Analysis of Rate

R.C.C. works with cement approved coarse sand 2cm (3/4") gauge approved stone ballast in the proporation
aggregate) in slabs excluding supply of reinforcement and its bending the same with 24 B.W. G.G.I. binding w
necessary centering and shuttering etc. and also including supply of all materials, labour, T&P etc. required f
works. Strength of the concrete shall no be less than M- 20.
Reference from UPPWD Analysis of rate - 1969, Item No.-279, Page No.-19
Concrete with 20 mm. gauge approved stone ballast, approved course sand and cement in the proportions of 4:2:1, inclu
Item labor and T & P etc.required for completion of the work.
No.-

Sl.No. Description Unit Qty Rate


279 Detail of cost for 2.83 cum
Materials
Stone ballast/agg. 20mm nominal size Cum 1.9125 1200.00
Stone ballast/agg. 10mm nominal size Cum 0.6375 1050.00
Carriage Cum 2.55 106.64
Coarse sand Cum 1.27 1120.00
Carriage Cum 1.27 106.64
Cement Bags 18.90 262.00
Carriage Bags 18.90 94.80
Add wastage at 2.5% on coarse sand and cement. 8301.35 2.50%
Labour
Mistri Day 1/10 393.00
Mason Day 1/2 377.00
Beldar Day 4.00 297.00
Coolie Day 4.00 297.00
Bhisti Day 2.00 328.00
Blacksmith Day 1/10 361.00
Total
T&P and Sundries etc, hire of C.C. Mixer, Lubricant etc. {10.50x(15041.77)/434.07
= 363.84} L.S.
Total
Add for water charges-@ 1.50%
Total
Contractor's profit @ 10.00%
Rate for 2.83 Cum

Reference from UPPWD Analysis of rate - 1969, Item No.-283, Page No.-21
R.C.C work with cement,approved course sand and 20 mm. gauge approved stone ballast in the proportion of 1:2:4 in lintels of doors and w
reinforcement and its bending but including its fixing and binding the same with 24 B.W.G. G.I. binding wire , and including neccessary cen
Item including the supply of binding wire , moulds and all other materials, labours and T & P etc. required for completion of the work.
No.-

As in item no. 283 but for slabs.

Sl.No. Description Unit Qty Rate


Cost of 1:2:4 as per item 279
Blacksmith for binding & fixing reinforcement Day 2 361.00
Cost of binding wire & extra cement & lobour for floating coat etc
={25.00x17199.61/455.85} = 943.27 L.S.

Cost of centering etc. with extra lobour etc={25.00x17199.61/455.35} = 943.27 L.S.


TOTAL
Add for water charges-@ 1.50%
Total
Contractor's profit @ 10.00%
Total
Rate for 2.83 Cum 17199.61 + 2912.44
Rate for 2.83 Cum
Reference from UPPWD Analysis of rate - 1969, Item No.-284, Page No.-22
Item As in item no. 283 but for slabs.
No.-

Sl.No. Description Unit Qty Rate


Rate as per S.I. 283

Add extra cost of centering and shuttering ={28.25x7106.73/194.50} = 1031.83 L.S.


Contractor's profit @ 10.00%
Rate for One Cum
Analysis of Rate
gauge approved stone ballast in the proporation 1:1.5:3 ( 1 cement :4.5
ts bending the same with 24 B.W. G.G.I. binding wire and includuing
supply of all materials, labour, T&P etc. required for proper completion of

Analysis of rate - 1969, Item No.-279, Page No.-19


course sand and cement in the proportions of 4:2:1, including supply of all materials,

Cost Rate Code Remark

2295.00
669.38
271.93 CPWD Rate
1422.40
135.43
4951.80
1791.72
207.53

39.30
188.50
1188.00
1188.00
656.00
36.10
15041.09

363.84
15404.93
231.07
15636.01
1563.60
17199.61

Analysis of rate - 1969, Item No.-283, Page No.-21


oved stone ballast in the proportion of 1:2:4 in lintels of doors and windows excluding supply of
me with 24 B.W.G. G.I. binding wire , and including neccessary centering and shuttering etc. and also
ours and T & P etc. required for completion of the work.

Cost Rate Code Remark


17199.61
722.00

943.27

943.27
2608.54
39.13
2647.67
264.77
2912.44
20112.04
7106.73
Analysis of rate - 1969, Item No.-284, Page No.-22

Cost Rate Code Remark


7106.73

1031.83
103.18
8241.74
Rate Analysis
Reference from UPPWD Analysis of rate - 1969, Item No.-586, Page No.-71
Item 12mm thick plaster with cement and fine sand of 1.25 FM mortar in 1:6 over brick work minimum thickness not to be less than 10m
No.- of all materials, labour and T&P etc. required for proper completion of the work.

Sl.No. Description Unit Qty Rate Cost

Detail of cost for 100 Sqft


Labour :-
Racking and washing surface
Mason Day 1/4 377.00 94.25
Coolie Day 1/4 297.00 74.25
Bhisti Day 1/10 328.00 32.80
Labour for plastering
Mason Day 3/4 377.00 282.75
Coolie Day 3/4 297.00 222.75
Bhisti Day 1/ 4 328.00 82.00
Sub Total 788.80
Scaffolding etc. L.S. 788.80 0.50/9.98 43.63
Material :-
Cement Bag 0.70 262.00 183.40
Coarse sand Cum 0.142 650.00 92.30
Carriage Cum 0.142 106.64 15.14
Total 1123.27
Add water charges @ 1.5% 16.85
Total 1140.12
Add for contractor's proffit @10% 114.01
Cost of 100 sqft 1254.13
Rate Per Sqm 134.94
ate Analysis

n 1:6 over brick work minimum thickness not to be less than 10mm thick including supply
n of the work.

Rate Code Remark


Rate Analysis
Reference from UPPWD Analysis of rate - 1969, Item No.-586, Page No.-71
Item 12mm thick plaster with cement and fine sand of 1.25 FM mortar in 1:6 over brick work minimum thickness not to be less than 10mm thick
No.- of all materials, labour and T&P etc. required for proper completion of the work.

Sl.No. Description Unit Qty Rate Cost

Detail of cost for 100 Sqft


Labour :-
Racking and washing surface
Mason Day 1/4 292.00 73.00
Coolie Day 1/4 192.00 48.00
Bhisti Day 1/10 230.00 23.00
Labour for plastering
Mason Day 3/4 292.00 219.00
Coolie Day 3/4 192.00 144.00
Bhisti Day 1/ 4 230.00 57.50
Sub Total 564.50
Scaffolding etc. L.S. 564.50 0.50/9.98 31.16
Material :-
Cement Bag 0.70 305.00 213.50
Coarse sand Cum 0.142 1533.70 217.79
Total 1026.95
Add water charges @ 1.5% 15.40
Total 1042.35
Add for contractor's proffit @10% 104.24
Cost of 100 sqft 1146.59
Rate Per Sqm 123.37
t to be less than 10mm thick including supply

Rate Code Remark

UPPWD S.R.
RMR Rate
SL.No. Rates of CPWD Schedule Rates as per CPWD 2013
basic material and labour
on UPPWD analysis of
Rate

Item Code Description of Item Rate Rate

1 2.6.1 Earth work in excavation by mechanical means (Hydraulic excavator) / manual means over areas (exceeding 30 cm 146.50 156.62
in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up
to 1.5 m, disposed earth to be levelled and neatly dressed.

2 5 Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15 landings, balconies, 6107.15 8241.74
shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases up to floor five level excluding the
cost of centering, shuttering, finishing and reinforcement, with 1:2:4 (1 cement : 2 coarse sand : 4 graded stone
aggregate 20 mm nominal size).

5.9.3 Centering and shuttering including strutting, propping etc. and removal of form for. Suspended floors, roofs, landings, 2974.40
balconies and access platform.

Total 9081.55 8241.74


3 6.4.2 Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in superstructure above plinth 5325.10 4949.15
level up to floor V level in all shapes and sizes in. Cement mortar 1:6 (1 cement : 6 coarse sand).
4 13.1.2 12 mm cement plaster of mix. 1:6 (1 cement : 6 fine sand). 133.85 134.94
5 4.1.8 Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - 3973.90 3816.87
All work up to plinth level. 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size).

6 11.3.1 Cement concrete flooring 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate) finished with a floating coat of 316.80 342.37
neat cement, including cement slurry, but excluding the cost of nosing of steps etc. complete. 40 mm thick with 20
mm nominal size stone aggregate.
7 5.22.1 Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all 64.05 71.53
complete upto plinth level. Mild steel and Medium Tensile steel bars.
8 17.35.1.1 Providing and fixing soil, waste and vent pipes. 100 mm dia. Sand cast iron S&S pipe as per IS: 1729. 854.85 860.78
9 9.1.2 Providing wood work in frames of doors, windows, clerestory windows and other frames, wrought framed and fixed in 73331.4 70053.84
position with hold fast lugs or with dash fasteners of required dia & length ( hold fast lugs or dash fastener shall be
paid for separately). Sal wood.

10 5.2.2 Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string 6319.2
courses, fillets, columns, pillars, piers, abutments, posts and struts etc. up to floor five level excluding cost of
centering, shuttering, finishing and reinforcement. 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate
20 mm nominal size).

5.9.6 Centering and shuttering including strutting, propping etc. and removal of form for Columns, Pillars, Piers, 4087.03
Abutments, Posts and Struts.
(Assume column size 0.23 x 0.45 m)

Total 10406.226 9672.70


Percentage
variation

-6.46%

10.19%
7.60%

-0.81%
4.11%

-7.47%

-10.46%

-0.69%
4.68%

7.58%
Name of Work:-Construction of Six No. type IV quarters at Dilkusha Colony,Lucknow
SL.No. Rates of CPWD Schedule Rates as per CPWD 2013 basic material and
analysis of Rate

Item Description of Item Qty Rate Amount Qty Rate


Code
1 2.6.1 Earth work in excavation by mechanical means (Hydraulic excavator) / manual means over areas 277.63 146.50 40672.86 277.63 156.62
(exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated
earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.

2 5 Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15 landings, 123.35 6107.15 123.35 8241.74
balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases up to
floor five level excluding the cost of centering, shuttering, finishing and reinforcement, with 1:2:4 (1
cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size).

5.9.3 Centering and shuttering including strutting, propping etc. and removal of form for. Suspended 2974.40
floors, roofs, landings, balconies and access platform.

Total 123.35 9081.55 1120239.17 123.35 8241.74


3 6.4.2 Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in 343.50 5325.10 1829149.48 343.50 4949.15
superstructure above plinth level up to floor V level in all shapes and sizes in. Cement mortar 1:6 (1
cement : 6 coarse sand).

4 13.1.2 12 mm cement plaster of mix. 1:6 (1 cement : 6 fine sand). 4231.38 133.85 566370.75 4231.38 134.94
5 4.1.8 Providing and laying in position cement concrete of specified grade excluding the cost of centering 83.12 3973.90 330299.06 83.12 3816.87
and shuttering - All work up to plinth level. 1:4:8 (1 cement : 4 coarse sand : 8 graded stone
aggregate 40 mm nominal size).
6 11.3.1 Cement concrete flooring 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate) finished with a 78.70 316.80 24932.16 78.70 342.37
floating coat of neat cement, including cement slurry, but excluding the cost of nosing of steps etc.
complete. 40 mm thick with 20 mm nominal size stone aggregate.

7 5.22.1 Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and 115612.40 64.05 7404974.04 115612.40 71.53
binding all complete upto plinth level. Mild steel and Medium Tensile steel bars.

8 17.35.1.1 Providing and fixing soil, waste and vent pipes. 100 mm dia. Sand cast iron S&S pipe as per IS: 1729. 100.00 854.85 85485.00 100.00 860.78

9 9.1.2 Providing wood work in frames of doors, windows, clerestory windows and other frames, wrought 3.45 73331.40 253103.33 3.45 70053.84
framed and fixed in position with hold fast lugs or with dash fasteners of required dia & length ( hold
fast lugs or dash fastener shall be paid for separately). Sal wood.

10 5.2.2 Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, 6.52 6319.20 6.52 9672.70
plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. up to floor
five level excluding cost of centering, shuttering, finishing and reinforcement. 1:1.5:3 (1 cement : 1.5
coarse sand : 3 graded stone aggregate 20 mm nominal size).

5.9.6 Centering and shuttering including strutting, propping etc. and removal of form for Columns, Pillars, 4087.03
Piers, Abutments, Posts and Struts.
(Assume column size 0.23 x 0.45 m)
Total 6.52 10406.23 67848.59 6.52 9672.70

G Total 11723074.44
No. type IV quarters at Dilkusha Colony,Lucknow
Rates as per CPWD 2013 basic material and labour on UPPWD
analysis of Rate
Percentage
variation
Amount

43482.48 -6.46%

1016645.83 10.19%
1700012.24 7.60%

570982.96 -0.81%
317247.18 4.11%

26944.52 -7.47%

8269754.77 -10.46%

86078.00 -0.69%

241790.83 4.68%

63066.00 7.58%

12336004.81 -4.97%
Rate Analysis

40mm. thick Cement concret flooring 1:2:4 (1 cement, 2 coarse sand,4 Stone aggregate of size 20 m
size ) laid in one layer finished with floating coat of neat cement and curing complete and including su
Item materials,labour T & P etc.required for proper completion of work
No.-

Reference from UPPWD Analysis of rate - 1969, Item No.-605, Page No.-77
Sl.No. Description Unit Qty Rate Cost
Detail of cost for 100 Sqft
Material :-
Stone Aggregate (Single size) : 20 mm
nominal sixe Cum 0.276 1200.00 331.20

Stone Aggregate (Single size) : 10 mm


nominal size Cum 0.092 1050.00 96.60
Carriage of stone aggregate below 40
mm nominal size Cum 0.368 106.64 39.24
Coarse sand Cum 0.184 1120.00 206.08
Carriage of coarse sand Cum 0.184 106.64 19.62
Cement Bag 2.75 262.00 720.50
Carriage of Cement Bag 2.75 94.80 260.70
Labour :-
Mistri Day 1/8 393.00 49.13
Mason Day 1 1/4 361.00 451.25
Beldar Day 1 297.00 297.00
Coolie Day 3/4 297.00 222.75
Bhisti Day 1/4 328.00 82.00
Sub Total 2776.07
Sundries, phanties etc
(2776.07x2/75.23 = 73.80) L.S. 73.80
Total 2849.87
Add water charges @ 1.5% 42.75
Total = 2892.62
Add for contractor's proffit @10% 289.26
Cost of 100 Sqft 3181.88
Rate Per Sqm 342.37
aggregate of size 20 mm nominal
mplete and including supply of all

age No.-77
Rate Code Remark
0.368
Rate Analysis
504 HYSD or iron in plain work such as reinforced concrete or reinforced brick work (when not included in
rates ) wrought to required shape as necessary including bending , and also including supply of
wastages and overlapping and hookes required for completion of the work.

Unit =Per Qtls

(A ) Materials :
Cost of steel Per qtl 0.508 qtl Rs 4600.00
Wastages 5% on steel Per qtl 0.0254 qtl Rs 4600.00
Carriage of steel Per qtl 0.5334 9.48
Total
(B) Labour :
Black smith Per day 1.00 no. Rs 393.00
Coolies Per day 1.50 no. Rs 297.00
Total
T & P etc. (2458.70.65+515.00)x0.40/62.59
Total
Contractor s profit @ 10%
Total
Rate for 0.508 Qtls Rs 3633.63
Rate for 1.00 Qtls Rs 7152.82
Say Rs 71.53
k (when not included in over all
so including supply of steel and

Rs 2336.80
Rs 116.84
5.06
Rs 2458.70

Rs 393.00
Rs 445.50
Rs 838.50
Rs 6.11
Rs 3303.30
Rs 330.33
Rs 3633.63
Rs 3633.63

Per Kg
Rate Analysis

Reference from UPPWD Analysis of rate - 1969, Item No.-337, Page No.-29
Item
Providing and fixing soil, waste and vent pipes. 100 mm dia. Sand cast iron S&S pipe as per IS: 1729.
No.-
Sl.No. Description Unit Qty Rate Cost
Details of cost for 1.00m

Material :-

soil, waste and vent pipes. 100 mm dia. Sand cast iron
Mtr 1.00 638.89 638.89
S&S pipe as per IS: 1729.

Add wastage 5% 31.94


Scaffolding L.S. 638.89.00x0.40/19.67 12.99
Labour :-
Fitter (grade 1) Day 1/10 393.00 39.30
Beldar Day 1/ 5 297.00 59.40
Sub Total 782.53
Add for contractor's proffit @10% 78.25
Cost of 1 metre 860.78
as per IS: 1729.

Rate Code Remark

UPPWD S.R.

UPPWD S.R.
Analysis of Rate
R.C.C. works with cement approved coarse sand 20 mm approved stone ballast in the proporation 1:1.5:3 ( 1 cement :1.5 coarse san
aggregate) in RCC T beam and Slab roofs and columns excluding supply of reinforcement and its bending the same with 24 B.W. G.G
and includuing necessary centering and shuttering etc. and also including supply of all materials, labour, T&P etc. required for prop
of works. Strength of the concrete shall no be less than M- 20.

Reference from UPPWD Analysis of rate - 1969, Item No.-279, Page No.-19
Concrete with 20 mm. gauge approved stone ballast, approved course sand and cement in the proportions of 4:2:1, including supply of
Item labor and T & P etc.required for completion of the work.
No.-

Sl.No. Description Unit Qty Rate Cost


279 Detail of cost for 2.83 cum
Materials
Stone ballast/agg. 20mm nominal size Cum 1.9125 1200.00 2295.00
Stone ballast/agg. 10mm nominal size Cum 0.6375 1050.00 669.38
Carriage Cum 2.55 106.64 271.93
Coarse sand Cum 1.27 1120.00 1422.40
Carriage Cum 1.27 106.64 135.43
Cement Bags 18.90 262.00 4951.80
Carriage Bags 18.90 94.80 1791.72
Add wastage at 2.5% on coarse sand and cement. 8301.35 2.50% 207.53
Labour
Mistri Day 1/10 393.00 39.30
Mason Day 1/2 377.00 188.50
Beldar Day 4.00 297.00 1188.00
Coolie Day 4.00 297.00 1188.00
Bhisti Day 2.00 328.00 656.00
Blacksmith Day 1/10 361.00 36.10
Total 15041.09
T&P and Sundries etc, hire of C.C. Mixer, Lubricant etc. {10.50x(15041.77)/434.07
= 363.84} L.S. 363.84
Total 15404.93
Add for water charges-@ 1.50% 231.07
Total 15636.01
Contractor's profit @ 10.00% 1563.60
Rate for 2.83 Cum 17199.61

Reference from UPPWD Analysis of rate - 1969, Item No.-283, Page No.-21
R.C.C work with cement,approved course sand and 20 mm. gauge approved stone ballast in the proportion of 1:2:4 in lintels of doors and windows excludin
reinforcement and its bending but including its fixing and binding the same with 24 B.W.G. G.I. binding wire , and including neccessary centering and shutte
Item including the supply of binding wire , moulds and all other materials, labours and T & P etc. required for completion of the work.
No.-

As in item no. 283 but for slabs.

Sl.No. Description Unit Qty Rate Cost


Cost of 1:2:4 as per item 279 17199.61
Blacksmith for binding & fixing reinforcement Day 2 361.00 722.00
Cost of binding wire & extra cement & lobour for floating coat etc
={25.00x17199.61/455.85} = 943.27 L.S. 943.27

Cost of centering etc. with extra lobour etc={25.00x17199.61/455.35} = 943.27 L.S. 943.27
TOTAL 2608.54
Add for water charges-@ 1.50% 39.13
Total 2647.67
Contractor's profit @ 10.00% 264.77
Total 2912.44
Rate for 2.83 Cum 17199.61 + 2912.44 20112.04
Rate for 2.83 Cum 7106.73
Reference from UPPWD Analysis of rate - 1969, Item No.-288, Page No.-22
Item No.- As in item no. 283 but in R.C.C. T- beams and slab roofs and columns.

Sl.No. Description Unit Qty Rate Cost


Rate as per S.I. 283 7106.73
Add extra for bricks or ballies supports stronger shuttering 7106.73 x 1.40/5.51 1805.70
Contractor's profit @ 10.00% on 1805.70 180.57
Rate for One Cum 9093.00

Reference from UPPWD Analysis of rate - 1969, Item No.-289, Page No.-22
Item No.- Extra for RCC in 1:1.5:3

Sl.No. Description Unit Qty Rate Cost


Stone ballast/agg. 20mm nominal size Cum 0.105 1200.00 126.00
Stone ballast/agg. 10mm nominal size Cum 0.035 1050.00 36.75
Carriage Cum 0.14 106.64 14.93
Coarse sand Cum 0.07 1120.00 78.40
Carriage Cum 0.07 106.64 7.46
Cement Bags 4.65 261.00 1213.65
Total 1477.19
Add for water charges-@ 1.50% 950.11 14.25
Total 1491.45
Contractor's profit @ 10.00% 149.14
Rate for 2.83 Cum 1640.59
Rate for One Cum 579.71
RATE FOR R.C.C. 1:1.5:3 IN lighter beams,ie having spans up to 6 metrs 9093.00 + 579.71 9672.72
Analysis of Rate
tone ballast in the proporation 1:1.5:3 ( 1 cement :1.5 coarse sand : 3
upply of reinforcement and its bending the same with 24 B.W. G.G.I. binding wire
cluding supply of all materials, labour, T&P etc. required for proper completion

alysis of rate - 1969, Item No.-279, Page No.-19


urse sand and cement in the proportions of 4:2:1, including supply of all materials,

Rate Code Remark

CPWD Rate

alysis of rate - 1969, Item No.-283, Page No.-21


d stone ballast in the proportion of 1:2:4 in lintels of doors and windows excluding supply of
e with 24 B.W.G. G.I. binding wire , and including neccessary centering and shuttering etc. and also
rs and T & P etc. required for completion of the work.

Rate Code Remark

alysis of rate - 1969, Item No.-288, Page No.-22


columns.

Rate Code Remark

lysis of rate - 1969, Item No.-289, Page No.-22

Rate Code Remark


Per Cum
Rate Analysis

40mm. thick Cement concret flooring 1:2:4 (1 cement, 2 coarse sand,4 Stone aggregate of size 2
size ) laid in one layer finished with floating coat of neat cement and curing complete and including
Item materials,labour T & P etc.required for proper completion of work
No.-

Reference from UPPWD Analysis of rate - 1969, Item No.-605, Page No.-77
Sl.No. Description Unit Qty Rate
Detail of cost for 100 Sqft
Material :-
graded brick aggregate 20mm Cum 0.368 2186.80
Coarse sand Cum 0.184 1533.70

Cement Bag 2.75 305.00


Labour :-
Mistri Day 1/8 292.00
Mason Day 1 1/4 260.00
Beldar Day 1 170.00
Coolie Day 3/4 170.00
Bhisti Day 1/4 205.00
Sub Total
Sundries, phanties etc
(2636.68x2/75.23 = 70.10) L.S.
Total
Add water charges @ 1.5%
Total =
Add for contractor's proffit @10%
Cost of 100 Sqft
Rate Per Sqm
sand,4 Stone aggregate of size 20 mm nominal
nd curing complete and including supply of all

Item No.-605, Page No.-77


Cost Rate Code Remark

804.74 Market rate


282.20 Market rate

838.75 UPPWD S.R.

36.50
325.00
170.00 UPPWD S.R.
127.50
51.25
2635.94

70.08
2706.02
40.59
2746.61
274.66
3021.27
325.09
Rate Analysis
Reference from UPPWD Analysis of rate Brick Bata Coba Treatment- 2009, Item No.-1, Page No.-12
Providing and laying "brick coba" 12 mm thick laid with brick bat coba 7.50 cm thick with gap of 1
20 mm thick base of cement mortar 1:4 cement and coarse sand mixed with water proofing comp
slurry mixed with aerclic cement concrete water proofing compound filled gaps of coba & top of c
proofing compound in 1:4 cement and coarse sand mortar finished smooth & top mashed false s
side wall parapet shall be mono tythic plaster wall upto 30 cm higher and junction and corner sh
ballast cement and coarse sand masonary Coba with top finished plaster mixed with acetic wate
by weight & including s/o all material, laboure, T & P etc. complete for proper completion of work.

Item No.-
Sl.No. Description Unit Qty
Detail of cost for 10 Sqm

i) Cement Slury
Cement Tonne 0.028

ii) Cement mortar 1:5 (1cement : 5coarse sand) Cum 0.224

iii) Roof Treanment with brick bats and cement mortar


Materials :
Bricks bats/brick aggregate Cum 0.94

Cement mortar 1:5 (1cement : 5coarse sand) Cum 0.50


Labour :
Beldar Day 1.75
Bhisti Day 0.28
Mason Ist class Day 0.05
Mason IInd class Day 0.05
Mat Day 0.04
Extra Labour for ramming :
Beldar Day 0.25
Sundries L.S. 13.65
iv) Cement Slury :
Cement Tonne 0.028
Beldar Day 0.2

v) 20mm cement Plaster 1:4 (1cement : 4 coarse sand) Sqm 10.00


vi) Waterproofing compound Kg 5.00
Extra for making chequers for 10

Fibre glass tissue reinforcement type II grade I Sqm 10.50


Mason IInd class Day 0.36
Beldar Day 0.36
chequer Plate L.S. 13.65
Add labour for laying 20mm bed
Mason IInd class Day 0.54
Beldar Day 0.54
Bhisti Day 0.45
Total
Add water charges @ 1% on all except labour
charges and (V)
Total

Add for contractor's proffit and OH @10% on all except (V)


Cost of 10 Sqm
Rate Per Sqm

Say Rs 1105
Item No.-1, Page No.-12
oba 7.50 cm thick with gap of 15 mm to each other , over
ixed with water proofing compound spreading cement
d filled gaps of coba & top of coba mortar mixed with water
smooth & top mashed false square 30 cm X 30 cm and
er and junction and corner shall be rounded by brick
plaster mixed with acetic water proofing compound @ 2%
for proper completion of work.

Rate Cost Rate Code Remark

6100.00 170.80

3763.32 842.98

850.00 799.00

3763.32 1881.66

192.00 336.00
230.00 64.40
292.00 14.60
260.00 13.00
205.00 8.20

192.00 48.00
1.76 24.02

6100.00 170.80
192.00 38.40

188.00 1880.00
40.00 200.00

65.00 682.50
260.00 93.60
192.00 69.12
176.00 2402.40

260.00 140.40
292.00 157.68
230.00 103.50
10141.06

73.23
10214.29

833.43
11047.72
1104.77

per Sqm
Rate Analysis
Reference from UPPWD Analysis of rate - 1969, Item No.-303, Page No.-25
Item Brick work class designation 7.50 in 1:6 (1 cement: 6 part of coarse sand 2.25 FM) mortar in super structure including supply of all materia
No.- etc. required for proper completion of the work.
Sl.No. Description Unit Qty Rate Cost

Detail of cost for 100 Cft


Material :-
Bricks Class 150 Nos 1300 4.80 6240.00
Coarse sand Cum 0.765 1533.70 1173.28
Cement Bag 3.75 305.00 1143.75
Labour :-
Mistri Day 1/6 328.00 54.67
Mason Day 2 292.00 584.00
Beldar Day 2 192.00 384.00
Coolie Day 2 192.00 384.00
Bhisti Day 1/2 230.00 115.00
Sub Total 10078.70
T&P etc L.S. 10078.70 0.75/152.18 49.67
A Total 10128.37
Extra labour in Superstructure for 1 1/2 brick
wall
Mason Day 1 292.00 292.00
Coolie Day 1 192.00 192.00
Scaffolding etc. L.S. 484.00 1.5/8.50 85.41
B Total 569.41

Extra labour in Superstructure for 1brick thick

Mason Day 1 292.00 292.00


Coolie Day 1 192.00 192.00
C Total 484.00
Total A+B+C 11181.78
Add water charges @ 1.5% 167.73
Total 11349.51
Add for contractor's proffit @10% 1134.95
Cost of 100 Cft 12484.46
Rate Per Cum 4408.26
including supply of all materials, labour, T&P

Rate Code Remark

UPPWD S.R.
RMR Rate
UPPWD S.R.

UPPWD S.R.

UPPWD S.R.

UPPWD S.R.
Rate Analysis
Reference from UPPWD Analysis of rate - 1969, Item No.-303, Page No.-25
Item Brick work class designation 7.50 in 1:6 (1 cement: 6 part of coarse sand 2.25 FM) mortar in super structure including supply of all
No.- etc. required for proper completion of the work.
Sl.No. Description Unit Qty Rate Cost

Detail of cost for 100 Cft


Material :-
Bricks Class 150 Nos 1300 4.80 6240.00
carriage of bricks Nos 1300 0.28 369.71
Coarse sand Cum 0.765 1120.00 856.80
carriage Cum 0.765 106.00 81.09
Cement Bag 3.75 262.00 982.50
carriage Bag 3.75 106.00 397.50
Labour :-
Mistri Day 1/6 393.00 65.50
Mason Day 2 361.00 722.00
Beldar Day 2 297.00 594.00
Coolie Day 2 297.00 594.00
Bhisti Day 1/2 328.00 164.00
Sub Total 11067.10
T&P etc L.S. 11067.10 0.75/152.18 54.54
A Total 11121.64
Extra labour in Superstructure for 1 1/2 brick
wall
Mason Day 1 361.00 361.00
Coolie Day 1 297.00 297.00
Scaffolding etc. L.S. 658.00 1.5/8.50 116.12
B Total 774.12

Extra labour in Superstructure for 1brick thick

Mason Day 1 361.00 361.00


Coolie Day 1 297.00 297.00
C Total 658.00
Total A+B+C 12553.76
Add water charges @ 1.5% 188.31
Total 12742.06
Add for contractor's proffit @10% 1274.21
Cost of 100 Cft 14016.27
Rate Per Cum 4949.15
Rate Analysis
25
arse sand 2.25 FM) mortar in super structure including supply of all materials, labour, T&P

Rate Code Remark

cpwd rate
Rate Analysis

Excavation in foundation in ordinary soil,lome,clay or sand] including lift upto 1.5 m & lead upto 30m
watering & ramming of excavated earth into the trenches or into the space beetween the building
Item foundation trenches or in to the plinth & removal & disposal of surplus earth as directed by the engineer -
No.- distance of 30m from the foundation trenches.

Reference from UPPWD Analysis of rate - 1969, Item No.-251, Page No.-13

Sl.No. Description Unit Qty Rate Cost


Detail of cost for 1000 Cft.
Labour :-
Mistry Day 1/8 393.00 49.13
Beldar Day 6 297.00 1782.00
Coolie Day 7 297.00 2079.00
Blacksmith Day 1/8 361.00 45.13
Total 3955.25
T&P and Basket etc. L.S. 3955.25 0.75/38.50 77.05
G.Total 4032.30

Add for contractor's proffit and overheads @10% 403.23


Cost of 1000 Cft. 4435.53
Hence Rate Per Cum 4435.53 /28.32 156.62
Rate Analysis

,clay or sand] including lift upto 1.5 m & lead upto 30m including filling
the trenches or into the space beetween the building & the sides of
al & disposal of surplus earth as directed by the engineer -in-charge upto a

WD Analysis of rate - 1969, Item No.-251, Page No.-13

Rate Code Remark

UPPWD S.R.

`
Rate Analysis

Providing and laying in position cement concrete of specified grade excluding the cost of centering and shutteri
Item upto plinth level 1:4:8 (1 cement:4 fine sand:8 graded stone aggregate 40mm nominal size)
No.-

Reference from UPPWD Analysis of rate - 1969, Item No.-275, Page No.-18

Sl.No. Description Unit Qty Rate


Detail of cost for 100 ft
Material :-

Graded stone aggregate 40mm Cum 2.07 1000.00

Carriage graded stone aggregate 40mm Cum 2.07 115.92

Graded stone aggregate 20mm Cum 0.76 1200.00

Carriage graded stone aggregate 20mm Cum 0.76 106.64


fine sand Cum 1.42 650.00
Carriage of fine sand Cum 1.42 106.64
Cement Bag 9.30 262.00

Add 2.5% for wastage on cement and sand


Labour :-

Mistri Day 1/8 292.00


Mason Day 1/3 377.00
Beldar Day 3 297.00
Coolie Day 3 297.00
Bhisti Day 1 328.00
Blacksmith Day 1/8 361.00
Sub Total

T&P and Sundries etc, Hire of C.C.Mixer,


lubricants etc. including wastage if materials
at 2.5% (9212.22x11/215.85 = 469.47) L.S.
Total
Add water charges @ 1.5%
Total =
Add for contractor's proffit @10%
Cost of 100 Cft
Rate Per Cum

Junior Engineer Assistant Engineer


Maint.Division 1,Civil Maint.Division 1,Civil
P.W.D. Lucknow P.W.D. Lucknow
g the cost of centering and shuttering-all work
m nominal size)

No.-275, Page No.-18

Cost Rate Code Remark

2070.00

239.95

912.00 UPPWD S.R.

81.05
920.40
151.00
2436.60

83.93

36.50
125.67
891.00 UPPWD S.R.
891.00
328.00
45.13
9212.22

469.47
9681.69
145.23
9826.91
982.69
10809.60
3816.87

Ex. Engineer
Maint.Division
1,Civil
P.W.D. Lucknow
Rate Analysis

Reference from UPPWD Analysis of rate - 1969, Item No.-401, Page No.-37
Supply and fixing Salwood wrought framed and fixed including simple moulding straight work as in Chaukh
Item supply of all materials, labour, T&P etc. required for proper completion of work.
No.-

Sl.No. Description Unit Qty Rate Cost


Take a size of opening as 4' x 7' section of Chaukhat
4" x 3"
Material :-
Salwood
1x18x1/3x1/4 = 1.5 cft wastage 5%
= 0.075 cft Total = 1.575
cft say 1.60 cft

Sal wood Cum 0.0453 52000.00 2355.60


Labour :-
Carpenter Mistri Day 1/16 393.00 24.56
Carpenter Day 1/2 371.00 185.50
Beldar Day 1/4 297.00 74.25
Sub Total 2639.91

Sundries 2639.91 1.5/60.46 65.50


Total 2705.41
Add for contractor's proffit @10% 270.54
Cost of 1.5 Cft 2975.95
Rate per Cum 70053.84

Junior Engineer Assistant Engineer


Maint.Division 1,Civil Maint.Division 1,Civil
P.W.D. Lucknow P.W.D. Lucknow
Rate Analysis

401, Page No.-37


ixed including simple moulding straight work as in Chaukhat frame including
for proper completion of work.

Rate Code Remark

DSR 2012-Item-
1199

UPPWD S.R.

Ex. Engineer
Maint.Division 1,Civil
P.W.D. Lucknow