DESCRIPTION COMPUTATION UNIT QUANTITY


1) EXCAVATION
Column Footing Depth: 1.5 m
(F-1) Dimension: 1.80 x 1.20 m
Total Volume: 1.5 x 1.80 x 1.20
= 3.24 cu.m.

Column Footing Depth: 1.5 m


(F-2) Dimension: 1.80 x 1.80 m
Total Volume: 1.50 x 1.80 x 1.80
= 4.86 cu.m.

Wall Footing Length: 9.3+0.90+0.90 = 11.10 m


(WF-1) Width: 0.40 m
Depth: 0.60 m
Total Volume: 11.10 x 0.40 x 0.60
= 2.664 cu.m.

2) CONCRETE
Column Footing Dimension: 1.80 x 1.20
(F-1) Thickness: 0.250 m
Total Volume: 1.80 x 1.20 x 0.250
= 0.54 cu.m.

Column Footing Dimension: 1.80 x 1.80


(F-2) Thickness: 0.250 m
Total Volume: 1.80 x 1.80 x 0.250
= 0.81 cu.m.

Wall Footing Length: 11.10 m


(WF-1) Width: 0.40 m
Thickness: 0.250 m
Total Volume: 1.110 cu.m.

Column Post (C-1) No. of the same column: 2


Height: 2.4 + 1.50 = 3.9 m
Dimension: 0.30 x 0.30
Total Volume: 3.9 x 0.30 x 0.30 x 2
= 0.702 cu.m.

Column Post (C-2) No. of the same column: 4


Height: 5.5
Dimension: 0.20 x 0.30
Total Volume: 1.32 cu.m.

No. of the same column: 4


Height: 4.9 + 1.5 = 6.40
Dimension: 0.20 x 0.30
Total Volume: 4 x 6.40 x 0.20 x 0.30
= 1.536 cu.m.

Column Post (C-3) No. of the same column: 2


Height: 4.9 + 1.5 = 6.40
Dimension: 0.150 x 0.30
Total Volume: 6.40 x 0.150 x 0.30 x 2
= 0.576 cu.m.

No. of the same column: 1


Height: 3.10
Dimension: 0.150 x 0.30
Total Volume: 3.10 x 0.150 x 0.30
= 0.140 cu.m.

No. of the same column: 1


Height 2.5
Dimension: 0.150 x 0.30
Total Volume: 2.5 x 0.150 x 0.30
= 0.1125 cu.m.

Roof Beam (RB-1) No. of the same beam: 2


Length: 2.0 m
Dimension: 0.15 x 0.30
Total Volume: 2 x 2 x 0.150 x 0.30
= 0.180 cu.m.

No. of the same beam: 2


Length: 1.950 m
Dimension: 0.15 x 0.30
Total Volume: 2 x 1.950 x 0.150 x 0.30
= 0.18 cu.m.

No. of the same beam: 2


Length: 14.250 m
Dimension: 0.15 x 0.30
Total Volume: 2 x 14.250 x 0.150 x 0.30
= 1.28 cu.m.

No. of the same beam: 8


Length: 1.5 m
Dimension: 0.15 x 0.30
Total Volume: 8 x 1.5 x 0.150 x 0.30
= 0.54 cu.m.

No. of the same beam: 2


Length: 7.4 m
Dimension: 0.15 x 0.30
Total Volume: 2 x 7.4 x 0.150 x 0.30
= 0.67 cu.m.

Slab (S-1) Area: 21.38 sq.m.


Thickness: 0.113 m
Total Volume: 21.38 x 0.113 = 2.42 cu.m.

Area: 11.10 sq.m.


Thickness: 0.113 m
Total Volume: 11.10 x 0.113 = 1.25 cu.m.

3) Masonry
CHB 4 Area: 6.26 + 5.46 + 6.20 + 6.20 + 2.87
= 26.99 m2
Deduction: 1.2 + 0.30 + 1.47 + 1.47 = 4.44
Total Area: 26.99 4.44 = 22.55 sq.m.

CHB 5 Area: 0.90 x 7 = 6.3 sq.m.

Area: 0.90 x 6.4 = 5.76 sq.m.

4) Reinforcement
Footing (F-1) No. of bars:
a)8 20mm
b)12 20mm

Development Length for


20mm = 0.345m
Hook Length = 0.30m

a) Length:
(2x0.345)+(2x0.30)+1.2
= 2.49 m
Total Length
= 2.49 x 12 = 29.88 m
b) Length:
(2x0.345)+(2x0.30)+1.8
= 3.09 m
Total Length
= 3.09 x 8 = 24.72 m

Footing (F-2) Total Length for F-1: 29.88 + 24.72 = 54.6


Total No. of F/L bars: 54.60/6 = 9.1 10

No. of bars: a) 12 20mm ; b) 12 20mm


Development Length for 20mm = 0.345m
Hook Length = 0.30m

a) Length:
2(0.345) + 2(0.30) + 1.80 = 3.09 m
Total Length: 3.09 x 12 = 37.08m

b) Length:
2(0.345) + 2(0.30) + 1.80 = 3.09 m
Total Length: 3.09 x 12 = 37.08m

Total Length for F-2: 37.08 + 37.08


= 74.16 m

No. of the same footing: 2


Total Length for F-2: 148.32 m
Total of F/L bars: 148.32/6 = 24.72 25