External Water System for SMS III (PKG 77-01A) : L-2 Schedule Classic Schedule Layout 06-Jan-17 14:19

Activity ID Activity Name Original Remaining Schedule % Start Finish Total 2017
Duration Duration Complete FloatN D January F March April May June July August S October N D

EWS Ex
External Water System for SMS III (PKG 77-01A) : L-2 Schedu 430 430 0% 15-Dec-16 14-Dec-17 0 1...

EWS.1 External Water supply for SMS III 430 430 0% 15-Dec-16 14-Dec-17 0 1...
2 Signing of Contract 1 1 0% 15-Dec-16* 15-Dec-16 S...
3 Issuance of Form V from Employer 3 3 0% 21-Dec-16* 23-Dec-16 419 I...
EWS.1.1.3 Mobilization activities at site
EWS.1. 5 5 0% 15-Dec-16 19-Dec-16 425 1...
5 Availability of Construction power at TOP 1 1 0% 15-Dec-16* 15-Dec-16 430 A...
6 Approval for bore well locations for Construction water/Tapping points 1 1 0% 15-Dec-16* 15-Dec-16 416 A...
7 Drinking water connections at TOP/Tapping points 5 5 0% 15-Dec-16* 19-Dec-16 416 D...
EWS.1.1.4 Release of Clear Fronts for construction from Employer
EWS.1. 1 1 0% 15-Dec-16 15-Dec-16 430 1...
8 Release of Clear Fronts for construction from Employer 0 0 0% 15-Dec-16* 15-Dec-16 430 R...
9 Cooling Towers 1 1 0% 15-Dec-16* 15-Dec-16 430 C...
10 1st Floor of Common Pump House 1 1 0% 15-Dec-16* 15-Dec-16 430 1...
11 WTP 2 area 1 1 0% 15-Dec-16* 15-Dec-16 430 W...
12 Civil Work in main ECR & WTP 2 ECR 1 1 0% 15-Dec-16* 15-Dec-16 430 C...
13 Press Filter area 1 1 0% 15-Dec-16* 15-Dec-16 430 P...
14 Slugde Pump House 1 1 0% 15-Dec-16* 15-Dec-16 430 S...
15 Makeup & drinking water Pumphouse in WTP 5 1 1 0% 15-Dec-16* 15-Dec-16 430 M...
16 Secondary Settling Tank (SST) area 1 1 0% 15-Dec-16* 15-Dec-16 430 S...
17 Slag Quenching Pump house 1 1 0% 15-Dec-16* 15-Dec-16 430 S...
18 EOHT area to access WTP 3-4-5 area 1 1 0% 15-Dec-16* 15-Dec-16 430 E...
19 Pipe Tunnel & Pipe trestle from pipe tunnel (J1-7) to TOP 1 1 0% 15-Dec-16* 15-Dec-16 430 P...
EWS.1.1.5 Supply of free issue items along with spares, tools tackles & all accessor
EWS.1. 105 105 0% 15-Dec-16 14-Mar-17 325 1...
21 WTP 1 Area 105 105 0% 15-Dec-16* 14-Mar-17 325 W...
22 WTP 2 Area 105 105 0% 15-Dec-16* 14-Mar-17 325 W...
23 WTP 3 Area 68 68 0% 15-Dec-16* 10-Feb-17 362 W...
24 WTP 4 Area 68 68 0% 15-Dec-16* 10-Feb-17 362 W...
25 WTP 5 & Common area 90 90 0% 15-Dec-16* 01-Mar-17 340 W...
EWS.1.1.6 Handing over of all necessary Approved/Commented drawings/document
EWS.1. 1 1 0% 15-Dec-16 15-Dec-16 430 1...
27 GA Drawings 1 1 0% 15-Dec-16* 15-Dec-16 430 G...
28 Civil Drawings 1 1 0% 15-Dec-16* 15-Dec-16 430 C...
29 Mechanical 1 1 0% 15-Dec-16* 15-Dec-16 430 M...
30 Electrical 1 1 0% 15-Dec-16* 15-Dec-16 430 E...
31 Instrumentation 1 1 0% 15-Dec-16* 15-Dec-16 430 I...
EWS.1.1.7 Basic Engineering
EWS.1. 132 132 0% 17-Dec-16 08-Apr-17 295 0...
33 Civil Engineering 90 90 0% 17-Dec-16* 03-Mar-17 31 C...
34 Civil Engg - Approval by MECON 75 75 0% 12-Jan-17 16-Mar-17 31 C...
35 Structural Engineering 68 68 0% 21-Dec-16* 16-Feb-17 347 S...
36 Structural Engg - Approval by MECON 45 45 0% 16-Jan-17* 22-Feb-17 347 S...
37 Equipment, Elect. & Instrumentation Engineering 107 107 0% 27-Dec-16* 28-Mar-17 295 E...
38 Equipment, Elect. & Instrumentation Engineering - approval by MECON 98 98 0% 16-Jan-17* 08-Apr-17 295 E...
EWS.1.1.8 Detail Engineering
EWS.1. 221 221 0% 19-Dec-16 23-Jun-17 205 2...
40 Cooling Towers 53 53 0% 21-Dec-16* 03-Feb-17 0 C...
41 PIPE RACK/CABLE GALLERIES 60 60 0% 19-Dec-16* 07-Feb-17 365 P...
42 ECR Bldg near WTP 2 45 45 0% 21-Jan-17* 01-Mar-17 340 E...
43 ECR Bldg - WTP 3,4,5 53 53 0% 09-Jan-17* 22-Feb-17 347 E...
44 Addl ECR Bldg at WTP 3,4,5 area 56 56 0% 16-Jan-17* 03-Mar-17 337 A...
45 Toilet Block at WTP-1 area (20 user) 30 30 0% 08-Apr-17* 03-May-17 265 T...
46 Soft water plant 113 113 0% 21-Dec-16* 27-Mar-17 310 S...
47 Chemical House Building 45 45 0% 30-Dec-16* 06-Feb-17 367 C...
48 Slag Quenching Pump house 45 45 0% 03-Jan-17* 10-Feb-17 352 S...

Actual Work Critical Remaining Work Summary Page 1 of 8 TASK filter: All Activities

Remaining Work Milestone Oracle Corporation


External Water System for SMS III (PKG 77-01A) : L-2 Schedule Classic Schedule Layout 06-Jan-17 14:19

Activity ID Activity Name Original Remaining Schedule % Start Finish Total 2017
Duration Duration Complete FloatN D January F March April May June July August S October N D

49 Filter Press Building 68 68 0% 23-Dec-16* 18-Feb-17 337 F...


50 Sludge Sump Pump House 30 30 0% 03-Jan-17* 28-Jan-17 359 S...
51 Interplant piping, Interplant Launder system 90 90 0% 23-Dec-16* 10-Mar-17 329 I...
52 Drinking water & distribution system 90 90 0% 23-Dec-16* 10-Mar-17 329 D...
53 BOF Drain Pumping system 68 68 0% 27-Dec-16* 22-Feb-17 347 B...
54 Seal water pumping system ETP 68 68 0% 23-Dec-16* 18-Feb-17 352 S...
55 Plumbing & Sewarage network 90 90 0% 28-Jan-17* 14-Apr-17 287 P...
56 Sewarage system, Road & Paving works etc 90 90 0% 08-Apr-17* 23-Jun-17 14 S...
EWS.1.1.8.1.8.18 Electrical & Automation
EWS. 107 107 0% 26-Dec-16 27-Mar-17 310 2...
58 WTP 3,4 & 5 area including ECR 60 60 0% 09-Jan-17* 01-Mar-17 340 W...
59 Soft water plant 83 83 0% 16-Jan-17* 27-Mar-17 310 S...
60 Pipe Rack/ Cable Gallaries 60 60 0% 26-Dec-16* 15-Feb-17 356 P...
61 Slag Quenching Pump house 45 45 0% 12-Jan-17* 18-Feb-17 352 S...
62 Cooling Towers 68 68 0% 30-Dec-16* 25-Feb-17 344 C...
63 Filter Press Building 68 68 0% 05-Jan-17* 03-Mar-17 337 F...
64 Sludge Sump Pump House 38 38 0% 12-Jan-17* 13-Feb-17 359 S...
65 Crane & Hoists for different buildings 75 75 0% 09-Jan-17* 14-Mar-17 325 C...
EWS.1.1.9 Clearance from Employer
EWS.1. 41 41 0% 06-Jan-17 10-Feb-17 362 1...
67 Submission of QAP 2 2 0% 06-Jan-17* 07-Jan-17 398 S...
68 Approval of QAP 3 3 0% 07-Jan-17* 10-Jan-17 398 A...
69 Submission of Concrete Mix Design 2 2 0% 03-Feb-17* 04-Feb-17 362 S...
70 Approval of Concrete Mix Design 6 6 0% 04-Feb-17* 10-Feb-17 362 A...
EWS.1.1.10 Thickner (5 Nos) for WTP 3,4 & 5
EWS.1. 377 377 0% 30-Dec-16 15-Nov-17 35 1...
71 Thickner (5 Nos) for WTP 3,4 & 5 377 377 0% 30-Dec-16 15-Nov-17 35 T...
EWS.1.1.10.1.10.1 Thickner 1 (Balance works)
EWS. 210 210 0% 09-Jan-17 06-Jul-17 190 0...
72 Thickner 1 (Balance works) 210 210 0% 09-Jan-17* 06-Jul-17 190 T...
73 Joint Site Inspection & handing over of site 3 3 0% 28-Jan-17* 31-Jan-17 190 J...
74 Handing over of Free issue itmes from Employer 30 30 0% 09-Jan-17* 03-Feb-17 370 H...
75 Erection 90 90 0% 16-Feb-17* 03-May-17 190 E...
76 E & I activity 75 75 0% 04-May-17* 06-Jul-17 190 E...
EWS.1.1.10.1.10.2 Thickner 2 (Balance works)
EWS. 210 210 0% 09-Jan-17 06-Jul-17 190 0...
77 Thickner 2 (Balance works) 210 210 0% 09-Jan-17* 06-Jul-17 190 T...
78 Joint Site Inspection & handing over of site 3 3 0% 28-Jan-17* 31-Jan-17 190 J...
79 Handing over of Free issue itmes from Employer 30 30 0% 09-Jan-17* 03-Feb-17 370 H...
80 Erection 90 90 0% 16-Feb-17* 03-May-17 190 E...
81 E & I activity 75 75 0% 04-May-17* 06-Jul-17 190 E...
EWS.1.1.10.1.10.3 Thickner 3 (Balance) - starting from Tie beam
EWS. 291 291 0% 30-Dec-16 02-Sep-17 121 0...
82 Thickner 3 (Balance) - starting from Tie beam 291 291 0% 30-Dec-16* 02-Sep-17 121 T...
83 Joint Site Inspection & handing over of site 2 2 0% 30-Dec-16* 31-Dec-16 121 J...
84 Area development/prepeartory works 5 5 0% 31-Dec-16* 04-Jan-17 121 A...
85 Civil works 195 195 0% 04-Jan-17 19-Jun-17 121 C...
86 Handing over of Free issue itmes from Employer 30 30 0% 09-Jan-17* 03-Feb-17 370 H...
87 Erection 90 90 0% 19-Jun-17* 02-Sep-17 121 E...
88 Order placement, Manufacturing & Supply of Chemical Dosing system etc. 177 177 0% 28-Jan-17* 27-Jun-17 200 O...
EWS.1.1.10.1.10.4 Thickner 4 (new)
EWS. 359 359 0% 05-Jan-17 04-Nov-17 47 0...
89 Thickner 4 (new) 359 359 0% 05-Jan-17* 04-Nov-17 47 T...
90 Joint Site Inspection & handing over of site 2 2 0% 05-Jan-17* 06-Jan-17 47 J...
91 Area development/prepeartory works 5 5 0% 06-Jan-17* 10-Jan-17 47 A...
92 Order placement, Manufacturing & Supply of Chemical Dosing system etc. 177 177 0% 28-Jan-17* 27-Jun-17 200 O...
93 Civil works 195 195 0% 10-Jan-17* 24-Jun-17 47 C...

Actual Work Critical Remaining Work Summary Page 2 of 8 TASK filter: All Activities

Remaining Work Milestone Oracle Corporation


External Water System for SMS III (PKG 77-01A) : L-2 Schedule Classic Schedule Layout 06-Jan-17 14:19

Activity ID Activity Name Original Remaining Schedule % Start Finish Total 2017
Duration Duration Complete FloatN D January F March April May June July August S October N D

94 Erection 90 90 0% 24-Jun-17* 08-Sep-17 47 E...


95 E & I activity 68 68 0% 08-Sep-17* 04-Nov-17 47 E...
EWS.1.1.10.1.10.5 Thickner 5 (new)
EWS. 365 365 0% 10-Jan-17 15-Nov-17 35 1...
96 Thickner 5 (new) 365 365 0% 10-Jan-17* 15-Nov-17 35 T...
97 Joint Site Inspection & handing over of site 2 2 0% 10-Jan-17* 11-Jan-17 43 J...
98 Area development/prepeartory works 3 3 0% 11-Jan-17* 13-Jan-17 43 A...
99 Order placement, Manufacturing & Supply of Chemical Dosing system etc. 177 177 0% 28-Jan-17* 27-Jun-17 200 O...
100 Civil works 195 195 0% 20-Jan-17* 04-Jul-17 35 C...
101 Erection 90 90 0% 04-Jul-17* 19-Sep-17 35 E...
102 E & I activity 68 68 0% 19-Sep-17* 15-Nov-17 35 E...
EWS.1.1.11 Cooling Towers
EWS.1. 407 407 0% 19-Dec-16 28-Nov-17 19 2...
103 Cooling Towers 407 407 0% 19-Dec-16 28-Nov-17 19 C...
EWS.1.1.11.1.11.1 CT - 1 (Secondary Circuit for CCP)
EWS. 402 402 0% 19-Dec-16 24-Nov-17 23 2...
104 CT - 1 (Secondary Circuit for CCP) 402 402 0% 19-Dec-16 24-Nov-17 23 C...
EWS.1.1.11.1.11.1.1.11.1.1 Civil Work
EW 267 267 0% 03-Feb-17 18-Sep-17 23 1...
Civil Work 267 267 0% 03-Feb-17* 18-Sep-17 23 C...
Drawing submission by L&T 3 3 0% 03-Feb-17* 06-Feb-17 23 D...
Drawing approval by MECON 5 5 0% 06-Feb-17* 10-Feb-17 23 D...
Area development/Layout 3 3 0% 11-Feb-17* 14-Feb-17 23 A...
Civil work 255 255 0% 14-Feb-17* 18-Sep-17 23 C...
EWS.1.1.11.1.11.1.1.11.1.2 Mechanical work
EW 402 402 0% 19-Dec-16 24-Nov-17 23 2...
Mechanical work 402 402 0% 19-Dec-16* 24-Nov-17 23 M...
Enquiary, Technical Discussion with vendors & order placement 5 5 0% 19-Dec-16* 22-Dec-16 173 E...
Drawing submission by L & T 15 15 0% 22-Dec-16* 04-Jan-17 395 D...
Drawing approval by MECON 11 11 0% 04-Jan-17* 13-Jan-17 395 D...
Supply 93 93 0% 02-May-17* 20-Jul-17 173 S...
Erection 60 60 0% 18-Sep-17 08-Nov-17 23 E...
E & I activity 45 45 0% 17-Oct-17* 24-Nov-17 23 E...
EWS.1.1.11.1.11.2 CT - 2 (Secondary Circuit for BOF & SRU)
EWS. 404 404 0% 19-Dec-16 25-Nov-17 22 2...
117 CT - 2 (Secondary Circuit for BOF & SRU) 404 404 0% 19-Dec-16 25-Nov-17 22 C...
EWS.1.1.11.1.11.2.1.11.2.1 Civil Work
EW 269 269 0% 03-Feb-17 19-Sep-17 22 1...
Civil Work 269 269 0% 03-Feb-17* 19-Sep-17 22 C...
Drawing submission by L & T 3 3 0% 03-Feb-17* 06-Feb-17 22 D...
Drawing approval by MECON 8 8 0% 06-Feb-17* 13-Feb-17 22 D...
Area development/Layout 3 3 0% 13-Feb-17* 15-Feb-17 22 A...
Civil work 255 255 0% 15-Feb-17* 19-Sep-17 22 C...
EWS.1.1.11.1.11.2.1.11.2.2 Mechanical work
EW 404 404 0% 19-Dec-16 25-Nov-17 22 2...
Mechanical work 404 404 0% 19-Dec-16* 25-Nov-17 22 M...
Enquiary, Technical Discussion with vendors & order placement 5 5 0% 19-Dec-16 22-Dec-16 190 E...
Drawing submission by L & T 15 15 0% 06-Feb-17* 18-Feb-17 329 D...
Drawing approval by MECON 23 23 0% 18-Feb-17* 10-Mar-17 329 D...
Supply 93 93 0% 02-May-17* 20-Jul-17 173 S...
Erection 60 60 0% 19-Sep-17* 09-Nov-17 22 E...
E & I activity 45 45 0% 19-Oct-17* 25-Nov-17 22 E...
EWS.1.1.11.1.11.3 CT - 3 (BOF GCP circuit)
EWS. 401 401 0% 19-Dec-16 23-Nov-17 25 2...
130 CT - 3 (BOF GCP circuit) 401 401 0% 19-Dec-16 23-Nov-17 25 C...
EWS.1.1.11.1.11.3.1.11.3.1 Civil Work
EW 269 269 0% 03-Feb-17 19-Sep-17 25 1...
Civil Work 269 269 0% 03-Feb-17* 19-Sep-17 25 C...
Drawing submission by L & T 3 3 0% 03-Feb-17* 06-Feb-17 25 D...
Drawing approval by MECON 8 8 0% 06-Feb-17* 13-Feb-17 25 D...

Actual Work Critical Remaining Work Summary Page 3 of 8 TASK filter: All Activities

Remaining Work Milestone Oracle Corporation


External Water System for SMS III (PKG 77-01A) : L-2 Schedule Classic Schedule Layout 06-Jan-17 14:19

Activity ID Activity Name Original Remaining Schedule % Start Finish Total 2017
Duration Duration Complete FloatN D January F March April May June July August S October N D

Area development/Layout 3 3 0% 13-Feb-17* 15-Feb-17 25 A...


Civil work 255 255 0% 15-Feb-17* 19-Sep-17 25 C...
EWS.1.1.11.1.11.3.1.11.3.2 Mechanical work
EW 401 401 0% 19-Dec-16 23-Nov-17 25 2...
Mechanical work 401 401 0% 19-Dec-16* 23-Nov-17 25 M...
Enquiary, Technical Discussion with vendors & order placement 5 5 0% 19-Dec-16* 22-Dec-16 421 E...
Drawing submission by L & T 11 11 0% 13-Feb-17* 21-Feb-17 338 D...
Drawing approval by MECON 11 11 0% 21-Feb-17* 02-Mar-17 338 D...
Supply 93 93 0% 18-Apr-17* 06-Jul-17 190 S...
Erection 68 68 0% 19-Sep-17* 15-Nov-17 25 E...
E & I activity 45 45 0% 16-Oct-17* 23-Nov-17 25 E...
EWS.1.1.11.1.11.4 CT - 4
EWS. 404 404 0% 19-Dec-16 25-Nov-17 22 2...
143 CT - 4 404 404 0% 19-Dec-16 25-Nov-17 22 C...
EWS.1.1.11.1.11.4.1.11.4.1 Civil Work
EW 275 275 0% 03-Feb-17 25-Sep-17 95 2...
Civil Work 275 275 0% 03-Feb-17* 25-Sep-17 22 C...
Drawing submission by L & T 3 3 0% 03-Feb-17* 06-Feb-17 22 D...
Drawing approval by MECON 15 15 0% 06-Feb-17* 18-Feb-17 352 D...
Area development/Layout 3 3 0% 07-Mar-17* 10-Mar-17 22 A...
Civil work 234 234 0% 10-Mar-17* 25-Sep-17 22 C...
EWS.1.1.11.1.11.4.1.11.4.2 Mechanical work
EW 404 404 0% 19-Dec-16 25-Nov-17 22 2...
Mechanical work 404 404 0% 19-Dec-16* 25-Nov-17 22 M...
Enquiary, Technical Discussion with vendors & order placement 6 6 0% 19-Dec-16* 23-Dec-16 419 E...
Drawing submission by L & T 15 15 0% 06-Feb-17* 18-Feb-17 329 D...
Drawing approval by MECON 23 23 0% 18-Feb-17* 10-Mar-17 329 D...
Supply 93 93 0% 18-Apr-17* 06-Jul-17 190 S...
Erection 60 60 0% 25-Sep-17* 14-Nov-17 22 E...
E & I activity 39 39 0% 24-Oct-17* 25-Nov-17 22 E...
EWS.1.1.11.1.11.5 CT-5
EWS. 407 407 0% 19-Dec-16 28-Nov-17 19 2...
156 CT-5 407 407 0% 19-Dec-16 28-Nov-17 19 C...
EWS.1.1.11.1.11.5.1.11.5.1 Civil Work
EW 276 276 0% 03-Feb-17 26-Sep-17 0 2...
Civil Work 276 276 0% 03-Feb-17* 26-Sep-17 0 C...
Drawing submission by L & T 3 3 0% 03-Feb-17* 06-Feb-17 0 D...
Drawing approval by MECON 8 8 0% 06-Feb-17* 13-Feb-17 0 D...
Area development/Layout 3 3 0% 03-Mar-17* 06-Mar-17 0 A...
Civil work 240 240 0% 06-Mar-17* 26-Sep-17 0 C...
EWS.1.1.11.1.11.5.1.11.5.2 Mechanical work
EW 407 407 0% 19-Dec-16 28-Nov-17 19 2...
Mechanical work 407 407 0% 19-Dec-16* 28-Nov-17 19 M...
Enquiary & Technical Discussion, vendors & order placement 5 5 0% 19-Dec-16 22-Dec-16 421 E...
Drawing submission by L & T 15 15 0% 13-Feb-17* 25-Feb-17 322 D...
Drawing approval by MECON 23 23 0% 25-Feb-17* 16-Mar-17 322 D...
Supply 93 93 0% 18-Apr-17* 06-Jul-17 190 S...
Erection 60 60 0% 26-Sep-17 15-Nov-17 0 E...
E & I activity 41 41 0% 25-Oct-17 28-Nov-17 0 E...
EWS.1.1.12 Secondary Settling Tank (SST)
EWS.1. 356 356 0% 19-Dec-16 16-Oct-17 71 1...
170 Joint Site Inspection & layout 2 2 0% 19-Dec-16* 20-Dec-16 71 J...
171 Area development/prepeartory works 24 24 0% 20-Dec-16* 09-Jan-17 71 A...
172 Civil Works 315 315 0% 09-Jan-17* 03-Oct-17 71 C...
173 Enquiary, Order placement to vendor 11 11 0% 16-Jan-17* 25-Jan-17 216 E...
174 Supply (Free issue items supplied by Employer) 38 38 0% 09-Jan-17* 10-Feb-17 362 S...
175 Manufacturing, Supply (L&T Scope) 165 165 0% 10-Feb-17* 30-Jun-17 196 M...
176 Erection 90 90 0% 10-Jun-17* 25-Aug-17 71 E...

Actual Work Critical Remaining Work Summary Page 4 of 8 TASK filter: All Activities

Remaining Work Milestone Oracle Corporation


External Water System for SMS III (PKG 77-01A) : L-2 Schedule Classic Schedule Layout 06-Jan-17 14:19

Activity ID Activity Name Original Remaining Schedule % Start Finish Total 2017
Duration Duration Complete FloatN D January F March April May June July August S October N D

177 Electrical activity 92 92 0% 31-Jul-17* 16-Oct-17 71 E...


EWS.1.1.13 ECR Bldg near WTP 3,4 & 5 (Balance work)
EWS.1. 332 332 0% 07-Jan-17 16-Oct-17 70 1...
179 Front clearance/Joint Site Inspection & handing over of site 2 2 0% 07-Jan-17* 09-Jan-17 70 F...
180 Area development/prepeartory works 3 3 0% 09-Jan-17* 11-Jan-17 70 A...
181 Civil Works 225 225 0% 12-Jan-17* 21-Jul-17 172 C...
182 Erection 135 135 0% 04-May-17* 26-Aug-17 70 E...
183 Electrical activity 90 90 0% 01-Aug-17* 16-Oct-17 70 E...
EWS.1.1.14 Filter Press Building
EWS.1. 357 357 0% 24-Jan-17 23-Nov-17 25 2...
185 Drawing submission by L & T 18 18 0% 24-Jan-17* 08-Feb-17 31 D...
186 Drawing approval by MECON 18 18 0% 30-Jan-17* 14-Feb-17 31 D...
187 Area development/Layout 3 3 0% 14-Feb-17* 16-Feb-17 31 A...
188 Civil Works 315 315 0% 16-Feb-17* 10-Nov-17 31 C...
189 Manufacturing & supply of Filter Press with all associate accesorries 240 240 0% 14-Feb-17* 05-Sep-17 118 M...
190 Erection 120 120 0% 20-Jul-17* 30-Oct-17 31 E...
191 E & I activity 60 60 0% 03-Oct-17* 23-Nov-17 25 E...
EWS.1.1.15 Soft water plant
EWS.1. 378 378 0% 31-Dec-16 17-Nov-17 32 1...
193 Drawing submission by L & T 11 11 0% 20-Mar-17* 28-Mar-17 32 D...
194 Drawing approval by MECON 11 11 0% 28-Mar-17* 06-Apr-17 32 D...
195 Front clearance/Area development/Layout 3 3 0% 06-Apr-17* 08-Apr-17 32 F...
196 Civil Works 165 165 0% 08-Apr-17* 26-Aug-17 32 C...
197 Enquiary, Order placement, Manufacturing & Supply of Strl/Soft water plant/utility items 248 248 0% 31-Dec-16 29-Jul-17 163 E...
198 Erection 75 75 0% 26-Aug-17* 28-Oct-17 32 E...
199 Sheeting work 60 60 0% 27-Sep-17* 17-Nov-17 32 S...
200 E&I activity 45 45 0% 10-Oct-17* 17-Nov-17 32 E...
EWS.1.1.16 High Rate Filtration Units with Monorail support Str
EWS.1. 357 357 0% 02-Jan-17 31-Oct-17 52 3...
202 Drawing submission by L & T 8 8 0% 03-Jan-17* 09-Jan-17 217 D...
203 Drawing approval by MECON 11 11 0% 09-Jan-17* 18-Jan-17 389 D...
204 Front clearance/Area development/Layout 3 3 0% 20-Mar-17* 22-Mar-17 217 F...
205 Civil Works 98 98 0% 23-Mar-17* 13-Jun-17 217 C...
206 Enquiary, Order placement, Manufacturing & Supply of Filtration plant unit with accessorries 282 282 0% 02-Jan-17* 29-Aug-17 52 E...
etc.
207 Erection 45 45 0% 29-Aug-17* 06-Oct-17 52 E...
208 E&I activity 30 30 0% 06-Oct-17* 31-Oct-17 52 E...
EWS.1.1.17 Common Pump House (Balance works)
EWS.1. 204 204 0% 24-Jan-17 14-Jul-17 180 1...
210 Joint Site Inspection 11 11 0% 24-Jan-17* 01-Feb-17 350 J...
211 Area development/prepeartory works 23 23 0% 01-Feb-17 20-Feb-17 350 A...
212 Civil works 60 60 0% 11-Apr-17* 31-May-17 232 C...
213 Structural Erection 53 53 0% 25-Feb-17* 11-Apr-17 180 S...
214 Equipment Erection 45 45 0% 11-Apr-17* 18-May-17 180 E...
215 E & I activity 45 45 0% 24-Apr-17* 31-May-17 180 E...
216 Sheeting work 53 53 0% 31-May-17* 14-Jul-17 180 S...
EWS.1.1.18 Chemical House Building
EWS.1. 259 259 0% 28-Jan-17 05-Sep-17 118 0...
218 Drawing submission by L & T 11 11 0% 28-Jan-17* 06-Feb-17 123 D...
219 Drawing approval by MECON 15 15 0% 09-Feb-17* 22-Feb-17 118 D...
220 Site Handing over/front clearance 2 2 0% 22-Feb-17 23-Feb-17 118 S...
221 Area development/Layout 3 3 0% 23-Feb-17* 25-Feb-17 118 A...
222 Civil Works 173 173 0% 25-Feb-17* 22-Jul-17 118 C...
223 Erection 68 68 0% 08-Jun-17* 04-Aug-17 118 E...
224 E & I activity 45 45 0% 28-Jul-17* 05-Sep-17 118 E...
EWS.1.1.19 ECR Bldg - WTP # 2
EWS.1. 312 312 0% 21-Feb-17 11-Nov-17 38 1...

Actual Work Critical Remaining Work Summary Page 5 of 8 TASK filter: All Activities

Remaining Work Milestone Oracle Corporation


External Water System for SMS III (PKG 77-01A) : L-2 Schedule Classic Schedule Layout 06-Jan-17 14:19

Activity ID Activity Name Original Remaining Schedule % Start Finish Total 2017
Duration Duration Complete FloatN D January F March April May June July August S October N D

225 ECR Bldg - WTP # 2 312 312 0% 21-Feb-17 11-Nov-17 21 E...


226 Drawing submission by L & T 11 11 0% 21-Feb-17* 01-Mar-17 38 D...
227 Drawing approval by MECON 11 11 0% 01-Mar-17* 10-Mar-17 38 D...
228 Joint site inspection 2 2 0% 10-Mar-17 11-Mar-17 38 J...
229 Area development/Layout 5 5 0% 11-Mar-17* 15-Mar-17 38 A...
230 Order placement, Manufacturing & Supply of Eqpt/utility/Elec items 152 152 0% 01-Mar-17* 07-Jul-17 188 O...
231 Civil Works 285 285 0% 15-Mar-17* 11-Nov-17 38 C...
232 Erection 75 75 0% 15-Aug-17* 18-Oct-17 46 E...
233 E & I activity 68 68 0% 09-Sep-17* 06-Nov-17 46 E...
EWS.1.1.20 PIPE RACK/CABLE GALLERIES
EWS.1. 315 315 0% 07-Jan-17 02-Oct-17 87 0...
235 Drawing submission by L & T 21 21 0% 07-Jan-17* 25-Jan-17 87 D...
236 Drawing approval by MECON 21 21 0% 11-Jan-17* 28-Jan-17 87 D...
237 Front clearance/Area development/Layout 5 5 0% 28-Jan-17* 01-Feb-17 87 F...
238 Order placement, Manufacturing & Supply of Eqpt/utility/cables/Strl items 225 225 0% 28-Jan-17* 08-Aug-17 152 O...
239 Civil Works 173 173 0% 01-Feb-17* 28-Jun-17 87 C...
240 Strl Erection 120 120 0% 06-Mar-17* 15-Jun-17 95 S...
241 Cable Termination 240 240 0% 11-Mar-17* 02-Oct-17 87 C...
242 Sheeting work 128 128 0% 18-May-17* 02-Sep-17 120 S...
243 E & I activity 120 120 0% 15-Jun-17* 25-Sep-17 95 E...
EWS.1.1.21 Interplant piping, Launder system
EWS.1. 404 404 0% 21-Dec-16 28-Nov-17 19 2...
244 Interplant piping, Launder system 404 404 0% 21-Dec-16 28-Nov-17 19 I...
245 Drawing submission by L & T 30 30 0% 24-Jan-17* 18-Feb-17 344 D...
246 Drawing approval by MECON 30 30 0% 31-Jan-17* 25-Feb-17 344 D...
247 Enquiary, Order placement of Launder 23 23 0% 27-Dec-16* 16-Jan-17 19 E...
248 Supply of Launder 120 120 0% 15-Apr-17* 26-Jul-17 166 S...
249 Enquiary, Order placement of Pipes 23 23 0% 21-Dec-16* 09-Jan-17 107 E...
250 Supply of Pipe 177 177 0% 04-Feb-17* 05-Jul-17 107 S...
251 Joint Site Inspection & handing over of site/facilities for entire launder & piping works 105 105 0% 24-Jan-17* 24-Apr-17 277 J...
including readiness of TOP

252 Erection - Launder system 128 128 0% 02-May-17* 18-Aug-17 19 E...


253 Erection - Piping 255 255 0% 10-Feb-17* 14-Sep-17 107 E...
254 Testing works 75 75 0% 25-Aug-17* 27-Oct-17 19 T...
255 E & I activity 90 90 0% 13-Sep-17* 28-Nov-17 19 E...
EWS.1.1.22 Toilet Block at WTP-1 area (20 user)
EWS.1. 204 204 0% 02-May-17 21-Oct-17 64 2...
257 Drawing submission by L & T 15 15 0% 02-May-17* 13-May-17 64 D...
258 Drawing approval by MECON 20 20 0% 10-May-17* 26-May-17 64 D...
259 Front clearance/Area development/Layout 5 5 0% 31-May-17* 03-Jun-17 64 F...
260 Civil Works 135 135 0% 03-Jun-17* 26-Sep-17 64 C...
261 E & I activity 30 30 0% 26-Sep-17* 21-Oct-17 64 E...
EWS.1.1.23 Addl ECR at WTP 3,4,5
EWS.1. 321 321 0% 21-Feb-17 20-Nov-17 29 2...
263 Drawing submission by L & T 27 27 0% 21-Feb-17* 15-Mar-17 29 D...
264 Drawing approval by MECON 24 24 0% 01-Mar-17* 22-Mar-17 29 D...
265 Front clearance/Area development/Layout 5 5 0% 25-Mar-17* 29-Mar-17 29 F...
266 Order placement, Manufacturing & Supply of Eqpt/utility/Elec items 165 165 0% 28-Mar-17* 15-Aug-17 143 O...
267 Civil Works 210 210 0% 29-Mar-17* 23-Sep-17 29 C...
268 Erection 83 83 0% 16-Aug-17* 25-Oct-17 29 E...
269 E & I activity 75 75 0% 16-Sep-17* 20-Nov-17 29 E...
EWS.1.1.24 Misc Rooms (10 nos)
EWS.1. 288 288 0% 01-Mar-17 31-Oct-17 52 3...
271 Drawing submission by L & T 11 11 0% 01-Mar-17* 09-Mar-17 52 D...
272 Drawing approval by MECON 18 18 0% 09-Mar-17* 24-Mar-17 52 D...

Actual Work Critical Remaining Work Summary Page 6 of 8 TASK filter: All Activities

Remaining Work Milestone Oracle Corporation


External Water System for SMS III (PKG 77-01A) : L-2 Schedule Classic Schedule Layout 06-Jan-17 14:19

Activity ID Activity Name Original Remaining Schedule % Start Finish Total 2017
Duration Duration Complete FloatN D January F March April May June July August S October N D

273 Front clearance/Area development/Layout 5 5 0% 24-Mar-17* 28-Mar-17 52 F...


274 Civil Works 210 210 0% 29-Mar-17* 22-Sep-17 52 C...
275 E & I activity 68 68 0% 04-Sep-17* 31-Oct-17 52 E...
EWS.1.1.25 Storm Water Drains
EWS.1. 234 234 0% 02-May-17 16-Nov-17 34 1...
277 Drawing submission by L & T 38 38 0% 02-May-17* 02-Jun-17 34 D...
278 Drawing approval by MECON 38 38 0% 02-Jun-17* 04-Jul-17 34 D...
279 Area development/Layout 5 5 0% 04-Jul-17* 07-Jul-17 34 A...
280 Joint Site Inspection & handing over of site/clear fronts 5 5 0% 07-Jul-17* 12-Jul-17 34 J...
281 Civil Works 150 150 0% 12-Jul-17* 16-Nov-17 34 C...
EWS.1.1.26 Road & Paving works
EWS.1. 165 165 0% 15-Jul-17 01-Dec-17 15 0...
283 Drawing submission by L&T 11 11 0% 15-Jul-17* 24-Jul-17 15 D...
284 Drawing approval by MECON 15 15 0% 24-Jul-17* 05-Aug-17 15 D...
285 Joint Site Inspection & handing over of site/clear fronts 5 5 0% 05-Aug-17 09-Aug-17 15 J...
286 Civil Works 135 135 0% 09-Aug-17 01-Dec-17 15 C...
EWS.1.1.27 Misc Build (Parking shed, Water Tank, High Mast etc.)
EWS.1. 168 168 0% 13-Jul-17 02-Dec-17 14 0...
288 Drawing submission by L & T 8 8 0% 13-Jul-17* 19-Jul-17 14 D...
289 Drawing approval by MECON 15 15 0% 19-Jul-17* 01-Aug-17 160 D...
290 Front clearance/Area development/Layout 2 2 0% 02-Aug-17* 03-Aug-17 14 F...
291 Civil Works 120 120 0% 03-Aug-17* 13-Nov-17 14 C...
292 Erection 38 38 0% 06-Oct-17* 07-Nov-17 14 E...
293 E & I activity 60 60 0% 12-Oct-17* 02-Dec-17 14 E...
EWS.1.1.28 Priority Works (CTS Sl no. 10.01.02)
EWS.1. 215 215 0% 15-Dec-16 14-Jun-17 215 1...
294 Priority Works (CTS Sl no. 10.01.02) 215 215 0% 15-Dec-16 14-Jun-17 215 P...
EWS.1.1.28.1.28.1 Employer (BSP/MECON)
EWS. 213 213 0% 15-Dec-16 13-Jun-17 217 1...
296 Handing over of Drawings for all Free issue items 11 11 0% 15-Dec-16* 23-Dec-16 419 H...
297 Approval of P&ID & Pipe, Cable routes by Employer 38 38 0% 15-Dec-16* 16-Jan-17 392 A...
EWS.1.1.28.1.28.1.1.28.1.3 Completion of Civil Works & Handing over in finished cond
EW 213 213 0% 15-Dec-16 13-Jun-17 217 1...
2 Completion of Civil Works & Handing over in finished condition of following areas with 213 213 0% 15-Dec-16* 13-Jun-17 217 C...
Protocol by BSP/MECON to L&T

A. Scale Pit Pump House for WTP-1 area & associated Piping work. 90 90 0% 15-Dec-16 01-Mar-17 340 A...
B. Readiness of Pipe Trench/Tunnel within Caster Shop for pipe laying 90 90 0% 15-Dec-16* 01-Mar-17 340 B...
C. Readiness of Scale Flume Tunnels for caster 1&2 & Caster 3&4 for pipe laying. 90 90 0% 15-Dec-16* 01-Mar-17 340 C...
D. Readiness of Twin Tunnel for Pipe & cable for pipe laying. 90 90 0% 15-Dec-16* 01-Mar-17 340 D...
3 E. Readiness of Common Pump House at WTP 3,4,5 areas for installation of the pumps 90 90 0% 15-Dec-16* 01-Mar-17 340 E...
(free issue supply by BSP) & associat
3 F. Readiness of ECR in SS 63 ready for installation of the pumps (free issue by BSP) & 90 90 0% 15-Dec-16* 01-Mar-17 340 F...
associated Piping.
G. Handing over of Main ECR for WTP 3,4,5 areas. 90 90 0% 15-Dec-16* 01-Mar-17 340 G...
3 Clear front for Civil & Structural work for pipe trestle above live railway track between WTP 90 90 0% 15-Dec-16* 01-Mar-17 302 C...
3,4,5 area & BRM WTP area.

Arrangement for Complete Shutdown of Railway track between WTP 3,4,5 area & BRM W 23 23 0% 14-Mar-17* 01-Apr-17 302 A...
3 Handing over of all free issue Electro-Mechanical Items in propoerly good condition with 90 90 0% 15-Dec-16* 01-Mar-17 340 H...
approved drawings/documents/pro
Availability of water at Cold well adjacent to Common pump house in WTP 3,4,5 area 213 213 0% 15-Dec-16* 13-Jun-17 217 A...
3 Availability of water at Cold well adjacent to Common pump house in WTP 3,4,5 area 213 213 0% 15-Dec-16* 13-Jun-17 217 A...

EWS.1.1.28.1.28.2 Contractor (L&T)


EWS. 189 189 0% 05-Jan-17 14-Jun-17 215 1...
312 Submission of engineering design & drawing - Pipe Route & Pipe GAD 11 11 0% 05-Jan-17* 14-Jan-17 215 S...
313 Approval of engineering design & drawing - Pipe Route & Pipe GAD 5 5 0% 14-Jan-17 18-Jan-17 215 A...
314 Completion of system for water circulation (based on availability of above all inputs) 174 174 0% 18-Jan-17 14-Jun-17 215 C...
EWS.1.1.29 Permanent Power
EWS.1. 1 1 0% 15-Dec-16 15-Dec-16 430 1...
316 Availability of Permanent Power 1 1 0% 15-Dec-16* 15-Dec-16 430 A...

Actual Work Critical Remaining Work Summary Page 7 of 8 TASK filter: All Activities

Remaining Work Milestone Oracle Corporation


External Water System for SMS III (PKG 77-01A) : L-2 Schedule Classic Schedule Layout 06-Jan-17 14:19

Activity ID Activity Name Original Remaining Schedule % Start Finish Total 2017
Duration Duration Complete FloatN D January F March April May June July August S October N D

EWS.1.1.30 Water for Trial


EWS.1. 1 1 0% 15-Dec-16 15-Dec-16 430 1...
318 Availability of Water for Trial 1 1 0% 15-Dec-16* 15-Dec-16 A...
319 Availability of Make up & Fire Fighting water 1 1 0% 15-Dec-16 15-Dec-16 430 A...
EWS.1.1.31 Trial, Testing Work & Commissioning
EWS.1. 82 82 0% 06-Oct-17 14-Dec-17 0 1...
321 Cold Trial & Preliminary Acceptance Test 71 71 0% 06-Oct-17* 05-Dec-17 0 C...
322 Commissioning 11 11 0% 05-Dec-17* 14-Dec-17 0 C...
EWS.1.1.32 Delay Analysis, Aggreement & Extension
EWS.1. 36 36 0% 15-Jun-17 15-Jul-17 179 1...
323 Delay Analysis, Aggreement & Extension 36 36 0% 15-Jun-17 15-Jul-17 179 D...

Actual Work Critical Remaining Work Summary Page 8 of 8 TASK filter: All Activities