Академический Документы
Профессиональный Документы
Культура Документы
User Manuals
(QA In-charge will create the notification and fill the fields like material, batch, process order
etc., and assign the task in header level.)
Under Reference objects Tab, Select required fields from F4 help like Material, Plant for Mat.,
Batch, Storage location, Prod.Order No., Coding, Description and enter text in subject data as
shown in the below screen:
Project -
User Manuals
Enter Complaint Qty., Select Business Area Ex.100-Parental Group, Select Code Group from F4
help and enter task text as shown in the below screen.
Project -
User Manuals
Click on Dates/Times
Project -
User Manuals
Enter Reported by (enter name who is created the notification) and click on Tasks Tab
Project -
User Manuals
(Note: QA In-charge will release the header lever task and send to QA Manager)
To enter mandatory partner by click on Goto on Menu bar as shown in below screen
Project -
User Manuals
Click on Partner
Project -
User Manuals
Click on Save
Project -
User Manuals
To send notification to QA Manger executes the transaction QM02 with input field Notification No.
Project -
User Manuals
Enter brief note to QA Manger and select Recipient user Id (QA Manager User ID) from F4 help,
select Express Message check box and click on Send button.
(To select the Recipient User ID, please refer the process mentioned in Customer Complaints
notification.)
Project -
User Manuals
Click on Save
Project -
User Manuals
(To see the notification sent by QA In-charge, QA Manager Access the notification by click on
Sap Business Workplace button on Sap Easy Access screen as shown in below screen:)
Click on Inbox.
Project -
User Manuals
QA manage looks into notification and execute the transaction QM02 for further process
Execute the transaction QM02 (QA Manager User ID) with input field Notification No.:
Project -
User Manuals
Enter brief note to Production Manger on Subject data as shown in the below screen:
Project -
User Manuals
Enter brief note to Production Manger, select Recipient (Production Manager User Id) from F4
help, select Express Message and click on Send button.
Project -
User Manuals
Click on Save
Project -
User Manuals
Production Manager looks into the notification and investigate the route cause and inform to QA
Manger
Execute the transaction QM02 (Production Manager User ID) with input field Notification no.
Project -
User Manuals
Enter the brief note to QA Manager under Subject data and click on Service for object .
Project -
User Manuals
Enter brief note to QA Manger and select Recipient (QA Manager User ID) from F4 help, select
Express Message check box and click on Send button.
Project -
User Manuals
Click on Save
Project -
User Manuals
QA Manager looks into the confirmation message through notification by Production Manager and
execute the transaction QM02 for further process.
Project -
User Manuals
QA manager go through the route cause assigned by production manager by click on Activities
tab and close the task.
Enter Notification end date and time (Malfunct.end) as shown in the below screen
Project -
User Manuals
Click on Save
Project -
User Manuals
QA Manager will inform the status to QA In-charge by execute the transaction QM02.
Execute the transaction QM02 (QA Manager User ID) with input field Notification No.
Project -
User Manuals
Enter brief note to QA In-charge under Subject data and click on Services for object icon
.
Project -
User Manuals
Enter brief note to QA In-charge, select Recipient (QA In-charge User Id) from F4 help, select
Express Message check box and click on Send button.
Project -
User Manuals
You can see the document flow by execute the transaction QM03
***