Вы находитесь на странице: 1из 61

CHAPTER 2

SUBSOIL EXPLORATION

2.1 SOIL EXPLORATION


All office, laboratory and field works are done in order to explore the subsurface of soil or
rock conditions at any given site to obtain the necessary information required in design and
construction. Subsoil exploration is the first step in the design of a foundation system. Soil
exploration consists essentially of boring, sampling and testing.

(a) Office, laboratory and field works:

Planning Boring Sampling Testing Report


for exploration program and phases of soil investigation

Usually, the proper program of soil investigation for a given project depends on the type
and importance of structure; nature of the subsoil involved; type of equipment available; ground
water condition; and the budget allocated for the exploration. At present, site investigation
drilling and testing are carried out in a routine way, with the absence of any significant plan. This
may result in a significant loss of money and time, since the work is carried out without reference
to the special requirements of the project.
If previous site investigation reports exist for construction in the same soil, this allows the
geotechnical engineer to judge the likely performance of the ground under and around the
proposed development. In any case, geological maps coupled with experience will give a
considerable amount of information of great value in the initial stages of design. At this stage,
there should also be interaction between the client and all his design professionals. Thus, the
design should be modified to reduce possible geotechnical problems. For example, if a large site
is to be developed as a business park, the buildings might be re-aligned with their long sides
parallel to the contours; this will reduce the amount of cut and fill, thus keeping the cost of
foundations and retaining structures to a minimum, while also reducing the risks of slope
instability.
From the knowledge of probable ground, groundwater conditions at and around the site, and
the required structural form(s), the geotechnical engineer can predict the types of foundations and
earth-retaining structures required for the project, and any possible problems (such as slope
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

instability, chemical attack on foundation concrete and construction difficulties) which may
therefore require further investigation.

(b) To explore subsurface conditions:


Drilling and trial pitting are normally carried out for a number of reasons, such as:
1. To establish the general nature of the strata below a site. This will decide whether the site is
good or not for the proposed project;
2. To determine depth (below the ground surface); thickness; extent of all soil layers in both
vertical and lateral directions. Also if rock is existing, the depth and the extent of its surface,
its thickness and nature should be defined and determined;
3. To determine for clay layers (if possible) whether it is a recent deposit or an old one that has
been compressed by pervious overburden which may be removed by erosion and whether
the clay has been subjected to cycles of wetting and drying;
4. To obtain disturbed and undisturbed soil samples for laboratory testing;
5. To allow field tests to be carried out;
6. To locate the level of water table, its seasonal variation and the methods of controlling it
during construction;
7. To install instruments such as piezometers, or extensometers, and
8. To verify the interpretation of geophysical surveys.

(c) To obtain information required in the design and construction


(i) For new structures:
Selection of the type and depth of foundation;
Determination of bearing capacity and settlement of the selected foundation;
Evaluation of the earth pressure against walls and abutments;
Suitability of soil and degree of compaction of fill material under slabs and earth
works;
Establishment of the ground water level;
Provisions against constructional difficulties;
Swelling potential; and
Chemical contents.

(ii) For existing structures:


Investigation of the safety of the structure;
Prediction of settlement; and
Determination of remedial steps against water table problems, serious settlement and
cracks.

(iii) For highways and airfields:


The location of the road and runways both vertically and horizontally;
The location and selection of borrow materials for fills and subgrade treatments;
The design of ditches, culverts and drains;
The design of roadway section;
The type of subgrade treatments; and

16
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

The location of local sources of construction materials for base, subbase, stabilizer, binder
and wearing courses and other structural works.

Mainly, subsoil exploration involves three phases; reconnaissance phase, preliminary site
investigation phase, and detailed site investigation phase.

2.1.1 RECONNAISSANCE PHASE


This phase consists of:
(a) Collection of all available information, and
(b) Reconnaissance of the site.
So that, it will indicate any settlement limitations and help to estimate foundation loads.

2.1.2 PRELIMINARY SITE INVESTIGATION PHASE


This phase consists of:
(a) Preliminary design data that satisfy building code requirements, and
(b) Number and depth of boreholes.
So, it involves knowing the distribution of structural loads which is required in the design
of foundations. Also, a few borings or tests pits are to be opened to establish the stratification
types of soil and location of water table. In addition, one or more borings should be taken to rock
when the initial boreholes indicate that the upper soil is loose or highly compressible.

2.1.3 DETAILED SITE INVESTIGATION PHASE


In this phase, additional boreholes, samples will be required for zones of poor soil at
smaller spacing and locations which can influence the design and construction of the foundation.

2.2 DRILLING OR BORING


2.2.1 TEST PITS
A pit is dug either by hand or by a backhoe. Probably in a test pit, the engineer can examine
in detail the subsoil strata and take disturbed or undisturbed samples at the desired location (see
Fig.(2.1)):

Advantages:
Inexpensive.
Provide detailed information of stratigraphy.
Large quantities of disturbed soils can be obtained for testing.
Large blocks of undisturbed samples can be carved out from the pits, and
Field tests can be conducted at the bottom of the pit.

Disadvantages:

17
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

Depth limited to about 6m.


Deep pits are uneconomical as in the case of investigation that involves basement
construction.
Excavation below groundwater (high water table) and into rock is difficult and
costly.
Too many pits may scar site and require backfill soils.
When the soil is unstable and has a tendency to collapse, this prevents the engineer
from entering the pit and accompanied by certain risks, and
Unsuitable in granular soils below water level or when the standard penetration
resistance test (N-value) is required.

Walls of test pit indicate four layers


(1) Clayey silt (2) Sandy silt (3) Clean sand (4) Sandy gravel

Fig.(2.1): Test pits.

2.2.2 DRILLING METHODS


Several methods can be used for drilling a hole into ground, these are:

(1) Auger Drilling


(a) Hand - auger drilling.
(b) Power - auger drilling.
(2) Wash Boring
(a) Jetting.
(b) Sludging (reverse drilling).

(3) Rotary Drilling


(a) Rotary drilling with flush.
(b) Rotary - percussion drilling.
(4) Percussion Drilling

18
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

Each of these methods has its merits and its demerits. However, Table (2.1) gives a guide
for selecting the most appropriate drilling method.

Table (2.1): Drilling method selection (after Budhu, 2007).

Wash boring Rotary drilling


Hand Rotary Rotary Percussio
Type of soil auger Jetting Sludgin drilling percussio n drilling
drilling g with n drilling
flush
Gravel X X X X ? ?
Sand ? ?
Silt Unconsolidate ? ?
Clay d formations ? slow slow
Sand with pebbles
X X X X ? ?
or boulders
shale Low to X X X slow
medium
Sandstone strength X X X
formations
Limestone X X X slow slow
Igneous (granite, Medium to
high strength X X X X slow
basalt)
Metamorphic formations
X X X X V slow
(slate, gneiss)
Rock with fractures or voids X X X !
Above water-table ? X
Below water-table ?
= Suitable drilling ! = Flush must be maintained to continue
? = Danger of hole collapsing
method drilling
? = Possible problems x = Inappropriate method of drilling

(5) Rock Core Drilling


o Used for obtaining rock cores.
o A core barrel which is fitted with a
drill bit, is attached to hollow drill
rods. Fig.(2.2) shows one box of
bedrock drill core. The core can be
drilled in various diameters. The
core in the picture is about 2.0
inches in diameter and is the most
common size drilled for mineral
exploration.

19
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

2.2.2.1 Auger Drilling Fig.(2.2): Core extracted from


a drill
(a) Hand - Augers hole placed in a core
The auger of (10 20) cm in diameter is rotated by turning and pushing down on the
handlebar. Then withdrawing and emptying the soil-laden auger to remove the excavated soil.
Several new auger sections are added until the required depth is reached. These augers can be
available in different types such as (see Fig.(2.3)):
Helical Auger.
Short flight Auger, and
Iwan Auger.

Advantages:
Inexpensive.
Simple to operate and maintain.
Not dependent on terrain.
Portable.
Used in uncased holes, and
Groundwater location can easily be identified and measured.

Disadvantages:
Slow compared with other methods.
Depth limited to about 6m.
Labor intensive.
Undisturbed samples can be taken only for soft clay deposit, and
Cannot be used in rock, stiff clays, dry sand, or caliches soils.

20
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

a. Helical (worm types) Augers b. Short flight Auger c.


Iwan (posthole) Auger

Fig.(2.3): Hand augers (after Allen, 1993).


(b) Power - Augers
Truck or tractor mounted type rig and equipped with continuous flight augers that bore a
hole 100 to 250 mm in diameter. These augers can have a solid or hollow stem of (20 -75) cm in
diameter (see Fig.(2.4)).

Advantages:

21
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

Used in clay or sand or silt soils.


Quick.
Used in uncased holes, therefore no need for using drilling mud.
Undisturbed samples can be obtained quite easily, and
Groundwater location can easily be identified and measured.

Disadvantages:
Depth limited to about 15m. At greater depth, drilling becomes expensive, and
Site must be accessible to motorized vehicle.

a. Continuous flight augers. b. Solid-stem auger


c. Hollow-steam auger

Fig.(2.4): Power or mechanical-augers.

2.2.2.2 Wash Boring


Water is pumped to bottom of borehole and soil washings are returned to surface. A drill bit
is rotated and dropped to produce a chopping action (see Fig.(2.5)).

22
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

Fig.(2.5): Wash boring rig.

(a) Jetting Method

Method: Water is pumped down the center of the drill-rods, emerging as a jet. It then
returns up the borehole or drill-pipe bringing with it cuttings and debris. The washing and
cutting of the formation is helped by rotation, and by the up-and-down motion of the drill-
string. A foot-powered treadle pump or a small internal-combustion pump is equally suitable.

(b) Sludging (Reverse Jetting)

Method: A hollow pipe of steel is moved up and down in the borehole while a one-way
valve can be used to improvise successfully and provide a pumping action. Water flows
down the borehole annulus (ring) and back up the drill pipe, bringing debris with it. A small
reservoir is needed at the top of the borehole for recirculation. Simple teeth at the bottom of
the drill-pipe, preferably made of metal, help cutting efficiency.

Advantages:
The equipment can be made from local, low-cost materials, and it is simple to use.
Possible above and below the water-table.
Suitable for clay to silt clay, silt soils and unconsolidated rocks, and

23
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

Used in uncased holes.

Disadvantages:
Slow drilling through stiff clays and gravels.
Undisturbed soil samples cannot be obtained.
Water is required for pumping.
Difficulty in obtaining accurate location of groundwater level.
Boulders can prevent further drilling, and
Depth is limited to about 30m.

2.2.2.3 Rotary Drilling

(a) Rotary Drilling with Flush

Method: A drill-pipe and bit are rotated to cut the rock. Air, water, or drilling mud is
pumped down the drill-pipe to flush out the debris. The velocity of the flush in the borehole
annulus must be sufficient to lift the cuttings (see Fig.(2.6)).

Advantages:
Quick.
Can drill any type of soil or rock.
Possible to drill to depths of over 40 meters.
Operation is possible above and below the water-table.
Undisturbed soil samples or rock cores can easily be recovered.
Water and mud support unstable formations, and
Possible to use compressed air flush.

Disadvantages:
Expensive equipment.
Terrain must be accessible to motorized vehicle.
Water is required for pumping.
Difficulty in obtaining accurate location of groundwater level.
There can be problems with boulders, and
Rig requires careful operation and maintenance (additional time required for setup and
cleanup).
(b) Rotary - Percussion Drilling
Method: In very hard rocks, such as granite, the only way to drill a hole is to pulverize the
rock, using a rapid-action pneumatic hammer, often known as a 'down-the-hole hammer'

24
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

(DTH). Compressed air is needed to drive this tool. The air also flushes the cuttings and dust
from the borehole. Rotation of 10 30 rpm ensures that the borehole is straight and
circular in cross section (see Fig.(2.6)).

Advantages:
Drills hard rocks.
Possible to penetrate gravel.
Fast, and
Operation is possible above and below the water-table.

Disadvantages:
Higher tool cost than other tools illustrated here.
Air compressor required, and
Experience needed to operate and maintain.

Fig.(2.6): Rotary drilling.


2.2.2.4 Percussion Drilling

25
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

Method: The lifting and dropping of a heavy (+ 50 kg) cutting tool will chip and
excavate material from a hole. The tool may be fixed to rigid drill-rods, a rope or a cable.
With a mechanical winch, depths of hundreds of meters can be reached.

Advantages:
Simple to operate and maintain.
Suitable for a wide variety of rocks.
Operation is possible above and below the water-table.
It is possible to drill to considerable depths, and
Can be used for boring observation wells.

Disadvantages:
Slow, compared with other methods.
Problems can occur with unstable rock formations.
Water is needed for dry holes to help remove cuttings, and
Due to high disturbance of soil, the obtained samples cannot be used for testing.

2.2.2.5 Rock Core Drilling

Steps in the Process: (after IDEA Drilling, 1997)

1. Drilling holes begins with installing a pipe called casing from the
surface through soils and sealed into bedrock.
2. Diamond core drilling uses a diamond bit, which rotates at the end
of drill rod (or pipe) inside the casing.
3. The opening at the end of the diamond bit allows a solid column of
rock to move up into the drill pipe and be recovered at the surface.
4. Most drill rods are 3m long. After the first 3m drilling, a new section
of pipe is screwed into the top end, so the combination of pipes can
be drilled deeper into the ground.
5. The diamond bit is rotated with gentle pressure while being
lubricated with water and drilling fluid to prevent overheating.
6. The driller adjusts rotation speed, pressure and water circulation for
different rock types and drilling conditions.
7. Inside the drill pipe is a core tube, which has a latching mechanism
attached to a cable. At the end of each 3m run, the cable is lowered
to winch the core tube containing the new rock core to the surface
where it can be recovered.
8. The drill core is stored in specially designed core boxes containing
compartments to hold sections of the core, and
9. The drill core is then logged and analyzed by a geologist.

26
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

2.3 UNDERGROUND WATER IN THE TEST HOLE


The depth of the water table (W.T.) as measured during drilling and sampling should be
carefully evaluated. It is always necessary to wait for at least 24 hours to check on the stabilized
water table for the final measurement. The technician should plug the top of the drill holes and
flag them for identification. Care is required to ensure that the water level in the drill hole is
always maintained. Any sudden drop or rise of the water table should be carefully recorded in the
field logs of borings.

2.4 GEOPHYSICAL METHODS


These methods represent indirect methods of subsoil exploration and mainly consist of:

(1) Ground Penetration Radar (GPR).


(2) Electrical Resistivity Method (ERM)
(3) Electromagnetic Method (EM), and
(4) Seismic Methods.

In subsoil investigation, the seismic methods are most frequently used. These methods are
based on the variation of the wave velocity in different earth materials. They involve in
generating a sound wave in the rock or soil, using a sledgehammer, a falling weight, or a small
explosive charge, and then recording its reception at a series of geophones located at various
distances from the shot point, as shown in Fig.(2.7). The time of the refracted sound arrival at
each geophone is noted from a continuous reader. Typical P wave velocity in various soils
and rocks in (m/sec) are shown in Table (2.2).

Requirements of seismic exploration:


Equipment to produce an elastic wave, such as a sledgehammer used to strike a plate on the
surface.
A series of detectors, spaced at intervals along a line from wave origin point, and
A time-recording mechanism to record the time of origin of the wave and the time of its
arrival at each detector.

Advantages of seismic exploration:


1. Permits a rapid coverage of large areas at a relatively small cost.
2. Not hampered by boulders and cobbles which obstruct borings, and
3.Used in regions not accessible to boring equipment, such as the middle of a rapid river.

Disadvantages of seismic exploration:


1. Lack of unique interpretation.
2. It is particularly serious when the strata are not uniform in thickness nor horizontal,
3. Irregular contacts often are not identified, and
4. The strata of similar geophysical properties sometimes have greatly different properties.

Note: Whenever possible, seismic data should be verified by one or two borings before
definite conclusions can be reached.

27
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

(b) Ground penetration radar. (a) Electrical resistivity method.

(c) Seismic survey method.

Fig.(2.7): Geophysical methods.

28
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

Table (2.2): Typical P wave velocity in various soils and rocks (after Das ,2007).

P wave
Type of soil or rock Velocity
(m/ sec)
Soil:
Sand, dry silt, and fine grained topsoil 200 -1000
500 -
Alluvium
2000
1000 -
Compacted clays, clayey gravel, and dense clayey sand
2500
Loess 250 - 750
Rock:
2500 -
Slate and shale
5000
1500 -
Sandstone
5000
4000 -
Granite
6000
Sound limestone 5000 -10000

2.5 SAMPLING
During the boring, three types of representative soil samples should be collected which are
valuable to geotechnical engineers; these are as follows:

(a) The disturbed samples (D): which were collected from auger cuttings at specified
depths?
(b) The undisturbed samples (U): which were obtained using a thin Shelby tubes of
100mm in diameter and (400-450)mm in length, and
(c) The (SS) samples: which were taken from standard split spoon sampler used in a
standard penetration test (S.P.T.) that performed at different intervals depending on soil
stratification.

All these samples are then sealed tightly in plastic bags to retain their in situ moisture
content, labeled and transported to the soil mechanics laboratory, to perform the required
tests.

2.5.1 DISTURBED SAMPLES

Disturbed samples can be collected during the drilling process from the auger cuttings at
certain intervals and/or each different stratum. In test pit excavation, large samples will
sometimes be required in order to fulfill the laboratory testing requirements. Such samples should

29
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

be at least (30 cm x 30cm) in size, wrapped in wax paper, and carefully transported to the
laboratory.
Representative samples can also be obtained by driving into the ground an open-ended
cylinder known as Split Spoon. Spoons with an inside diameter of about 5 cm consists of four
parts: a cutting shoe at the bottom; a barrel consisting of a length of pipe split into one half; and a
coupling at the top for connection to the drill rod.

2.5.2 UNDISTURBED SAMPLES


These samples can be obtained by pushing a thin-walled Shelby or seamless steel tube
which is attached to a sampler into the soil at the desired depth. The operation must be performed
carefully so as to experience minimum deformation. The sampler head contains a check valve
and vents for the escape of air or water. The principal advantages of the Shelby tube sampler are
its simplicity and the minimal disturbance of soil.
Fig.(2.8) shows some details of standard split-spoon and thin-wall tube samplers that are
commonly used in in-situ testing and sample recovery equipment. A modification in the design
of the split spoon sampler allows the insertion of brass thin-wall liners into the barrel. Four
sections of brass liners (each 4 inch long) can be used. Such a device allows the sampling and
penetration test at the same time. This method was initiated in California and known as the
California sampler.

2.5.3 ROCK CORE SAMPLES


Samples of rock are generally obtained by rotary core drilling. Diamond core drilling is
primarily used in medium-hard to hard rocks. Special diamond core barrels up to 20 cms in
diameter are occasionally used and larger ones can be used. Such large samples enable the
geologist to study the formation and texture of the foundation rock in detail.

A summary of different sampler types which can be used to obtain disturbed or undisturbed
samples of each type of soil are listed in Table (2.3).

30
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

Fig.(2.8):
Table (2.3): Details
Types ofof samplers
commonly used
used samplers
for forand
taking soil in
rocksitu testing
samples (after
from Moore,
test holes.
1980).
Type of sampler Procedure Type of soil and Remarks
All types of soils,
Auger boring, wash boring,
Highly disturbed sampler Due to high disturbance it is unsuitable for
and percussion drilling.
foundation exploration.
Cohesive, cohesionless soils and soft
rocks,
For taking disturbed samples which
Standard Penetration are required for physical and geotechnical
Split spoon sampler
Test. analysis of soil as well as chemical tests.
In cohesionless soils, the penetration
number (N) is used for making both strength
and settlement estimates.
16 gauge seamless steel For taking undisturbed samples from
tube (7.5- 15) cm dia.;
cohesive soil,
Thin wall Shelby tube preferably pushed by static
Unsuitable for granular soils and hard
force instead of driven by
hammer. materials.
Core barrel sampler:
(a) Single For taking undisturbed continuous rock
Rotary drilling
tube, and samples.
(b) Double tube core barrel.
For taking undisturbed samples in soft and
Piston samplers Rotary drilling
slightly stiff cohesive soils.
Hard carved samples:
Cut by hand from side of For taking disturbed samples in cohesive or
Spring core catcher, and
test pit. cohesionless soils.
(b) Scraper bucket.
For taking disturbed samples in
Cut by hand from side of
Hand-cut samples cohesionless soil or disturbed and
test pit.
undisturbed block samples in cohesive soil.

2.6 SAMPLE DISTURBANCE


Certain amounts of disturbance during sampling must be regarded as inevitable:-

1. Effect of stress relief:


Due to boring, the stress state in soil will be changed as a result of a stress relief.

2. Effect of area ratio (Ar %):


It is the ratio of the volume of soil displacement to the volume of the collected sample.

31
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

D o 2 Di 2
Ar x100
Di 2 .(2.1)
where, D i and Do are inner and outer diameters of the used sampler.
For stiff clay < 20%, for soft clay 10% and samples with A r > 20% considered as disturbed
samples.

3. Effect of friction and adhesion:


If the length of sampler is large with respect to diameter, a bearing capacity failure may occur
due to disturbance of sample.
D Di
Ci o x100
Di ..(2.2)
where, Ci inside clearance = (0.3 0.4)% and not more than 1%.

4. Effect of the way in which the force is applied to the spoon: that means by pushing
or driving or by constant rate of penetration.

2.7 TESTING
The tests performed on each type of the three different soil samples are as follows:
As a rule, undisturbed samples (U) can be tested for strength and compressibility to determine the
stress strain characteristics of the material, in addition to classification and chemical tests.
Whereas, disturbed (D) or (SS) samples as available were mainly used for physical and
geotechnical analysis of soil as well as chemical tests.

2.7.1 LABORATORY TESTS


The obtained samples should be tested according to the procedure of the American Society
for Testing and Materials (ASTM) or the British Standards (BS) whichever is appropriate. The
test program of the samples includes the followings:

1. Classification Tests:
Sieve and hydrometer analysis, natural water content, Atterberge limits, specific gravity,
and wet and dry unit weights.

2. Compaction Test:
Modified Procter compaction test must be carried out on some soil samples to obtain the
( dmax . )
maximum dry density and the relevant optimum moisture content (OMC).

3. Shear Strength and Compressibility Tests:


Unconfined or Triaxial compressive strength test, one-dimensional consolidation, and
swelling tests.

32
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

4. Chemical Tests:
Sulphate Content (SO3-2)%, Total Soluble Salts (T.S.S.), Organic Matter Content (ORG.)
%, PH- value, Carbonate Content (CO3-2), Chlorides Content (Cl-1)% , and Gypsum
content %.

2.7.2 FIELD TESTS


During the subsoil exploration, several field tests for soils or rocks as given in Tables
(2.4) and (2.5), respectively, can be performed depending on the available testing equipment,
required parameters for design of foundations, and the economic point of view.

Table (2.4): Types of field tests for soils.

Purpose of test Type of test


1. SPT N-value
Standard or Dynamic Penetration Test (SPT).
(for granular soil)
Static Penetration Test (CPT)
Vane shear test (for soft to medium fine grained soil, clay and silt clay;
up to Cu =1.0 kg/cm2),
Tor vane shear test (for soft soil; up to Cu =5.0 kg/cm 2),
2. Undrained shear strength Pocket penetrometer,
(for cohesive soil) Pressuremeter test; it is of three types:
Menard (to obtain;
R D ,.,.Su ,.E s ,.G,.m v ,.Cc ),

Self boring (to obtain;


R D ,.,.Su ,.u ,.Es ,.G,.m v ,.Cc ,.C v ),
E ...and...G
Screw boring (to obtain; s ).
Pavements: plate bearing ;CBR test,
Footings: plate bearing test,
3. Bearing capacity
Piles subjected to vertical loads: load test,
Batter piles: lateral load test.
Seismic Tests:
Cross-hole,
4. Elastic and shear modulus Down-hole, and
c- Surface refraction (to measure D s
R , E , G
, liquefaction resistance
and thickness of soil layers).
Pumping Test:
Constant head test,
5. Permeability
Variable head test,
Piezometers test (or ground water observation).
Field or In-place Density:
6. Compaction control For Sand: a- Sand cone method, b- Rubber balloon method,
For Clay: a- Penetration needle, b- Core cutter method.

Table (2.5): Types of field tests for rocks.

Purpose of test Type of test

33
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

1. Strength &
Field Vane Shear1, Direct Shear, Point Load, Pressuremeter 2, Uniaxial
Rock Quality Designation
Compressive2, Borehole Jacking2.
(RQD %)
2. Bearing capacity Plate Bearing1, Standard Penetration1.
Hydraulic Fracturing, Pressuremeter, Overcoring, Flat Jack, Uniaxial
3. Stress Conditions
(Tunnel) Jacking2, Chamber (Gallery) Pressure2.
Geophysical (Refraction)3, Pressuremeter or Dilatometer, Plate Bearing,
4. Mass Deformability Uniaxial (Tunnel) Jacking2, Borehole Jacking2, Chamber (Gallery)
Pressure2.
5. Anchor Capacity Anchor / Rockbolt Loading.
Constant Head, Rising or Falling Head, Well Slug Pumping, Pressure
6. Rock Mass Permeability
Injection.
Notes: 1. Primarily for clay shales, badly decomposed, or moderately soft rocks, and rock with soft seams.
2. Less frequently used.
3. Dynamic deformability.
2.8 LOGS OF BORINGS AND RECORDS OF TESTING RESULTS
At the beginning, a map giving specific locations of all borings should be available. Each
boring should be identified (by number) and its location documented by measurement to
permanent features. Such a map is shown in Fig.(2.9). For each boring, all pertinent data should
be recorded in the field on a boring log sheet. These sheets are preprinted forms containing
blanks for filling in appropriate data. Fig.(2.10) shows an example of a boring log sheet.
Soil data obtained from a series of test borings can best be presented by preparing a
geologic profile, which shows the arrangement of various layers of soil, the groundwater table,
existing and proposed structures, and soil properties data. An example of a geologic profile is
shown in Fig.(2.11).
Depending on the results of the laboratory tests and the field observations, the actual subsoil
profiles or logs of borings can more accurately be sketched (see Fig.(2.12)). In addition to, the
actual description of soil strata in each borehole is summarized within records of tests results.
90m

B-1 7.5m B-2


15m 30m 30m 15m

45m

15m B-3

7.5m B-5
B-4

Fig.(2.9): Example map showing boring locations on site plan.

DRILLING COMPANY, INC. BORE HOLE NO.: -------------


PROJECT: LOCATION: --------------------

34

Fig.(2.10): Boring log sheet.


Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

Name ---------------------------------------------------- Date Time Depth Casing at


Address ------------------------------------------------ ------------- -------------- ---------------- ------------------------------------
CASING (SIZE AND TYPE) ---------------------------------
SAMPLE SPOON (SIZE AND TYPE) ---------------------
HAMMER (CSG): WT. ------------, DROP ------------------
(SPOON): WT. ------------, DROP ------------------
DATE: STARTED --------------------------------------------, COMPLETED ----------------------, DRILLER ----------------------

Field Depth of
'N'- Value
Samples Sampling (m) Visual Description of Soil
No. Type From To 6 6 6
1 D 0.0 2.0 Black and grey moist fill,
2 U 2.0 4.0 Black peat.
3 S.S 4.5 5.0 11 14 6 Sandy clay and silt mixture.
4 D 5.0 7.0 Sandy silt and clay mixture.
5 U 7.0 9.0 Silt with fine gravel and traces of fine sand.
6 S.S 9.5 10.0 4 8 3 Sandy clay and silt mixture.

(N.G.S.)
Natural ground surface BH.no.1 BH.no.2 BH.no.3
0

silt mixture
2 and
clay silt mixture
Fig.(2.11): Example of geologic profile.
and
clay
4

silt mixture
and
Depth (m)

E.O.B.
6 clay

clay mixture
8 and
silt

10 silt mixture
and
clay
12
E.O.B. E.O.B.
35
Tanahi District / Duhok city.
Fig.(2.12): Log of borings for 1st. stage of garden city housing project
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

A RECORD OF TESTS RESULTS

36
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

A RECORD OF TESTS RESULTS

37
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

2.9 NUMBER OF BOREHOLES


can be drawn with reasonable accuracy and then the preliminary program can be adjusted to
suit subsoil conditions. Obviously, the more boreholes and the closer they are spaced, the more
accurate the resulting geologic profile will be. Boreholes number and layout may need to be
changed as more information emerges, so that, additional boreholes may be required during the
survey.
The layout of the borings should aim not only to provide soil profiles and samples at
positions related to the proposed structures and their foundations, but should also be arranged to
check the hypotheses formed during the survey, the geological succession, the presence of drift
deposits and the extent of the various materials on site in order to allow cross-sections to be
drawn. Also, when a structure is to be found on slope, the overall stability of the structure and the
slope obviously must be investigated, and a deep borehole near the top of the slope is very useful.
For example, a typical investigation for a motorway in the UK might use 5 to l0m deep borings
every 150m along the proposed road line, with four 25 to 30m deep borings at the proposed
position of each bridge structure.
However, for rough guidelines, if soil conditions are relatively uniform or the geological
data are limited, Tables (2.6, 2.7 and 2.8) can be used as a guide in planning of the preliminary
program:

Table (2.6): Number and spacing of boreholes according to the type of project
(after Hvorslev 1949, and Road Research Laboratory 1952).

Distance between borings (m)


Minimum number
Project Horizontal stratification of soil of boreholes
uniform average erratic
Multi-story building 45 30 15 4
1 or 2 story building 60 30 15 3
Bridge, pier, abutment, Tv. Tower ---- 30 7.5 1-2
Highways 300 150 30 ----
150 15 3
Borrow pits 60 150 ----
300 0
Isolated small structures: such as small 1

38
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

houses.
4
Compact projects: such as buildings,
deeper and closely
dams, bridges or small landslips
spaced
Extended projects: such as motorways,
shallower
railways, reservoirs and land reclamation
and widely spaced
schemes.

Table (2.7): Number of borings for medium to heavy weight buildings, tanks, and other
similar structures on shallow foundations (after Sowers, 1979).

Subsurface Conditions Structure Footprint Area for Each Exploratory Boring (m2)
Poor quality and / or erratic 100 300
Average 200 400
High quality and uniform 300 1000
Table (2.8): Minimum borings guidelines (after MDT Manual, 2008).

Geotechnical
Minimum number of borings
feature
Provide at least 1 boring per substructure unit 30 m width,
Provide at least 2 borings per substructure unit 30 m width,
Shallow Foundations
Provide additional borings in areas where erratic subsurface conditions are
encountered.

Provide at least 1 boring per bridge pier location for driven piles,
Provide at least 1 boring per drilled shaft location, unless the shaft is
Deep Foundations part of a group in which case a single boring per group is sufficient,
Provide additional borings in areas where erratic subsurface conditions are
encountered, especially for shafts socketed into bedrock.

Provide at least 1 boring for each retaining wall,


For walls of length > 30 m, space borings 30 m to 60 m with locations
alternating from in front of the wall to behind the wall,
Retaining Structures For anchored walls, provide additional borings in the anchorage zone space at
30 to 60 m,
For soil-nailed walls, provide additional borings at a distance of 1.0 1.5
times the height of the wall behind the wall spaced at 30 to 60 m.
When approach embankments are to be placed over soft ground, provide at
Bridge Approach least 1 boring at each embankment to determine if any problems associated
Embankments over with stability and settlement of the embankment are present,
Soft Ground Typically, test borings taken for the approach embankments are located at the
proposed abutment locations and serves a dual function.

Provide borings at a minimum spacing of approximately 300 m,


Roadways Provide additional borings in areas where erratic subsurface conditions are
encountered.

39
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

Typically, space borings every 60 m for erratic conditions, to 120 m for uniform
conditions with at least 1 boring taken in each separate landform,
Roadway Cuts and
For high cuts and fills and other critical locations, provide a minimum of 3
Embankments
borings along a line perpendicular to centerline or planned slope face to
establish geologic cross-section for analysis.

Provide a minimum of 3 borings along a line perpendicular to centerline or


Landslides planned slope face to establish geologic cross-section for analysis,
The actual number of borings depends on the extent of stability problem.

Varies widely depending on ground improvement technique(s) being


Ground Improvement
employed, for more information, see FHWA Ground Improvement Technical
Techniques
Summaries, FHWA SA 98 086R.

Material Sites (Borrow Space boring every 30 m to 60 m.


Sources, Quarries)

2.10 DEPTH OF BORINGS


It is good practice on any site to sink at least one deep borehole to establish the site geology.
On extended projects several of these may be necessary, partly in order to establish the depth of
weathering. Hvorslev (1949) and MDT Manual (2008) suggested a number of general rules
which remain applicable:
The borings should be extended to strata of adequate bearing capacity and should
penetrate all deposits which are unsuitable for foundation purposes such as
unconsolidated fill, peat, organic silt and very soft and compressible clay;
The soft strata should be penetrated even when they are covered with a surface layer of
high bearing capacity;
When structures are to be founded on clay and other materials with adequate strength to
support the structure but subject to consolidation by an increase in the load, the borings
should penetrate the compressible strata or be extended to such a depth that the stress
increase for still deeper strata is reduced to values so small that the corresponding
consolidation of these strata will not materially influence the settlement of the proposed
structure;
In case of very heavy loads or when seepage or other considerations are governing, the
borings may be stopped when rock is encountered or after a short penetration into strata of
exceptional bearing capacity and stiffness, provided it is known from explorations in the
vicinity of the area that these strata have adequate thickness or are underlaid by still
stronger formations. But, if these conditions are not satisfied, some of the borings must be
extended until it has been established that the strong strata have adequate thickness
irrespective of the character of the underlying material;
When the structure is to be founded on rock, it must be verified that bedrock and not
boulders have been encountered, and it is advisable to extend one or more borings from 3
to 6m into solid rock in order to determine the extent and character of the weathered zone
of the rock;

40
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

For rough guidelines, the following criteria can be used for minimum depths, from
considerations of stress distribution or seepage,:

1. Foundations:
All borings should extend below all deposits such as top soils, organic silts, peat,
artificial fills, very soft and compressible clay layers;
Boring should be sufficiently deep for checking the possibility of a weaker soil at greater
depth which may settle under the applied load;
Deeper than any strong layer at the surface checking for a weaker layer of soil under it
which may cause a failure (see Fig.(2.13a));
The depth at which the net increase in stress due to the foundation or building load is less
than 5% of the effective overburden pressure;
The depth at which the net vertical total stress increases because the foundation or
building load is less than 10% of the stress applied at foundation level (contact pressure);
For isolated spread footings or raft foundations, explore to a depth equal 1.5B (B = least
width of the footing or the raft) (see Fig.(2.13b));
For group of interfering footings, explore to a depth equal 1.5B ' (where, B ' =
width of interfering footings) (see Fig.(2.14));
For heavy structures (pressure 200 kPa), the depth of borings should be extended to
2B (width of footing);
L
10
For strip footings, explore to not less than 3B (width of footing) for B 6m and B .
For multistory buildings, explore to:
(i) D D f 3.S0.7 (in meter). for light steel or narrow concrete buildings,
0 .7
(ii) D Df 6.S (in meter) ... for heavy steel or wide concrete buildings.
where, D = Depth of boring, D f = Depth of footing, and S = Number of stories.
2
If piled foundation is expected, the borehole depth D =( Df + L+ 1.5B) or D = (L +
3
3m) into the bearing stratum (see Fig.(2.15a));

2. Reservoirs: Explore soil to:


(i) The depth of the base of the impermeable stratum, or
(ii) Not less than 2 x maximum hydraulic head expected.

3. Dams: Because the critical factor is the safety against seepage and foundation failure,
boreholes should penetrate not only soft or unstable soils, but also permeable soils to such a
depth that seepage patterns can be predicted. Thus, it is recommended:-
For earth structures, explore soil to 1.5 times the base width of the dam, and
For concrete structures, explore to a depth 1.5 2.0 times the height of the dam, and
for any case, the depth of boring must be checked with (1.5 2.0) of the
water head.

41
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

4. Roads, highways, and air fields: the minimum depth is 5m below the finished road level,
provided that vertical alignment is fixed but should extend below artificial fill. In practice,
some realignment often occurs in cuttings, and side drains may be dug up to 6m deep or to
bore to at least 1.5 times the embankment height in fill areas, and to at least 5m below
finished road level in cut.

5. Retaining walls, slopes stability problems: Explore to:P


1.5B (wall base width) or 1.5H (wall height) whichever is greater below the bottom of
the wall or its supporting piles (see Fig.(2.15b)), Moreover,
It must be below an artificial fills, and deeper than possible surface of sliding;
G.S.

6. Canals, deep cut and fill sections on side hills: Explore at least to:
(i) 3m below the finished level in cut, or
Borehole

(ii) B when B H , or
(iii) H when B H (see Figs.(2.16a and 2.16b)).
Strong layer

7. Embankments: The depth of exploration should be at least equal to the height of the
Weak layer
embankment and should ideally penetrate all soft soils if stability is to be investigated. If
settlements are critical then soil may be significantly stressed to depths below the bottom of
the embankment equal to the embankment width (see Fig.(2.16c)).
(a) Existence of rock layer

B S B

LB
Column
Footing
Plan
P1 P2 P

G.S. S 4B G.S.
Df
Borehole depth Borehole depth

(D f 1.5B) D = 1.5B B (D f 1.5B)

Section

(b) Isolated spread footing (c) Raft or mat foundation.


42

Fig.(2.13): Depth of borings for spread and raft foundations.


Fig.(2.14): Depth of borings for adjacent spread footings.
(b) Multiple rows of adjacent spread footings.
43
B B

S 2B
B ( D f D)
Df S S
G.S.
P3 P2 P1
4B S
B
B B B
S
S

(D f 1.5B)
Df
G.S.
P3 P2 P1
B
S
B L=W
S
B
B S B
B S
W
Chapter 2: Subsoil Exploration Foundation Engineering for Civil Engineers
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration
G.S.

L
Backfill Soil

Fig.(2.15): Depth of borings for piles, and retaining walls.

Base Soil

G.S.

hichever is greater
f B.H. = 1.5B or 1.5H

(b) Retaining walls

44
Depth of borehole = 3m mimm.

Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

Fig.(2.16): Depth of borings for cuts and fills, canals, and embankments.

45
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

2.11 FIELD LOAD TEST


It is a method to investigate the stress-strain (or load settlement) relationship of soils.
Then, the results are used in estimating the bearing capacity. In this test, the load is applied to a
model footing and the amount of load necessary to induce a given amount of settlement is
measured.
Round plates from (150 750)mm in diameter by 150mm increment (i.e., 150, 300,
450, 600, 750)mm are available as well as square plates of (1.0 ft2) area. The minimum thickness
of plate is (1 inch or 25.4mm).

Df B G.S.
P
2.5 B 2.5 B
Round plate square plate

Procedure of load test as given by ASTM D110 72:


(1) Excavate a pit to width at least 6 times as wide as the used plate, and to the depth that the
foundation is to be placed.

46
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

If it is specified that three sizes of plates are to be used for the test, the pit should be large
enough so that, there is an available spacing between tests of 3 times the diameter (D) of the
450mm
D = 750mm
largest plate. This is useful for studying the size effect of footings.
300mm
G.S.
Df 3D 3D 2.5 B

2.5 B

(2) A square loading plate 2.5cm thick and (30 x 30)cm is placed on the surface of the soil at
the bottom of the pit. There should not be any surcharge load placed on the soil within a
distance of (60cm) from around the plate.
(3) A vertical load is placed on the plate in increments and settlements are recorded as an
average from at least three dial gauges accurate to (0.025mm) attracted to an independent
suspension system. Load increment should be approximately 1/10 of the estimated
allowable soil pressure. For each load increment, settlement readings should be taken at
regular intervals of not less than (1 hr.) until there is no further settlement. The same time
duration should be used for all the loading increments.
(4) The test is continued until a settlement of 25mm is observed or until the load increments
reached 1.5 times the estimated allowable soil pressure.
(5) If the load is released, the elastic rebound of the soil should be recorded for periods of time
equal to the same time durations of each applied load increment.
(6) The result of each test can be represented graphically as follows (see Fig.2.17):-
(a) Settlement versus log time curve (for each load increment),
(b) Load-settlement curve (for all increments) from which qult . is obtained.

c
(a) Load - settlement curve

Fig.(2.17): Typical load test results.

47
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

For cohesive soil (bearing capacity is independent of footing size):


qf qp

s s Bf
f p
Bp
................................................................................(2.3)

For cohesionless soil (bearing capacity increases with size of footing):

Bf
qf qp
Bp
2
2B f
s s
f p
Bp Bf
.................................................................(2.4)

Settlement for both cohesive and cohesionless soils:


sf / Bf Bf n
( )
sp / Bp Bp
.....................................................................(2.5)
sf sp Bf Bp
where, and are settlements of footing and plate, and are their respective widths;
Bf
5
Bp Bp
provided that = 1.0 ft for as well as the footing and plate carry the same
intensity of load, and (n) is an exponent that depends on soil type; with some of its values
are:
Type of soil n
Clay 0.03 - 0.50
Sandy clay 0.08 - 0.10
Dense sand 0.40 - 0.50
Medium sand 0.25 - 0.35
Loose sand 0.20 - 0.25

For c soils (bearing capacity from two-plate load tests; after Housel, 1929):

V A.q P.s .................................................................................(2.6)


where,
V = total load on a bearing area,
A = contact area of footing or plate,
q = bearing pressure beneath A,
P = perimeter of footing or plate, and
s = shear perimeter.

48
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

This method needs data from two-plate load tests so that Eq.(2.6) can be solved for q and s
(for given settlement). After the values of q and s are known, the size of a footing required to
carry a given load can be calculated.

2.12 FIELD PENETRATION TESTS


2.12.1 DYNAMIC OR STANDARD PENETRATION TEST (SPT)
This test is preferred for very hard deposits, particularly of cohesionless soils for which
undisturbed samples cannot be easily obtained. It utilizes a split-spoon sampler shown previously
in Fig.(2.8a) that is driven into the soil.
The test consists of driving the standard split-barrel sampler of dimensions (680mm length,
30mm inside diameter and 50mm outside diameter) a distance of 460mm (18'') into the soil at the
bottom of the boring. This was done by using a 63.5kg (140Ib) driving mass (or hammer) falling
"free" from a height of 760mm (30"). Then, counting the number of blows required for driving
the sampler the last 305mm (12") to obtain the (N) number (neglecting the no. of blows for the
upper first 150mm).

Note: The SPT- value is rejected or halted in any one of the following cases:
(a) if 50 blows are required for any 150mm increment, or
(b) if 100 blows are obtained, or
(c) if 10 successive blows produce no advancement.
The number of blows (N) can be correlated with the relative density ( D r ) of cohesionless
soil (sand) and with the consistency of cohesive soil (clay) as shown in Tables (2.9, 2.10 and
2.11).

Table (2.9): Relative density of sands according to results


of standard penetration test.

Relative density
SPT- value e max einsitu
N/30cm Dr x100
e max e min
0-4 0 -15 Very loose 28
4 - 10 15 - 35 Loose 28 - 30
10 - 30 35 - 65 Medium 30 - 36
30 - 50 65 - 85 Dense 36 - 41
> 50 85 - 100 Very dense > 41

Table (2.10): Relation of consistency of clay, SPT N-value, and


q
unconfined compressive strength ( u ).
SPT- value consistency q u (ksf ) q u ( kg / cm 2 )

49
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

N/30cm
Below Very soft 0 - 0.5 0 - 0.25
2-4 Soft 0.5 - 1 0.25 - 0.5
4-8 Medium 1-2 0.5 - 1
8 - 15 Stiff 2-4 1-2
15 - 30 Very stiff 4-8 2-4
> 30 Hard >8 >4

Table (2.11): Empirical values for ,..D r , and of granular soils based
on the SPT at about 6 m depth and normally consolidated.

Description Very loose Loose Medium Dense Very dense


Dr 0 - 0.15 0.15 0.35 0.35 0.65 0.65 - 0.85 > 0.85
Relative density
N70 ------
SPT : Fine 1-2 3-6 7-15 16-30
> 40
Medium 2-3 4-7 8-20 21-40
> 45
Coarse 3-6 5-9 10-25 26-45

: ------
Fine 26-28 28-30 30-34 33-38
< 50
Medium 27-28 30-32 32-36 36-42
------
Coarse 28-30 30-34 33-40 40-50
wet 70-100 90-115 110-130 110-140 130-150
: Pcf
(kN/m3) (11-16) (14-18) (17-20) (17-22) (20-23)

2.12.1.1 Corrections for N value

(1) W.T. Correction (in case of presence of W.T.):

N corr. 15 0.5( N field 15) ....(2.7)


For N > 15:
and
N corr. N field ..............(2.8)
For N 15:

If N-value is measured above water table, no need


for this correction.

(2) Overburden pressure, C N ; Energy ratio, 1 ; Rod length, 2 ; Sampler;


3 ; and Borehole dia., 4 Corrections:

N70 N field .C N ..1..2 ..3..4 ....(2.9)

50
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

where,
N70 corrected (N) using the subscript for the energy ratio E rb and ( ' ) to indicate it
has been adjusted or corrected,
C N = adjustment for overburden pressure for p 25.(kPa ) and can be calculated from
the following formula:

2000
C N 0.77 log
Po .......(2.10)
If p 25.(kPa ) , no need for overburden pressure
correction.

where,
p o overburden pressure in ( kPa ),
i : factors obtained from (Table 2.12) as:
1 hammer correction = (average energy ratio)/(drill rig energy) = E r / E rb ;
2 rod length correction;
3 sampling method correction; and
4 borehole diameter correction.

Table (2.12): Hammer, borehole, sampler, and rod


i correction factors.

Hammer correction 1
Average energy ratio Er
Donut Safety
Country
R-P = Rope -Pulley: 1 r rb
R-P Trip R-P Trip E /E
USA
North America 45 ---- 70-80 80-100
Japan 67 78 ------ -------
UK ---- ---- 50 60
China 50 60 ------ -------

Rod length correction 2

51
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

> 10m 2 = 1.00


6 -10 = 0.95
Length N is too high for L < 10 m
4-6 = 0.85
0-4 = 0.75

3
Sampling method correction

Without liner: 3 = 1.00


With liner: Dense sand, Clay = 0.80 N is too high with liner
Loose sand. = 0.90

Borehole diameter correction 4

60 -120 mm 4 = 1.00
Hole diameter 150 mm = 1.05 N is too small for oversize hole
200 mm = 1.15

Notes:

1. It is evident that all i =1.0 for the case of a small borehole, no sampler liner, length of
drill rod > 10 m and the given drill rig has E r 70 . In this case, the only adjustment is
for overburden pressure (i.e., N corr. N field .C N ).
E r1
N2 ..N1
2. Large values of E r decrease the blow count (N) linearly (i.e.,
E r2 ). This
equation is used to convert any energy ratio to any other base.
30
N corr. 10. 30...blows / 30cm.
N field 10...blows / 10cm , then 10
3. If

2.12.3 STATIC OR CONE PENETRATION TEST (CPT)


This is a simple static test used for soft clays and fine to medium coarse sands. The test is
not applicable in gravels and stiff hard clays. It is performed by pushing the standard cone
(according to ASTM D3441 with a 60o point and base diameter = 35.7mm with cross-section area
of 10 cm2) into the ground at a rate of (10 20) mm/sec. Several cone configurations can be used
such as:
1. Mechanical or the earliest "Dutch Cone Type",
2. Electric friction with strain gauges,
3. Electric piezo for pore water measurement,
4. Electric piezo/friction to measure q c , q s and u or (pwp), and
5. Seismic cone to compute dynamic shear modulus.

52
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

Fig.(2.18b) shows the operations sequence of a mechanical cone as: in position (1) the cone
is seated; position (2) advances the cone tip to measure q c ; position (3) advances the friction
sleeve to measure q s ; and position (4) advances both tip and sleeve to measure q t = q c + q s .
Therefore, at any required depth, the tip and sleeve friction resistances q c and q s are measured
and then used to compute a friction ratio f R as:
q
f R (%) s x100
qc ; f R < 1% for sands; f R > 5 or 6% for clays and peat.
The data collected from the CPT can be correlated to establish the undrained shear strength
S u of cohesive soils, allowable bearing capacity of piles, to classify soils; and to estimate ,..D r
for sands. A typical data set is shown in Fig.(2.19b).

CPT Correlations

q c is related to the undrained shear strength S u of cohesive soils


1. The cone resistance
as:
q po
Su c
N k .(2.11)

where, p o .z = overburden pressure at point where q c is measured., and


N k = cone factor computed from Fig.(2.20).

2. The q c and f R results are used to classify soils from Fig.(2.21) for standard
electronic cone.
q
3. The cone resistance c can be related to the pore pressure as:
q po
Su T
N kT ..(2.12)

where, q T q c u.(1 a ) ,
a = area ratio depends on the cone type,
N 13 (5.5.I p / 50)
u = measured pore water pressure, and kT .
I 30
For normally consolidated clays of low sensitivity (S t 4) and p a value of N k
about 18 and N kT of 14 may be satisfactory (see Figs. (2.18) to (2.25)).

53
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

(c) Typical output.


qf Positions of the Dutch cone during
a pressure record.

Fig.(2.18): Mechanical (or Dutch) cone, operations sequence, and tip resistance data.

(a) Piezocone. (b) Cone Penetration record for clay soil.

Fig.(2.19): Electric cone and CPT data.

54
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

Fig.(2.20): Cone factor N k vs. I P Fig.(2.21): Soil classification chart for


(after Anagnostopoulos etal., 2003 ). standard electric
cone.
(after Anagnostopoulos etal.,
2003 ).

55
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

Dr Dr

(a) Cone bearing vs. relationship.



(b) Correlation between peak friction angle and c
q
for uncemented, quartz sands (after
Robertson and Campanella, 1983).

Fig.(2.24): Correlations between cone data and angle of internal friction ( ).

D q / N ratio.
Fig.(2.25): Relationship between mean grain size ( 50 ) and c

56
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

(after Robertson et al., 1983 and Ismael and Jeragh, 1986)

2.13 VANE SHEAR TEST


It is a field test used to determine the in-situ shearing resistance (undrained shear
2
strength) of soft to medium clay and silt clay having U.C.S.< 1.0 ( kg / cm ), then to be used for
design of foundations and slopes.

Apparatus (see Fig.(2.26):


1. Van shear test equipment;
2. Drilling rig;
3. Casing (as required); and
4. Other necessary tools and supplies such as stop watch, pipe, etc..

57
T

Foundation Engineering for Civil Engineers T Chapter 2: Subsoil Exploration

S
D

Fig.(2.26): Vane shear apparatus.


Procedure:
1. The equipment is installed in place properly either at the ground surface without a hole
(case 1) or at the bottom of a borehole (case 2) and then the vane is pushed into the
soil layer to the required depth; (see Fig.(2.27)).
2. A torque is applied at a uniform rate of 0.1o per sec. or (1o-6o per minute).
S H
3. Readings are taken every minute interval until failure happens.

S D

58
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

Calculation:
(i) Case (1): In this case, the vane is not embedded in soil, so that only
the bottom end takes pant in shearing. If the soil is isotropic and
homogenous, then:
Total shear resistance at failure developed along cylindrical surface = .D.H.S
(b) Total resistance of bottom ends, considering a ring of radius r and thickness dr
D/2
(2.r.dr ).S
= 0
D/2
D
T (.D.H.S) (2.r.dr ).S.r
(c) The torque T at failure will then equal: 2 0

.D 2Su D
T (H )
or 2 6 .....(2.13)

(ii) Case (2): If the top end of the vane is also embedded in soil, so shearing takes place
on top and bottom ends:
.D 2Su D
T (H )
or 2 3 .....(2.14)

59
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

Notes:
S u in (kg/cm2); and H and D in (cm).
Use consistent units, such as: T in (kg-cm);
It is found that the S u values obtained by vane shear test are too large for design.
Therefore, Bjerrum's (1972) proposed a reduction factor using the following formula:
S u , design ..S u , field
.....(2.15)
I
where, is a correction factor depends on plasticity index p and obtained from Fig.(2.28a);
Also, Aas et al. (1986) proposed another charts (see Fig.(2.28b)) taking into account the
effects of aging and OCR (Overconsolidation ratio).

Ip , %

Ip , % Vane strength ratio S u, v / Po


Bjerrum correction factor for vane-shear test. Reinterpretation of the Bjerrum chart of part a by
[(Bjerrum, 1972) and Ladd et al., 1977)]. (Aas et al. (1986) to include effects of aging and OCR ).


SOLVED PROBLEMS

Problem (2.1): A thin-walled tube (OD = 76.2mm, ID = 73mm) was pushed into a soft clay at
the bottom of a borehole a distance of 600mm. When the sampler was recovered a
measurement done inside the tube indicated a recovered sample length of 575mm.
Calculate the recovery and area ratios.

60
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

Solution:
575
Lr 0.958
Recovery ratio: 600
(76.2) 2 (73) 2
Ar x100 8.96%
Area ratio: (73) 2

Problem (2.2): A three story steel frame office building will be built on a site where the soils are
expected to be of average quality and uniformity. The building will have a (30m x 40m)
footprint and is expected to be supported on spread footing foundations located about (1m)
below the ground surface. The site appears to be in its natural condition, with no evidence
of previous grading. Bedrock is several hundred feet below the ground surface. Determine
the required number and depth of the borings.

Solution:
Number of borings:
From Table (2.7), one boring will be needed for every 200 to 400 m2 of footprint area.
Since the total footprint area is 30 x 40 =1200 m2, use (4) four borings.

Depth of borings:
For subsurface condition of average quality, the minimum depth is: 4.
4.5.S0.7 D f 4.5(3) 0.7 1 11m.
However, it would be good to drill at least one of the borings to a slightly greater depth to
check lower strata. In summary, the exploration plan will be 4 borings with, 3 borings to 11
m, and 1 boring to 15 m.

Problem (2.3): Given: Available information about:


Structure: Multistory building with 3 stories and basement
No. of columns = 16, Column load = 1000 kN
Raft dimensions: 16m x 16m x 1m, Foundation at 3m below G.S.
d = 16 kN/m3 , sat = 20 kN/m3 , W.T. at 6m below G.S.
Soil profile:
Required: Number, layout, and depth of B.Hs.?

Solution:

Number and layout of borings:


From Table (2.7), for poor quality and/or erratic subsurface conditions, one boring is
needed for every (100 to 300) m2 of footprint area. Since the total footprint area is 16x16
= 256m2 > 200m2 (average value), use one or two borings.

61
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

Depth of borings:

(a) d 1.5(16 ) 24 m

(b) 10% of contact pressure:


16 .(1000 ) 24 (16 )(16 )(1)
q contact( net) (3)(16 ) 38 .5..kPa
(16 )(16 )
38 .5(16 )(16 )
0.1.(38 .5) ,
(16 d ) 2 . .....d = 34.6 m
(c) 5% of overburden pressure:
38 .5(16 )(16 )
0.05 .[16 (6) (d 3)( 20 10 )] ,
(16 d ) 2 ...d = 15.5 m
From (b and c) take the lower d = 15.5 m
0.7 0.7
(d) d 6.S 6.( 4) 15.83m
From (24m, 15.5m, and 15.83m) take the highest d = 24 m
Use D = 24 + 3 = 27 m from G.S.

Problem (2.4): A wide strip footing applying net pressure of 35 kPa is to be constructed 1.0 m
below the surface of uniform soil having unit weight of 19 kN/m3. The footing is 5.0 m wide
and the water table is at ground surface. Is 12 m depth of boring (measured from ground
surface) sufficient for subsoil exploration program.

Solution:

(a) d 3( B) 3(5) 15 m
(35)(5)(1)
0.1.(35) ,.......................
(b) 10% of contact pressure: ( 5 d )(1 d ) d = 4.3 m
(35)(5)(1)
0.05(9 9d ) ,................
(c) 5% of overburden pressure: (5 d )(1 d ) d = 5.2 m
From (b and c) take the lower d = 4.3 m

From (15 m, and 4.3 m) take the highest d = 15 m, and so the depth from ground

surface D 15 1 16 m, 12 m is not sufficient.

62
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

Problem (2.5): A standard penetration test was performed on dense sand soil. If N field = 20,
p 205...kPa , determine N60 and N70 for
rod length = 12m, hole diameter = 150mm, o
each of the following conditions:
Use safety hammer with E r 80, and no liner.
Use safety hammer with E r 60, and with sample liner.
po 100.kPa , 205 mm hollow stem auger, hole depth = 6m, use safety hammer with
c.
E r 55, and no liner.

Solution:
2000 2000
C N 0.77. log 10 0.77. log 10 0.76
p 205...kPa 25 kPa po (kPa ) 205
(a) Since o
From (Table 2.12):
1 E r / E rb 80 / 70 1.14
2 = 1.00 (for L = 12m (rod length 10m)),
3 = 1.00 (for no liner),
4 = 1.05 (for B.H. diameter = 150mm),

N70 N field ..C N ..1..2 ..3..4 = 20 (0.76)(1.14)(1.00)(1.00)(1.05) = 18

and
70
N60 (18) 21
N60 ..E r 60 N70 .. E r 70 , 60
or

C N 0.76
(b)
From (Table 2.12):
1 E r / E rb 60 / 70 0.86
2 = 1.00 (for L = 12m (rod length) 10m),
3 = 0.80 (dense sand with liner),
4 = 1.05 (for B.H. diameter = 150mm),

N70 N field ..C N ..1..2 ..3..4 = 20 (0.76)(0.86)(1.00)(0.80)(1.05) = 10

and
70
N60 (10) 11
N60 ..E r 60 N70 .. E r 70 , 60
or
2000
C N 0.77. log 10 1.00
po 100...kPa 25 kPa 100
(c) Since

63
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

From (Table 2.12):


1 E r / E rb 55 / 70 0.79
2 = 0.95 (for L 6m (rod length) 10m),
3 = 1.00 (for no liner),
4 = 1.00 (for 205mm hollow stem auger),

N70 N field ..C N ..1..2 ..3..4 = 20 (1.00)(0.79)(0.95)(1.00)(1.00) = 15

and
70
N60 (15) 17
N60 ..E r 60 N70 .. E r 70 , 60
or

Problem (2.6): A standard penetration test SPT has been conducted in a coarse sand to a
depth of 4.8 m below the ground surface. The blow counts obtained in the field were as
follows: 0 6 in: 4 blows; 6 -12 in: 6 blows; 12 -18 in: 8 blows. The test was conducted
using a USA-style donut hammer in a 150mm diameter boring with a standard sampler and
N60 ?
liner. If the vertical effective stress at the test depth was 70 kN/m2, determine

Solution:

The raw SPT value is N = 6 + 8 = 14


2000
C N 0.77. log 10 1.12
p 70...kPa 25 kPa 70
Since o
From (Table 2.12):
1 E r / E rb 45/60 = 0.75
2 = 0.85 (for L 4.8m (rod length) 6m),
G.S. 3 = 0.90 (for loose sand with liner),
4 = 1.05 (for B.H. diameter = 150mm),

2m W.T.
N60 N field ..C N ..1..2 ..3 ..4 = 14(1.12)(0.75)(0.85)(0.90)(1.05) = 10 blows

Fine sand
s(2.7):
Problem atA standard penetration test was carried out in sand at 5m depth below the
3m
ground surface gave (N = 28) as shown in the figure below. Find the corrected N-value?
N field 28..blows / 30cm
Solution:

Water table correction:

N 15 0.5.( N field 15)


For N 15 ...

64
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

N = 15 + 0.5 (28 15) = 21


Overburden correction:

Po = 2(18) + 3(20 9.81) = 66.57 kPa 25 kPa


2000 2000
C N 0.77 log 0.77 log 1.14
Po = 66.57
Ncorr. N..C N = 21(1.14) = 23 blows

Problem (2.8): A standard penetration test was carried out at a depth of (10m) in a saturated
fine sand yielded a blow count of (N = 41). If the saturated unit weight of the sand equals
(19 kN/m3), find the corrected value of (N).

Solution:
Water table correction:

N 15 0.5.( N field 15)


For N 15 .
N = 15 + 0.5 (41 15) = 28 blows

Overburden correction:

Po = 10 (19 9.81) = 91.9 kPa 25 kPa


2000 2000
C N 0.77 log 0 . 77 log 1.03
Po = 91.9
Ncorr. N..C N = 28(1.03) = 28.8, say 28 blows

Problem (2.9): It is proposed to construct a spread wall footing of (3m width) in sand at (1.5m)
below the ground surface to support a load of 12 Ton/m. The SPT results from a soil boring
soil(sat.)
are as shown below. If the water table is located at 0.9m from G.S. and 17.6
kN/m3, determine the average corrected N-value required for design?

SPT sample depth


1.5 2.25 3.0 3.75 4.5 5.25 6
(m)
N field 31 25 22 20 28 33 31

Solution:
P N
Find o at each depth and correct field values up to at least a depth B below the base of
foundation according to the magnitude of overburden pressure in comparison with 25 kPa.

65
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

2000
C N 0.77 log
Overburden pressure correction: Po
For 1.5m depth:
Po = 0.9(17.6) + (0.6)(17.6 9.81) = 20.5 kPa 25 kPa, therefore, C N =1.00
For 4.5m depth:
Po = 0.9(17.6) + (3.6)(17.6 9.81) = 43.9 kPa 25 kPa, therefore, C N =1.28

Find the average corrected N-value as a cumulative average down to the depth indicated,
and then, choose the N-value for design as the lowest average N-value.
SPT
sample Po CN N avg
.
N field N C N .N field N 15 0.5( N 15)
depth (kN/m ) 2

(m)
1.5 31 20.5 1.00 31 23 23
2.25 25 26.3 1.45 36 25 24
3.0 22 32.2 1.38 30 22 23
3.75 20 38.0 1.32 26 20 22
4.5 28 43.9 1.28 35 25 23

Navg.
For 1.5m depth: 23
23 25
N avg .
For 2.25m depth: 2 24
23 25 22
N avg .
For 3.0m depth: 3 23
23 25 22 20
N avg .
For 3.75m depth: 4 22
23 25 22 20 25
N avg .
For 4.5m depth: 5 23

N avg. (lowest )
N-value for design = 22 blows

q c 300.(kg / cm 2 )
Problem (2.10): Given: at depth z = 8m in sand with 11.15 (kN/ m3).
Required: estimate angle of internal friction ( ).

Solution:

po 8(11.15) 89.2...kPa

66
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

q 300(100)
c 336
q c Vb .po , Vb (bearing capacity factor) po 89.2
q c 300.(kg / cm 2 ) p o 89.2.kPa
1. Using Fig.(2.22) with and , the intersection is
above D r 100% ; with D r 100% and using Fig.(2.23) obtain = 42 to 46, say =
44o,

Vb =336 project to curves and down to obtain: = 34.5 to 39.5 ,


2. From Fig.(2.24a) at
say =37o,
300.(98.07)
29.4.MPa
, obtain = 46o.
q 1000
3. From Fig.(2.24b) and c =
(37 44 46)
42
A better estimate might be obtained by taking an average value: 3 o

but this value is still, high, because it is recommended to use not over (40o).

Problem (2.11): Classify the soil of Fig.(2.19b) at (10-12)m depth. Also, estimate the
3
undrained shear strength u if the average =19.65 kN / m for the entire depth of CPT. It
S
is known that the profile is entirely in cohesive soil.

Solution:

q c = 11 MPa and f R =4%


From Fig.(2.19b), at average depth of 11.0m:
p o =19.65(11) = 216 kPa, from Fig.(2.19) estimate N k 18 .

q c = 11000 kPa and f R = 4%, the soil is stiff, sandy silt and (the
Using Fig.(2.21), with
11000 216
Ip S
expected = 10 or less), u = 18 600 kPa.

Problem (2.12): Load-settlement data obtained from load test of square plate of size (1.0 ft)
are as shown below. If a square footing of size (7.0 ft) settles (0.75 inch), what is the
allowable soil pressure of the footing? Consider sandy soil.

Load (Tsf) 2 5 8 10 14 16 19
Settlement (inch) 0.1 0.2 0.3 0.4 0.6 0.8 1.0

Solution:

67
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

Bf
qf qp
Bp 0.75 0.75
2 sp 0.25
2
s s 2B f 2x7 3.05
f p 1 7
For cohesionless soil: B p Bf ,

s 0.25 Pressure (Tsf)


Now by drawing the given data and for p ,
q p 6 .5 sp 0.25 q p 6.5
T/ft2, and

Settlement (inch)
B 7
q f q p f 6.5
Bp 1
45.5 T/ft2 .

Problem (2.13): Use Housels method to determine the size of square footing required to carry
a column load P = 45 tons if the two plate loading tests results are as given below:-
plate size (1) = 35 x 35 cms, corresponding load = 5.6 tons; relative to 1.0
cm settlement.
plate size (2) = 50 x 50 cms, corresponding load = 10 tons; relative to 1.0
cm settlement.

Solution:
From Housel's method (Eq. 2.6): V A. q + P. s
5.6 0.123 q + 1.4 s
10 0.25 q + 2 s
Solving the two equations, gives: q = 26.9 and s = 1.63.
Again from Eq.(2.6) shown above, the footing area required to carry 45 tons load is
calculated as:
45 = B2 q + 4B s
45 = B2 (26.9) + 4B (1.63)
26.9 B2 + 6.52 B 45 = 0
B2 + 0.24 B 1.67 = 0

0.24 (0.24) 2 4(1)(1)(1.67) 0.24 2.59


B 1.18
( 2)(1) 2 m
Take the footing size as 1.20 m x 1.20 m.

68
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

Problem (2.14): A vane tester with a diameter d = 9.1cms and a height h = 18.2 cms requires
a torque of 110 N-m to shear a clay soil sample, with a plasticity index of 48%. Find the soil

Su ?
un-drained cohesion
Solution:
For CASE (2) with top and bottom vane ends embedded in soil, the torque is given by:
.D2 .Su ,field D
T (H )
2 3
T 0.110
S u , field 40
.D 2 D .(0.091) 2 0.091
(H ) 0.182 3
or 2 3 2 kN/m2
From Fig.(2.28a) for a plasticity index of 48%, Bjerrum's correction factor = 0.80, and

Su ,design ..Su ,field 0.8(40)


Therefore, 32 kPa

PROBLEMS

P2.1 Name several sources for information and preliminary evaluation of a building site.

P2.2 Explain briefly the difference between preliminary exploration and detailed exploration.

P2.3 Give useful information obtained from a typical subsurface investigation.

P2.4 Give factors that are relevant to planning for a well-balanced exploration program.

P2.5 How does someone select the depth of boring, boring layout, and type of samples?

P2.6 What is a test pit? Give few negative and positive aspects of it.

P2.7 What is a test boring? How does it differ from a test pit?.

P2.8 What are disturbed and undisturbed soil samples? How do you obtain each of them?.

P2.9 Describe Shelby-tube sampler features. How does it differ from split-spoon sampler?

P2.10 What is a core sample? How is it obtained? What sort of information can be obtained after
evaluation.

P2.11 What is a vane shear test? Describe the apparatus.

P2.12 What are boring logs? Define them.

P2.13 Can a split-spoon sampler penetrate a typical rock formation? Can a fight auger penetrate a
rock formation? Explain briefly.

69
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

P2.14 Shelby tubes are usually pushed into a strata. However, some practitioners regard driving the
tube an acceptable approach. How might the disturbance be affected by the two methods for
each type listed below? (a) Very soft clay, and (b) Hard clay.

P2.15 a- List general rules of estimating the number and depth of soil investigation boreholes.
b- What are the different types of samplers you may use to obtain undisturbed samples
of cohesive soil?
P2.16 a- The load-settlement data obtained from load test of a square plate of size (1ft X1ft) are
as shown below. If a square footing of size (7ft X 7ft) settles 0.75 inch, what is the
allowable soil pressure (consider the soil is a cohesionless soil)?

Load (Tsf) 2 5 8 10 14 16 19
Settlement (inch) 0.1 0.2 0.3 0.4 0.6 0.8 1.0
b- Compute the area ratio (Ar) of the standard split spoon dimensions (OD = 51 mm and
ID = 38mm). Then, what ID would be required to give Ar = 10%?
P2.17 For cone penetration records shown in the table below, plot the CPT data including f R

and then estimate Su and at a depth of 5.6m if I P = 30. Take av = 16.5 kN/m3 up to
ground water table (GWT) at depth of 3m and = 19.81 kN/m3 for soil below the GWT.

Depth (m) qs (kPa) q c (MPa) Soil Classification


0.50 22.02 1.86 sandy silt
1.50 27.77 1.83 silt and clayey silt
1.60 28.72 1.16 silty clay
2.10 32.55 1.15 silty clay
2.50 24.89 2.28 silty sand
3.10 22.02 0.71 silty clay
3.50 12.44 0.29 Clay
4.10 15.32 0.38 Clay
4.50 21.06 1.09 silty clay
5.60 28.72 1.57 silt and clayey silt

P2.18 For the cone penetration records of clay soil shown in the figure below, if LL = 45 and PL

= 20% estimate Su and at the 7 8 m depth. Assume avg. = 16.5 kN/m3 for soil
Sleeve friction qs Point 3resistance qc Friction ratio fR
above the GWT and kPa = 19.81 kN/m below kPa it. %
Depth z , meters
Depth z , meters

70
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

q
P2.19 In the soil profile shown in the figure below, if the cone penetration resistance ( c ) at
point (x) as determined by an electric friction cone penetrometer is 0.80 MN/m2 find:
(a) the over-consolidation ratio, OCR ,
G.S.
Cu .
(b) the un-drained cohesion
Clay
W.T. 2m 1.01
q c o C
OCR 0.37 OCR . u.field
o o where, 22 .( PI)
0.48
Use: ; and
x 4m s at
o , o are total and effective vertical stresses in (MN/m2).
and

71
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

S S
P2.20 For a vane shear data shown in the figure below, estimate u ,.v and u ,.remolded if 100
I P
diameter vane is used with H/ D =2 (rectangular). Also estimate if p = 40 and o
mm200
T for Su,v

=125 kPa.

Tremolded
16.7

0-

8
P2.21 Vane shear tests were conducted in a layer of clay. The vane dimensions were 63.5 mm
(D) x 127mm (H). At certain depth, the torque required to cause failure was 0.051 N-m.
1.5m
The liquid limit of the clay was 46 and the plastic limit was 21. Estimate the undrained
cohesion of the clay to be used in design by applying Bjerrum's relationship:

1.7 0.54 log 10 (PI(%)) .


P2.22 Given: A two-thin walled sample tubes of dimensions are as follows:
Sand

OD ID Length
(inch) (inch) (inch)
3.0 2.875 24
3.5 3.375 24

Required: What is the area ratio of each of these two sample tubes? and what kind of
sample disturbance is obtained?

P2.23 For the soil profile shown in the figure below, along with the standard penetration numbers
C u ..and ..OCR with depth.
in the clay layer, determine the variation of
0.689
N
OCR 0.193 60
Cu.(kN/m 2 ) 29 N 060.72 o
Use: ; and

where, o = effective vertical stresses in (MN/m2).

72
9.0m
7.5m
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration
14
13

6.0m
Sand
4.5m

P2.24 For the soil profile shown in the figure below, along with the standard penetration numbers
in sand layers, calculate the corrected N-values and then estimate an average peak soil
2
friction angle using: 1. .(deg .) 27 .1 0.3.N 60 0.00054 .( N 60 )

.(deg .) tan 1 ( N 60 / 12 .2 20 .3( o )) 0.34
2. 100

8
9
P2.25 For the log of boring shown the in figure below, make reasonable estimates of the relative
6

density D r ..and .. for the sand both above and below the GWT. Assume that E r 60 for
8

the N-values shown, the unit weight of sand increases linearly from (15 to 18.1) kN/m3
N 60
close to the ground surface up to water table level and sat 19.75 kN/m3 below GWT.
Also, estimate the N-value you would use for a square footing of (2m x 2m) located at
19.75
Nvalues
-2m depth? sat
0.0
- 0.3 Top soil
-6
3.0m
q u 50.kPa
q u 60.kPa -10

- 4.0 -8 W.T.
Depth (m)

-7

- 6.0 -9

-11

- 8.0 -15

73
-14
clay
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

REFERENCES
Aas, G., et al., (1986),Use of in situ tests for foundation design on clay, 14 th. PSC, ASCE, pp.
1-30.
Allen, D.V., (1993),Low-cost hand drilling, Consallen Group Sales Ltd.,
Loughton.
Anagnostopoulos, A., Koukis, G., Sabatakakis, N., and Tsiambaos, G.
(2003),Empirical correlations of soil parameters based on cone
penetration tests (CPT) for Greek soils, Geotechnical and Geological
Engineering, Vol. 21, No. 4, 377387.
Bjerrum, L. (1972),Embankments on soft ground, In Proc. ASCE Spec. Conf.
Performance Earth Earth-Supported Structures, Purdue University, 2:1
54, Geotechnical Journal, 20(4): 718-745.
Budhu, M. (2007),Soil mechanics and foundations, 2 nd. edition, Wiley,
section 2.6, Soils exploration Program, Pgs.21.
Das, Braja M. (2007), Principles of foundation engineering, 6th Edition,
Nelson a division of Thomson Canada Limited.
Housel, W.S. (1929),Discussion of: The science of foundations, Trans.
ASCE, Vol. 93, pp.322-330.

74
Foundation Engineering for Civil Engineers Chapter 2: Subsoil Exploration

Hvorslev, M.J. (1949),Subsurface exploration and sampling of soils for civil


engineering purposes, US Waterways Experimental Station, Vicksburg,
Mississippi.
IDEA Drilling,(1997),Bedrock core drilling: Mineral exploration, In
Minnesota, http:// Idea drilling.com/ 1997 9th Avenue North Virginia.
Ismael, N.F. and Jeragh, A.M. (1986).Static cone tests and settlement of calcareous desert
sands, CGJ, Vol. 23, No. 3, Aug.,pp. 297-303.
Ismael, Nabil F. and Vesic, Aleksandar S. (1981), "Compressibility and bearing capacity," ASCE
Journal of the Geotechnical Engineering Division. Vol. 107. No. GTI2, pp. 1677-1691.
Ladd, C.C., Foote, R., Ishihara, K., Schlosser, F. and Poulos, H.G. (1977), "Stress deformation
and strength characteristics, State-of-the-art report, Proceedings. Ninth International
Conference on Soil Mechanics and Foundation Engineering. Vol. 2, p. 421-494, Tokyo.
MDT Geotechnical Manual, (2008),Subsurface Investigations / Field Tests, Section 8.2.4,
Pgs.12-14.
Moore, R. (1980), Reasoning about knowledge and action, PhD. Dissertation, Cambridge MA,
MIT, Published as TN-191, SRT International, Menlo Park, CA.
Road Research Laboratory (1952),Soil mechanics for road engineers, Department of scientific
and industrial research, HMSO, London.
Robertson, P.K. and Campanella, R.E. (1983),Interpretation of cone
penetration tests, Part I: sand, CGJ, Vol.20, No.4, Nov., pp. 718-733.
Robertson, P.K., Campanella, R.G. and Wightman, A. (1983),SPT-CPT
correlation, JGED, ASCE, Vol. 109, No. 1, pp. 1449-1459.
Schmertmann, J.H. (1978),Guidelines for cone penetration test: performance
and design, FHWA-TS-78-209(report), U. S. Dept. of Transportation, 145
pp.
Sowers, G.F. (1979), Introductory soil mechanics and foundations: Geotechnical engineering,
4th ed., MacMillan Publishing Co., New York, NY, p. 621.
Terzaghi, K. (1943), Theoretical soil mechanics, John Wiley & Sons, New
York.
Terzaghi, K., Peck, R. and Mesri, G. (1996),Soil mechanics in engineering practice, John
Wiley-Interscience Publication, John Wiley & Sons, New York.

75

Вам также может понравиться