TABLE OF CONTENTS
1 GENERAL.....................................................................................1
1.1 POLICY..........................................................................................1
1.2 OBJECTIVE.....................................................................................1
1.3 INTERFACE WITH QUALITY MANUAL..................................................1
1.4 INSPECTION..................................................................................2
1.5 QUALITY PROCEDURE......................................................................2
1.5.1 INSPECTION NOTIFICATION.............................................................2
1.5.2 VALIDATION OF THE NOTICE............................................................2
2 ORGANIZATIONAL CHART...........................................................2
3 DEFINITION OF DUTIES..............................................................3
4.1 GENERAL.......................................................................................8
4.2 DRAWING CONTROL PROGRAM........................................................8
4.3 PREPARATION OF AS-BUILT DRAWING..............................................8
4.4 REQUEST FOR DESIGN CHANGE.......................................................8
4.5 ESTIMATION OF SCOPE CHANGE......................................................9
5 DESIGN CONTROL AND DEVELOPMENT........................................9
6 PROCESS CONTROL.....................................................................9
7.1 REFERENCES................................................................................12
7.2 RESPONSIBILITIES.......................................................................12
7.3 MINIMUM TEST AND/OR INSPECTION REQUIREMENTS CIVIL WORKS
..................................................................................................13
7.4 MINIMUM TEST AND/OR INSPECTION REQUIREMENTS ELECTRO-
MECHANICAL WORKS....................................................................16
8 MATERIAL CONTROL STORAGE..................................................20
8.1 GENERAL.....................................................................................20
8.2 RECEIVING..................................................................................20
8.3 WAREHOUSING............................................................................20
8.4 STOCK CONTROL..........................................................................21
8.5 ISSUING OF MATERIALS................................................................22
8.6 DOCUMENTATION.........................................................................22
9 QUALITY RECORDS....................................................................22
12.1 PURPOSE.....................................................................................27
12.2 SCOPE.........................................................................................27
12.3 RESPONSIBILITY...........................................................................27
12.4 AUDIT.........................................................................................27
13 INSPECTION CHECKLIST & LABORATORY FORMS......................30
DESIGN & CONSTRUCTION OF
PUTATAN WATER TREATMENT PLANT 2
1 GENERAL
1.1 Policy
It is the policy of the Consortium that its project when completed, shall
comply with the contract specifications, standards, drawings applicable
local regulation and acceptable construction practices.
1.2 Objective
1.4 Inspection
Consultants engineers will check the work and if satisfied then only
the inspection request form will be signed. Consortium is required
to give consultants 24 hours to enable to carry out an inspection.
2 ORGANIZATIONAL CHART
Please see enclosed QA/QC Organizational Chart.
The organizational chart will be revised and resubmitted in case of
any change of key personnel.
3 DEFINITION OF DUTIES
Major Duties
A. The day to day preparation for issue of all new or revised
procedures, work instructions and forms.
B. Ensuring all information is available for management review
meetings, and meeting reports and minutes are distributed to
relevant persons
C. Ensure that all procedures are followed by all workers,
Responsible for the successful delivery of a Project within time,
cost, safety, quality and environmental constraints
D. Provide hands-on, day-to-day Project management during the
execution phase of Projects
E. Establish Project monitoring budget (from Tender Budget),
Establishment of PMT to ensure appropriate management of
design, construction, commercial, financial, administration,
safety, quality, environment and communications
F. Establish site operational (design & construction), commercial,
financial, administration, safety, quality, environmental and
communication procedures
G. Ensure appropriate reporting both internally to the
Management Board and contractually to the Client
DESIGN & CONSTRUCTION OF
PUTATAN WATER TREATMENT PLANT 2
Major Duties
A. Job instruction and observance of QA/QC plan.
B. Training/testing of laborers.
C. Maintain all required reports.
D. Conduct activities relating to the quality assurance and
quality control of the work at the jobsite and laboratory.
E. Equipment maintenance.
F. Control of the construction materials.
G. Verify all completed work against drawing standard and
specification.
DESIGN & CONSTRUCTION OF
PUTATAN WATER TREATMENT PLANT 2
3.7 Organization
When the remedial work has been completed, the quality control
reports will be delivered to QA/QC Manager and Engineer. These
steps shall be repeated, until the work is determined to be acceptable
by the QC specialists.
4 DOCUMENT CONTROL
4.1 General
Engineering management to be executed by consulting engineers
and the consortium will assist to consultants for this project.
If there will be any field changes, the project field engineer shall
review the drawing scheduling engineer shall keep all the records
DESIGN & CONSTRUCTION OF
PUTATAN WATER TREATMENT PLANT 2
In the event of scope change, cost engineer shall estimate the work
involved with field engineers, the results of which shall be submitted
to the project manager, the scope change work shall be processed in
accordance with contract document, change of work.
Process
Mechanical
Electrical and Instrumentation
Civil Works including Structural and Architectural Design
6 PROCESS CONTROL
Type
Description
Serial Number
Latest calibration (including certificate)
Next calibration date
Type of monitoring/measurements to be performed
Monitoring and measuring equipment will bear a tag, sticker or other
identification indicating calibration and/or verification status. Where
this is not practical, the calibration or verification status will be
traceable through the records maintained in the Asset Register.
7.1 References
7.2 Responsibilities
7.3.3 Concrete
Ready Mix Concrete
For Fresh Concrete
Slump Test ASTM C143
Water
Tests: One (1) Certificate from Project Engineer or one (1) Chemical
Analysis, if source is questionable
Admixtures
Tests: One (1) Certificate from Project Engineer or Mill Certificate per
shipment
7.3.10Welded Connections
Dye Penetrant Test, a non-destructive type of test (NDT) shall
be conducted by an accredited testing company to check 5% of
total welded connections of structural steel members in the
building
7.3.11Fence
b. Wet test - carried out by introducing fluid into the system, to check
if it can run normally (e.g without leakage, excessive noise and
vibration, etc).
Equipment vendor, who will provide the Work Method Statement, and
the Client will be involved in this activity.
Socket Outlets:
All outlets located outside the plant should be verified to be
IP56 rated and with the following specifications:
o Single phase, 230V, with 2 flat pin + E
All breakers should be verified to be of the RCD type.
7.4.6.7 Transformer
Tests: Ratio tests at the rated voltage connection and all tap
connection.
Polarity and phase relation tests on the rated voltage
connection.
Applied potential tests.
Induced potential tests.
Non-load and excitation current at rated voltage on the
rated voltage connection
Resistance measurements of all windings on the rated
voltage connections
DESIGN & CONSTRUCTION OF
PUTATAN WATER TREATMENT PLANT 2
QA/QC Engineers will run the whole process line with water loaded
then adjust parameters accordingly by aiming at the optimum
performance of the system. Water quality will be measured regularly
and results will be utilized to direct parameter adjustments.
Please refer to the approved HAZOP and HAZCON for further details
on the related general safety provisions.
8.1 General
The responsibility at the construction site for all material handling
and operation lies with the material controller reporting to project
manager, who with his staff controls records, receiving,
warehousing and issuing of materials. Consortium will assign well
experienced competent personnel to ensure the implementation of
these procedures and the system to this project.
8.2 Receiving
8.3 Warehousing
All storage areas are safe, secure, and tidy secure areas, with
access limited to authorized personnel.
Where the material has a shelf life, the storekeeper will ensure
that an adequate and effective rotation of stock occurs by
recording dates which will be reviewed prior to issuance.
DESIGN & CONSTRUCTION OF
PUTATAN WATER TREATMENT PLANT 2
8.6 Documentation
Copies of forms listed below basically used in the material control
program:
A. Material Receiving Report
DESIGN & CONSTRUCTION OF
PUTATAN WATER TREATMENT PLANT 2
9 QUALITY RECORDS
All information formats generated internally, sent externally or
received will be documented. This documentation may be in paper
format, electronic format, records of telephone or personal meetings
or observation notes. Control of this documentation will be extended
to all periods of the Project and functions (e.g. environmental, quality,
safety and health).
The Client will have access to obtain primary records and information
at any time through request according to agreed communication
protocols. At completion of the Project, the Consortium may provide
the client with any primary records required, either soft or hard
copies.
The Project will maintain a lot register and the status will be
progressively updated as work on the lot moves forward.
The document controller will ensure that the most recent drawings,
specifications and schedules are in use and registered as Issued for
Construction or For Reference as appropriate.
To ensure that all quality issues are reported, resolved and not
repeated, the following hierarchy of controls will be used:
11 RISK MANAGEMENT
The risk register will initially define and manage common foreseeable
risks and also assist in determining which project activities involve
DESIGN & CONSTRUCTION OF
PUTATAN WATER TREATMENT PLANT 2
12 AUDIT FUNCTION
12.1 Purpose
The periodic review of actions and of inspection results that all works
is being performed in accordance with contractual requirements and
that deviations are being corrected or accepted.
12.2 Scope
The audit program described in this section applies to all quality
related work performed by consortium or subcontractors during
construction of the project.
12.3 Responsibility
The construction manager has overall responsibility for the
implementation of an effective quality control program. Planning and
implementing the audit program shall be done under the direction of
the QA/QC Manager.
12.4 Audit
12.4.1Audit Team
12.4.2Audit Schedules
12.4.3Unscheduled Audits
12.4.4Audit Planning
12.4.5Notice of Audit
12.4.6Audit Conduct
The audit shall proceed, seeing the prepared plans and checklists as a
guide. However, the audit team leader may deviate from the plan
when progress in the audit reveals the need in order to properly cover
the scope of audit. A record of the activity audited, names and
responsibilities of persons contacted, and the audit findings shall be
documented in the audit report checklists used shall become part of
the audit record file, and shall indicate items that were checked and
found acceptable as well as those found to require corrective actions.
The audit team leader shall schedule a post audit meetings with
construction manager to discuss audit findings and recommend
corrective actions.
12.4.8Audit Report
The audit findings and recommendations shall be documented in an
audit report issued to the construction manager of the job audited.
An information copy of each audit shall be transmitted to the project
manager responsible for the site audited.
DESIGN & CONSTRUCTION OF
PUTATAN WATER TREATMENT PLANT 2
The QA/QC Materials Manager, the Project Manager and the manager
of engineering, shall review the action reported for each finding and,
if action is considered satisfactory, issue a close out report.
Laboratory Forms
(Third Party Laboratory Testing Center format)
Reporting Forms
Daily Site Report (Weather Chart)
Weekly Report
DESIGN & CONSTRUCTION OF
PUTATAN WATER TREATMENT PLANT 2