00
Delay detonators Nos 77.00 23.00
Electric detonators Nos 10.00 13.00
Detonating fuse coil Rm 50.00 11.00
Use rate of drill rod 2.5 m long Rm 144.00 42.67
Reconditioning charges @ 10%
Use rate of air hose Hour 24.00 5.78
Use rate of water hose Hour 24.00 5.78
Sundries( paint / template etc ) LS 2.00 20.00
Total cost of Materials Rs:

Description Unit Quantity Rate


in Rs.
Drilling jumbo Hour 11.00 368.40
Fuel / Energy charges Hour 11.00 43.90
Air compressor 15 cmm ( ele ) Hour 6.00 138.80
Fuel / Energy charges Hour 6.00 962.30
Jack hammer ( 4 x 6 hrs ) Hour 24.00 19.80
Fuel / Energy charges Hour 24.00 0.00
Pusher leg Hour 24.00 12.70
Fuel / Energy charges Hour 24.00 0.00
Convey mucker Hour 6.00 822.80
Fuel / Energy charges Hour 6.00 267.90
Dumper ( 2 x 6 hrs ) Hour 12.00 580.70
Fuel / Energy charges Hour 12.00 409.60
Pump 10 hp ( ele ) Hour 6.00 6.70

355787507.xlsx 85
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Fuel / Energy charges Hour 6.00 77.00
Ventilation fans 20 hp Hour 2.00 11.50
Fuel / Energy charges Hour 2.00 154.00
Sundries(explosive van / magazine ) LS 2.00 20.00
Total hire charges of Machinery Rs:

Description Unit Quantity Rate


in Rs.
Crew for Drilling jumbo Hour 11.00 163.30
Crew for Air compressor Hour 6.00 163.30
Crew for Jack hammer Hour 24.00 306.20
Crew for Convey mucker Hour 6.00 163.30
Crew for Dumper Hour 12.00 212.20
Crew for Pump Hour 6.00 77.70
Crew for ventilation fans Hour 2.00 26.80
Surveyor Day 0.50 590.00
Foreman Day 1.00 480.00
Fitter / Mechanic Day 2.00 415.00
Blaster ( Licensed ) Day 1.00 480.00
Helper blasting Day 2.00 370.00
Hammerman 2 Nos Day 2.00 370.00
work inspector 1 in each shift Day 3.00 400.00
Khalasi for mucking shift 4 Nos Day 4.00 415.00
mazdoor
for mucking shift 8 Nos Day 8.00 310.00
for other 2 shifts 1 No each shift Day 2.00 310.00
for cleaning & miscellaneous Day 2.00 310.00
Total cost of Labour Rs:
528.60
harges 13.615% 72.00
ontractor's profit) 600.60

Rs:
Rs:
Rs:
Total Rs:
1.00% Rs:
4.50% Rs:
1.60% Rs:
ges @ 2.50% Rs:
Total Rs:
eads on (A+B+C+other percentages) 13.615% Rs:
46.00 @RS/Cum 39.80
46.00 cum Rs:
cum (A+B+C+D)/46.0 Rs:

355787507.xlsx 86
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
benching tunnelling methods including excavation for supports in all types of soil / rock strata requiring supports (
ore benching including cost of all other materials, machinery, labour,scaling excavated surface, ventilation, lighting
outside tunnel upto specified dump area and all other ancillary operations etc., complete with initial lead upto 1 km

RATE ANALYSIS UNIT : 50.00

Particulars Unit Quantity Rate


in Rs.
Small dia explosive kg 44.00 70.00
Delay detonators Nos 84.00 23.00
Electric detonator Nos 10.00 13.00
Detonating fuse coil Rm 50.00 11.00
Use rate of drill rod 2.5 m long Rm 157.00 42.67
Reconditioning charges @ 10%
Use rate of air hose Hour 26.00 5.78
Use rate of water hose Hour 26.00 5.78
Sundries( paint / template etc ) LS 2.00 20.00
Total cost of Materials Rs:

Description Unit Quantity Rate


in Rs.
Drilling jumbo Hour 12.00 368.40
Fuel / Energy charges Hour 12.00 43.90
Air compressor 15 cmm ( ele ) Hour 6.50 138.80
Fuel / Energy charges Hour 6.50 962.30
Jack hammer ( 4 x 6.5 hrs ) Hour 26.00 19.80
Fuel / Energy charges Hour 26.00 0.00
Pusher leg Hour 26.00 12.70
Fuel / Energy charges Hour 26.00 0.00
Convey mucker Hour 6.50 822.80
Fuel / Energy charges Hour 6.50 267.90
Dumper ( 2 x 6.5 hrs ) Hour 13.00 580.70
Fuel / Energy charges Hour 13.00 409.60
Pump 10 hp ( ele ) Hour 6.50 6.70
Fuel / Energy charges Hour 6.50 77.00
Ventilation fans 20 hp Hour 3.00 11.50
Fuel / Energy charges Hour 3.00 154.00
Sundries(explosive van / magazine ) LS 2.00 20.00
Total hire charges of Machinery Rs:

Description Unit Quantity Rate


in Rs.
Crew for Drilling jumbo Hour 12.00 163.30
Crew for Air compressor Hour 6.50 163.30
355787507.xlsx 87
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Crew for Jack hammer Hour 26.00 306.20
Crew for Convey mucker Hour 6.50 163.30
Crew for Dumper Hour 13.00 212.20
Crew for Pump Hour 6.50 77.70
Crew for Ventilation fan Hour 3.00 26.80
Surveyor Day 0.50 590.00
Foreman Day 1.00 480.00
Fitter / Mechanic Day 2.00 415.00
Blaster ( Licensed ) Day 2.00 480.00
Helper blasting Day 4.00 370.00
Hammerman 2 Nos Day 2.00 370.00
work inspector 1 in each shift Day 3.00 400.00
Khalasi
for pushing muck in heading portion Day 4.00 415.00
for mucking shift 4 Nos Day 4.00 415.00
mazdoor
for mucking shift 8 Nos Day 8.00 310.00
for other 2 shifts 1 No each shift Day 2.00 310.00
for cleaning &miscellaneous Day 2.00 310.00
Total cost of Labour Rs:
568.30
harges 13.615% 77.40
ontractor's profit) 645.70

Rs:
Rs:
Rs:
Total Rs:
1.00% Rs:
4.50% Rs:
1.60% Rs:
ges @ 2.50% Rs:
Total Rs:
eads on (A+B+C+other percentages) 13.615% Rs:

50.00 @RS/Cum 39.8


50.00 cum Rs:
cum (A+B+C+D)/50.0 Rs:

en due to natural causes such as geological faults etc., out of tunnel including breaking large fragments by blastin
dump area or as directed including cost of all materials, machinery,labour, ventilation, drainage, lighting and all o
ad upto 1 km and all lifts.

RATE ANALYSIS UNIT : 100.00

Particulars Unit Quantity Rate


in Rs.

355787507.xlsx 88
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Use rate of drill rod Rm 15.00 27.67
Reconditioning charges @ 10%
Explosive small dia. kg 8.00 70.00
Detonator ( ele ) Nos. 30.00 13.00
Detonating fuse coil Rm 20.00 11.00
Use rate of air hose Hour 4.00 5.78
Use rate of water hose Hour 4.00 5.78
Sundries LS 1.00 20.00
Total cost of Materials Rs:

Description Unit Quantity Rate


in Rs.
Air compressor 15 cmm ( ele ) Hour 1.00 138.80
Fuel / Energy charges Hour 1.00 962.30
Jack hammer Hour 4.00 19.80
Fuel / Energy charges Hour 4.00 0.00
Pump 10 hp ( ele ) Hour 1.00 6.70
Fuel / Energy charges Hour 1.00 77.00
Convey mucker Hour 6.00 822.80
Fuel / Energy charges Hour 6.00 267.90
Dumper 4.5 cum Hour 12.00 580.70
Fuel / Energy charges Hour 12.00 409.60
Sundries LS 1.00 20.00
Total hire charges of Machinery Rs:

Description Unit Quantity Rate


in Rs.
Crew for Air compressor Hour 1.00 163.30
Crew for Jack hammer Hour 4.00 306.20
Crew for Pump Hour 1.00 77.70
Crew for Convey mucker Hour 6.00 163.30
Crew for Dumper Hour 12.00 212.20
Blaster ( Licensed ) Day 0.50 480.00
Helper blasting Day 0.50 370.00
mazdoor Day 8.00 310.00
Total cost of Labour Rs:
79.00
harges 13.615% 10.80
ontractor's profit) 89.80

Rs:
Rs:
Rs:
Total Rs:
1.00% Rs:

355787507.xlsx 89
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
4.50% Rs:
1.60% Rs:
ges @ 2.50% Rs:
Total Rs:
eads on (A+B+C+other percentages) 13.615% Rs:
100.00 @RS/Cum 39.8
100.00 cum Rs:
cum (A+B+C+D)/100.0 Rs:

water collected by natural drainage inside tunnel including providing sump wherever necessary, cost of all mate
ntilation and all other ancillary operations etc., complete.

RATE ANALYSIS UNIT : 15.00

Particulars Unit Quantity Rate


in Rs.
Use rate of G.I.pipe 100 mm dia Hour 1.00 4.67
Sundries LS 0.10 20.00
Total cost of Materials Rs:

Description Unit Quantity Rate


in Rs.
Electric pump 20 hp Hour 1.00 12.30
Fuel / Energy charges Hour 1.00 154.00
Sundries(Starter/Switches ete) LS 0.10 20.00
Total hire charges of Machinery Rs:

Description Unit Quantity Rate


in Rs.
Crew charges for Pump Hour 1.00 77.70
Laying & dismantling pipe LS 0.05 20.00
mazdoor Day 0.10 310.00
Total cost of Labour Rs:
7.30
harges 13.615% 1.00
ontractor's profit) 8.30

Rs:
Rs:
Rs:
Total Rs:
1.00% Rs:
4.50% Rs:
1.60% Rs:

355787507.xlsx 90
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
ges @ 2.50% Rs:
Total Rs:
eads on (A+B+C+other percentages) 13.615% Rs:
15.00 Kwhr Rs:
Kwhr (A+B+C+D)/15.0 Rs:

sides and arch of tunnel in cement mortar 1 : 3 proportion by weight including cost of all materials, machin
her ancillary operations etc., complete with lead upto 1 km and all lifts.

RATE ANALYSIS UNIT : 36.00

Particulars Unit Quantity Rate


in Rs.
Cement kg 600.00 5.65
Sand (Screened) cum 1.10 392.00
Use rate of grout hose 20 m Hour 8.00 5.78
Use rate of water hose 20 m Hour 8.00 5.78
Use rate of guniting nozzle Hour 8.00 3.50
Sundries LS 2.00 20.00
Total cost of Materials Rs:

Description Unit Quantity Rate


in Rs.
Guniting equipment Hour 8.00 110.10
Fuel / Energy charges Hour 8.00 0.00
Air compressor 8.5 cmm ( ele ) Hour 8.00 170.80
Fuel / Energy charges Hour 8.00 433.10
Pump 10 hp ( ele ) Hour 1.00 6.70
Fuel / Energy charges Hour 1.00 77.00
Drilling jumbo Hour 4.00 368.40
Fuel / Energy charges Hour 4.00 43.90
Sundries LS 2.00 20.00
Total hire charges of Machinery Rs:

Description Unit Quantity Rate


in Rs.
Crew for Guniting equipment Hour 8.00 204.10
Crew for Air compressor Hour 8.00 153.10
Crew for pump Hour 1.00 77.70
Crew for Drilling jumbo Hour 4.00 163.30
Mason Cl I Day 1.00 415.00
mazdoor Day 6.00 310.00
Total cost of Labour Rs:
162.90
harges 13.615% 22.20

355787507.xlsx 91
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
ontractor's profit) 185.10

Rs:
Rs:
Rs:
Total Rs:
1.00% Rs:
4.50% Rs:
1.60% Rs:
ges @ 2.50% Rs:
Total Rs:
13.615% Rs:
0.60 tonne @ 129.70
1.10 65.90
36.00 sqm Rs:

sqm (A+B+C+D)/36.0 Rs:

r+38 mm thickness) for slabs duly fixing chain weld wire mesh 100 x 100x5 mm in between the two layers inclu
rges, all heads, lifts, centering, scaffolding, machine mixing, laying concrete with shortcrete machine etc. complet
er-in-Charge

RATE ANALYSIS UNIT : 36.00

Particulars Unit Quantity Rate


in Rs.
Cement kg 1548.00 5.65
Sand (Screened) cum 2.41 392.00
Coarse aggregate 10-4.75 mm size cum 1.03 710.00
Use rate of grout hose 20 m Hour 8.00 5.78
Use rate of water hose 20 m Hour 8.00 5.78
Use rate of guniting nozzle Hour 8.00 3.50
Welded steel wire fabric 100 x 100 x 5 mm kg 108.00 165.00
Sundries LS 2.00 20.00
Total cost of Materials Rs:

Description Unit Quantity Rate


in Rs.
Guniting equipment Hour 8.00 110.10
Fuel / Energy charges Hour 8.00 0.00
Air compressor 8.5 cmm ( ele ) Hour 8.00 170.80
Fuel / Energy charges Hour 8.00 433.10
Pump 10 hp ( ele ) Hour 1.00 6.70
Fuel / Energy charges Hour 1.00 77.00
Drilling jumbo Hour 4.00 368.40

355787507.xlsx 92
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Fuel / Energy charges Hour 4.00 43.90
Sundries LS 2.00 20.00
Total hire charges of Machinery Rs:

Description Unit Quantity Rate


in Rs.
Crew for Guniting equipment Hour 8.00 204.10
Crew for Air compressor Hour 8.00 153.10
Crew for pump Hour 1.00 77.70
Crew for Drilling jumbo Hour 4.00 163.30
Mason Cl I Day 1.00 415.00
mazdoor Day 6.00 310.00
Total cost of Labour Rs:
162.90
harges 13.615% 22.20
ontractor's profit) 185.10

Rs:
Rs:
Rs:
Total Rs:
1.00% Rs:
4.50% Rs:
1.60% Rs:
ges @ 2.50% Rs:
Total Rs:
13.615% Rs:
1.55 tonne @ 129.70
2.41 65.90
36.00 sqm Rs:
sqm (A+B+C+D)/36.0 Rs:

r steel rock bolts with mechanical / wedge type anchorage including drilling 35 mm dia holes, providing 15 cm
plate washers and nuts, tightening bolt by torque wrench, cost of all materials, machinery, labour, ventilation, ligh
omplete with lead upto 1 km and all lifts.

RATE ANALYSIS UNIT : 20.00

Particulars Unit Quantity Rate


in Rs.
Rein.Steel with 5 % wastage kg 86.91 35.00
Steel plate for washers kg 65.94 39.50
Steel plate for wedges kg 6.18 39.50
M S Nuts for bolts kg 4.00 90.00
Use rate of drill rod Rm 20.00 42.67
Reconditioning charges @ 10%

355787507.xlsx 93
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Use rate of air hose 4 Nos Hour 6.00 5.78
Use rate of water hose 4 Nos Hour 6.00 5.78
Sundries ( gas for cutting / heating etc ) LS 5.00 20.00
Total cost of Materials Rs:

Description Unit Quantity Rate


in Rs.
Air compressor 15 cmm ( ele ) Hour 1.50 138.80
Fuel / Energy charges Hour 1.50 962.30
Pump 10 hp ( ele ) Hour 1.00 6.70
Fuel / Energy charges Hour 1.00 77.00
Jack hammer Hour 6.00 19.80
Fuel / Energy charges Hour 6.00 0.00
Pusher leg Hour 6.00 12.70
Fuel / Energy charges Hour 6.00 0.00
Drilling jumbo Hour 4.00 368.40
Fuel / Energy charges Hour 4.00 43.90
Sundries ( lathe, blower etc ) LS 5.00 20.00
Total hire charges of Machinery Rs:

Description Unit Quantity Rate


in Rs.
Crew for Air compressor Hour 1.50 163.30
Crew for pump Hour 1.00 77.70
Crew for Jack hammer Hour 6.00 306.20
Crew for Drilling jumbo Hour 4.00 163.30
Fitter Day 0.50 415.00
Gas cutter Day 1.00 415.00
Turner Day 1.00 480.00
Blacksmith Day 1.00 415.00
Khalasi ( 2 x 0.5 ) Day 1.00 415.00
Hammerman Day 0.50 370.00
mazdoor Day 2.00 310.00
Total cost of Labour Rs:
277.50
harges 13.615% 37.80
ontractor's profit) 315.30

Rs:
Rs:
Rs:
Total Rs:
1.00% Rs:
4.50% Rs:
1.60% Rs:
ges @ 2.50% Rs:

355787507.xlsx 94
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Total Rs:
13.615% Rs:
0.16 tonne @ 151.50
20.00 Rm Rs:
Rm (A+B+C+D)/20.0 Rs:

ion permanent structural steel supports as per details including cost of all materials, machinery, labour, cutti
rainage and all other ancillary operations etc., complete with initial lead upto 1 km and all lifts .

RATE ANALYSIS UNIT : 1.00

Particulars Unit Quantity Rate


in Rs.
Structural steel beams kg 760.00 37.50
Structural steel plates kg 115.00 39.50
Steel bars for tie rods & anchors kg 150.00 37.50
For cutting sections:
Oxygen gas @ 2.4 cum / t cum 2.40 45.00
Acetylene gas @ 0.8 cum / t cum 0.80 330.00
For welding sections:
Electrodes 4 x 300 mm @ 125 Nos / t Nos. 125.00 11.00
For field connections:
M.S.Bolts / Nuts & Washers kg 50.00 90.00
Sundries LS 5.00 20.00
Total cost of Materials Rs:

Description Unit Quantity Rate


in Rs.
Bending machine Hour 8.00 42.60
Fuel / Energy charges Hour 8.00 115.50
Welding set Hour 16.00 16.00
Fuel / Energy charges Hour 16.00 92.40
Drilling Jumbo Hour 12.00 368.40
Fuel / Energy charges Hour 12.00 43.90
Sundries ( lathe / drilling / grinder ) LS 30.00 20.00
Total hire charges of Machinery Rs:

Description Unit Quantity Rate


in Rs.
Crew for Drilling Jumbo Hour 12.00 163.30
Crew fir Bending machine Hour 8.00 122.50
For cutting & preparing sections:
Structural steel Marker Day 1.00 480.00
Gas cutter Day 2.00 415.00
Fitter Day 2.00 415.00

355787507.xlsx 95
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Turner / Driller Day 3.00 480.00
Khalasi Day 2.00 415.00
Helper fabrication Day 4.00 370.00
For welding sections:
Welder Day 2.00 415.00
Helper fabrication Day 2.00 370.00
Khalasi Day 2.00 415.00
For erection of supports:
Foreman Day 1.00 480.00
Structural steel Erector Day 2.00 480.00
Helper erector Day 2.00 370.00
Khalasi Day 4.00 415.00
Total cost of Labour Rs:
15069.60
harges 13.615% 2051.70
ontractor's profit) 17121.30

Rs:
Rs:
Rs:
Total Rs:
1.00% Rs:
4.50% Rs:
1.60% Rs:
ges @ 2.50% Rs:
Total Rs:
13.615% Rs:
1.03 tonne @ 151.50
1.00 tonne Rs:
tonne (A+B+C+D)/1.0 Rs:

ion temperary structural steel supports as per details and dismantling the same before concreting including
nding, welding, grinding, ventilation, lighting, drainage and all other ancillary operations etc.,complete with initial l

RATE ANALYSIS UNIT : 1.00

Particulars Unit Quantity Rate


in Rs.
Structural steel beams kg 760.00 37.50
Structural steel plates kg 115.00 39.50
Tie rods & anchors kg 150.00 37.50
For cutting sections:
Oxygen gas @ 2.40 cum / t cum 2.40 45.00
Acetylene @ 0.8 cum / t cum 0.80 330.00
For welding sections:

355787507.xlsx 96
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Electrodes @ 125 Nos / t Nos. 125.00 11.00
For field connections:
M.S.Bolts / Nuts / Washers kg 50.00 90.00
Sundries LS 20.00 20.00
Total cost of Materials for 20 uses of supports Rs:
Cost per use considering 20 uses Rs:

Description Unit Quantity Rate


in Rs.
Bending machine Hour 8.00 42.60
Fuel / Energy charges Hour 8.00 115.50
Welding set Hour 16.00 16.00
Fuel / Energy charges Hour 16.00 92.40
Sundries LS 30.00 20.00
Total hire charges of Machinery Rs:
Cost per use considering 20 uses Rs:

antling):
Description Unit Quantity Rate
in Rs.
Drilling Jumbo Hour 18.00 368.40
Fuel / Energy charges Hour 18.00 43.90
Sundries LS 10.00 20.00
Total hire charges of Machinery Rs:

Description Unit Quantity Rate


in Rs.
Crew for Bending machine Hour 8.00 122.50
For cutting & preparing sections:
Structural steel Marker Day 1.00 480.00
Gas cutter Day 2.00 415.00
Fitter Day 2.00 415.00
Turner / Driller Day 3.00 480.00
Khalasi Day 2.00 415.00
Helper fabrication Day 4.00 370.00
For welding sections:
Welder Day 2.00 415.00
Helper fabrication Day 2.00 370.00
Khalasi Day 2.00 415.00
Total cost of Labour Rs:
Cost per use considering 20 uses Rs:

Description Unit Quantity Rate


in Rs.
Crew for Drilling jumbo Hour 8.00 163.30

355787507.xlsx 97
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
For erection of supports:
Foreman Day 1.00 480.00
Structural steel Erector Day 2.00 480.00
Helper erector Day 2.00 370.00
Khalasi Day 4.00 415.00
For dismantling of supports:
Foreman Day 0.50 480.00
Structural steel Erector Day 1.00 480.00
Helper erector Day 1.00 370.00
Khalasi Day 2.00 415.00
Total cost of Labour Rs:
7529.90
harges 13.615% 1025.20
ontractor's profit) 8555.10

Rs:
Rs:
on and dismantling Rs:
Rs:
mantling Rs:
Total Rs:
1.00% Rs:
4.50% Rs:
1.60% Rs:
ges @ 2.50% Rs:
Total Rs:
13.615% Rs:
1.0300 tonne @ 151.50
1.00 tonne Rs:
tonne (A+B+C+D)/1.0 Rs:

sition reinforcement steel for tunnel RCC works including cleaning, straightening, cutting, bending, hooking, lappin
5 mm dia.soft annealed steel wire, including cost of all materials, labour,machinery, ventilation, lighting, drainage e

RATE ANALYSIS UNIT : 1.00

Particulars Unit Quantity Rate


in Rs.
Rein.Steel with 5 % wastage tonne 1.05 35000.00
Binding wire 1.25 mm dia kg 13.50 70.00
Sundries ( chairs / spacers etc ) LS 5.00 20.00
Total cost of Materials Rs:

Description Unit Quantity Rate


in Rs.

355787507.xlsx 98
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Nil 0.00 0.00
0.00 0.00
Total hire charges of Machinery Rs:

Description Unit Quantity Rate


in Rs.
Bar bender Day 9.00 490.00
mazdoor Day 15.00 310.00
Total cost of Labour Rs:
9060.00
harges 13.615% 1233.50
ontractor's profit) 10293.5

355787507.xlsx 99
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

Rs:
Rs:
Rs:
Total Rs:
1.00% Rs:
4.50% Rs:
1.60% Rs:
ges @ 2.50% Rs:
Total Rs:
13.615% Rs:
1.05 tonne @ 151.50
1.00 tonne Rs:
tonne (A+B+C+D)/1.0 Rs:

-10 ( 28 days cube compressive strength not less than


using 40 mm down size approved, clean, hard,
l excavated muck for filling and levelling over-cuts
ncluding cost of all materials, machinery, labour, cleaning
aying, levelling, compacting, finishing, curing, lighting,
h initial lead upto 1 km and all lifts. ( Cement
, Blending Ratio of CA--50:30:20, FA : 0.40 cum,

RATE ANALYSIS UNIT : 28.00

Unit Quantity Rate Amount


in Rs. in Rs.
kg 6160.00 5.65 34804.00
cum 12.60 980.00 12348.00
cum 7.56 1045.00 7900.20
cum 5.04 710.00 3578.40
cum 11.20 392.00 4390.40
kg 24.64 95.00 2340.80
LS 2.00 20.00 40.00
Rs: 65401.80

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 8.00 405.40 3243.20
Hour 8.00 346.40 2771.20
Hour 16.00 758.40 12134.40
Hour 16.00 893.90 14302.40
Hour 8.00 6.70 53.60
Hour 8.00 77.00 616.00
Hour 8.00 8.00 64.00
Hour 8.00 7.70 61.60

355787507.xlsx 100
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
LS 2.00 20.00 40.00
Rs: 33286.40

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 8.00 318.20 2545.60
Hour 16.00 265.20 4243.20
Hour 8.00 77.70 621.60
Hour 8.00 146.90 1175.20
Day 1.00 415.00 415.00
Day 1.00 400.00 400.00

Day 2.00 310.00 620.00


Day 3.00 310.00 930.00
Day 2.00 310.00 620.00
Day 7.00 310.00 2170.00
Day 14.00 310.00 4340.00
Day 2.00 310.00 620.00
Day 2.00 310.00 620.00
Rs: 19320.60
690.00
harges 13.615% 93.90
ontractor's profit) 783.90

Rs:
Rs:
Rs:
Total Rs:
1.00% Rs:

355787507.xlsx 101
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
4.50% Rs:
1.60% Rs:
ges @ 2.50% Rs:
Total Rs:
13.615% Rs:
11.20 cum @ 31.3 Rs./Cum
25.20 cum @ 30.2 Rs./Cum
6.16 tonne @ 129.7 Rs./Tonne
28.00 cum Rs:
cum (A+B+C+D)/28.0 Rs:
6 Kms Rs:
1 Kms Rs:
6 Kms Rs:
1 Kms Rs:
sqm Rs:
Say Rs:

M-20 ( 28 days cube compressive strength not less than 20 N / sqmm ) grade cement concrete using 40 mm and
es crushed from tunnel muck for kerb and bed lining including cost of all materials, machinery, labour, formwork, b
agitator cars, placing in position, levelling, vibrating, finishing, curing, ventilation, lighting,drainage and all other an
o 1 km and all lifts.( Cement content 330 kg / cum for use of super plasticiser(0.4% by wt. of cement),CA : 0.90cum

RATE ANALYSIS UNIT : 28.00

Particulars Unit Quantity Rate


in Rs.
Cement 43 Gr kg 9240.00 5.65
Cement for incidentals @ 1 kg / cum kg 28.00 5.65
Fine aggregate (Un-Screened ) cum 11.20 392.00
Coarse aggregate 40-20 mm cum 12.60 980.00
Coarse aggregate 20-10 mm cum 7.56 1045.00
Coarse aggregate 10-4.75 mm cum 5.04 710.00
Super plasticiser kg 36.96 95.00
Use rate of shuttering for kerb / bed sqm 28.00 155.53
Sundries LS 2.00 20.00
Total cost of Materials Rs:

Description Unit Quantity Rate


in Rs.
Batching plant 2 x 1.00 cum Hour 8.00 405.40
Fuel / Energy charges Hour 8.00 346.40
Agitator car 2 cum ( 2 Nos ) Hour 16.00 758.40
Fuel / Energy charges Hour 16.00 893.90
Needle Vibrator Hour 8.00 8.00
Fuel / Energy charges Hour 8.00 7.70
355787507.xlsx 102
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Pump 10 hp ( Ele ) Hour 8.00 6.70
Fuel / Energy charges Hour 8.00 77.00
Sundries LS 5.00 20.00
Total hire charges of Machinery Rs:

Description Unit Quantity Rate


in Rs.
Crew for Batching plant Hour 8.00 318.20
Crew for Agitator car Hour 16.00 265.20
Crew for vibrator Hour 8.00 146.90
Crew for pump Hour 8.00 77.70
For scaling & cleaning bed
Hammerman Day 2.00 370.00
mazdoor Day 6.00 310.00
For loading cement to BP bin
mazdoor Day 3.00 310.00
For miscellaneous work at BP
mazdoor Day 2.00 310.00
For wetting C.A & curing
mazdoor Day 2.00 310.00
Laying concrete for kerb/ invert
Mason Cl I Day 2.00 415.00
Mason Cl II Day 2.00 370.00
mazdoor Day 21.00 310.00
work inspector Day 1.00 400.00
Labour charges for shuttering sqm 28.00 79.80
Total cost of Labour Rs:
859.60

355787507.xlsx 103
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
harges 13.615% 117.00
ontractor's profit) 976.60

Rs:
Rs:
Rs:
Total Rs:
1.00% Rs:
4.50% Rs:
1.60% Rs:
ges @ 2.50% Rs:
Total Rs:
13.615% Rs:
9.27 tonne @ 129.70
11.20 65.90
25.20 65.90
28.00 cum Rs:
cum (A+B+C+D)/28.0 Rs:

M-20 ( 28 days cube compressive strength not less than 20 N / sqmm ) grade cement concrete using 40 mm an
ates crushed from tunnel muck for sides and arch lining including cost of all materials, machinery, labour, formwo
nt in agitator cars, placing in position, levelling, vibrating, finishing, curing, ventilation, lighting,drainage and all oth
pto 1 km and all lifts.( Cement content 330 kg / cum for use of super plasticiser(0.4% by wt. of cement),CA : 0.90cu
Ratio of CA--50:30:20, FA : 0.40 cum)

RATE ANALYSIS UNIT : 48.00

Particulars Unit Quantity Rate


in Rs.
Cement 43 Gr kg 15840.0 5.65
Cement for incidentals @ 1 kg / cum kg 48.00 5.65
Fine aggregate (Un-Screened ) cum 19.20 392.00
Coarse aggregate 40-20 mm cum 21.60 980.00
Coarse aggregate 20-10 mm cum 12.96 1045.00
Coarse aggregate 10-4.75 mm cum 8.64 710.00
Super plasticiser kg 63.36 95.00
Use rate of end shuttering sqm 6.00 155.53
Use rate of steel gantry sqm 100.00 79.80
Sundries ( placer pipe etc ) LS 5.00 20.00
Total cost of Materials Rs:

Description Unit Quantity Rate


in Rs.
Air compressor ( Ele ) 8.5 cmm Hour 16.00 170.80
Fuel / Energy charges @ 75 % load Hour 12.00 433.10
355787507.xlsx 104
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Batching plant 2 x 1.00 cum Hour 12.00 405.40
Fuel / Energy charges Hour 12.00 346.40
Agitator car 2 cum ( 2 Nos ) Hour 32.00 758.40
Fuel / Energy charges Hour 32.00 893.90
Concrete placer pump Hour 16.00 102.00
Fuel / Energy charges Hour 16.00 2.00
Needle Vibrator / Shutter vibrator Hour 8.00 8.00
Fuel / Energy charges Hour 8.00 7.70
Pump 10 hp ( Ele ) Hour 8.00 6.70
Fuel / Energy charges Hour 8.00 77.00
Sundries LS 5.00 20.00
Total hire charges of Machinery Rs:

Description Unit Quantity Rate


in Rs.
Crew charges for Air compressor Hour 16.00 153.10
Crew charges for Batching plant Hour 16.00 318.20
Crew charges for Agitator car Hour 32.00 265.20
Crew charges for placer pump Hour 16.00 16.80
Crew charges for vibrator Hour 8.00 146.90
Crew charges for Pump Hour 8.00 77.70
For scaling & cleaning
Stone chiseller Cl II Day 0.50 370.00
mazdoor Day 1.00 310.00
For dismantling / Laying track
Surveyer Day 0.50 590.00
Fitter shuttering Day 0.50 370.00
Helper shuttering 2 x 0.5 Day 1.00 370.00

355787507.xlsx 105
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Khalasi 6 x 0.5 Day 3.00 415.00
mazdoor 2 x 0.5 Day 1.00 310.00
For Moving / Positioning gantry
Surveyer Day 0.50 590.00
Foreman Day 0.50 480.00
Fitter shuttering Day 0.50 370.00
Helper shuttering 2 x 0.5 Day 1.00 370.00
Khalasi 6 x 0.5 Day 3.00 415.00
mazdoor 2 x 0.5 Day 1.00 310.00
For loading cement to BP bin
mazdoor Day 5.00 310.00
For miscellaneous works of BP
mazdoor Day 2.00 310.00
For Erection/Dismantling bulk head sqm 6.00 79.80
For Laying concrete by placer
Masom Cl I Day 3.00 415.00
mazdoor Day 9.00 310.00
work inspector Day 3.00 400.00
For wetting C.A / Curing etc
mazdoor Day 3.00 310.00
Total cost of Labour Rs:
676.10
harges 13.615% 92.10
ontractor's profit) 768.20

Rs:
Rs:
Rs:
Total Rs:
1.00% Rs:
4.50% Rs:
1.60% Rs:
ges @ 2.50% Rs:
Total Rs:
13.615% Rs:
15.89 tonne @ 129.70
19.20 65.90
43.20 65.90
48.00 cum Rs:
cum (A+B+C+D)/48.0 Rs:

M-25 ( 28 days cube compressive strength not less than 25 N / sq mm ) grade cement concrete using 20 mm dow
tes including cost of all materials, machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
uring etc.,complete for RCC works of gallery, sluice, spillway crest, spillway d / s face, energy dissipating structure
locations with initial lead upto 1 km and all lifts.( Cement content : 400 kg / cum with use of super plasticiser,CA :
cum)

355787507.xlsx 106
cum)
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

RATE ANALYSIS
RATE ANALYSIS UNIT : 48.00

Particulars Unit Quantity Rate


in Rs.
Cement 43 Gr kg 19200.0 5.65
Cement for incidentals @ 1 kg / cum kg 48.00 5.65
Fine aggregate (Un-Screened ) cum 21.60 392.00
Coarse aggregate 20-10 mm cum 28.08 1045.00
Coarse aggregate 10-4.75 mm cum 15.12 710.00
Super plasticiser kg 63.36 95.00
Use rate of end shuttering sqm 6.00 155.53
Use rate of steel gantry sqm 100.00 79.80
Sundries ( placer pipe etc ) LS 5.00 20.00
Total cost of Materials Rs:

Description Unit Quantity Rate


in Rs.
Air compressor ( Ele ) 8.5 cmm Hour 16.00 170.80
Fuel / Energy charges @ 75 % load Hour 12.00 433.10
Batching plant 2 x 1.00 cum Hour 12.00 405.40
Fuel / Energy charges Hour 12.00 346.40
Agitator car 2 cum ( 2 Nos ) Hour 32.00 758.40
Fuel / Energy charges Hour 32.00 893.90
Concrete placer pump Hour 16.00 102.00
Fuel / Energy charges Hour 16.00 2.00
Needle Vibrator / Shutter vibrator Hour 8.00 8.00
Fuel / Energy charges Hour 8.00 7.70
Pump 10 hp ( Ele ) Hour 8.00 6.70
Fuel / Energy charges Hour 8.00 77.00
Sundries LS 5.00 20.00
Total hire charges of Machinery Rs:

Description Unit Quantity Rate


in Rs.
Crew charges for Air compressor Hour 16.00 153.10
Crew charges for Batching plant Hour 16.00 318.20
Crew charges for Agitator car Hour 32.00 265.20
Crew charges for placer pump Hour 16.00 16.80
Crew charges for vibrator Hour 8.00 146.90
Crew charges for Pump Hour 8.00 77.70
For scaling & cleaning
Stone chiseller Cl II Day 0.50 370.00
mazdoor Day 1.00 310.00
For dismantling / Laying track
Surveyer Day 0.50 590.00
Fitter shuttering Day 0.50 370.00
355787507.xlsx 107
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Helper shuttering 2 x 0.5 Day 1.00 370.00
Khalasi 6 x 0.5 Day 3.00 415.00
mazdoor 2 x 0.5 Day 1.00 310.00
For Moving / Positioning gantry
Surveyer Day 0.50 590.00
Foreman Day 0.50 480.00
Fitter shuttering Day 0.50 370.00
Helper shuttering 2 x 0.5 Day 1.00 370.00
Khalasi 6 x 0.5 Day 3.00 415.00
mazdoor 2 x 0.5 Day 1.00 310.00
For loading cement to BP bin
mazdoor Day 5.00 310.00
For miscellaneous works of BP
mazdoor Day 2.00 310.00
For Erection/Dismantling bulk head sqm 6.00 79.80
For Laying concrete by placer
Masom Cl I Day 3.00 415.00
mazdoor Day 9.00 310.00
work inspector Day 3.00 400.00
For wetting C.A / Curing etc
mazdoor Day 3.00 310.00
Total cost of Labour Rs:
676.10
harges 13.615% 92.10
ontractor's profit) 768.20

Rs:
Rs:
Rs:
Total Rs:
1.00% Rs:
4.50% Rs:
1.60% Rs:
ges @ 2.50% Rs:
Total Rs:
13.615% Rs:
19.25 tonne @ 129.70
21.60 65.90
43.20 65.90
48.00 cum Rs:
cum (A+B+C+D)/48.0 Rs:

es in concrete / rock by percussion drilling using jack hammer or stooper drills as directed to specified depth fo
ng cost of all materials, machinery, labour, cleaning holes, ventilation, lighting, drainage and all other ancillary ope

RATE ANALYSIS UNIT : 100.00

Particulars Unit Quantity Rate

355787507.xlsx 108
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
in Rs.
Use rate of drill rod Rm 100.00 42.67
Reconditioning charges @ 10%
Use rate of air hose 4 Nos Hour 32.00 5.78
Use rate of water hose 4 Nos Hour 32.00 5.78
Sundries LS 3.00 20.00
Total cost of Materials Rs:

Description Unit Quantity Rate


in Rs.
Air compressor 15 cmm ( ele ) Hour 8.00 138.80
Fuel / Energy charges Hour 8.00 962.30
Pump 10 hp ( ele ) Hour 4.00 6.70
Fuel / Energy charges Hour 4.00 77.00
Jack hammer Hour 32.00 19.80
Fuel / Energy charges Hour 32.00 0.00
Pusher leg Hour 32.00 12.70
Fuel / Energy charges Hour 32.00 0.00
Drilling jumbo Hour 8.00 368.40
Fuel / Energy charges Hour 8.00 43.90
Sundries LS 5.00 20.00
Total hire charges of Machinery Rs:

Description Unit Quantity Rate


in Rs.
Crew charges for Air compressor Hour 8.00 163.30
Crew charges for Pump Hour 4.00 77.70
Crew charges for Jack Hammer Hour 32.00 306.20
Crew charges for Drilling Jumbo Hour 8.00 163.30
mazdoor Day 2.00 310.00
Total cost of Labour Rs:
133.40
harges 13.615% 18.20
ontractor's profit) 151.60

Rs:
Rs:
Rs:
Total Rs:
1.00% Rs:
4.50% Rs:
1.60% Rs:
ges @ 2.50% Rs:
Total Rs:
14% Rs:
100.00 Rm Rs:
Rm (A+B+C+D)/100.0 Rs:

s under specified pressure for consolidation / contact grouting including cost of all materials, machiner
ilation,lighting, drainage and other ancillary operations etc., complete with lead upto 1 km and all l
355787507.xlsx 109
s under specified pressure for consolidation / contact grouting including
PRLIS Stage-2cost of allVolume-3C,
P.S DPR materials, Part-IV
machiner
ilation,lighting, drainage and other ancillary operations etc., complete with lead upto 1 km and all l

portion, the grout intake will be heavy due to inadequate


of concrete by placer pump.
zone is considered at 75 kg per metre. Beyond contact
kg per metre to 50 kg per metre depending on the
g / after excavation.
on /contact grouting is considered at 50 kg per metre.
hift is considered at 1500 kg.
r 8 hours.
g grouting of top holes.
mping water to storage tank.
185.00 / Rm Rs:
: 800
( cost / life ) Rs:
185.00 / Rm Rs:
: 800
( cost / life ) Rs:

RATE ANALYSIS UNIT : 1.50

Particulars Unit Quantity Rate


in Rs.
Cement tonne 1.50 5650.00
Use rate of grouting hose 50 m Hour 8.00 11.56
Use rate of water hose 50 m Hour 8.00 11.56
Sundries LS 2.00 20.00
Total cost of Materials Rs:

Description Unit Quantity Rate


in Rs.
Grouting machine Hour 8.00 24.90
Fuel / Energy charges Hour 8.00 38.50
Pump 10 hp ( ele ) Hour 2.00 6.70
Fuel / Energy charges Hour 2.00 77.00
Drilling jumbo Hour 2.00 368.40
Fuel / Energy charges Hour 2.00 43.90
Sundries LS 2.00 20.00
Total hire charges of Machinery Rs:

Description Unit Quantity Rate


in Rs.
Crew for Grout pump Hour 8.00 244.90
Crew for pump Hour 2.00 77.70

355787507.xlsx 110
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Crew for Drilling jumbo Hour 2.00 163.30
mazdoor Day 2.00 310.00
Total cost of Labour Rs:
2040.80
harges 13.615% 277.90
ontractor's profit) 2318.70

Rs:
Rs:
Rs:
Total Rs:
1.00% Rs:
4.50% Rs:
1.60% Rs:
ges @ 2.50% Rs:
Total Rs:
13.615% Rs:
1.50 tonne @ 129.50
1.50 tonne Rs:
tonne (A+B+C+D)/1.50 Rs:

holes vertical or inclined in rock / concrete in tunnel by percussion drilling using waggon drill or other suitable dr
s, machinery, labour, ventilation, lighting, drainage etc., complete.

RATE ANALYSIS UNIT : 120.00

Particulars Unit Quantity Rate


in Rs.
Use rate of cross bit 75 mm dia Rm 120.00 125.00
Use rate of air hose 20 m Hour 16.00 4.63
Use rate of water hose 20 m Hour 16.00 4.63
Use rate of extension rods Rm 120.00 8.90
Total cost of Materials Rs:

Description Unit Quantity Rate


in Rs.
Waggon drill Hour 16.00 188.50
Fuel / Energy charges Hour 16.00 0.00
Air compressor 15 cmm ( ele ) Hour 8.00 138.80
Fuel / Energy charges Hour 8.00 962.30
Pump 10 hp ( ele ) Hour 6.00 6.70
Fuel / Energy charges Hour 6.00 77.00
Sundries LS 2.00 20.00
Total hire charges of Machinery Rs:

355787507.xlsx 111
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

Description Unit Quantity Rate


in Rs.
Crew for Waggon drill Hour 16.00 265.20
Crew for Air compressor Hour 8.00 163.30
Crew for Pump Hour 6.00 77.70
mazdoor Day 2.00 310.00
Total cost of Labour Rs:
55.30
harges 13.615% 7.50
ontractor's profit) 62.80

Rs:
Rs:
Rs:
Total Rs:
1.00% Rs:
4.50% Rs:
1.60% Rs:
ges @ 2.50% Rs:
Total Rs:
13.615% Rs:
120.00 Rm Rs:
(A+B+C+D)/120.0 Rs:

of soil including boulders upto 0.30 m diameter for dam, spillway, intake structure and other appurten
atly in dump area or disposing off the same as directed etc., complete with initial lead upto 1 km and
UNIT 880
Particulars Unit Quantity Rate
in Rs.
0.00 0.00
0.00 0.00
Rs:

Description Unit Quantity Rate


in Rs.
Shovel 0.85 cum capacity Hour 8.00 1706.60
Fuel / Energy charges Hour 8.00 893.90
Dumpers 5 cum capacity 6 Nos Hour 48.00 580.70
Fuel / Energy charges Hour 48.00 409.60
Tipper 5 cum capacity 1 No Hour 8.00 446.70
Fuel / Energy charges Hour 8.00 307.20
Rs:

Description Unit Quantity Rate


in Rs.
Crew for Shovel Hour 8.00 221.00

355787507.xlsx 112
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Crew for Dumper Hour 48.00 212.20
Crew for Tipper Hour 8.00 165.80
work inspector Day 1.00 400.00
mazdoor Day 16.00 310.00
Total cost of Labour Rs:
21.20
harges 14% 2.90
ontractor's profit) 24.10

Rs:
Rs:
Rs:
Total Rs:
13.615% Rs.
880.00 39.8
880.00 cum Rs:
(A+B+C+D)/880 Rs:

y rock (including HDR) without blasting including boulders above 0.3 m upto 0.6 m dia for dam, spillway, inta
ng the excavated material neatly in dump area or disposing off the same as directed etc., complete with initial lea

UNIT : 520
Particulars Unit Quantity Rate
in Rs.
NIL 0.00 0.00
0.00 0.00
Total cost of Materials Rs:

Description Unit Quantity Rate


in Rs.
Shovel 0.85 cum capacity Hour 8.00 1706.60
Fuel / Energy charges Hour 8.00 893.90
Dumpers 5 cum capacity( 4 Nos) Hour 32.00 580.70
Fuel / Energy charges Hour 32.00 409.60
Tipper 5 cum capacity( 1 No) Hour 8.00 446.70
Fuel / Energy charges Hour 8.00 307.20
Rs:

Description Unit Quantity Rate


in Rs.
Crew for Shovel Hour 8.00 221.00
Crew for Dumper Hour 32.00 212.20
Crew for Tipper Hour 8.00 165.80
work inspector Day 1.00 400.00
Crowbarman Day 2.50 370.00
mazdoor Day 10.00 310.00
Total cost of Labour Rs.
27.50
harges 13.615% 3.70

355787507.xlsx 113
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
ontractor's profit) 31.20

Rs:
Rs:
Rs:
Total Rs:
13.615% Rs.
520.00 39.8
520.00 cum Rs:
(A+B+C+D)/520 Rs:

ock (including F&F rock) requiring blasting including boulders above 0.6 m upto 1.2 m dia. for dam, sp
s and placing the excavated material neatly in dump area or disposing off the same as directed etc., complete wit
upto 1 km and all lifts.

UNIT : 520.00
Description Unit Quantity Rate
in Rs.
Use rate of 1.5 m drill rod Rm 216.00 20.75
Reconditioning charges @ 10%
Use rate of air hose 4 Nos. Hour 26.00 11.56
Explosive small dia kg 104.00 70.00
Electric detonators Nos 154.00 13.00
Fuse coil Rm 320.00 11.00
Sundries LS 5.00 20.00
Rs.

Description Unit Quantity Rate


in Rs.
Shovel 0.85 cum capacity Hour 8.00 1706.60
Fuel / Energy charges Hour 8.00 893.90
Dumpers 5 cum capacity 4 Nos. Hour 32.00 580.70
Fuel / Energy charges Hour 32.00 409.60
Tipper 5 cum capacity 1 No Hour 8.00 446.70
Fuel / Energy charges Hour 8.00 307.20
Air compressor 8.5 cmm ( ele ) 2 Nos Hour 13.00 170.80
Fuel / Energy charges Hour 13.00 433.10
Jack hammers 4 Nos. Hour 26.00 19.80
Fuel / Energy charges Hour 26.00 0.00
Rs:

Unit Quantity Rate


in Rs.
Crew for Shovel Hour 8.00 221.00
Crew for Dumper Hour 32.00 212.20
Crew for Tipper Hour 8.00 165.80
Crew for Air compressor Hour 13.00 153.10
Crew for Jack hammer Hour 26.00 306.20
355787507.xlsx 114
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
work inspector Day 1.00 400.00
Blaster Day 1.00 480.00
Helper blaster Day 1.00 370.00
Crowbarman Day 2.50 370.00
Stone breaker Day 1.00 370.00
mazdoor Day 10.00 310.00
Total cost of Labour Rs.
49.00
harges 13.615% 6.70
ontractor's profit) 55.70

Rs:
Rs:
Rs:
Total Rs:
13.615% Rs.
520.00 39.8
520.00 cum. Rs:
(A+B+C+D)/520 Rs:

of all toughness by blasting including boulders above 1.2 m dia. for dam, spillway, intake structure and other appu
n dump area or stack yard including levelling as directed etc., complete with initial lead upto 1 km and all lifts.

RATE ANALYSIS
UNIT
320.00
Unit Quantity Rate
in Rs.
Use rate of drill rod 1.5 m long Rm 310.00 27.67
Reconditioning charges @ 10%
Use rate of air hose 4 Nos. Hour 48.00 11.56
Explosive small dia kg 95.00 70.00
Ordinary detonators Nos 10.00 7.00
Electric detonators Nos 333.00 13.00
Fuse coil Rm 450.00 11.00
Sundries LS 5.00 20.00
Rs:

Unit Quantity Rate


in Rs.
Shovel 0.85 cum capacity Hour 8.00 1706.60
Fuel / Energy charges Hour 8.00 893.90
Dumpers 5 cum capacity 3 Nos. Hour 24.00 580.70
Fuel / Energy charges Hour 24.00 409.60
Tipper 5 cum capacity 1 No Hour 4.00 446.70
Fuel / Energy charges Hour 4.00 307.20

355787507.xlsx 115
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Angle dozer 90 hp Hour 1.00 1715.50
Fuel / Energy charges Hour 1.00 625.30
Air compressor 8.5 cmm (ele) 2 Nos. Hour 24.00 170.80
Fuel / Energy charges Hour 24.00 433.10
Jack hammers 4 Nos. Hour 48.00 19.80
Fuel / Energy charges Hour 48.00 0.00
Rs.

Unit Quantity Rate


in Rs.
Crew for Shovel Hour 8.00 221.00
Crew for Dumper Hour 24.00 212.20
Crew for Tipper Hour 4.00 165.80
Crew for Dozer Hour 1.00 221.00
Crew for Air compressor Hour 24.00 153.10
Crew for Jack hammer Hour 48.00 306.20
work inspector Day 1.00 400.00
Blaster Day 1.00 480.00
Helper blaster Day 1.00 370.00
Crowbarman Day 1.00 370.00
Stone breaker Day 2.00 370.00
mazdoor Day 6.00 310.00
Rs.
94.80
harges 13.615% 12.90
ontractor's profit) 107.70

Rs:
Rs:
Rs:
Total Rs:
13.615% Rs.
320.00 39.8
320.00 cum Rs:
(A+B+C+D)/320 Rs:

3 m long cold twisted deformed steel dowel bars with one end driven into 45 to 50 mm diame
other end provided with L-bend for embedding in concrete / masonry of over flow / non-over flow blo
cost of drilling and cleaning hole, filling hole with cement mortar 1 : 1 proportion, driving anchor ro
complete with initial lead upto 1 km and all lifts.

RATE ANALYSIS
UNIT:
25
Particulars Unit Quantity Rate
in Rs.
Use rate of drill bit 50 mm dia Rm 37.50 62.50

355787507.xlsx 116
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Use rate of air hose 50 m Hour 4.00 18.63
Anchor rod 25 mm dia kg 303.22 35.00
Cement kg 75.00 5.65
Sand ( screened ) cum 0.05 392.00
Total cost of Materials Rs:

Description Unit Quantity Rate


in Rs.
Air compressor 8.5 cmm ( ele ) Hour 4.00 170.80
Fuel / Energy charges Hour 4.00 433.10
Waggon drill Hour 4.00 188.50
Fuel / Energy charges Hour 4.00 0.00

355787507.xlsx 117
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Total hire charges of Machinery Rs:

Description Unit Quantity Rate


in Rs.
Crew for Air compressor Hour 4.00 153.10
Crew for Waggon drill Hour 4.00 265.20
Bar bender Day 0.50 490.00
Mason Cl- II Day 0.50 370.00
mazdoor Day 1.00 310.00
Total cost of Labour Rs:

ad charges 13.615%
ng contractor's profit)

Rs:
Rs:
Rs:
Total Rs:
verheads on (A+B+C) 13.615% Rs.

0.08 tonne @ 129.70


0.05 tonne @ 151.50
25.00 Nos. Rs:
(A+B+C+D)/25 Rs:

osition reinforcement steel for RCC,below 36 dia rods overlaps and wastages wherever require
led steel wire, including cost of all materials, machinery, labour etc., complete with initial lead upto
er NHAI-data
UNIT : 1.00
Unit Quantity Rate
in Rs.
Rein.Steel with 5 % wastage tonne 1.05 35000.00
Binding wire 1.25 mm dia kg 9.00 70.00
Rs:

Unit Quantity Rate


in Rs.
Rs:

Unit Quantity Rate


in Rs.
Bar bender Day 2.00 490.00
mazdoor Day 6.84 310.00

3100.40
harges 13.615% 422.10
ontractor's profit) 3522.50

355787507.xlsx 118
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

eads on A+B+C 13.615%


1.05 Rs/Tonne 151.50
1.00 tonne

M-20 ( 28 days cube compressive strength not less than 20 N / sq mm ) grade cement concrete using 40 mm down
tes including cost of all materials, machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing,
uring etc.,complete for RCC works of gallery, sluice, spillway crest, spillway d / s face, energy dissipating structure
locations with initial lead upto 1 km and all lifts.

h use of super plasticiser,CA : 0.90 cum, blending ratio of CA--50:30:20, FA : 0.40 cum)

RATE ANALYSIS
UNIT:
240.00
Particulars Unit Quantity Rate
in Rs.
Cement for mix kg 74400 5.65
Cement for incidentals @ 3 kg / cum kg 720.00 5.65
Coarse aggregate 40-20 mm cum 108 980.00
Coarse aggregate 20-10 mm cum 64.8 1045.00
Coarse aggregate 10 mm below cum 43.2 710.00
Fine aggregate (Un-Screened ) cum 96 392.00
Super Plasticizer or AEA kg 297.60 95.00
Use rate of shuttering sqm 360.00 326.08
Scaffolding of shuttering @ 15%
Total cost of Materials Rs:

Description Unit Quantity Rate


in Rs.
Batching plant 2 x 1.5 cum Hour 8.00 518.10
Fuel / Energy charges Hour 8.00 423.40
Air compressor 7 cmm ( ele ) Hour 8.00 131.90
Fuel / Energy charges Hour 8.00 346.40
Tipper Hour 32.00 446.70
Fuel / Energy charges Hour 32.00 307.20
Tower crane 5 t Hour 16.00 867.10
Fuel / Energy charges Hour 16.00 200.20
Concrete bucket Hour 40.00 15.80
Fuel / Energy charges Hour 40.00 0.00
10 hp pump ( ele ) Hour 8.00 6.70
Fuel / Energy charges Hour 8.00 77.00
Needle vibrator 60 mm dia ( ele ) Hour 16.00 9.70
Fuel / Energy charges Hour 16.00 11.50
Sundries LS 10.00 20.00

355787507.xlsx 119
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Total hire charges of Machinery Rs:

Description Unit Quantity Rate


in Rs.
Crew for Batching plant Hour 8.00 318.20
Crew for Air compressor Hour 8.00 153.10
Crew for Tipper ( 4 ) Hour 32.00 165.80
Crew for Tower crane ( 2 ) Hour 16.00 176.80
Crew for Pump Hour 8.00 77.70
Crew for Needle vibrator ( 2 ) Hour 16.00 146.90
Mason Class-I Day 4.00 415.00
Foreman Day 2.00 480.00
mazdoor
for silo ( cement handling ) Day 2.00 310.00
for batching plant Day 2.00 310.00
for conveyor system Day 2.00 310.00
for laying & vibrating Day 6.00 310.00
for cleaning / washing / curing Day 2.00 310.00
Labour cost for shuttering sqm 360.00 119.70
Labour cost for scaffolding @ 15%
Total cost of Labour Rs:

harges 13.615%
ontractor's profit)

Rs:
Rs:
Rs:
Total Rs:
3.0%
harges @ 2.50%
ack @ 4.0%
Total Rs:
eads on (A+B+C+other percentages) 13.615% Rs.
96.00 cum @ 65.90
216.00 cum @ 65.90
75.12 tonne @ 129.70
240.00 cum Rs:
Cum (A+B+C+D)/240 Rs:

15 ( 28 days cube compressive strength not less than 15 N / sq mm ) grade cement concrete using 40 mm down s
ng cost of all materials, machinery, labour, formwork, centering, scaffolding, cleaning, batching, mixing, placing in
,complete for plain concrete works with initial lead upto 1 km and all lifts. ( Cement content : 260 kg / cum with us
io of CA -- 50:30:20, FA : 0.40 cum)

RATE ANALYSIS
UNIT: 14
Particulars Unit Quantity Rate

355787507.xlsx 120
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
in Rs.
Cement for mix kg 3640.00 5.65
Cement for incidentals @ 3 kg / cum kg 42.00 5.65
Coarse aggregate 40-20 mm cum 6.3 980.00
Coarse aggregate 20-10 mm cum 3.78 1045.00
Coarse aggregate 10 mm below cum 2.52 710.00
Fine aggregate (Un-Screened ) cum 5.6 392.00
Super Plasticizer kg 14.56 95.00
Use rate of shuttering for 40 uses sqm 14.00 217.39
Total cost of Materials Rs:

Description Unit Quantity Rate


in Rs.
Concrete mixer 300 / 200 ltr ( ele ) Hour 8.00 51.70
Fuel / Energy charges Hour 8.00 38.50
10 hp pump ( ele ) Hour 1.00 6.70
Fuel / Energy charges Hour 1.00 77.00
Needle vibrator 60 mm dia ( ele ) Hour 8.00 8.00
Fuel / Energy charges Hour 8.00 7.70
Total hire charges of Machinery Rs:

Description Unit Quantity Rate


in Rs.
Crew for Concrete mixer Hour 8.00 204.10
Crew for Pump Hour 1.00 77.70
Crew for Needle vibrator Hour 8.00 146.90
Mason Class-I Day 1.00 415.00
mazdoor
for batching cement ( cement handling Day 2.00 310.00
for batching other materials Day 9.00 310.00
for loading mortar pans Day 4.00 310.00
for laying Day 3.00 310.00
for conveying concrete Day 14.00 310.00
for cleaning / washing / curing Day 1.00 310.00
Labour cost of shuttering sqm 14.00 79.80
Total cost of Labour Rs:

harges 13.615%
ontractor's profit)

Rs:
Rs:
Rs:
Total Rs:
13.615% Rs.
5.60 cum @ 65.90
12.60 cum @ 65.90

355787507.xlsx 121
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
3.68 tonne @ 129.70
14.00 cum Rs:
Cum (A+B+C+D)/14 Rs:

sting and commissioning of vertical lift gates and stoplog gate elements, consisting of skin plate, horizontal
added slide blocks/bearings, guide shoes,rubber seals, clamps etc., with all accessories including cost of all
g etc.,complete as per specifications and approved drawings (without painting on sand-blasted or mechanical clea
f rates under items in this chapter and add as applicable separately)

2002 (Spillway Stop log gate Elements


Vent Size: 12.624 X 0.50 M 16 Elements

7350.00 / Each Rs: 7350.00


: 1000
( cost / life ) Rs: 7.35
14203.00 / Each Rs: 14203.00
: 600
( cost / life ) Rs: 23.67
RATE ANALYSIS UNIT : 119.000

particulars Unit Quantity Rate


in Rs.
Structural steel
Angles / beams / channels / bars kg 5280.00 37.50
Plates / flats kg 112880.00 37.00
Alloy steel components
Lifting pins kg 520.00 420.00
Bolt / Nut / Washer
GI bolts / nuts / washers kg 600.00 120.00
Rubber seals
Bottom seal Rm 210.00 780.00
Side seals Rm 18.00 1210.00
Oxygen gas cum 2714.00 45.00
Acetyline gas cum 905.00 330.00
Welding electrodes Nos 86554.00 11.00
Welding electrodes ( LH ) Nos 16486.00 18.00
Use rate welding holder set Hour 12880.00 7.65
Use rate gas cutting torch set Hour 2714.00 2.08
Sundries LS 400.00 20.00
Total cost of Materials Rs:

Description Unit Quantity Rate


in Rs.
Welding transformer Hour 12880.00 16.00
Fuel / Energy charges Hour 12880.00 92.40
Pug cutting machine Hour 6440.00 6.40
Fuel / Energy charges Hour 6440.00 3.80
Mobile crane 16 T Hour 360.00 2278.10
355787507.xlsx 122
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Fuel / Energy charges Hour 360.00 75.00
Stationery derric crane Hour 238.00 86.10
Fuel / Energy charges Hour 238.00 0.00
Grinding machine Hour 238.00 22.50
Fuel / Energy charges Hour 238.00 38.50
Drilling machines Hour 357.00 22.50
Fuel / Energy charges Hour 357.00 38.50
Bending Machine Hour 240.00 42.60
Fuel / Energy charges Hour 240.00 115.50
Sundries LS 180.00 20.00
Total hire charges of Machinery Rs:

Description Unit Quantity Rate


in Rs.
Crew for Mobile crane 16T Hour 360.00 489.20
Crew for Drilling machine Hour 357.00 187.20
Crew for Grinding machine Hour 238.00 187.20
Crew for Bending machine Hour 240.00 122.50
Foreman Day 120.00 480.00
Marker / Fabricator / Erector Day 195.00 480.00
Gas cutter Day 100.00 415.00
Welder ( General ) Day 1442.00 415.00
Welder ( X - ray ) Day 275.00 480.00
Khalasi Day 2023.00 415.00
Helper fabrication / erection Day 2727.00 370.00
Electrician Day 10.00 480.00
Total cost of Labour Rs:
es @ 30% on total cost of labour
Total Cost of Labour
33793.00
harges 13.615% 4600.90
ontractor's profit) 38393.90

Rs:
Rs:
Rs:
Total Rs:
0.00% Rs:
materials) Total Rs:
3% Rs:
Total Rs:
eads on (A+B+C+D+E) 13.615% Rs:

Rs. 18.90 per tonne


66.30 per tonne
119.00 tonne Rs:
Rate per tonne Rs:
nd commissioning of adequate capacity Class- II type moving gantry crane consisting of rail mounted gan
ravel arrangements, rope drums, gear systems, electric motors, electro-magnetic brake system, cabin, control pa
c., with all accessories for operating spillway stop log gate elements and river sluice /canal sluice emergency gate
etc., complete with all leads and lifts.
355787507.xlsx 123
nd commissioning of adequate capacity Class- II type moving gantry crane consisting of rail mounted gan
ravel arrangements, rope drums, gear systems, electric motors, electro-magnetic brake system, cabin, control pa
c., with all accessories for operating spillway stop log gate elements andStage-2
PRLIS river sluice /canalVolume-3C,
P.S DPR sluice emergency
Part-IVgate
etc., complete with all leads and lifts.

RATE ANALYSIS UNIT : 30.856


25
particulars Unit Quantity Rate
in Rs.
Structural steel
Angles / beams / channels / bars kg 1743.00 37.50
Plates / flats kg 19700.00 37.00
Chequered plates kg 820.00 63.00
Cast steel components :
Rope drums 2 Nos/Gears kg 1320.00 220.00
pinions kg 1165.00 210.00
Wheels / Pulleys kg 2255.00 180.00
Plummer blocks / Couplings kg 817.00 180.00
Forged steel components
Hook / Shackle kg 127.00 260.00
Alloy steel components
Shafts kg 556.00 230.00
Pins kg 524.00 420.00
Bronze alloy components :
Bronze bearings / bush kg 181.00 920.00
Wire rope 28 mm dia 6/37 construction kg 406.00 200.00
MS Bolt / Nut / Washer kg 63.00 90.00
MS pipe 32 mm dia for railing Rm 50.00 185.00
Worm reducers Nos. 4.00 224400.0
Electric motor 17.5 hp No. 1.00 85800.00
Electric motor 5 hp Nos. 2.00 33000.00
Electric motor 3 hp No. 1.00 23100.00
Ele-magnetic / Thruster brakes Nos. 4.00 35200.00

Electric cable / switch / control panel etc LS 3.00 50380.00


Oxygen gas cum 579.00 45.00
Acetyline gas cum 193.00 330.00
Welding electrodes Nos 1123.00 11.00
Welding electrodes ( LH ) Nos 10110.00 18.00
Grease kg 50.00 260.00
Use rate welding holder set Hour 1197.00 7.65
Use rate gas cutting torch set Hour 150.00 2.08
Sundries LS 200.00 20.00
Total cost of Materials Rs:

Description Unit Quantity Rate


in Rs.
Welding transformer Hour 1197.00 16.00
Fuel / Energy charges Hour 748.00 92.40
Tower crane 5 t capacity Hour 6.00 867.10
Fuel / Energy charges Hour 6.00 200.20
Pug cutting machine Hour 235.00 6.40

355787507.xlsx 124
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Fuel / Energy charges Hour 235.00 3.80
Mobile derric crane Hour 100.00 519.70
Fuel / Energy charges Hour 100.00 307.20
Grinding machine Hour 32.00 22.50
Fuel / Energy charges Hour 32.00 38.50
Drilling machines Hour 16.00 22.50
Fuel / Energy charges Hour 16.00 38.50
Sundries LS 500.00 20.00
Total hire charges of Machinery Rs:

Description Unit Quantity Rate


in Rs.
Crew for Mobile crane Hour 100.00 165.80
Crew for Tower crane Hour 6.00 176.80
Crew for Drilling machine Hour 16.00 187.20
Crew for Grinding machine Hour 32.00 187.20
Foreman Day 74.00 480.00
Marker / Fabricator / Erector Day 124.00 480.00
Gas cutter Day 48.00 415.00
Welder ( General ) Day 112.00 415.00
Khalasi Day 20.00 415.00
Helper fabrication / erection Day 350.00 370.00
Electrician Day 10.00 480.00
Total cost of Labour Rs:
es @ 30% on total cost of labour
Total Cost of Labour
17194.70
harges 13.615% 2341.10
ontractor's profit) 19535.80

Rs:
Rs:
Rs:
Total Rs:
0.00% Rs:
materials) Total Rs:
3% Rs:
Total Rs:
eads on (A+B+C+D+E) 13.615% Rs:

Rs. 18.90 per tonne


66.30 per tonne
30.856 tonne Rs:
25.000 t capacity Rs:
Rate per tonne Rs:
Rate per tonne capacity Rs:
d commissioning of rail track using 45 kg / m standard rails on spillway bridge for movement of gantry crane for
ts / river sluice / canal sluice emergency gate including cost of all materials,machinery, labour, complete as per sp
echanical cleaning surfaces which are added extra as perscedule of rates under items in this chapter and add as a

355787507.xlsx 125
ts / river sluice / canal sluice emergency gate including cost of all materials,machinery, labour, complete as per sp
echanical cleaning surfaces which are added extra as perscedule of rates under items in this chapter and add as a
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

ists of 45 kg / m standard rails fixed by welding and


te at intervals. The width of track shall be as per the
ications.
analysis.
: 20.722
cation drawings

els / bars with 2.5 % wastage : 1570


wastage : 975
363 :
: 246
stage : 18450

10 % of total with 2.5 % wastage : 180


0 % of total with 2.5 % wastage : 1625

for 2 sides : 222


equired sizes gas cutting is assumed.
utting torch manually : 222
g average cutting progress of 2 m / hour : 111
( 111 x 0.60 ) : 67
( 111 x 1.80 ) : 201
r working ( 111 x 60 / 50 ) : 133

: 210
& @ 15 electrodes / hr
( 180 / 15 ) x 8 / 2 : 48
@ 15 electrodes / hr
( 1625 / 15 ) x 8 / 6 : 145
Total : 193

stitch welding & @ 75 % hrs for run welding.


( 48 x 0.25 + 145 x 0.75 ) : 121

urs use of drilling machine considered.


nishing 8 hours use of grinding machine considered.
crane for 4 hours considered.

Foreman Marker / Gas cutter/


Fabricator / Welder
Erector /
--- 17 17
--- 6 ---
3 6 ---
2 2 ---
2 --- 18
1 1 ---
8 32 35

355787507.xlsx 126
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
abricated parts. The cost of materials is inclusive of all
rate analysis 75 percent of total cost excluding the cost
cost ) is considered for assessing excise duty.

7350.00 / Each Rs: 7350.00


: 1000
( cost / life ) Rs: 7.35
14203.00 / Each Rs: 14203.00
: 600
( cost / life ) Rs: 23.67
RATE ANALYSIS UNIT : 200.000

particulars Unit Quantity Rate


in Rs.

Str steel angle / beam / channel / bars kg 1570.00 37.50


Structural steel plate / flats kg 975.00 37.00
Rails kg 18450.00 52.53
MS bolts and nuts kg 246.00 90.00
Oxygen gas cum 201.00 45.00
Acetyline gas cum 67.00 330.00
Welding electrodes Nos 1805.00 11.00
Use rate welding holder set Hour 193.00 7.65
Use rate gas cutting torch set Hour 133.00 2.08
Sundries LS 10.00 20.00
Total cost of Materials Rs:

Description Unit Quantity Rate


in Rs.
Welding transformer Hour 193.00 16.00
Fuel / Energy charges Hour 121.00 92.40
Mobile derric crane Hour 4.00 519.70
Fuel / Energy charges Hour 4.00 307.20
Grinding machine Hour 8.00 22.50
Fuel / Energy charges Hour 8.00 38.50
Drilling machines Hour 50.00 22.50
Fuel / Energy charges Hour 50.00 38.50
Sundries LS 10.00 20.00
Total hire charges of Machinery Rs:

Description Unit Quantity Rate


in Rs.
Crew for Mobile crane Hour 4.00 165.80
Crew for Drilling machine Hour 50.00 187.20
Crew for Grinding machine Hour 8.00 187.20
Foreman Day 8.00 480.00
Marker / Fabricator / Erector Day 32.00 480.00
Gas cutter Day 17.00 415.00
Welder ( General ) Day 18.00 415.00
Helper fabrication / erection Day 52.00 370.00

355787507.xlsx 127
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Electrician Day 1.00 480.00
Total cost of Labour Rs:
es @ 30% on total cost of labour
Total Cost of Labour
422.30
harges 13.615% 57.50
ontractor's profit) 479.80

Rs:
Rs:
Rs:
Total Rs:
materials) 0 Rs:
Total Rs:
3% Rs:
eads on (A+B+C+D+E) Total Rs:
0.13615 Rs:
Rs. 18.90 per tonne
66.30 per tonne
200.000 Rm Rs:
Rate per Rm Rs:
g and commissioning of automatic lifting beam with all accessories for handling, lowering and lifting of spillway sto
, machinery, labour, cutting, aligning, welding, finishing, etc., complete as per specifications and drawings with all
mechanical cleaning surfaces which are added extra as perscedule of rates under items in this chapter and add a
separately)

y stop log elements consists of fabricated beam with


/ dis-engaging type hooks for under water hooking /
m is an independent attachment to moving gantry crane.

ting beam as per data sheet : 3.528

els / bars with 2.5 % wastage : 13


wastage : 3389
S : 1570 :
: 101
conforming to IS : 305 :
: 5
o IS : 2004 :
: 130
S : 1363 :
astage : 3
: 11

10 % of total with 2.5 % wastage : 175


ng at 90 % of total with 2.5 % wastage : 1575

355787507.xlsx 128
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

2 sides : 172
n 2 sides / odd shapes etc ) at 10 % : 17
Total : 189
equired sizes gas cutting is assumed.
manually : 40
ug cutting machine : 149
g average cutting progress of 2 m / hour : 20
chine at ( av ) 3 m / hour : 50
0.60 ) : 42
: 126
r working ( 20 x 60 / 50 ) : 24
n / hr working ( 50 x 60 / 50 ) : 60

: 211
& @ 15 electrodes / hr :
: 47
@ 15 electrodes / hr
: 140
Total : 187

stitch welding & @ 75 % hrs for run welding.


: 117

derric crane for 4 hours and stationery derric crane for

2 hours use of drilling machine considered.


hours use of grinding machine considered.

Foreman Marker / Gas cutter/


Fabricator / Welder
Erector /
5 10 10
1 ---
3 6 ---
2 --- 18
1 ---
10 18 28

abricated parts. The cost of materials is inclusive of all


rate analysis 75 percent of total cost excluding the cost
cost ) is considered for assessing excise duty.

7350.00 / Each Rs: 7350.00


: 1000
( cost / life ) Rs: 7.35
14203.00 / Each Rs: 14203.00
: 600
( cost / life ) Rs: 23.67

355787507.xlsx 129
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

RATE ANALYSIS UNIT : 3.528

particulars Unit Quantity Rate


in Rs.
Structural steel
Angles / beams / channels / bars kg 13.00 37.50
Plates / flats kg 3389.00 37.00
Alloy steel components
Lifting pins kg 101.00 420.00
Bronze alloy components :
Bronze bush kg 5.00 920.00
Forged steel components :
Lifting hooks kg 103.00 260.00
MS pipe 100 mm dia kg 11.00 175.00
Bolt / Nut / Washer
MS bolts / nuts / washers kg 3.00 90.00
Oxygen gas cum 126.00 45.00
Acetyline gas cum 42.00 330.00
Welding electrodes Nos 175.00 11.00
Welding electrodes ( LH ) Nos 1575.00 18.00
Use rate welding holder set Hour 187.00 7.65
Use rate gas cutting torch set Hour 24.00 2.08
Sundries LS 25.00 20.00
Total cost of Materials Rs:

Description Unit Quantity Rate


in Rs.
Welding transformer Hour 187.00 16.00
Fuel / Energy charges Hour 117.00 92.40
Pug cutting machine Hour 60.00 6.40
Fuel / Energy charges Hour 60.00 3.80
Mobile derric crane Hour 4.00 519.70
Fuel / Energy charges Hour 4.00 307.20
Stationery derric crane Hour 8.00 86.10
Fuel / Energy charges Hour 8.00 0.00
Grinding machine Hour 2.00 22.50
Fuel / Energy charges Hour 2.00 38.50
Drilling machines Hour 2.00 22.50
Fuel / Energy charges Hour 2.00 38.50
Sundries LS 10.00 20.00
Total hire charges of Machinery Rs:

355787507.xlsx 130
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

Description Unit Quantity Rate


in Rs.
Crew for Mobile crane Hour 4.00 165.80
Crew for Drilling machine Hour 2.00 187.20
Crew for Grinding machine Hour 2.00 187.20
Foreman Day 10.00 480.00
Marker / Fabricator / Erector Day 18.00 480.00
Gas cutter Day 10.00 415.00
Welder ( General ) Day 18.00 415.00
Helper fabrication / erection Day 52.00 370.00
Electrician Day 1.00 480.00
Total cost of Labour Rs:
es @ 30% on total cost of labour
Total Cost of Labour
17020.90
harges 13.615% 2317.40
ontractor's profit) 19338.30

Rs:
Rs:
Rs:
Total Rs:
0.00% Rs:
materials) Total Rs:
3% Rs:
Total Rs:
eads on (A+B+C+D+E) 13.615% Rs:

Rs. 18.90 per tonne


66.30 per tonne
3.528 tonne Rs:
Rate per tonne Rs:
f soils of foundation of structures as per drawing and technical specification, including setting out, construction o
s and other deleterious matter, dressing of sides and bottom and backfilling with approved material.Depth upto 3

Unit 240.00 cum

Description Unit Quantity Rate


in Rs.
NIL 0.00 0.00

Description Unit Quantity Rate


in Rs.
Hydraulic excavator 1.0 cum bucket hour 6.00 1706.60
capacity
Fuel/ Energy charges hour 6.00 893.90
Total in Rs.

355787507.xlsx 131
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

Description Unit Quantity Rate


in Rs.
work inspector day 0.32 400.00
Mazdoor day 8.00 310.00
crew for excavator hour 6.00 221.00
Total in Rs.
16.40
harges 13.615% 2.20
ontractor's profit) 18.60

Rs
Rs
Rs
Rs
eads on (A+B+C) 13.615% Rs:
240.00 cum 39.8
240.00 cum Rs:
cum (A+B+C+D)/240.0 Rs.

hanical Means ( Data adopted from MORTH)


nds of soils of foundation of structures as per drawing and
setting out, construction of shoring and bracing, removal of stumps
ssing of sides and bottom and backfilling with approved material.

Unit 240.00 cum

355787507.xlsx 132
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

Description Unit Quantity Rate

in Rs.
NIL 0.00 0.00

Description Unit Quantity Rate

in Rs.
Hydraulic excavator 1.0 cum hour 6.00 1706.60
bucket capacity
Fuel/ Energy charges hour 6.00 893.90

Total in Rs.

Description Unit Quantity Rate


in Rs.
work inspector day 0.32 400.00
Mazdoor day 8.00 310.00
crew for excavator hour 6.00 221.00
Total in Rs.
16.40
ead charges 13.62% 2.20
ing contractor's profit) 18.60

Rs
Rs
Rs
Rs
overheads on (A+B+C) 13.615% Rs:
240.00 cum 39.8
240.00 cum Rs:
cum (A+B+C+D)/240.0 Rs.

asting for foundations of canal cross drainage and other appurtenant structures and placing the excavated stuff
e same as directed etc., complete with initial lead upto 50 m and initial lift upto 3 m.

Unit: 180.00

Description Unit Quantity Rate


in Rs.
355787507.xlsx 133
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
NIL 0.00 0.00

Description Unit Quantity Rate


in Rs.
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 1706.60

Fuel/ Energy charges hour 6.00 893.90


Total in Rs.

Description Unit Quantity Rate


in Rs.
work inspector day 0.24 400.00
Mazdoor day 6.00 310.00
crew for excavator hour 6.00 221.00
Total in Rs.

18.20
harges 13.615% 2.50
ontractor's profit) 20.70

Rs
Rs
Rs
Rs
eads on (A+B+C) 13.62% Rs:
180.00 cum 39.8

355787507.xlsx 134
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
180.00 cum Rs:
cum (A+B+C+D)/180.0 Rs.
sting including boulders above 0.6 m upto 1.2 m dia. For foundations of canal cross drainage and other appurte
uff neatly in specified dump area or disposing off the same as directed etc.,complete with initial lead upto 50 m an

RATE ANALYSIS UNIT : 100

Particulars Unit Quantity Rate


in Rs.
Use rate of drill rod 1.6 m length Rm 43.50 20.75
Reconditioning charges @ 10%
Use rate of air hose 2 Nos. Hour 6.00 0.23
Explosive small dia ( Kelvex-220 ) kg 20.00 70.00
Electric detonators Nos 29.00 13.00
Detonating fuse coil Rm 70.00 11.00
Sundries LS 0.50 20.00
Total cost of Materials Rs:

Description Unit Quantity Rate


in Rs.
Air compressor 8.5 cmm ( diesel ) Hour 3.00 275.60
Fuel / Energy charges Hour 3.00 914.20
Jack hammers 2 Nos. Hour 6.00 19.80
Fuel / Energy charges Hour 6.00 0.00
Total hire charges of Machinery Rs:

Description Unit Quantity Rate


in Rs.
Crew for Air compressor Hour 3.00 195.90
Crew for Jack hammer Hour 6.00 306.20
work inspector Day 1.00 400.00
Blaster Day 0.50 480.00
Helper blaster Day 0.50 370.00
Crowbarman Day 6.00 370.00
Stone breaker Day 3.00 370.00
mazdoor Day 51.00 310.00
Total cost of Labour Rs:
223.90
harges 13.615% 30.50
ontractor's profit) 254.40

Rs:
Rs:
Rs:
Total Rs:
eads on (A+B+C) 13.62% Rs:
100.00 cum 39.8
100.00 cum Rs:
cum (A+B+C+D)/100.0 Rs.

355787507.xlsx 135
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

M-20 ( 28 days cube compressive strength not less than20 N / sq mm ) grade cement concrete using 40 mm down
tes for cantiliver / counterfort retaining walls including cost of all materials,machinery, labour, formwork, scaffo
osition,levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.(Cement content:
t. of cement),CA : 0.90cum, Blending Ratio of CA--50:30:20, FA : 0.40 cum)

e add only lead charges @ 500 ltr / cum.

tes : 0.90 cum Blending ratio : 50 : 30 : 20


nt content : 320 kg Super plasticizer : 1.28 kg
0 x 13 x 8 / 320 16.25 cum per day

te considered for counterfort walls.


exure-A Item-IRR-CCDW-2-3 ) Rs: 244.56
d@: 25 % of shuttering
m-IRR-CCDW-2-3 ) Rs: 75.30
olding : 25 % of labour for shuttering

355787507.xlsx 136
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

ame as in item IRR-CCDW-2-3 with average 2 mazdoors extra for lift

RATE ANALYSIS UNIT : 16.25

Particulars Unit Quantity Rate


in Rs.
Cement for mix kg 5200.00 5.65
Cement for incidentals @ 5 kg / cum kg 81.25 5.65
Coarse aggregate 40-20 mm cum 7.31 980.00
Coarse aggregate 20-10 mm cum 4.39 1045.00
Coarse aggregate 10 mm below cum 2.93 710.00
Fine aggregate (Un-Screened) cum 6.50 392.00
Super Plasticizer kg 20.80 95.00
Use rate of shuttering for 40 uses sqm 52.81 225.53
Scaffolding @ of shuttering 25%
Sundries LS 0.50 20.00
Total cost of Materials Rs:

Description Unit Quantity Rate


in Rs.
Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 53.50
Fuel / Energy charges Hour 8.00 81.30
5 hp pump ( diesel ) Hour 0.50 10.20
Fuel / Energy charges Hour 0.50 81.30
Needle vibrator 40 mm dia ( petrol ) Hour 8.00 7.60
Fuel / Energy charges Hour 8.00 20.60
Total hire charges of Machinery Rs:

Description Unit Quantity Rate


in Rs.
Crew for Concrete mixer Hour 8.00 204.10
Crew for Pump Hour 0.50 103.60
Crew for Needle vibrator Hour 8.00 146.90
Mason Class-I Day 1.00 415.00
work inspector Day 1.00 400.00
mazdoor
for batching materials Day 11.00 310.00
for loading mortar pans Day 4.00 310.00
for laying Day 5.00 310.00
for conveying concrete Day 16.25 310.00

355787507.xlsx 137
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
for cleaning/ washing/ curing Day 1.00 310.00
Labour cost for shuttering sqm 52.81 79.80
Labour cost for scaffolding @ 25%
Total cost of Labour Rs:
1260.90
harges 13.615% 171.70
ontractor's profit) 1432.60

Rs:
Rs:
Rs:
Total Rs:
eads on (A+B+C) 13.615% Rs:
6.50 cum @ 65.90
14.63 cum @ 65.90
5.28 tonne @ 129.70
16.25 cum Rs:
cum (A+B+C+D)/16.25 Rs:

M-20 ( 28 days cube compressive strength not less than 20 N / sq mm ) grade cement concrete using 20 mm dow
tes for columns and beams including cost of all materials, labour, machinery,formwork, scaffolding, cleaning, batc
nishing, curing etc.,complete with initial lead upto 50 m and all lifts.CA : 0.80cum, Blending Ratio of CA--65:35, FA

RATE ANALYSIS UNIT : 15.76

Particulars Unit Quantity Rate


in Rs.
Cement for mix kg 5200.80 5.65
Cement for incidentals @ 5 kg / cum kg 78.80 5.65
Coarse aggregate 20-10 mm cum 8.20 1045.00
Coarse aggregate 10 mm below cum 4.41 710.00
Fine aggregate (Un-Screened) cum 7.09 392.00
Super Plasticizer kg 20.80 95.00
Use rate of shuttering sqm 78.80 225.53
Scaffolding @ of shuttering 50%
Sundries LS 1.00 20.00
Total cost of Materials Rs:

Description Unit Quantity Rate


in Rs.
Concrete mixer 300/200 ltr ( diesel ) Hour 8.00 53.50
Fuel / Energy charges Hour 8.00 81.30
5 hp pump ( diesel ) Hour 0.50 10.20

355787507.xlsx 138
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Fuel / Energy charges Hour 0.50 81.30
Needle vibrator 40 mm dia ( petrol ) Hour 8.00 7.60
Fuel / Energy charges Hour 8.00 20.60
Total hire charges of Machinery Rs:

355787507.xlsx 139
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

Description Unit Quantity Rate


in Rs.
Crew for Concrete mixer Hour 8.00 204.10
Crew for Pump Hour 0.50 103.60
Crew for Needle vibrator Hour 8.00 146.90
Mason Class-I Day 1.00 415.00
work inspector Day 1.00 400.00
mazdoor
for batching materials Day 11.00 310.00
for loading mortar pans Day 4.00 310.00
for laying Day 3.00 310.00
for conveying concrete Day 15.76 310.00
for cleaning/ washing/ curing Day 1.00 310.00
Labour cost for shuttering sqm 78.80 79.80
Labour cost for scaffolding @ 50%
Total cost of Labour Rs:
1515.40
harges 13.615% 206.30
ontractor's profit) 1721.70

Rs:
Rs:
Rs:
Total Rs:
eads on (A+B+C) 13.615% Rs:
5.28 tonne @ 129.70
7.09 65.90
12.61 65.90
15.76 cum Rs:
cum (A+B+C+D)/15.76 Rs.

kg 48 5.65 271.20
Nos 512 5.00 2560.00

cum 0.2 392.00 78.40


2909.60

day 0.24 415.00 99.60


day 0.56 370.00 207.20
day 1.89 310.00 585.90
892.70
892.70
3802.30

355787507.xlsx 140
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
3802.30 13.615% 517.68

MT 0.048 0.00 0.00


512 0.28 141.21

0.2 89.80 17.96


4479.15
4479.00

355787507.xlsx 141
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
cessories including cost of all materials,machinery, labour etc.,complete as per specifications and

Rs: 37500.00
Rs: 24000.00
Total Rs: 61500.00
3% Rs: 1845.00
Total Rs: 63345.00
13.615% Rs: 8624.42

18.90 per tonne 18.900


66.30 per tonne 66.3
1.00 tonne Rs: 72054.62
Rate per tonne Rs: 72055.00

ning of delivery mains with all accessories including cost of all materials,machinery, labour etc.,complete as per s

Rs:
Rs:
Total Rs:
0.0300 Rs:
Total Rs:
eads on 0.13615 Rs:
ISA 100X100X10 @ 14.9 kgs/m
4x5x14.9 @ Rs 298.00 11771.00
0.7x8x14.9 @ Rs 83.44 3295.88
Rs 9155 9155.00
ct Scrap Spider Cost 298x19.75*0.8 -Rs 4708.4 -4708.40
alue taken 50% of Initial Cost

19513.50
19513.48/2.71 7200.00
Or Say Rs.
arts Rs. 18.9 per tonne
66.3 per tonne
1 tonne Rs:

h metal surface for painting by sand blasting method as per specifications including cost of all materials, labour, m
ead for sand upto 1 km and all lifts.
RATE ANALYSIS UNIT : 100

particulars Unit Quantity Rate


in Rs.
Sand (Screened) cum 30.00 392.00
Use rate of air hose Hour 8.00 18.63
Use rate of sand blast gun nozzle Hour 8.00 3.50
Sundries( Rust inhibitive, seive etc ) LS 5.00 20.00
Total
355787507.xlsx 142
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Add 10% towards scaffolding/laddor @ 0.10
Total cost of Materials

Description Unit Quantity Rate


in Rs.
Air compressor 7 cmm diesel Hour 8.00 241.30
Fuel / Energy charges Hour 8.00 731.40
Sand blasting equipment Hour 8.00 110.10
Fuel / Energy charges Hour 8.00 0.00
Total hire charges of Machinery

Description Unit Quantity Rate


in Rs.
Crew for Air compressor Hour 8.00 195.90
Crew for Sand blasting equipment Hour 8.00 204.10
mazdoor Day 15.00 310.00
Total cost of Labour

355787507.xlsx 143
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
78.50
harges 13.615% 10.70
ontractor's profit) 89.20

Rs:
Rs:
Rs:
Total Rs:
0.00% Rs:
materials) Total Rs:
3% Rs:
Total Rs:
eads on (A+B+C+D+E) 13.615% Rs:
30.00 cum @ 65.90
100.00 sqm Rs:
Rate per sqm Rs:

d surfaces with one coat of inorganic zinc silicate (airless spray preferred)70+/- 5 and two super coats with a tota
less coaltar epoxy brown paint paint each coat 150 microns ( total 300 microns) cost of all materials, labour, sca

RATE ANALYSIS UNIT : 100

particulars Unit Quantity Rate


in Rs.
inorganic zinc silicate ltr 12.00 550.00
Thinner @ 10% ltr 1.20 140.00
Solventless Coal tar epoxy paint ltr 40.00 250.00
Thinner @ 10% ltr 4.00 140.00

Sundries ( brushes,ladders,platforms etc ) 3.00 20.00


Total cost of Materials Rs:

Description Unit Quantity Rate


in Rs.
Hire Charges of Airless Spray Gun Hr 6.00 121.40

Hire Charges of Air Compressor-7 Cmm (diesel) Hr 6.00 241.30


Fuel Charges of Air Compressor Hr 6.00 731.40

Total cost of Machinery Rs:

Description Unit Quantity Rate


in Rs.
Crew Charges of Air Compressor Day 6.00 195.90
Painter Class-I Day 20.00 480.00
Helper Day 20.00 310.00
Total cost of Labour Rs:

355787507.xlsx 144
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
169.80
harges 13.615% 23.10
ontractor's profit) 192.90

Rs:
Rs:
Rs:
Total Rs:
0 Rs:
materials) Total Rs:
0.03 Rs:
Total Rs:
13.615% Rs:
100.00 sqm Rs:
Rate per sqm Rs:

ng including boulders above 1.2 m dia. for canals, seating


ed by removing all projections by hammering / chiselling,
placing the excavated rock neatly in approved dump
d etc.,complete with initial lead upto 1 km and all lifts.

RATE ANALYSIS Unit: 386.00


A. MATERIALS:
particulars Unit Quantity Rate
in Rs.
Use rate of T.C bit 100 mm dia Rm 104.00 150.00

Use rate of Extension rod with coupling sleeve Rm 104.00 6.68

355787507.xlsx 145
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

Use rate of Jack hammer drill rod 1.5 m Rm 12.00 27.67


reconditioning charges @ 10%

Use rate of 50 m air hose for waggon drill Hour 10.50 18.63

Use rate of 25 m air hose for JH 2 Nos Hour 1.00 11.56


High strength ANFO booster kg 38.00 68.00
ANFO kg 155.00 48.00
Diesel oil ltr 35.00 59.10
Explosive small dia ( Kelvex-220 ) kg 4.00 70.00
Ordinary detonators Nos 20.00 7.00
D-cord Rm 145.00 10.00
Detonating fuse coil Rm 20.00 11.00
Sundries LS 5.00 20.00
Total cost of Materials Rs:

B. MACHINERY:
Description Unit Quantity Rate
in Rs.
Tippers 5 cum capacity Hour 24.84 446.70
Fuel / Energy charges Hour 24.84 307.20
Shovel 0.85 cum capacity Hour 6.21 1706.60
Fuel / Energy charges Hour 6.21 893.90
Angle dozer Hour 2.00 1715.50
Fuel / Energy charges Hour 2.00 625.30
Air compressor 8.5 cmm ( diesel ) Hour 11.50 275.60
Fuel / Energy charges Hour 11.50 914.20
Waggon drill Hour 10.50 188.50
Fuel / Energy charges Hour 10.50 0.00
Jack hammer Hour 2.00 19.80
Fuel / Energy charges Hour 2.00 0.00
Total hire charges of Machinery Rs:

C. LABOUR:
Description Unit Quantity Rate
in Rs.
Crew for Tipper Hour 24.84 165.80
Crew for Shovel Hour 6.21 221.00
Crew for Dozer Hour 2.00 221.00
Crew for Air compressor Hour 11.50 195.90
Crew for Waggon drill Hour 10.50 265.20
Crew for Jack hammer Hour 2.00 306.20
work inspector Day 2.00 400.00
Blaster Day 1.00 480.00
Helper blaster Day 1.00 370.00
Stone chiseller Cl - II Day 1.00 370.00
Stone breaker Day 1.00 370.00
mazdoor Day 3.00 310.00
Total cost of Labour Rs:

355787507.xlsx 146
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
labour component/unit qty 38.60
Add contractor's profit and overhead charges 13.615% 5.30
labour component/unit qty (including contractor's profit) 43.90

Rs:
Rs:
Rs:
Total Rs:
13.615% Rs:
386.00 Cum Rs:
(A+B+C+D)/386 Rs.
say Rs:
4 kms Rs:
1 km Rs:
Rs:

ding boulders upto 0.3 m diameter for canal, seating of embankment, filter drains / catch water drains etc.,
el and profile, cost of all materials, machinery, labour, placing the excavated soil neatly in dump area or for the form
etc.,complete with initial lead upto 1 km and all lifts.

RATE ANALYSIS UNIT : 925.00

Unit Quantity Rate Amount


in Rs. in Rs.
0.00 0.00 0.00
0.00 0.00 0.00
Rs: 0.00

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 8.00 1706.60 13652.80
Hour 8.00 893.90 7151.20
Hour 48.00 446.70 21441.60
Hour 48.00 307.20 14745.60
e charges of Machinery Rs: 56991.20

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 8.00 221.00 1768.00
Hour 48.00 165.80 7958.40
Day 1.00 400.00 400.00
Day 30.00 310.00 9300.00
Rs: 19426.40
21.00

355787507.xlsx 147
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
harges 13.615% 2.90
ontractor's profit) 23.90

Rs:
Rs:
Rs:
Rs:
eads on (A+B+C) 13.615% Rs:
925.00 cum Rs:
cum (A+B+C+D)/925 Rs.
Say Rs:

ater drains etc., including dressing of bed and sides to required level and profile, cost of all materia
avated soft rock neatly in dump area or for formation of service road as directed etc.,complete with
RATE ANALYSIS UNIT : 630.00

Unit Quantity Rate Amount


in Rs. in Rs.
0.00 0.00 0.00
Rs: 0.00

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 8.00 1706.60 13652.80
Hour 8.00 893.90 7151.20
Hour 40.00 446.70 17868.00
Hour 40.00 307.20 12288.00
Rs: 50960.00

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 8.00 221.00 1768.00
Hour 40.00 165.80 6632.00
Day 1.00 400.00 400.00
Day 11.00 370.00 4070.00
Day 22.00 310.00 6820.00
Rs: 19690.00
31.30
harges 13.615% 4.30
ontractor's profit) 35.60

Rs:
Rs:
Rs:
Total Rs:

355787507.xlsx 148
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
eads on (A+B+C) 13.615% Rs:
630.00 cum Rs:
cum (A+B+C+D)/630 Rs.
Say Rs:

F&F rock) requiring blasting including boulders above 0.6 m upto 1.2 m dia. for canals, seating of embank
g dressing bed and sides to required level and profile, cost of all materials, machinery, labour, placing the excavat
oad as directed etc., complete with lead upto 1 km and all lifts.

RATE ANALYSIS UNIT : 805.00

355787507.xlsx 149
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Unit Quantity Rate Amount
in Rs. in Rs.
Rm 316.00 20.75 6557.00
655.70
Hour 24.00 11.56 277.50

kg 161.00 70.00 11270.00


Nos 12.00 7.00 84.00
Nos 215.00 13.00 2795.00
Rm 520.00 11.00 5720.00
LS 5.00 20.00 100.00
Rs: 27459.20

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 8.00 1706.60 13652.80
Hour 8.00 893.90 7151.20
Hour 40.00 446.70 17868.00
Hour 40.00 307.20 12288.00

Hour 12.00 275.60 3307.20


Hour 12.00 914.20 10970.40
Hour 39.00 19.80 772.20
Hour 39.00 0.00 0.00
Rs: 66009.80

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 8.00 221.00 1768.00
Hour 40.00 165.80 6632.00
Hour 12.00 195.90 2350.80
Hour 39.00 306.20 11941.80
Day 1.00 400.00 400.00
Day 1.00 480.00 480.00
Day 1.00 370.00 370.00
Day 16.00 370.00 5920.00
Day 16.00 370.00 5920.00
Day 32.00 310.00 9920.00
Rs: 45702.60
56.80
harges 13.615% 7.70
ontractor's profit) 64.50

Rs:
Rs:

355787507.xlsx 150
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Rs:
Total Rs:
eads on (A+B+C) 13.615% Rs:
805.00 cum Rs:
cum (A+B+C+D)/805 Rs.
Say Rs:

ding boulders above 1.2 m dia. for canals, seating


y removing all projections by hammering / chiselling,
cing the excavated rock neatly in approved dump
c.,complete with all leads and lifts,as per drawing and as

Unit: 386.00

Unit Quantity Rate Amount


in Rs. in Rs.
Rm 104.00 150.00 15600.00

Rm 104.00 6.68 694.51

Rm 12.00 27.67 332.00


10% 33.20

Hour 10.50 18.63 195.56

Hour 1.00 11.56 11.56


kg 38.00 68.00 2584.00
kg 155.00 48.00 7440.00
ltr 35.00 59.10 2068.50
kg 4.00 70.00 280.00

355787507.xlsx 151
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Nos 20.00 7.00 140.00
Rm 145.00 10.00 1450.00
Rm 20.00 11.00 220.00
LS 5.00 20.00 100.00
Rs: 31149.34

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 24.84 446.70 11096.03
Hour 24.84 307.20 7630.85
Hour 6.21 1706.60 10597.99
Hour 6.21 893.90 5551.12
Hour 2.00 1715.50 3431.00
Hour 2.00 625.30 1250.60
Hour 11.50 275.60 3169.40
Hour 11.50 914.20 10513.30
Hour 10.50 188.50 1979.25
Hour 10.50 0.00 0.00
Hour 2.00 19.80 39.60
Hour 2.00 0.00 0.00

Rs: 55259.13

Unit Quantity Rate Amount


in Rs. in Rs.
Hour 24.84 165.80 4118.47
Hour 6.21 221.00 1372.41
Hour 2.00 221.00 442.00
Hour 11.50 195.90 2252.85
Hour 10.50 265.20 2784.60
Hour 2.00 306.20 612.40
Day 2.00 400.00 800.00
Day 1.00 480.00 480.00
Day 1.00 370.00 370.00
Day 1.00 370.00 370.00
Day 1.00 370.00 370.00
Day 3.00 310.00 930.00
Rs: 14902.73
38.60
13.615% 5.30
actor's profit) 43.90

Rs:
Rs:

355787507.xlsx 152
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Rs:
Total Rs:
s on (A+B+C) 13.615% Rs:
386.00 Cum Rs:
Cum (A+B+C+D)/386 Rs.
say Rs:
2 kms Rs:
1 km Rs:
Rs:
Say Rs:

355787507.xlsx 153
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

ATION SCHEME IN

, ventilation, lighting,
with initial lead upto 1km

cum

Amount
in Rs.
2800.00
1242.00
65.00
550.00
5077.33
507.73
115.63
115.63
40.00
10513.32

Amount
in Rs.
2947.20
351.20
694.00
4811.50
396.00
0.00
254.00
0.00
5348.20
1741.35
3774.55
2662.40
33.50
385.00
11.50
154.00
40.00
23604.40

Amount

355787507.xlsx 154
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
in Rs.
1306.40
816.50
6124.00
1061.45
1379.30
388.50
26.80
295.00
480.00
830.00
480.00
740.00
740.00
1200.00
1660.00

1240.00
620.00
620.00
20007.95

10513.32
23604.40
20007.95
54125.67
541.26
2435.66
866.01
1353.14
59321.73
8076.65

1532.30
68930.68
1790.00

ting, scaling excavated


perations etc., complete

cum

355787507.xlsx 155
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
Amount
in Rs.
2240.00
845.00
550.00
2628.33
262.83
416.25
370.00
390.04
532.68
40.00
8275.14

Amount
in Rs.
624.60
4330.35
316.80
0.00
26.80
308.00
24.60
308.00
3623.20
5280.80
1540.80
0.00
40.00
16423.95

Amount
in Rs.
734.85
4899.20
310.80
155.40
6857.20
295.00
1920.00
830.00
480.00
740.00
1110.00
1600.00
2490.00

355787507.xlsx 156
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

7440.00
620.00
620.00
31102.45

8275.14
16423.95
31102.45
55801.54
558.02
2511.07
892.82
1395.04
61158.48
8326.73
1194.00
70679.21
2356.00

avated surface, removing


cillary operations etc.,

cum

Amount
in Rs.
3780.00
1564.00
130.00
550.00
6400.00
640.00
138.75
138.75
40.00
13381.50

Amount
in Rs.
3684.00

355787507.xlsx 157
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
439.00
902.20
6254.95
514.80
0.00
330.20
0.00
4936.80
1607.40
6968.40
4915.20
43.55
500.50
23.00
308.00
40.00
31468.00

Amount
in Rs.
1633.00
1061.45
7961.20
979.80
2546.40
505.05
53.60
295.00
480.00
830.00
480.00
740.00
740.00
1200.00
1660.00

2480.00
620.00
620.00
24885.50

13381.50
31468.00

355787507.xlsx 158
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
24885.50
69735.00
697.35
3138.08
1115.76
1743.38
76429.56
10405.88
1934.28
88769.72
1827.00

ost of providing supports )


cavated muck outside

cum

Amount
in Rs.
2870.00
1771.00
130.00
550.00
6144.00
614.40
138.75
138.75
40.00
12396.90

Amount
in Rs.
4052.40
482.90
832.80
5773.80
475.20
0.00
304.80
0.00
4936.80
1607.40
6968.40
4915.20
40.20

355787507.xlsx 159
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
462.00
23.00
308.00
40.00
31222.90

Amount
in Rs.
1796.30
979.80
7348.80
979.80
2546.40
466.20
53.60
295.00
480.00
830.00
480.00
740.00
740.00
1200.00
1660.00

2480.00
620.00
620.00
24315.90

12396.90
31222.90
24315.90
67935.70
679.36
3057.11
1086.97
1698.39
74457.53
10137.39
1830.80
86425.72
1879.00

355787507.xlsx 160
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
g supports ( excluding
tion, lighting, drainage
ad upto 1 km and all lifts.

cum

Amount
in Rs.
3080.00
1932.00
130.00
550.00
6698.67
669.87
150.31
150.31
40.00
13401.16

Amount
in Rs.
4420.80
526.80
902.20
6254.95
514.80
0.00
330.20
0.00
5348.20
1741.35
7549.10
5324.80
43.55
500.50
34.50
462.00
40.00
33993.75

Amount
in Rs.
1959.60
1061.45
355787507.xlsx 161
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
7961.20
1061.45
2758.60
505.05
80.40
295.00
480.00
830.00
960.00
1480.00
740.00
1200.00

1660.00
1660.00

2480.00
620.00
620.00
28412.75

13401.16
33993.75
28412.75
75807.66
758.08
3411.34
1212.92
1895.19
83085.19
11312.05

1990.00
96387.24
1928.00

s by blasting if necessary
ng and all other ancillary

cum

Amount
in Rs.

355787507.xlsx 162
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
415.00
41.50
560.00
390.00
220.00
23.13
23.13
20.00
1692.75

Amount
in Rs.
138.80
962.30
79.20
0.00
6.70
77.00
4936.80
1607.40
6968.40
4915.20
20.00
19711.80

Amount
in Rs.
163.30
1224.80
77.70
979.80
2546.40
240.00
185.00
2480.00
7897.00

1692.75
19711.80
7897.00
29301.55
293.02

355787507.xlsx 163
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
1318.57
468.82
732.54
32114.50
4372.39
3980.00
40466.89
405.00

st of all materials,

Kwhr

Amount
in Rs.
4.67
2.00
6.67

Amount
in Rs.
12.30
154.00
2.00
168.30

Amount
in Rs.
77.70
1.00
31.00
109.70

6.67
168.30
109.70
284.67
2.85
12.81
4.55

355787507.xlsx 164
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
7.12
311.99
42.48
354.47
23.6

als, machinery, labour,

sqm

Amount
in Rs.
3390.00
431.20
46.25
46.25
28.00
40.00
3981.70

Amount
in Rs.
880.80
0.00
1366.40
3464.80
6.70
77.00
1473.60
175.60
40.00
7484.90

Amount
in Rs.
1632.80
1224.80
77.70
653.20
415.00
1860.00
5863.50

355787507.xlsx 165
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

3981.70
7484.90
5863.50
17330.10
173.30
779.85
277.28
433.25
18993.79
2586.00
77.82
72.49
21730.10

604.00

layers including cost and


etc. complete as per

sqm

Amount
in Rs.
8746.20
944.72
731.30
46.25
46.25
28.00
17820.00
40.00
28402.72

Amount
in Rs.
880.80
0.00
1366.40
3464.80
6.70
77.00
1473.60

355787507.xlsx 166
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
175.60
40.00
7484.90

Amount
in Rs.
1632.80
1224.80
77.70
653.20
415.00
1860.00
5863.50

28402.72
7484.90
5863.50
41751.12
417.51
1878.80
668.02
1043.78
45759.23
6230.12
200.78
158.819
52348.94
1454

viding 15 cm long 20 mm
tilation, lighting, drainage

Rm

Amount
in Rs.
3041.98
2604.63
244.18
360.00
853.33
85.33

355787507.xlsx 167
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
34.69
34.69
100.00
7358.84

Amount
in Rs.
208.20
1443.45
6.70
77.00
118.80
0.00
76.20
0.00
1473.60
175.60
100.00
3679.55

Amount
in Rs.
244.95
77.70
1837.20
653.20
207.50
415.00
480.00
415.00
415.00
185.00
620.00
5550.55

7358.84
3679.55
5550.55
16588.94
165.89
746.50
265.42
414.72

355787507.xlsx 168
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
18181.47
2475.41
24.09
20680.98
1034.00

abour, cutting, bending,

tonne

Amount
in Rs.
28500.00
4542.50
5625.00

108.00
264.00

1375.00

4500.00
100.00
45014.50

Amount
in Rs.
340.80
924.00
256.00
1478.40
4420.80
526.80
600.00
8546.80

Amount
in Rs.
1959.60
980.00

480.00
830.00
830.00

355787507.xlsx 169
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
1440.00
830.00
1480.00

830.00
740.00
830.00

480.00
960.00
740.00
1660.00
15069.60

45014.50
8546.80
15069.60
68630.90
686.31
3088.39
1098.09
1715.77
75219.47
10241.13
156.045
85616.64
85617.00

g including cost of all


with initial lead upto 1 km

tonne

Amount
in Rs.
28500.00
4542.50
5625.00
0.00
108.00
264.00
0.00

355787507.xlsx 170
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
1375.00
0.00
4500.00
400.00
45314.50
2265.73

Amount
in Rs.
340.80
924.00
256.00
1478.40
600.00
3599.20
179.96

Amount
in Rs.
6631.20
790.20
200.00
7621.40

Amount
in Rs.
980.00

480.00
830.00
830.00
1440.00
830.00
1480.00

830.00
740.00
830.00
9270.00
463.50

Amount
in Rs.
1306.40

355787507.xlsx 171
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

480.00
960.00
740.00
1660.00

240.00
480.00
370.00
830.00
7066.40

2265.73
179.96
7621.40
463.50
7066.40
17596.99
175.97
791.86
281.55
439.92
19286.30
2625.83
156.045
22068.17
22068.00

oking, lapping / welding


, drainage etc.,complete

tonne

Amount
in Rs.
36750.00
945.00
100.00
37795.00

Amount
in Rs.

355787507.xlsx 172
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
0.00
0.00
0.00

Amount
in Rs.
4410.00
4650.00
9060.00

355787507.xlsx 173
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

37795.00
0.00
9060.00
46855.00
468.55
2108.48
749.68
1171.38
51353.08
6991.72
159.075
58503.88
58504.00

cum

355787507.xlsx 174
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

65401.80
33286.40
19320.60
118008.80
1180.09

355787507.xlsx 175
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
5310.40
1888.14
2950.22
129337.64
17609.32
350.56
761.04
798.952
148857.52
5316.34
38.44
-12.52
86.49
-27.18
5401.57
5402.00

40 mm and down size


formwork, batching,
d all other ancillary
CA : 0.90cum, Blending

cum

Amount
in Rs.
52206.00
158.20
4390.40
12348.00
7900.20
3578.40
3511.20
4354.81
40.00
88487.21

Amount
in Rs.
3243.20
2771.20
12134.40
14302.40
64.00
61.60
355787507.xlsx 176
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
53.60
616.00
100.00
33346.40

Amount
in Rs.
2545.60
4243.20
1175.20
621.60

740.00
1860.00

930.00

620.00

620.00

830.00
740.00
6510.00
400.00
2234.40
24070.00

355787507.xlsx 177
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

88487.21
33346.40
24070.00
145903.61
1459.04
6565.66
2334.46
3647.59
159910.36
21771.80
1202.0596
738.08
1660.68
185282.97
6617.00

g 40 mm and down size


our, formwork, batching,
and all other ancillary
,CA : 0.90cum, Blending

cum

Amount
in Rs.
89496.00
271.20
7526.40
21168.00
13543.20
6134.40
6019.20
933.17
7980.00
100.00
153171.57

Amount
in Rs.
2732.80
5197.20
355787507.xlsx 178
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
4864.80
4156.80
24268.80
28604.80
1632.00
32.00
64.00
61.60
53.60
616.00
100.00
72384.40

Amount
in Rs.
2449.60
5091.20
8486.40
268.80
1175.20
621.60

185.00
310.00

295.00
185.00
370.00

355787507.xlsx 179
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
1245.00
310.00

295.00
240.00
185.00
370.00
1245.00
310.00

1550.00

620.00
478.80

1245.00
2790.00
1200.00

930.00
32451.60

153171.57
72384.40
32451.60
258007.57
2580.08
11610.34
4128.12
6450.19
282776.30
38499.99
2060.6736
1265.28
2846.88
327449.13
6822.00

20 mm down size
ng, mixing, placing in
ng structures, training
ticiser,CA : 0.90 cum,

355787507.xlsx 180
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

cum

Amount
in Rs.
108480.00
271.20
8467.20
29343.60
10735.20
6019.20
933.17
7980.00
100.00
172329.57

Amount
in Rs.
2732.80
5197.20
4864.80
4156.80
24268.80
28604.80
1632.00
32.00
64.00
61.60
53.60
616.00
100.00
72384.40

Amount
in Rs.
2449.60
5091.20
8486.40
268.80
1175.20
621.60

185.00
310.00

295.00
185.00
355787507.xlsx 181
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
370.00
1245.00
310.00

295.00
240.00
185.00
370.00
1245.00
310.00

1550.00

620.00
478.80

1245.00
2790.00
1200.00

930.00
32451.60

172329.57
72384.40
32451.60
277165.57
2771.66
12472.45
4434.65
6929.14
303773.47
41358.76
2496.47
1423.44
2846.88
351899.01
7331.00

ied depth for


ncillary operations etc.,

Rm

Amount

355787507.xlsx 182
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
in Rs.
4266.67
426.67
185.00
185.00
60.00
5123.33

Amount
in Rs.
1110.40
7698.40
26.80
308.00
633.60
0.00
406.40
0.00
2947.20
351.20
100.00
13582.00

Amount
in Rs.
1306.40
310.80
9798.40
1306.40
620.00
13342.00

5123.33
13582.00
13342.00
32047.33
320.47
1442.13
512.76
801.18
35123.88
4782.12
39905.99
399.00

, machinery, labour,
m and all lifts.
355787507.xlsx 183
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

9250.00
hours
11.56
9250.00
hours
11.56

tonne

Amount
in Rs.
8475.00
92.50
92.50
40.00
8700.00

Amount
in Rs.
199.20
308.00
13.40
154.00
736.80
87.80
40.00
1539.20

Amount
in Rs.
1959.20
155.40

355787507.xlsx 184
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
326.60
620.00
3061.20

8700.00
1539.20
3061.20
13300.40
133.00
598.52
212.81
332.51
14577.24
1984.69
194.25
16756.18
11171.00

r suitable drilling

Rm

Amount
in Rs.
15000.00
74.00
74.00
1068.48
16216.48

Amount
in Rs.
3016.00
0.00
1110.40
7698.40
40.20
462.00
40.00
12367.00

355787507.xlsx 185
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

Amount
in Rs.
4243.20
1306.40
466.20
620.00
6635.80

16216.48
12367.00
6635.80
35219.28
352.19
1584.87
563.51
880.48
38600.33
5255.44
43855.77
366.00

appurtenant works
o 1 km and all lifts.
cum
Amount
in Rs
0.00
0.00
0.00

Amount
in Rs
13652.80
7151.20
27873.60
19660.80
3573.60
2457.60
74369.60

Amount
in Rs
1768.00

355787507.xlsx 186
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
10185.60
1326.40
400.00
4960.00
18640.00

0.00
74369.60
18640.00
93009.60
12663.26
35024.00
140696.86
160.00

pillway, intake structure


th initial lead upto 1 km

cum
Amount
in Rs.
0.00
0.00
0.00

Amount
in Rs
13652.80
7151.20
18582.40
13107.20
3573.60
2457.60
58524.80

Amount
in Rs
1768.00
6790.40
1326.40
400.00
925.00
3100.00
14309.80

355787507.xlsx 187
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

0.00
58524.80
14309.80
72834.60
9916.43
20696.00
103447.03
199.00

for dam, spillway, intake


omplete with initial lead

cum.
Amount
in Rs
4482.00
448.20
300.63
7280.00
2002.00
3520.00
100.00
18132.83

Amount
in Rs
13652.80
7151.20
18582.40
13107.20
3573.60
2457.60
2220.40
5630.30
514.80
0.00
66890.30

Amount
in Rs
1768.00
6790.40
1326.40
1990.30
7961.20
355787507.xlsx 188
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
400.00
480.00
370.00
925.00
370.00
3100.00
25481.30

18132.83
66890.30
25481.30
110504.43
15045.18
20696.00
146245.61
281.00

other appurtenant works


all lifts.

cum
Amount
in Rs
8576.67
857.67
555.00
6650.00
70.00
4329.00
4950.00
100.00
26088.34

Amount
in Rs
13652.80
7151.20
13936.80
9830.40
1786.80
1228.80

355787507.xlsx 189
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
1715.50
625.30
4099.20
10394.40
950.40
0.00
65371.60

Amount
in Rs
1768.00
5092.80
663.20
221.00
3674.40
14697.60
400.00
480.00
370.00
370.00
740.00
1860.00
30337.00

26088.34
65371.60
30337.00
121796.94
16582.65
12736.00
151115.59
472.00

mm diameter 1.50 m
er flow blocks and
anchor rod, cost of all

Nos.
Amount
in Rs
2343.75

355787507.xlsx 190
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
74.52
10612.70
423.75
19.60
13474.32

Amount
in Rs
683.20
1732.40
754.00
0.00

355787507.xlsx 191
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
3169.60

Amount
in Rs
612.40
1060.80
245.00
185.00
310.00
2413.20
96.50
13.10
109.60

13474.32
3169.60
2413.20
19057.12
2594.626888

9.7275
7.58
21669.05
866.00

ver required, tying


lead upto 1 km and

tonne
Amount
in Rs
36750.00
630.00
37380.00

Amount
in Rs
0.00

Amount
in Rs
980.00
2120.40
3100.40

355787507.xlsx 192
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
37380.00
0.00
3100.40
40480.40
5511.41
159.075
46151.00

40 mm down size
ng, mixing, placing in
ng structures, training

cum
Amount
in Rs
420360.00
4068.00
105840.00
67716.00
30672.00
37632.00
28272.00
117388.80
17608.32
829557.12

Amount
in Rs
4144.80
3387.20
1055.20
2771.20
14294.40
9830.40
13873.60
3203.20
632.00
0.00
53.60
616.00
155.20
184.00
200.00

355787507.xlsx 193
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
54400.80

Amount
in Rs
2545.60
1224.80
5305.60
2828.80
621.60
2350.40
1660.00
960.00
0.00
620.00
620.00
620.00
1860.00
620.00
43092.00
6463.80
71392.60
297.50
40.50
338.00

829557.12
54400.80
71392.60
955350.52
28660.52
23883.76
38214.02
1046108.82
142427.72
6326.4
14234.4
9743.06
1218840.40
5079.00

mm down size approved,


, placing in position,
cum with use of super

cum
Amount

355787507.xlsx 194
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
in Rs
20566.00
237.30
6174.00
3950.10
1789.20
2195.20
1383.20
3043.46
39338.46

Amount
in Rs
413.60
308.00
6.70
77.00
64.00
61.60
930.90

Amount
in Rs
1632.80
77.70
1175.20
415.00

620.00
2790.00
1240.00
930.00
4340.00
310.00
1117.20
14647.90
1058.20
144.10
1202.30

39338.46
930.90
14647.90
54917.26
7476.98
369.04
830.34

355787507.xlsx 195
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
477.56
64071.18
4577.00

, horizontal and vertical


st of all
hanical cleaning surfaces

hours

hours

tonne

Amount
in Rs.

198000.00
4176560.00

218400.00

72000.00

163800.00
21780.00
122130.00
298650.00
952094.00
296748.00
98532.00
5654.17
8000.00
6632348.17

Amount
in Rs.
206080.00
1190112.00
41216.00
24472.00
820116.00
355787507.xlsx 196
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
27000.00
20491.80
0.00
5355.00
9163.00
8032.50
13744.50
10224.00
27720.00
3600.00
2407326.80

Amount
in Rs.
176112.00
66830.40
44553.60
29400.00
57600.00
93600.00
41500.00
598430.00
132000.00
839545.00
1008990.00
4800.00
3093361.00
928008.30
4021369.30

6632348.17
2407326.80
4021369.30
13061044.27
0.00
13061044.27
391831.33
13452875.59
1831609.01

4498.20
15779.40
15304762.2
128612.00
ounted gantry frame, top
, control panel, wire rope,
ergency gates including

355787507.xlsx 197
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

tonne
t capacity
Amount
in Rs.

65362.50
728900.00
51660.00

290400.00
244650.00
405900.00
147060.00

33020.00

127880.00
220080.00

166520.00
81200.00
5670.00
9250.00
897600.00
85800.00
66000.00
23100.00
140800.00

151140.00
26055.00
63690.00
12353.00
181980.00
13000.00
9157.05
312.50
4000.00
4252540.05

Amount
in Rs.
19152.00
69115.20
5202.60
1201.20
1504.00

355787507.xlsx 198
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
893.00
51970.00
30720.00
720.00
1232.00
360.00
616.00
10000.00
192686.00

Amount
in Rs.
16580.00
1060.80
2995.20
5990.40
35520.00
59520.00
19920.00
46480.00
8300.00
129500.00
4800.00
330666.40
99199.92
429866.32

4252540.05
192686.00
429866.32
4875092.37
0.00
4875092.37
146252.77
5021345.14
683656.14

1166.36
4091.51
5710259.14

185061.55
228410.00
try crane for handling and
ete as per specifications
and add as applicable

355787507.xlsx 199
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

kg
kg

kg
kg

Nos
Nos

Rm

m
hours
cum
cum
hours

hours

hours
hours

hours

Helper

17
6
6
4
18
1
52

355787507.xlsx 200
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

hours

hours

Rm

Amount
in Rs.

58875.00
36075.00
969178.50
22140.00
9045.00
22110.00
19855.00
1476.45
277.08
200.00
1139232.03

Amount
in Rs.
3088.00
11180.40
2078.80
1228.80
180.00
308.00
1125.00
1925.00
200.00
21314.00

Amount
in Rs.
663.20
9360.00
1497.60
3840.00
15360.00
7055.00
7470.00
19240.00

355787507.xlsx 201
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
480.00
64965.80
19489.74
84455.54

1139232.03
21314.00
84455.54
1245001.57
0.00
1245001.57
37350.05
1282351.62
174592.17
802.91
2816.56
1460563.26
7303.00
spillway stop log gate
ngs with all leads and lifts.
r and add as applicable

tonnes

kg
kg

kg

kg

kg

kg
kg

Nos
Nos

355787507.xlsx 202
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

Rm
Rm
Rm

m
m
hours
hours
cum
cum
hours
hours

Rm

hours

hours
hours

hours

Helper

20
1
12
18
1
52

hours

hours

355787507.xlsx 203
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

tonne

Amount
in Rs.

487.50
125393.00

42420.00

4600.00

26780.00
1925.00

270.00
5670.00
13860.00
1925.00
28350.00
1430.55
50.00
500.00
253661.05

Amount
in Rs.
2992.00
10810.80
384.00
228.00
2078.80
1228.80
688.80
0.00
45.00
77.00
45.00
77.00
200.00
18855.20

355787507.xlsx 204
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

Amount
in Rs.
663.20
374.40
374.40
4800.00
8640.00
4150.00
7470.00
19240.00
480.00
46192.00
13857.60
60049.60

253661.05
18855.20
60049.60
332565.85
0.00
332565.85
9976.98
342542.83
46637.21

137.025
240.34
389557.39
110419.00
nstruction of shoring and
epth upto 3 m

Amount
in Rs.
0.00

Amount
in Rs.
10239.60

5363.40
15603.00

355787507.xlsx 205
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

Amount
in Rs.
128.00
2480.00
1326.00
3934.00

0.00
15603.00
3934.00
19537.00
2659.96
9552.00
31748.96
132.00

355787507.xlsx 206
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

Amount

in Rs.
0.00

Amount

in Rs.
10239.60

5363.40

15603.00

Amount
in Rs.
128.00
2480.00
1326.00
3934.00

0.00
15603.00
3934.00
19537.00
2659.96
9552.00
31748.96
132.00

avated stuff neatly in

cum

Amount
in Rs.
355787507.xlsx 207
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
0.00

Amount
in Rs.
10239.60

5363.40
15603.00

Amount
in Rs.
96.00
1860.00
1326.00
3282.00

0.00
15603.00
3282.00
18885.00
2571.19
7164.00

355787507.xlsx 208
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
28620.19
159.00
her appurtenant
pto 50 m and initial lift

cum

Amount
in Rs.
902.63
90.26
1.39
1400.00
377.00
770.00
10.00
3551.28

Amount
in Rs.
826.80
2742.60
118.80
0.00
3688.20

Amount
in Rs.
587.70
1837.20
400.00
240.00
185.00
2220.00
1110.00
15810.00
22389.90

3551.28
3688.20
22389.90
29629.38
4034.04
3980.00
37643.42
376.00

355787507.xlsx 209
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

0 mm down size
work, scaffolding,
nt content: 320 kg / cum

/ sqm

/ sqm

355787507.xlsx 210
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

cum

Amount
in Rs.
29380.00
459.06
7166.25
4584.94
2076.75
2548.00
1976.00
11910.75
2977.69
10.00
63089.44

Amount
in Rs.
428.00
650.40
5.10
40.65
60.80
164.80
1349.75

Amount
in Rs.
1632.80
51.80
1175.20
415.00
400.00

3410.00
1240.00
1550.00
5037.50

355787507.xlsx 211
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
310.00
4214.44
1053.61
20490.35

63089.44
1349.75
20490.35
84929.53
11563.16
428.35
963.7875
684.98
98569.81
6066.00

20 mm down size
eaning, batching, mixing,
A--65:35, FA : 0.45 cum))

cum

Amount
in Rs.
29384.52
445.22
8563.98
3133.09
2780.06
1976.30
17771.69
8885.84
20.00
72960.71

Amount
in Rs.
428.00
650.40
5.10

355787507.xlsx 212
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
40.65
60.80
164.80
1349.75

355787507.xlsx 213
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

Amount
in Rs.
1632.80
51.80
1175.20
415.00
400.00

3410.00
1240.00
930.00
4885.60
310.00
6288.24
3144.12
23882.76

72960.71
1349.75
23882.76
98193.22
13369.00660347
684.76412
467.3628
830.8672
113545.22
7204.00

355787507.xlsx 214
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

355787507.xlsx 215
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

ete as per specifications

39500
24000
63500
1905
65405
8904.89

7200
18.9
66.3
81595

ls, labour, machinery,

sqm

Amount
in Rs.
11760.00
149.00
28.00
100.00
12037.00
355787507.xlsx 216
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
1203.70
13240.70

Amount
in Rs.
1930.40
5851.20
880.80
0.00
8662.40

Amount
in Rs.
1567.20
1632.80
4650.00
7850.00

355787507.xlsx 217
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

13240.70
8662.40
7850.00
29753.10
0.00
29753.10
30645.69
30645.69
4172.41
1977
36795.10
368.00

with a total thickness of


labour, scaffolding etc.,

sqm

Amount
in Rs.
6600
168
10000
560

60
17388.00

Amount
in Rs.
728.40

1447.80
4388.40

6564.60

Amount
in Rs.
1175.40
9600.00
6200.00
16975.40

355787507.xlsx 218
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

17388.00
6564.60
16975.40
40928.00
0.00
40928.00
1227.84
42155.84
5739.52
47895.36
1437.00

Cum

Amount
in Rs.
15600.00

694.51

355787507.xlsx 219
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

332.00
33.20

195.56

11.56
2584.00
7440.00
2068.50
280.00
140.00
1450.00
220.00
100.00
31149.34

Amount
in Rs.
11096.03
7630.85
10597.99
5551.12
3431.00
1250.60
3169.40
10513.30
1979.25
0.00
39.60
0.00
55259.13

Amount
in Rs.
4118.47
1372.41
442.00
2252.85
2784.60
612.40
800.00
480.00
370.00
370.00
370.00
930.00
14902.73

355787507.xlsx 220
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

31149.34
55259.13
14902.73
101311.20
13793.52
115104.72
298.20
298.00
39.80
-31.30
307.00

drains etc., including


r for the formation of

cum

355787507.xlsx 221
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

0.00
56991.20
19426.40
76417.60
10404.26
86821.86
93.90
94.00

all materials,
mplete with lead upto 1
cum

0.00
50960.00
19690.00
70650.00

355787507.xlsx 222
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
9619
80269.00
127.40
127.00

g of embankment, filter
he excavated rock in

cum

355787507.xlsx 223
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

27459.20
66009.80

355787507.xlsx 224
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
45702.60
139171.60
18948.21
158119.81
196.40
196.00

Cum

355787507.xlsx 225
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

31149.34
55259.13

355787507.xlsx 226
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV
14902.73
101311.20
13793.52
115104.72
298.20
298.00
43.90
-30.20
311.70
312.00

355787507.xlsx 227
PRLIS Stage-2 P.S DPR Volume-3C, Part-IV

Rates of Materials ( SSR 2015-16)

Deduct Deduct diff. in Seignor


blasting stone cost age
S.No. Description of Material Unit Initial Rate Charges Total Charges

1 Cement Kg 5.65 5.65


2 Coarse aggregate 80-40 mm Cum 635.00 0 165 470.00
3 Coarse aggregate 40-20 mm Cum 1145.00 0 165 980.00
4 Coarse aggregate 20-10 mm Cum 1210.00 0 165 1045.00
5 Coarse aggregate 10 mm below 875.00 0 165 710.00
6 Sand(As per TS MDC) Cum 392 392
7 Sand(screened) Cum 392 392

8 HYSD BARS Fe500(tata/sail/vsp/Jindal) MT 35000 35000


9 Structural Steel MT 37500 37500
10 MS Plates MT 39500 39500

Excavated Earth spoil 2 Km 43.9 + 0+ 0- 0= 43.9


Excavated rock spoil 2Km 42.3 + 0+ 0- 0= 42.3
Sand 70 km 83.6 + 312.5 + 420 - 31.3 = 784.8
Cement:12Km 52.2 + 54.6 + 0- 18.9 = 87.9
Steel:12Km 52.2 + 54.6 + 0- 18.9 = 87.9
Metal4 Km 71.1 + 0+ 0- 30.2 = 40.9
Manufactured sand from
spoil 4km 71.1 + 31.3 = 39.8

355787507.xlsx 20
LEAD STATE
Name of Work: PRLIS (Package No. 1 ) Earth Work Excavation of Approach Cha
Reservoir and construction of stage 1 Pumping station and Design , Manufacture
Turbine pump and Synchronous motor sets for 8 No.s of 145 MW for stage 1 p
Mahaboobnagar

SSR Item
S.No Description of Item Source of Supply
No.

1 Manufactured sand Spoil bank


2 Metal/Stone Spoil bank
3 Cement At site

4 Steel At site

CERTIFICATES
1. Certified that the quantities , leads and lifts have been checked and found to be correct.
2. Certified that no nearer quarry is available than that specified in the lead chart.
3. Certified that the quarries adopted for the work have been inspected by me on 09 -09-2
and the quantity available is adequate for execution of the work.
4. Certified that the seigniorage charges allowed in this estimate rates are actually payable
5. Certified that the " Value Added Tax " @ 5 % on the rates of finished itmes of work is add
LEAD STATEMENT
vation of Approach Channel including Intake Structure and Tunnel from Foreshore of Srisai
Design , Manufacture , Supply , Erection , Testing and Commissioning of Vertical - Stage -
of 145 MW for stage 1 pumping station near Anjanagiri Resevoir at Narlapur(V), Kollapur(M
Mahaboobnagar District.

Lead(Km)
Lead charges Initial lead Net Lead
MT CT Equi.M.T
4 - 4 71.10 31.30 39.80
4 - 4 71.10 30.20 40.90
0 - 0 0 129.70 129.70

0 - 0 0 151.50 151.50

and found to be correct.


n the lead chart.
ected by me on 09 -09-2015 . The quality of the materilal is good
k.
ates are actually payable.
shed itmes of work is added which is actually payable.
om Foreshore of Srisailam
ng of Vertical - Stage - Francis
Narlapur(V), Kollapur(M)

Remarks

Including loding &


unloading
Including loding &
unloading

Вам также может понравиться