Академический Документы
Профессиональный Документы
Культура Документы
Consider a project involving the following activities and precedence relationship. The cost of each
activity is listed.
Duration (week)
Precedence Cost per week
Activity Optimistic Most likely Pessimistic
Activity ($/week)
(a) (m) (b)
A - 5,000 2 3 5
B A 3,000 3 5 8
C A 6,000 4 6 9
D B 2,000 1 2 4
E C 4,000 3 4 7
F D 7,000 1 2 4
G D 4,000 2 3 5
H G 8,000 1 2 3
J B,E 6,000 4 6 8
K E,F,H 5,000 2 4 7
L J 3,000 2 3 6
b) Use the CPM Forward and Backward Pass Computation as follows. The Critical Path is shown
(thick line path).
d) The cost distribution is conducted by assigning the cost of the activities per week (See
attached). The S-curve is plotted accordingly.
200,000
180,000
160,000
140,000
120,000
Early Start
100,000
Late Start
80,000 Target
60,000
40,000
20,000
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
LateStartTime
weekly Duration Week
Activity cost 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
A 5,000 3 5,000 5,000 5,000
B 3,000 5 3,000 3,000 3,000 3,000 3,000
C 6,000 6 6,000 6,000 6,000 6,000 6,000 6,000
D 2,000 2 2,000 2,000
E 4,000 4 4,000 4,000 4,000 4,000
F 7,000 2 7,000 7,000
G 4,000 3 4,000 4,000 4,000
H 8,000 2 8,000 8,000
J 6,000 6 6,000 6,000 6,000 6,000 6,000 6,000
K 5,000 4 5,000 5,000 5,000 5,000
L 3,000 3 3,000 3,000 3,000
Total 5,000 5,000 5,000 6,000 6,000 6,000 9,000 9,000 9,000 7,000 7,000 6,000 6,000 10,000 10,000 10,000 21,000 21,000 11,000 8,000 8,000 8,000
Cummulative 5,000 10,000 15,000 21,000 27,000 33,000 42,000 51,000 60,000 67,000 74,000 80,000 86,000 96,000 106,000 116,000 137,000 158,000 169,000 177,000 185,000 193,000
TargetTime
weekly Duration Week
Activity cost 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
A 5,000 3 5,000 5,000 5,000
B 3,000 5 1,500 3,000 3,000 3,000 3,000 1,500
C 6,000 6 6,000 6,000 6,000 6,000 6,000 6,000
D 2,000 2 1,000 2,000 1,000
E 4,000 4 4,000 4,000 4,000 4,000
F 7,000 2 7,000 7,000
G 4,000 3 2,000 4,000 4,000 2,000
H 8,000 2 4,000 8,000 4,000
J 6,000 6 6,000 6,000 6,000 6,000 6,000 6,000
K 5,000 4 2,500 5,000 5,000 5,000 2,500
L 3,000 3 3,000 3,000 3,000
Total 5,000 5,000 5,000 6,000 7,500 9,000 9,000 9,000 9,000 6,500 6,000 7,000 8,000 17,000 19,000 14,000 12,500 11,000 11,000 8,000 5,500 3,000
Cummulative 5,000 10,000 15,000 21,000 28,500 37,500 46,500 55,500 64,500 71,000 77,000 84,000 92,000 109,000 128,000 142,000 154,500 165,500 176,500 184,500 190,000 193,000