Weekly Progress Report

Project : 11 kv diversion , Duct works & 132 kv Trough protection.

Date Work done Staf

Trail trench verification & Surveying @ sheet


5/27/2017 2
15
Cable Joint Inspection with client @ sheet no
5/28/2017 2
11 Trail trench no 01
Cable Joint Inspection with client @ sheet no
5/29/2017 11 Trail trench no 06 & sheet no 10 & TT no 2
11
Cable Joint Inspection with client @ sheet no
5/30/2017 13 Trail trench no 34 & 35 And revising 2
Betterment work shop drawing.
Shop Drawing Submitted for Betterment
5/31/2017 2
work sheet 1 -17 & sheet 19

6/1/2017 Revaising Duct shop drawing (sheet 1 to 8) 2


Client: Chiana State Construction

Skilled Un Skilled Total Remarks

Balaji, M.Ganesan,
1 1 4
Dhoni prsad
Balaji, M.Ganesan,
1 1 4
Dhoni prsad

Balaji, M.Ganesan,
1 1 4
Dhoni prsad

Pakyaraj, M.Ganesan,
1 1 3
Dhoni prsad

- - 2 Pakyaraj

- - 2 Pakyaraj
Weekly Planning
Project : 11 kv diversion , Duct works & 132 kv Trough protection.

Date Work done Staf

Preparation of Revised Shop Drawing for


6/3/2017 2
Betterment and duct works
Trail trench verification & Surveying @ sheet
6/4/2017 2
16

Trail trench verification & Surveying @ sheet


6/5/2017 2
17
Client: Chiana State Construction

Skilled Un Skilled Total Remarks

- - 2 Pakyaraj

Balaji, M.Ganesan,
1 1 4
Dhoni prsad

Balaji, M.Ganesan,
1 1 4
Dhoni prsad