Milestone Review Number 2

1 Tasks completed since last Milestone


Created questionnaire
Created statistical analysis
Produced podcast

2 Status of project as a whole


Work is going at a good pace to be completed before the deadline, all is to complete
now is the production of the Ident and software diary to do alongside the production

3 Tasks planned to be completed by next Milestone


Complete TV Ident production
Complete software diary

4 Review of schedule (ILP or Timeline) so far and identify changes made to


schedule
N/A

5 Additional General Comments


Assignment very close to complete and will be completed for deadline