PROYECTO : : REHABILITACION Y MEJORAMIENTO DE SISTEMA DE AGUA POTABLE, REDES DE DESAGUE Y PLANTA DE TRATAMIENTO DE LA LOCALIDAD DE PHARA, DISTRITO DE PHARA PROVINCIA SANDIA
PRESUPUESTADO
ITEM MATERIALES PRIMER MES SEGUNDO MES TERCER MES CUARTO MES QUINTO MES SEXTO MES
UND. COSTO S/.
TRANSPORTE DE MATERIALES PARA REDES DE DESAGUE S/. 36,127.65 9,031.91 9,031.91 9,031.91 9,031.91
TRANSPORTE DE MATERIALES PARA LAGUNA OXIDACION S/. 20,716.29 7,043.54 6,836.38 6,836.38
COSTO DIRECTO 1,964,538.57 248,999.02 383,117.91 478,752.91 410,936.63 262,889.92 179,842.18
GASTOS GENERALES (8%) S/. 157,163.09 21,130.17 22,000.00 22,000.00 30,380.00 30,380.00 31,272.92
GASTOS DE SUPERVISION DE OBRA (2.5%) S/. 49,113.46 8,000.00 8,000.00 8,000.00 8,513.46 8,500.00 8,100.00
PRESUPUESTO TOTAL S/. 2,170,815.12 278,129.19 413,117.91 508,752.91 449,830.09 301,769.92 219,215.10
PRESUPUESTO ACUMULADO S/. 2,170,815.12 278,129.19 691,247.10 1,200,000.00 1,649,830.10 1,951,600.02 2,170,815.13
PORCENTAJE ACUMULADO % 12.81% 31.84% 55.28% 76.00% 89.90% 100.00%
1,200,000.00 970,815.13
ASIGNACIONES PRESUPUESTALES S/. PRIMERA ASIGNACION PRESUPUESTAL SEGUNDA ASIGNACION PRESUPUESTAL
CRONOGRAMA DE ADQUISICION DE MANO DE OBRA DETALLADO
PROYECTO : : REHABILITACION Y MEJORAMIENTO DE SISTEMA DE AGUA POTABLE, REDES DE DESAGUE Y PLANTA DE TRATAMIENTO DE LA LOCALIDAD DE PHARA, DISTRITO DE PHARA PROVINCIA SANDIA
OBRA : : SISTEMA DE AGUA POTABLE
PARTIDA : : MANO DE OBRA
PRESUPUESTADO PRIMER MES SEGUNDO MES TERCER MES CUARTO MES QUINTO MES SEXTO MES
ITEM MATERIALES CANTIDAD COSTO COSTO CANTIDAD COSTO CANTIDAD COSTO CANTIDAD COSTO CANTIDAD COSTO CANTIDAD COSTO CANTIDAD COSTO
UND. TOTAL UNITARIO PARCIAL INSUMOS S/. INSUMOS S/. INSUMOS S/. INSUMOS S/. INSUMOS S/. INSUMOS S/.
1 OPERADOR DE EQUIPO LIVIANO HH 778.09 7.94 6,178.03 36.00 285.84 200.00 1,588.00 240.00 1,905.60 160.00 1,270.40 102.00 809.88 40.09 318.31
2 TOPOGRAFO HH 278.22 9.64 2,682.02 190.00 1,831.60 88.22 850.44 - - - -
3 CAPATAZ HH 46.74 8.73 408.04 46.74 408.04 - - - - -
4 OPERARIO HH 5,912.41 7.94 46,944.54 355.00 2,818.70 769.00 6,105.86 1,359.00 10,790.46 1,419.00 11,266.86 1,300.00 10,322.00 710.41 5,640.66
5 OFICIAL HH 1,881.07 6.41 12,057.66 113.00 724.33 245.00 1,570.45 432.00 2,769.12 451.00 2,890.91 414.00 2,653.74 226.07 1,449.11
6 PEON HH 40,460.87 5.29 214,038.00 ### 12,844.12 5,260.00 27,825.40 9,306.00 49,228.74 9,711.00 51,371.19 8,902.00 47,091.58 4,853.87 25,676.97
PROYECTO : : REHABILITACION Y MEJORAMIENTO DE SISTEMA DE AGUA POTABLE, REDES DE DESAGUE Y PLANTA DE TRATAMIENTO DE LA LOCALIDAD DE PHARA, DISTRITO DE PHARA PROVINCIA SAN
OBRA : REDES DE DESAGUE
PARTIDA : : MANO DE OBRA
PRESUPUESTADO PRIMER MES SEGUNDO MES TERCER MES CUARTO MES QUINTO MES SEXTO MES
CANTIDA CANTIDA
ITEM MATERIALES CANTIDAD COSTO COSTO CANTIDAD COSTO CANTIDAD COSTO CANTIDAD COSTO COSTO CANTIDAD COSTO COSTO
D D
UND.
TOTAL UNITARIO PARCIAL INSUMOS S/. INSUMOS S/. INSUMOS S/. INSUMOS S/. INSUMOS S/. INSUMOS S/.
1 DIBUJANTE HH 19.83 9.00 178.47 8.00 72.00 8.00 72.00 3.83 34.47 - - -
2 OPERADOR DE EQUIPO PESADO Y LIVIANO HH 694.68 7.94 5,515.76 200.00 1,588.00 200.00 1,588.00 200.00 1,588.00 94.68 751.76 - -
3 TOPOGRAFO HH 622.20 9.64 5,997.98 5.08 48.97 217.12 2,093.04 200.00 1,928.00 200.00 1,927.97 - -
4 OPERARIO HH 2,482.49 7.94 19,710.97 894.00 7,098.36 695.00 5,518.30 546.00 4,335.24 347.49 2,759.07 - -
5 OFICIAL HH 667.58 6.41 4,279.19 240.00 1,538.40 186.00 1,192.26 145.00 929.45 96.58 619.08 - -
6 PEON HH 36,369.79 5.29 192,396.19 13,093.00 69,261.97 10,180.00 53,852.20 8,001.00 42,325.29 ### 26,956.73 - -
PROYECTO : : REHABILITACION Y MEJORAMIENTO DE AGUA POTABLE, REDES DE DESAGUE Y PLANTA DE TRATAMIENTO DE LA LOCALIDAD DE PHARA
OBRA : : LAGUNA DE OXIDACION
PARTIDA : : MANO DE OBRA
PRESUPUESTADO PRIMER MES SEGUNDO MES TERCER MES CUARTO MES QUINTO MES SEXTO MES
ITE
MATERIALES CANTIDAD COSTO COSTO CANTIDAD COSTO CANTIDAD COSTO CANTIDAD COSTO CANTIDAD COSTO CANTIDAD COSTO CANTIDAD COSTO
M UND.
TOTAL UNITARIO PARCIAL INSUMOS S/. INSUMOS S/. INSUMOS S/. INSUMOS S/. INSUMOS S/. INSUMOS S/.
1 DIBUJANTE HH 56.95 9.00 512.55 8.00 72.00 - - - 24.00 216.00 24.95 224.55
2 OPERADOR DE EQUIPO LIVIANO HH 10.69 7.94 84.88 - - - - 10.69 84.88 -
3 OPERADOR DE EQUIPO PESADO HH 5.08 7.94 40.34 5.08 40.34 - - - - -
4 TOPOGRAFO HH 125.29 9.64 1,207.81 40.00 385.60 40.00 385.60 32.00 308.48 - - 13.29 128.12
5 OPERARIO HH 2,326.92 7.94 18,475.74 40.00 317.60 40.00 317.60 40.00 317.60 344.00 2,731.36 932.00 7,400.08 930.92 7,391.50
6 OFICIAL HH 2,233.26 6.41 14,315.20 80.00 512.80 80.00 512.80 80.00 512.80 204.00 1,307.64 895.00 5,736.95 894.26 5,732.21
7 PEON HH 13,977.26 5.29 73,939.71 420.00 2,221.80 420.00 2,221.80 420.00 2,221.80 1,532.00 8,104.28 5,593.00 29,586.97 5,592.26 29,583.06
PROYECTO : : REHABILITACION Y MEJORAMIENTO DE SISTEMA DE AGUA POTABLE, REDES DE DESAGUE Y PLANTA DE TRATAMIENTO DE LA LOCALIDAD DE PHARA
PRESUPUESTADO
ITEM MATERIALES PRIMER MES SEGUNDO MES TERCER MES CUARTO MES QUINTO MES SEXTO MES
UND. COSTO S/.
1 MATERIALES S/. 879,950.09 108,710.47 175,579.25 207,076.52 209,412.06 137,261.55 41,910.35
REHABILITACION DE SISTEMA DE AGUA POTABLE S/. 406,490.70 22,680.44 72,017.25 94,253.80 102,890.40 97,507.07 17,141.74
MEJORAMIENTO REDES DE DESAGUE S/. 336,886.97 84,025.07 100,300.91 84,272.86 68,288.12 - -
PLANTA DE TRATAMIENTO CON LAGUNA DE OXIDACION S/. 136,572.43 2,004.97 3,261.09 28,549.85 38,233.53 39,754.49 24,768.61
2 MANO DE OBRA S/. 618,963.06 102,070.47 105,693.75 119,195.05 111,957.25 103,902.08 76,144.48
REHABILITACION DE SISTEMA DE AGUA POTABLE S/. 282,308.29 18,912.63 37,940.15 64,693.92 66,799.36 60,877.20 33,085.05
MEJORAMIENTO REDES DE DESAGUE S/. 228,078.56 79,607.70 64,315.80 51,140.45 33,014.61 -
PLANTA DE TRATAMIENTO CON LAGUNA DE OXIDACION S/. 108,576.22 3,550.14 3,437.80 3,360.68 12,143.28 43,024.88 43,059.43
3 EQUIPOS Y MAQUINARIAS S/. 372,847.00 50,549.05 94,937.03 96,055.30 114,304.81 7,692.47 9,308.36
REHABILITACION DE SISTEMA DE AGUA POTABLE S/. 35,851.95 5,745.67 8,954.67 6,803.89 6,715.96 5,768.57 1,863.19
MEJORAMIENTO REDES DE DESAGUE S/. 49,536.71 18,071.04 13,638.09 11,078.44 6,749.17 - -
PLANTA DE TRATAMIENTO CON LAGUNA DE OXIDACION S/. 287,458.35 26,732.34 72,344.27 78,172.97 100,839.69 1,923.90 7,445.17
4 TRANSPORTE DE MATERIALES S/. 92,778.41 14,422.08 16,218.81 20,362.06 22,433.69 11,605.06 7,736.71
REHABILITACION DE SISTEMA DE AGUA POTABLE S/. 35,934.47 5,390.17 7,186.89 7,186.89 7,186.89 5,390.17 3,593.45
MEJORAMIENTO REDES DE DESAGUE S/. 36,127.65 9,031.91 9,031.91 9,031.91 9,031.91 - -
PLANTA DE TRATAMIENTO CON LAGUNA DE OXIDACION S/. 20,716.29 - - 4,143.26 6,214.89 6,214.89 4,143.26
COSTO DIRECTO 1,964,538.57 275,752.07 392,428.83 442,688.93 458,107.81 260,461.16 135,099.90
GASTOS GENERALES (8%) S/. 157,163.09 21,130.17 22,000.00 22,000.00 30,380.00 30,380.00 31,272.92
GASTOS DE SUPERVISION DE OBRA (2.5%) S/. 49,113.46 8,000.00 8,000.00 8,000.00 8,513.46 8,500.00 8,100.00
PRESUPUESTO TOTAL S/. 2,170,815.12 304,882.24 422,428.83 472,688.93 497,001.27 299,341.16 174,472.82
PRESUPUESTO ACUMULADO S/. 2,170,815.12 304,882.24 727,311.07 1,200,000.00 1,697,001.27 1,996,342.43 2,170,815.13
PORCENTAJE ACUMULADO % 14.04% 33.50% 55.28% 78.17% 91.96% 100.00%
1,200,000.00 970,815.12
ASIGNACIONES PRESUPUESTALES S/. PRIMERA ASIGNACION PRESUPUESTAL SEGUNDA ASIGNACION PRESUPUESTAL