PROJECT SCHEDULE
PROJECT: REPLACEMENT OF PIPE IN MPPL
Mechanical Scope of
S.No. Activity Description Gang No. Work Start Date
Note:
Simulataneously all activities will be carried out at both locations. (Except Joint Coating).
RMADA OFFSHORE CONSTRUCTIONS PRIVATE LIMITED
ROJECT SCHEDULE
PLACEMENT OF PIPE IN MPPL
Remarks
End Date
07.05.2017
07.05.2017
09.05.2017
11.05.2017
11.05.2017
11.05.2017
11.05.2017
12.05.2017
12.05.2017
12.05.2017
13.05.2017
13.05.2017