Project Task Information

Estimated Start Previous Estimated Actual Completion


Project Task Remarks
Date Completion Date Date

Phase 1 Plan

MAS Preparation
No firm approval from PDO, only email
09/01/2017 10/01/2017 05/04/2017
confirmation to proceed for installation.
Engineering Drawing Preparation

Phase 2 Plan

Procurement Local Purchase (LP)


Kidde material order placed after the
11/01/2017 12/01/2017 10/04/2017
confirmation of installation from PDO.
Procurement Foreign Purchase (FP)

Phase 3 Plan

LP Material Arrival 13/01/2017 20/01/2017 07/05/2017 Local purchase items are ready to
dispatch, foreign purchase items shall be
FP Material Arrival (Kidde) 13/01/2017 01/04/2017 07/07/2017 delivered after Muscat arrival.

Installation of Mechanical Equipment 21/01/2017 28/01/2017 14/05/2017 Pipe, fittings, cable & conduits shall be
supplied and installed as per the
scheduled date. Kidde material shall be
Installation of Electrical Devices 02/04/2017 10/04/2017 14/05/2017
installed after the arrival.
Phase 4 Plan

Room Integrity Test 11/04/2017 12/04/2017 10/07/2017

Mechanical Parts Pneumatic Test 13/04/2017 14/04/2017 10/07/2017

Electrical Device Test 14/04/2017 14/04/2017 10/07/2017

Phase 5 Plan

Documentation 14/04/2017 14/04/2017 12/07/2017

Handing Over 14/04/2017 14/04/2017 12/07/2017