February, 2017
Prepared for:
The information contained in this document is solely for the use of the client
identified on the cover sheet, and for the purposes specified herein. AECOM
accepts no responsibility and undertakes no duty to any third party who may rely
PEOPLE
on this document.
CLIENTS
All rights reserved. No section or element of this document may be removed from
this document, reproduced, electronically stored, or transmitted in any form
without the written permission of AECOM.
EXCELLENCE
INTEGRITY
SAFETY
INNOVATION
PROJECT NAME: Development of Exhibition cum Convention Centre -Dwarka, New Delhi
Anchal Jain
Govind Rathod
PREPARED : 6.02.2017
Jayakrishna Vasam
Abhay Mishra
Nidhi Sharma
CHECKED: 7.02.2017
Ajay Pillai
Revision Record
12. Village Panchayats, Zilla Parishad, Municipal Delhi Development Authority (DDA)
Corporation, Local body (complete postal addresses Municipal Corporation of Delhi (MCD)
with telephone nos to be given)
13. Name of the applicant Delhi Mumbai Industrial Corridor Development Corporation
Limited (DMICDC Ltd)
14. Registered Address Delhi Mumbai Industrial Corridor Development Corporation
Ltd.
Room No. 341 B, 3rd Floor, Hotel Ashok, Chanakyapuri,
New Delhi 110021
15. Address for correspondence: Delhi Mumbai Industrial Corridor Development Corporation
Ltd., Room No. 341 B, 3rdFloor, Hotel Ashoka, Chanakya
Puri, New Delhi 110021
16. Name Name: Mr Alkesh K. Sharma
Designation (Owner/ Partner/ CEO) Designation: CEO & MD, DMICDC
Address: Delhi Mumbai Industrial Corridor Development
Corporation Ltd.
Room No. 341 B, 3rdFloor, Hotel Ashoka,
Chanakya Puri; New Delhi 110021; Pin code: 110021
Email: ceo@dmicdc.com
Telephone No.: +91-2611-8883-8;
Fax No.: +91-2611-8889
Capacity corresponding to sectoral activity (such as production capacity for manufacturing, mining lease area and
production capacity for mineral production, area for mineral exploration, length for linear transport infrastructure,
generation capacity for power generation etc.,)
1.1 Activity
A. Construction, operation or decommissioning of the Project involving actions, which will cause physical
changes in the locality (topography, land use, changes in water bodies, etc.)
1.4 Pre-construction investigations e.g. Yes Soil investigation, geotechnical survey and other testing will be
bore houses, soil testing? conducted before commencement of construction activities.
1.5 Construction works? Yes New buildings will be constructed such as Exhibition centre,
convention centre, hotels, service apartments, arena and offices.
1.6 Demolition works? No No demolition work is envisaged.
1.7 Temporary sites used for construction Yes No labour camps have been planned to be set up for construction
works or housing of construction work.
workers?
It is estimated that about 5500 local labourers workers will be
engaged for construction and related activities during the peak.
Influx of migrant labour is not expected.
1.8 Above ground buildings, structures or Yes Above ground buildings will include exhibition halls, convention
earthworks including linear structures, centre, hotels, service apartments, arena and offices. Other than
cut and fill or excavations. this, there will be provision of cut and fill for basement, foundation,
& other MEP services etc.
1.9 Underground works including mining No NA
or tunneling?
1.10 Reclamation works? No NA
1.11 Dredging? No NA
1.12 Offshore structures? No NA
1.13 Production and manufacturing No None, it is an Area Development Project.
processes?
1.14 Facilities for storage of goods or Yes During construction phase, there will be provision for storage of
materials? construction materials like cement, brick etc.
Common storage facilities/ warehouses will also be created.
1.15 Facilities for treatment or disposal of Yes During construction stage, waste will be generated mainly from
solid waste or liquid effluents? construction activities and municipal solid waste from labour resting
During operation stage, the waste will include liquid and solid waste
from convention centre. For disposal of liquid waste, two Sewage
Treatment Plant have been proposed:
The incoming Main from municipality water supply line shall be led
into centralized Fire tanks with an overflow connection to raw water
tanks; thereafter the water shall be treated and stored in domestic
water storage tanks.
1.24 Changes in water bodies or the land No There are no water bodies in the project site.
surface affecting drainage or run-off? The project does not envisage any alterations in water courses or
change in drainage or the land surface affecting drainage or run-off.
1.25 Transport of personnel or materials Yes During construction phase, workers and construction materials will
for construction, operation or be transported to the project construction site.
decommissioning?
During operation phase, increased traffic will be observed.
1.26 Long-term dismantling or No NA
decommissioning or restoration
works?
1.27 Ongoing activity during No NA
decommissioning which could have
an impact on the environment?
1.28 Influx of people to an area in either Yes During construction phase, local labourers will be hired from the
temporarily or permanently? vicinity of the site; no influx of migrant labour is foreseen. Hence,
setting up of labour camps is not envisaged.
B. Use of Natural resources for construction or operation of the Project (such as land, water, materials or
energy, especially any resources which are non-renewable or in short supply):
2.1 Land especially undeveloped or Yes About 89.72 ha of land have been earmarked for development
agricultural land (ha) of Exhibition cum Convention Centre (ECC). The selected site
is relatively flat and is unobstructed with majority being
agricultural land. Notification has been issued by Ministry of
th
Urban Development dated 12 May, 2016 describing the
modification in the land use of land proposed for development
of ECC falling in Zone-II (Dwarka) to Public, Semi Public and
socio-cultural facilities.
2.2 Water (expected source & Yes During construction phase, approx. 2.1 MLD will be required
competing users) unit: KLD for all construction works and will also meet water requirement
for domestic purpose and workers at site. The water required
for both drinking and construction activities during the
construction phase will be sourced from DJB through water
tankers.
2.4 Construction material stone, Yes It has been proposed that the construction material will be
aggregates, sand / soil (expected sourced only from authorized quarries in and around the
source MT) region. Two quarry sites - Badarpur stone quarry and Jaitpur
Quarry situated approximately 26km and 29km have been
identified to source stones, aggregates, sand, etc. Steel and
cement will be purchased from reputed manufacturers with
valid test certificates as per BIS specifications. Aluminium,
bricks, stones, marbles, paint, tiles, electrical ware, glass will
be purchased from local markets. All material will be delivered
to site and shall be processed for final installation at site only.
2.5 Forests and timber (source MT) Yes Wood for Doors shutters/ furniture, windows will be sourced
from authorised vendors. Details on quantities will be
provided at the detailed master plan level.
2.6 Energy including electricity and fuels Yes During construction phase of the project, no labor camps have
(source, competing users) Unit: fuel been planned, power requirement will only be limited to
(MT), energy (MW) operation of construction equipments and machinery, that will
sourced from nearest grid substation. 250 KVA x 6 Nos,
125KVA x9 Nos, 65 KVA x 12 Nos of capacity will be used for
C. Use, storage, transport, handling or production of substances or materials, which could be harmful to
human health or the environment or raise concerns about actual or perceived risks to human health.
S.No. Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates,
wherever possible) with source of information data
3.1 Use of substances or materials, which are No During construction phase, usage of maximum of 1m 3/ day of
hazardous (as per MSIHC rules) to human High Speed Diesel for operation of Diesel Generators is
health or the environment (flora, fauna, and envisaged.
4.4 Other industrial process wastes Yes No industry is envisaged in the project site.
4.5 Surplus product No NA
4.6 Sewage sludge or other sludge from Yes Approx. 1.7- 2.0 Tonnes
effluent treatment
4.7 Construction or demolition wastes Yes There will be generation of construction wastes.
4.8 Redundant machinery or equipment No NA
6.3 From construction or demolition Yes Due to the various activities, there will be short-term noise impacts
in the immediate vicinity of the project site. The construction
activities will include the following noise generating activities:
Operation of diesel generators.
Excavation etc.
6.5 From construction or operational traffic Yes There will be increased noise due to vehicular traffic during
operation phase.
6.6 From lighting or cooling systems No NA
G. Risks of contamination of land or water from releases of pollutants into the ground or into sewers,
surface waters, groundwater, coastal waters or the sea:
It will be stored in drums and kept in covered rooms and will be sold
to authorize vendors only. Special care will be taken to prevent
leakages and spills. E-waste generated from the complex shall be
given to approve recycler of SPCB.
7.2 From discharge of sewage or other No During construction phase, domestic effluents will be collected in
septic tanks followed by soak pits.
effluents to water or the land (expected
mode and place of discharge)
During operation phase, two sewage treatment plants have been
proposed of capacities of 2.75 MLD for Phase-I and3.95 MLD for
Phase-II respectively.
H. Risk of accidents during construction or operation of the Project, which could affect human health or the
environment
8.3 Could the project be affected by natural Yes New Delhi falls in Zone-IV of earthquake zones-according to the
Indian Standard Seismic Zoning Map; detailed disaster
disasters causing environmental damage
management plan will be prepared for the site. Chances of
(e.g. floods, earthquakes, landslides,
events involving flooding in the area are very less likely.
cloudburst etc)?
Landslide: area is a flat land, Hence N.A
I. Factors which should be considered (such as consequential development) which could lead to
environmental effects or the potential for cumulative impacts with other existing or planned activities in
the locality
9.4 Have cumulative effects due to proximity to Yes ECC is envisioned to be on a scale of a Central Business
other existing or planned projects with similar District, which will be having a similar effect as of Pragati
Maidan.
effects
J. Environmental Sensitivity
Schools:
Senior Secondary School 0.5km,NE
2.5km, NE
Paramount International School
1.5km, NNW
Nehru Academy School
1.5km, NW
Infant Jesus School
2.5km,North
Ambedkar University
ECC Dwarka
February, 2017
Form I-A- Exhibition Cum-Convention Centre at
Dwarka, Delhi
Prepared for:
The information contained in this document is solely for the use of the client
identified on the cover sheet, and for the purposes specified herein. AECOM
accepts no responsibility and undertakes no duty to any third party who may rely
PEOPLE
on this document.
CLIENTS
All rights reserved. No section or element of this document may be removed from
this document, reproduced, electronically stored, or transmitted in any form
without the written permission of AECOM.
EXCELLENCE
INTEGRITY
SAFETY
INNOVATION
PROJECT NAME: Development of Exhibition cum Convention Centre -Dwarka, New Delhi
Anchal Jain
Govind Rathod
PREPARED : Jayakrishna Vasam 6.02.2017
Abhay Mishra
Nidhi Sharma
CHECKED: Ajay Pillai 7.02.2017
Revision Record
Tables
Table 1-1: Geographical coordinates outlining the site ....................................................................................................... 9
Table 1-2: Key project details ............................................................................................................................................. 13
Table 1-3 : Vehicular share from the proposed development ........................................................................................... 15
Table 1-4: Projected traffic flow (in PCUs) ......................................................................................................................... 16
Table 1-5 : Parking Requirement for ECC ......................................................................................................................... 16
Table 1-6: Details of Proposed Soil Sampling Locations .................................................................................................. 17
Table 1-7: Details of Monitoring Program for Soil Quality ................................................................................................. 17
Table 1-8: Method for Soil Analysis .................................................................................................................................... 18
Table 1-9: Results of Soil Quality Analysis......................................................................................................................... 18
Table 1-10: Standard Soil Classification ............................................................................................................................ 19
Table 2-1 : Water demand estimated for the proposed ECC-Phase I .............................................................................. 25
Table 2-2 : Water demand estimated for the proposed ECC-Phase II ............................................................................. 28
Table2-3 : Parameters for design of sewage treatment plant ........................................................................................... 32
Table 2-4 : Rain water Harvesting Potential for the proposed Exhibition and Convention Centre ................................. 32
Table 5-1: Air Quality data collected at Site ....................................................................................................................... 38
Table 5-2: Details of Monitoring Program for Ambient Air Quality .................................................................................... 38
Table 5-3: Brief summary of the Methodology followed for Analysis of Ambient Air Quality ........................................... 38
Table 5-4: Ambient Air Quality in the Study Area ............................................................................................................... 39
Table 5-5: Climatological Summary (obtained from nearest IMD MET Station at Palam (2007-2011)) ......................... 43
Table 5-6: Annual Rainfall (mm) at the nearest IMD MET Station .................................................................................... 43
Table 5-7: Wind speed and direction .................................................................................................................................. 44
Table 5-8: Meteorological data collected at Site ................................................................................................................ 46
Table 5-9 : Parking Requirement for ECC ......................................................................................................................... 49
Table 5-10 Details of the internal roads ............................................................................................................................. 52
Table 5-11 Details of the internal roads.............................................................................................................................. 55
Attach Maps of (i) site location, (ii) surrounding features of the proposed site (within 500 meters) and (iii) the
site (indicating levels & contours) to appropriate scales. If not available attach only conceptual plans.
The ECC campus, which is being planned in close proximity to the international airport terminal will also
capture hotel room demand from foreign tourists arriving in Delhi. The project shall be developed as a
leading (Meetings, Incentives, Conferences, and Exhibitions destination, (MICE), combining business-cum-
entertainment experience. The destination creation will include strategic placement and brand creation for
the proposed facility to enhance the experience of MICE events by creating a unique mix of enabling land
uses which are not comparable to any existing exhibition venue. The coordinates of site boundary are
provided in Table 1-1.
Table 1-1: Geographical coordinates outlining the site
The site is located in close proximity to various transport links such as Indira Gandhi International Airport,
Delhi Rewari Railway line and Dwarka Sec-21 Metro station, providing connectivity within Delhi and
nearby regions.
State Delhi
District South West
Total Built up area 10,20,000 sqm
Total site area for ECC 89.72 Ha
Estimated Number of Visitors at ECC 3,87,970
Total Parking requirement 27,000 ECS
Total Power requirement 100 MW
Fresh Water Requirement 2.0 MLD for Phase I and 2.9 MLD for Phase II (Total 4.9 MLD)
Treated water re-use 2.2 MLD for Phase I and 3.1 MLD for Phase II (Total 5.3 MLD)
Source of water Delhi Jal Board (DJB)
Waste water Generation 2.3 MLD for Phase I and 3.3 MLD for Phase II (Total 5.6 MLD)
Solid Waste Generation ~75 80 TPD( at peak time, 120days)
Solid Waste Generation ~23 - 25 TPD (non-peak)
Source of Power State Electricity Board
Total Project Cost ~INR 24,505 crores
3 Hotel (4 Star) _ 2 No. 1000 kVA & 2 No. 750 kVA & 1 No. 380 kVA
6 Retail _ 7 No. 2000 kVA & 2 X 1500 KVA 1 X 1000 KVA &
1 No. 250 kVA
7 Office _ 2 No. 1500 kVA & 8 No. 1000 kVA & 9 No. 750
kVA & 1 No. 500 kVA & 2 No. 320 kVA
Note: Nos. of DGs are based on the broad estimate and may change during operation phase.
1.2.4 Connectivity
The site is located in close proximity to various transport links such as Indira Gandhi International
Airport, Delhi Rewari Railway line and Dwarka Sec-21 Metro station, providing connectivity within
Delhi and nearby regions.
Presently, the access to the site is from the Urban Extension Road II (UER -II), Dwarka sector roads
and local village roads. UER-II (also known as Najafgarh road) of 100m ROW and 6 lane carriageway
flanks the site on its northern side connecting the site to NH-8. Dwarka Sector road (60m ROW with 6
carriage way) connects the site to Sector 22 and Sector 23. The same road is proposed to link to
Northern Peripheral Road (Dwarka Expressway) in Gurgaon Manesar Master Plan 2021.The site is also
flanked by sector road of 60 metres ROW in the west direction connecting the site to sector 19 and 24
and running parallel to Najafgarh drain. There are local roads with 2 lane width and intermediate lane
width going towards south which connects with the nearby Barthal and Bijwasan villages. Major
linkages that would have direct impact on the traffic being generated from the ECC are shown below.
i) UER II (100 m ROW) and Site, ii) Dwarka Sector road (Towards Sector 22&23) and Site and iii) Dwarka Sector
road ( towards Sector 19)
The site has good transit connections with the Delhi Metro Station from Sector 21 which is less than a
kilometre away. The line is proposed to extend southwards to Gurgaon, thereby enhancing the
connectivity of the site.
The DelhiRewari railway line is in the proximity of the project site with a railway station at Bijwasan,
which is approximately 3 km from the project site. This railway line connects the south-west parts of the
NCR with Rajasthan, Gujarat, Madhya Pradesh and Punjab.
It has been estimated that the total car parking spaces (Equivalent Car Space (ECS)) required for the
development will be 27, 000. The total area required for these car parks will be approximately 864000
sq. m (32 sqm for each car park). The parking requirement for each land use has been presented in
Table 1-6.
Activity use Area (Sq.m.) Parking (ECS/ 100 Total Parking (ECS)
Sq.m.)
1.3 What are the likely impacts of the proposed activity on the existing facilities adjacent to the proposed
site? (Such as open spaces, community facilities, details of the existing land use and disturbance to the
local ecology).
1.3.1 Impact on Existing facilities
The proposed project is to be developed in an area of 89.72 hectare. The site has been designated for
Public Semi Public use as per the Delhi Master Plan. The project will involve construction of roads and
other infrastructures, green areas, open spaces, commercial spaces etc. With these upcoming
The site area is a flat land with limited vegetation around the site. The survey-area (extending up to 10
km from the boundary of the project site) consists of highly degraded thorn forests, with much of the
land converted into farmland, pasture, plantations, and most of the rest occupied by habitations. The
project construction activities will necessarily comprise of removal of vegetation. Clearing of vegetation
on the site will involve removal of local floral species found on the site.
It is expected that the development of this project, will bring in improvement in the landscape of the
area. It has been planned to plant trees and develop lawns interspersed with project facilities together
with conservation of existing plantations.
1.4 Will there be any significant land disturbance resulting in erosion, subsidence & instability? (Details of
soil type, slope analysis, vulnerability to subsidence, seismicity etc may be given).
The pre-project status with respect to soil characteristics (physical, chemical and bacteriological), land
use pattern in the study area around the proposed project site forms the baseline status of land
environment. A soil sampling program was carried out at representative four locations selected in the
basis of type of land use (nearness to agricultural fields, drainage, source of pollution etc). The details of
soil monitoring locations are given in Table 1-7.
Particulars Details
Frequency One grab sample from each station once during the Study Period
Parameters Texture, % Moisture, % Sand, % Silt, % Clay, % Organic Matter, Bulk Density, pH, Electrical
Conductivity, NKP, Sodium Absorption Ratio, B, Na Pb, Fe, Zn and Water Holding Capacity
Soil sampling was done to establish the baseline characteristics so as to assess the anticipated impacts
due to proposed project. Soil samples were collected using auger from a depth of 30 cm (sub surface)
from the upper surface. Samples were homogenised before testing. The samples were packed in
dependable, waterproof containers and analysed as per ASTM, USEPA, IS: 2720, M.L. Jackson (Soil
Chemical Analysis). The methods adopted for analysis of soil samples for various parameters is given in
Table 1-9. The sampled soil quality results are presented in Table 1-9 and characteristics are described
further.
The results of the soil quality analysis were compared with the standard soil classification provided by
the Indian Council of Agricultural Research (ICAR) and as given in Table 1-11 below.
In qualitatively terms, soil texture refers to the feel of the soil material, whether coarse and gritty, or fine
and smooth. In general, soil behaviour can be inferred from the texture.
At project site and within its 10km radius, soil is found to be Sandy loam as shown in Figure 1-5. The
Sand percentage observed in the soil ranged from 65.9% to 87.3%, silt 1.5% to 17.7 % and clay 10.9 to
16.4% and was observed highest at Project site and lowest at Bamnoli. Water holding capacity ranges
from 42.14 to 48.52% at all soil quality monitoring locations. Total nitrogen content present in the soil
available in the region ranges between 136.3-315.9 mg/kg and phosphorus content was observed to be
below detection limit at all the locations monitored. This indicates that soil in the study area having low
levels of Phosphorus and Nitrogen. Soil in the study area contains very low quantity of Micro-nutrient
such as Copper and Zinc and Manganese. Range for potassium lies between 772.8 2233.92 mg/kg and
sodium ranges between 25.97-164.85 mg/kg. Land parcels can be classified according to its possible
use for irrigation based on soils. As the soils present in study area predominantly is sandy loam, land
can be classified as class 1 i.e., the highest level of irrigation suitability and thus the highest payment
capacity.1
1
http://abe-research.illinois.edu/courses/tsm352/lectures/Soil%20Properties.pdf
The proposed site area is primarily a flat land and is not prone to high level natural erosions. The
proposed construction will involve limited cutting and filling operations. The construction activities will
result in loss of scanty vegetation and some trees. Digging and excavations in the project area would
make the land susceptible to erosion during rainy season. However, these impacts will be limited to
construction phase only. During project operations, green cover/ landscaping will reduce the chances of
erosion and subsidence.
The average plain elevation of the South west district is about 215.5 221.5 meters above mean sea
level. The project site has minimal variations in contour levels with the present topography depicting the
drainage towards the existing Najafgarh drain which is around 3 km in the West direction from the site.
Since limited cut and fill activities are anticipated, no drastic changes in contour levels are expected.
It has been planned to develop a drainage system for collection of storm water for the area. Rainwater
from paved area, lawns and roads shall be allowed to flow through sloping channels /pipes in external
areas. The surface run-off will be connected to the online storm water drainage network connected to
rainwater recharge pits for recharging the ground water. The overflow of the recharge pits shall be
connected to the main storm water trunk line of the entire development.
The map showing natural drainage around the project area is provided in figure below.
It has been proposed that the construction material will be sourced only from authorized quarries in and around
the region. Two quarry sites has been identified which are Badarpur stone quarry and Jaitpur Quarry situated at
26km and 29km approx. from the site in south east direction respectively.
1.6 Give details regarding water supply, waste handling etc. during the construction period.
The water requirement for the construction phase will include water for construction activities such as curing and
formation of concrete mixtures and water for domestic consumption. The water requirement for domestic purpose
and workers at site will be 45litres per person per day (lpcd). The water required for both drinking and
construction activities during the construction phase will be sourced from DJB through water tankers. During
construction, foundation laying, brick-soaking, masonry, curing, concreting, whitewashing, laying of roofs and
3 2
flooring activities require water. It is estimated that about 2m of water will be required per sq m of built up total
area. Hence, the total volume of construction water required for the project during construction phase will be 2.1
MLD.
It is expected that during construction phase, approximately 198 KLD (for about 5500 labourers) of sewage will
be generated. The sewage generated from the portable toilets will be collected in septic tanks which will be
emptied into the main sewerage system of the area. Soak pits will provide at the construction areas to absorb
wash waters and other domestic waste water.
The expected solid waste during construction phase will include two types of wastes i.e. Construction debris and
Domestic solid waste. The waste from construction activities has been estimated to be in the range of 40-60
kg/sq.m3. Construction and demolition (C&D) waste will be stored at the construction site in either skips or
suitable containers and will be directly emptied at the notified disposal site/sites or transported to an available
suitable facility. Waste disposal will be the responsibility of the site contractor.
1.7 Will the low lying areas & wetlands get altered? (Provide details of how low lying and wetlands are getting
modified from the proposed activity).
No. The site area is a flat land. No low-lying areas or wetlands are found in the surrounding area.
1.8 Whether construction debris & waste during construction cause health hazard? (Give quantities of various types
of wastes generated during construction including the construction labour and the means of disposal).
No health hazards are expected during the construction phase. The expected solid waste during construction
phase will include two types of wastes i.e. Construction debris and Domestic solid waste. The type and quantities
of the solid waste generation during construction phase are as follows:
o Construction debris will mainly comprise of excavated soil, rocks, bricks, mortar, metals, wood and
packaging wastes. Such wastes like bricks, stones, mortar will be used to level low lying areas within the
project site which will constitute about 90% of the debris, other wastes like wood packaging material,
metal, jute will be sold to scrap dealers.
o Municipal solid waste will comprise of food waste, packaging wastes generated onsite. This waste will
be properly collected and disposed off to designated disposal site as approved by authority.
o Used Oil from Diesel Generators will be collected on site and would be properly handled and stored in
secure containers. Used oil will be disposed off to CPCB/ DPCC approved designated disposal site.
2
CSE brochure on Green Buildings
3
http://www.tifac.org.in/index.php?option=com_content&view=article&id=710&Itemid=205
2. Water Environment
2.1 Give the total quantity of water requirement for the proposed project with the breakup of requirements for various
uses. How will the water requirement be met? State the sources & quantities and furnish a water balance
statement.
Construction Phase
The water required for both drinking and construction activities during the construction phase will be sourced from
DJB through water tankers. During construction, foundation laying, brick-soaking, masonry, curing, concreting,
whitewashing, laying of roofs and flooring activities require water. It is estimated that about 2m 3 of water will be
4
required per sq m of built up total area. Hence, the total volume of construction water required for the project
during construction phase will be 2.1 MLD.
Operation Phase
Water Sourcing
It is proposed that during operation phase, water requirement for the entire development will be met from the
Main Supply of DJB. Water will be sourced out of the six underground reservoirs (UGRs) planned for Dwarka as
per the MPD-2021. These UGRs have an individual capacity to cater to a population of 0.15-0.20 million
populations, with a reserve quantum to meet the demand for commercial area development.
Phase-wise water requirement for ECC has been calculated for domestic requirements (Visitor population water
demand, employee water demand, and other water demand for each component of planned ECC).
Water requirement for various project components is presented in Table 2-1 : and Table 2-2. It has been
estimated that the total water demand of the project is approx. 10.2 MLD water (4.2 MLD for Phase I and 6.0
MLD for Phase II). This will be met by using fresh water 4.9 MLD (2.0 MLD for Phase I and 2.9 MLD for Phase II)
and recycled treated sewage water 5.3 MLD (2.2 MLD for Phase I and 3.1 MLD for Phase II). Fresh water will be
used for domestic purposes. Waste water will be treated in two planned STPs (2.75 MLD for Phase I and 3.95
MLD for Phase II) and the treated waste water will be used in landscaping, HVAC cooling tower. Water Balance
for both the phases is presented in Figure 2-1 and
4
CSE brochure on Green Buildings
S. No. Description Visitor Visitor Water Employee Employee Water Other Water Gross Water 80% Flow to
Population Requirement Population Requirement @ 45 litrs Requirement Requirement Sewer
per person (LPD)
i. Exhibition Centre BUA= 37260 Sqm. 41,918 251,508 207 9,315 5,000 265,823 212,658
Water requirement @6 litrs per person for visitor
ii. Convention Centre BUA= 60000 Sqm. 6,000 36,000 440 19,800 - 55,800 44,640
Water requirement @6 litrs per person for visitor
iv. Hotel (5 Stars) Keys =600 600 600,000 1,372 61,740 661,740 529,392
1000 ltrs per key
v. Hotel (4 Stars) Keys =187 187 84,150 320 14,400 98,550 78,840
450 ltrs per key
vi. Hotel (Budget) Keys =350 350 157,500 480 21,600 179,100 143,280
450 ltrs per key
vii. Commercial (Retails) BUA= 144600 Sqm. 106,324 637,944 6,379 287,055 - 924,999 739,999
Water requirement @6 litrs per person for visitor
viii. Commercial (Office) BUA= 85400 Sqm. - - 14,686 660,870 - 660,870 528,696
Water requirement @45 litrs per person
Total water requirement 1,768,416 1,074,780 2,848,196 2,278,557
Treated water available from the STP @ 95% of total sewer 2165 KL/Day
generation.
80% discharge as
sewage 95% treated waste water
Sewage
Generated
2279 KLD
S. Description Visitor Population Visitor Water Employee Employee Water Other Water Gross Water 80% Flow to
No. Requirement Population Requirement @ 45 litrs Requirement Requirement (LPD) Sewer
per person
i. Exhibition Centre BUA= 162740 Sqm. 183,083 1,098,498 903 40,635 15,000 1,154,133 923,306
Water requirement @6 litrs per person for
visitor
ii. Arena (Theme Destination)BUA= 50000 25,000 150,000 760 34,200 5,000 189,200 151,360
Sqm.
Water requirement @6 litrs per person for
visitor
iii. Grand Foyer BUA= 47260 Sqm. 3,781 22,685 - 22,685 18,148
Water requirement @6 litrs per person for
visitor
iv. Hotel (5 Stars) Keys =700 700 700,000 1,601 72,045 772,045 617,636
1000 ltrs per key
v. Hotel (4 Stars) Keys =613 613 275,850 1,052 47,340 323,190 258,552
450 ltrs per key
vi. Hotel (Budget) Keys =650 650 292,500 892 40,140 332,640 266,112
450 ltrs per key
vii. Service Apartment Keys =500 500 100,000 572 25,740 125,740 100,592
200 ltrs per key
viii. Commercial (Retails) BUA= 25400 Sqm 18,676 112,056 1,121 50,445 - 162,501 130,001
Water requirement @6 litrs per person for
visitor
ix. Commercial (Office) BUA= 129600 Sqm. - - 22,288 1,002,960 - 1,002,960 802,368
Water requirement @45 litrs per person
Total water requirement 2,751,589 1,313,505 4,085,094 3,268,075
Treated water available from the STP @ 95% of total sewer 3106 KL/Day
generation.
80% discharge as
sewage 95% treated waste water
Sewage
Generated
3269 KLD
There shall be separate provision of 1.5 days water storage capacity for ECC project. The incoming Main from
municipality water supply line shall be led into centralized Fire tanks with an overflow connection to raw water tanks;
thereafter the water shall be treated and stored in domestic water storage tanks.
Water Treatment
Water treatment plant shall be provided in accordance with the various requirements of use as mentioned below:
1. Domestic Water: Treated water sourced from the Municipal Corporations Mains shall be further passed
through pressure sand filter with dosing systems for disinfection. Further specialized treatment, may be
provided based on the source water analysis report. Water shall be used for domestic usage in toilets, wash
room (wash basin and health faucet), Kitchen (for dishwashing etc), Water Body makeup and other areas
where direct human contact / use is envisaged.
2. Ultra-Soft Water: Part of domestic water shall be passed through a polishing softener and stored in a separate
soft water tank located within Boiler plant room space. This will be used as feed water for steam boilers and
pre-fab compressors in Kitchen.
3. Soft Water: Provision of polishing softener and activated carbon filter shall be made to ensure the chemical
limit of make-up water requirement of air conditioning cooling towers is acceptable.
4. Flushing Water: In accordance with Client brief, Flushing water for the 89.72 Ha. Development shall be
sourced from the Centralised STP and shall have acceptable parameters as per governing requirement.
Water Distribution
Central Utility Building
Centralized Underground water storage tanks are proposed to be provided for firefighting, domestic, flushing, irrigation &
soft water and pump room housing fire pumps, water treatment plant, and hydro-pneumatic system and pumping system
for the entire master plan in the basement of Central utility building. The treated recycled water (Non potable water) for
89.72 Ha developments shall be provided from sewage treatment plant.
Domestic and flushing water supply of 89.72 Ha developments shall be fed by respective hydro-pneumatic systems
through ring mains. Following systems have also been proposed:
Solar hot water system shall be installed which shall contribute 20% of the total hot water demand.
Water will be fed at constant pressure by hydro-pneumatic system for the following uses:
2.2 What is the capacity (dependable flow or yield) of the proposed source of water?
As per MPD 2021, 22.0 MGD (100MLD) of water is allocated for commercial usages in Dwarka. Six underground
reservoirs (UGRs) have been planned for Dwarka as per the MPD-2021, with an individual capacity to cater to a
population of 0.15-0.20 million populations, with a reserve quantum to meet the demand for this area development. It
has been planned to source water from these six UGRs.
2.3 What is the quality of water required, in case, the supply is not from a municipal source? (Provide physical, chemical,
biological characteristics with class of water quality).
Not applicable since the water requirement will be sourced from main supplies of Delhi Jal Board (DJB).
2.4 How much of the water requirement can be met from the recycling of treated wastewater? (Give the details of quantities,
sources and usage).
The expected waste water generation from the project is 2.75 MLD from Phase I and 3.95 MLD from Phase II. It is
proposed that sewage will be treated to various degrees to be used for flushing, irrigation and as make-up water in
cooling towers of air conditioning system and of DG sets and for horticulture for external areas with no or minimal
effluent to external sewage system.
The water balance diagram shows recycling of treated water has been presented in Figure above.
2.5 Will there be diversion of water from other users? (Please assess the impacts of the project on other existing uses and
quantities of consumption).
As the water for the proposed project will be sourced from municipal supply i.e. water supply diversion of water from
other sources is not anticipated.
It has been proposed that two STPs will be installed with capacities 2.75 MLD for Phase I and 3.95 MLD for Phase II
respectively.
The treated effluent from the Sewage Treatment Plant (STP) shall be stored in treated water storage tank. The treated
water is to be used for the cooling tower make up and horticulture purpose. Excessive sludge shall be stored in the
sludge holding tank for final dewatering and disposal through screw pump and filter press / centrifuge. The parameter
which shall be adopted for the design of sewage treatment plant is presented in Table2-3.
1. pH 6.5 8.5
2. TSS <= 10 mg/lt
3. B O D (5 days at 20 deg. C) <= 10 mg/lt
4. COD <= 60 mg/lt
5. TDS <= 1000
6. Turbidity < 1.0 NTU
7. E. Coli Removal to the level of log 6
2.7 Give details of the water requirements met from water harvesting? Furnish details of the facilities created.
To minimise localised flooding during monsoon season, perforated pipe drainage system has been planned for open-to-
sky courtyard/ lawn. Rainwater from paved area, lawns and roads shall be allowed to flow through sloping channels
/pipes connected to the online storm water drainage network. The rainwater shall be conveyed into the rainwater
harvesting tanks/pits. The overflow of the rainwater harvesting tanks/pits shall be connected to the main storm water
trunk line of the entire development.
The total water harvesting potential for the proposed project has been calculated using the formula as below:
Table 2-4 : Rain water Harvesting Potential for the proposed Exhibition and Convention Centre
Land use Area. (Ha.) Total runoff generated/
(cum/hr), Q
Roof Top Area 27.00 (approx.) 5063.76
2.8 What would be the impact of the land use changes occurring due to the proposed project on the runoff characteristics
(quantitative as well as qualitative) of the area in the post construction phase on a long term basis? Would it aggravate
the problems of flooding or water logging in any way?
The proposed project will include paved areas and thus, the runoff from the plot is expected to increase due to reduced
infiltration though the quality of the run off is expected to improve due to low sediment level and thus require minimal
2.9 What are the impacts of the proposal on the ground water? (Will there be tapping of ground water; give the details of
ground water table, recharging capacity, and approvals obtained from competent authority, if any).
2.10 What precautions/ measures are taken to prevent the run-off from construction activities polluting land & aquifers? (Give
details of quantities and the measures taken to avoid the adverse impacts).
Adequate control measures have been proposed to check the surface run-off, as well as uncontrolled flow of water into
any water body. The following management measures are suggested to protect the water quality during the construction
phase.
2.11 How is the storm water from within the site managed? (State the provisions made to avoid flooding of the area, details of
the drainage facilities provided along with a site layout indication contour levels).
The storm water manholes will be planned all along the peripheral roads of each facility. The manholes will be connected
through a network of drains (of 450mm to 600mm diameter) for collection and transfer to rainwater harvesting system.
Storm water network will be provided all along the roads. Separate storm water drainage system will be provided for
collecting rainwater from roof and stored in underground tanks. Overflow from these storage tanks and all the surface
runoff shall be connected to the storm water network which will be directed to the recharge pits.
2.12 Will the deployment of construction labourers particularly in the peak period lead to unsanitary conditions around the
project site. (Justify with proper explanation).
No. Mostly local laborers will be employed during the construction phase and thus very little quantities of wastes will be
generated. Community toilets will be provided along with a septic tank to avoid unsanitary conditions.
2.13 What on-site facilities are provided for the collection, treatment & safe disposal of sewage? (Give details of the quantities
of wastewater generation, treatment capacities with technology & facilities for recycling and disposal).
It has been proposed that two STPs will be installed with capacities 2.75 MLD for Phase I and 3.95 MLD for Phase II
respectively. The treated effluent from the Sewage Treatment Plant shall be stored in Treated water storage tank. The
treated water is to be used for the cooling tower make up and horticulture purpose. Excessive sludge shall be stored in
the sludge holding tank for final dewatering and disposal through screw pump and filter press / centrifuge.
2.14 Give details of dual plumbing system if treated waste is used for flushing of toilets or any other use.
The treated effluent will be reused for flushing of toilets and for gardening. Unutilized treated effluent, if any, shall be
discharged into the municipal sewerage network which is available around the proposed site with all necessary
permissions and approvals. Reuse of treated effluent within the complex will reduce the overall requirement of fresh
water.
At present, the site area seems to support relatively low biodiversity, with its existing vegetation being of relatively low
ecological value. However, no significant vegetation and biodiversity was found in the immediate site area and hence
there will be no major threat to the biodiversity due to the development of the project.
3.2 Will the construction involve extensive clearing or modification of vegetation? (Provide a detailed account of the trees &
vegetation affected by the project).
The project construction activities will necessarily comprise of removal of vegetation. This loss of herbaceous ground
cover will be compensated by development of green spaces.
3.3 What are the measures proposed to be taken to minimize the likely impacts on important site features (Give details of
proposal for tree plantation, landscaping, creation of water bodies etc along with a layout plan to an appropriate scale)
Recommendations regarding plantation at and around the Project-site:
Suggested Shrub-species (Names in brackets are the most common vernacular names)
4. Fauna
4.1 Is there likely to be any displacement of fauna - both terrestrial and aquatic or creation of barriers for their movement?
Provide the details.
No displacement of fauna is anticipated. During the construction period, these species might get temporarily disturbed or
even migrated to nearby areas for a very brief period. The proposed peripheral greenbelt will provide an excellent habitat
for these species once it is fully developed.
4.2 Any direct or indirect impacts on the avifauna of the area? Provide details.
The region falls in the path of the various winters, summer and passage migrant birds entering the Indian subcontinent
through Pakistan via the Indus Valley and headed farther south. As the construction activities will be carried for only a
short duration, no significant impact on avifauna is anticipated.
4.3 Prescribe measures such as corridors, fish ladders etc. to mitigate adverse impacts on fauna.
Not applicable. The proposed project would not have any adverse impact on fauna. The peripheral green belt planned
will provide a suitable habitat for small group of faunal species.
CO, NOx and SPM are the primary pollutants anticipated as tailpipe emissions from light vehicles travelling along on-site
paved roads.
The basic considerations while designing this air quality examination programme included:
Topography;
Representative location w.r.t upwind and downwind directions;
Representative location w.r.t regional background eg. semi-urban, rural area;
Ecologically sensitive locations within 10 km;
Availability of source of Power; and
Accessibility.
AAQ monitoring equipment were placed at sensitive receptors (i.e. within nearby villages), where safety and power were
provided. Monitors were placed on one-storey dwellings, away from major roads and nearby flow obstructions (i.e.
trees).
The parameters to be monitored, frequency and number of samples taken at each station are presented in the table
below .
The protocol and analysis procedures followed to examine the collected samples were as per IS-5182 (Indian Standards
for Ambient Air Quality Parameters). The applied testing procedures are given in brief in Table 5-3.
Table 5-3: Brief summary of the Methodology followed for Analysis of Ambient Air Quality
Sr. No. Pollutant Code of Practice Methods of Measurement
The analysis of the above results clearly shows that all the monitored values exceed the limits prescribed by Central
Pollution Control Board for PM 10 and PM2.5 respectively. The summary of results is presented in the following sub
sections.
Inferences
The PM-10 concentration recorded at all the five sampling locations exceeds the limits of prescribed CPCB limits of
100g/m3. The minimum value recorded was 109.5 g/m3 at Project site (AQ-1). The maximum value recorded was
3 3 3
419.7 g/m at Kapashera (AQ-5). The 98 percentile values ranged from 272.6 g/m to 418.2 g/m . The average
3 3
values varied from 186.4 g/m to 290.7 g/m . The graphical representation is provided in Figure 5-2
5.2 What are the impacts on generation of dust, smoke, odorous fumes or other hazardous gases? Give details in relation to
all the meteorological parameters.
With implementation of the proposed air quality management plans, there will be limited generation of dust, smoke,
odorous fumes, which too will be limited to the construction phase of the project. The meteorological conditions
prevalent in the area and the micrometeorology of the study area have been presented below. The impacts on air quality
have also been addressed later in the section.
The long-term climate trend data was obtained for the years (2007-2011), from the closest Indian Meteorological
Department (IMD) surface station at IGI Airport, Palam, and Delhi. Mean monthly normal of atmospheric parameters,
wind roses for each month giving the wind direction speed were collected and have been presented in Table 5-5. Most
probable wind speed class and wind direction in the area has been assessed and presented. Hourly-based recorded
meteorological data has been further employed for dispersion modelling for air quality impact assessment.
Table 5-5: Climatological Summary (obtained from nearest IMD MET Station at Palam (2007-2011))
B. Precipitation
The data obtained from IMD station at Palam for the average annual rainfall in the years 2007-2011 has been presented
in Table 5-6 below.
Table 5-6: Annual Rainfall (mm) at the nearest IMD MET Station
2007 620.0mm
2008 718.3mm
2009 462.0mm
2010 979.4mm
2011 412.1mm
Source: IMD, Years 2007-2011
The rainfall is fairly well distributed throughout the monsoon season starting from July which ends in September; with
annual average rainfall over period of five years is 532mm.
During the summer months of April, May and June, temperatures rises to 40-45C; winters are typically cold with
temperatures during December and January falling to 4 to 5C. February, March, October and November are climatically
the best months. The average of mean monthly maximum temperature as assessed from the Climatological data
gathered from IMD surface station at IGI Airport, Palam, Delhi is 30.4C and average of mean monthly minimum
temperature is 14.1C. The average of monthly relative humidity is 61.5%.
Ground level pollutant concentration is inversely proportional to the wind speed. It can be referred from Table 5-7 below
that the wind speed is maximum in the month of May and blows at a speed of 13.09 kmph whereas month of November
experiences lowest wind speed being 5.36 kmph. The predominant wind direction is North West.
The predominant wind direction in May (during hot & dry condition) is North-West and in June & July (during monsoon
season) the predominant wind direction is from Southeast.
E. Mixing Height
Mixing Height (MH) is the vertical extent through which the contaminant plume can be mixed. During the winter, average
mixing height is lower as compared to other seasons and atmospheric dispersion is typically at a minimum and therefore
the pollutants will not be as widely dispersed. During the summer months, the average mixing height is typically at its
greatest resulting in increased mixing through a greater volume of the troposphere, and hence lower pollutant
concentrations.
As studied from secondary data, the monthly average mixing height over Delhi varies from 100-1200 meters.
An automatic micro-meteorological station was installed at the project site (Bamnoli village) to record hourly
meteorological parameters for a period of 8 weeks. On-site meteorological data was collected in respect of wind speed,
direction, temperature, humidity and rainfall and is presented below in Table 5-8 :
G. Wind Rose
During the monitoring period, the direction of the wind is predominantly from West followed by West North west and
West South West same as long terms trend. The average wind speed during the monitoring period was observed as
2.26m/s and a very low calm period of 0.26% is reported. The wind rose diagram for the study period is presented in
Figure 5-8.
Construction Phase
During the construction phase, the major pollutant of concern will be particulate matter (PM10 and PM2.5).The dust
emissions will vary substantially from day to day based on the level of activity, the specific operations and the prevalent
meteorological conditions. The construction activities will involve:
The excavation activities for the Project shall be carried out in phases. Power shall be sourced from the grid during the
construction activities; DG will be used for power back-up.
Operation Phase
The likely sources of air emissions can be due to:
Operation of Diesel Generators in case of emergency power back up; and
Vehicular movement in the area.
The diesel generators will be pertinent to the site operations as an emergency power back up, i.e. only during power
failure. While, emissions due to traffic to and from the project site will be to and from different directions on the expressway
for a short period during morning and evening hours.
Mitigation Measures
Impact Significance
The overall impact on ambient air quality is assessed to be moderate. It is assessed that with implementation of
suggested mitigation measures the overall impact on ambient air quality can be maintained as minor.
It has been estimated that the total car parking spaces (Equivalent Car Space (ECS)) required for the development will be
27, 000. The total area required for these car parks will be approximately 864000 sq. m (32 sqm for each car park). The
parking requirement for each land use has been presented in Table 5-9.
Activity use Area (Sq.m.) Parking (ECS/ 100 Total Parking (ECS)
Sq.m.)
It has been proposed that the car paring will be constructed in the basement area of project facilities. Parking area with
entry points have been shown in Figure 5-9 below. Service access to the Exhibition Centre does not conflict with other
vehicular access onsite and has an unobstructed route to the exhibition halls.
The proposed 100m ROW UER II will be connecting the National Highway No.8 (NH 8) and National Highway No. 1
(G.T. Karnal Road) crossing National Highway No. 10 (Rohtak Road) and passing from NH 8 (Gurgaon Road) via
Dwarka Sub-city-Village Bhartal-Village Dhulsaras - Village Chhawla - Village Tajpur - Village Goyla Khurd-Deenpur-
Roshanpura-Najafgarh-Masoodabad-Village, Nangli Sakrawati- Village Dichaon Kalan-Village Baderwara and village
Mundka connecting NH 10 Rohtak Road).
A third concentric circle to ring road that runs parallel to the UER II (as mentioned above) is also proposed by DDA and
also under the road development plan for NCR; which is referred to as Urban Extension road one (UER I).
The Transport Department of the NCT of Delhi has proposed to develop an Interstate Bus Terminal (ISBT) is located
towards the north-east side of the site. It is envisaged that this terminal will help decongest traffic by restricting buses
from Haryana and Rajasthan to Delhi with handling capacity of 60,000 daily passengers.
The land adjoining to MRTS sector 21 station is with Indian railways (IR) and is proposed for Integrated Metropolitan
Passenger Terminal (IMPT). The IMPT has been proposed to decongest the existing New Delhi and Old Delhi railway
station.
It has been proposed to develop internal roads of various hierarchies. The details of internal road for ECC are presented
in Table 5-10 below.
The entry points for trucks / multi-axle vehicles carrying display materials/ supplies to the exhibition/conference have
been proposed from the west side of the development. This will enable loading/ unloading of the supplies in proximity to
the 10 proposed exhibition halls. The entry points for personal vehicles such as cars have been proposed from west and
north direction with rest the project site. The proposed entry points have been shown in Figure 5-11. The figure shows
the entry of vehicles from the planned roads networks along the east and north boundaries as well as serving access
from the west. The expressway access the north-west and south-east will include grade separated routes and will
provide access to basement car park areas serving exhibition, convention and arena.
The movement of traffic entering the site shall be properly managed so as to cause minimum problems
to local users on this road;
The EPC contractors will undertake consultation with local Police and local Panchayat prior to
movement of the construction traffic particularly for the movement of heavy machinery;
The construction vehicles shall be allowed to move in the site only through exclusive entry and exit
points;
Adequate training shall be given to the drivers of construction vehicles for speed restrictions; and
Roads damaged due to project vehicle shall be repaired and maintained at regular intervals during the
construction period.
This includes various transport improvement strategies, in order to reduce the traffic congestion due to
goods and passenger movement on the roads connecting to the project site. In order to accommodate the
increased traffic, following measures have been suggested:
A highway patrol shall be established to manage the traffic within the region
Hierarchy in roads should be adopted to segregate the traffic according to the size, frequency and
density of traffic. During events at ECC, primary access shall be from the existing Palam flyover; while
for Gurgaon and further south of Gurgaon, it shall be through the proposed Dwarka Expressway. For
the traffic from Uttam Nagar and Janakpuri side, access shall be made from the primary roads on the
western end of Dwarka Sub-city
The number of existing lane on the roads connecting to the airport shall be increased to accommodate
the increasing traffic on the road
Comprehensive traffic and travel surveys shall be conducted every 5 years to monitor traffic
characteristics and travel behaviour to develop strategies for effective transportation.
Improvement Plan
Widening of all the primary roads and the local village roads connecting Badli Najafgarh Dwarka to
enhance the accessibility to the site and carry the existing and anticipated future traffic loads;
Proposed grade separators to all major interchanges
Pedestrian facilities shall be planned for movement of pedestrians on all major corridors and junctions in the
study area. The pedestrian facilities which shall be provided for the safe movement of pedestrians are
The parking facilities shall be developed as per the guidelines and provisions of Delhi Master Plan (DMP)
2021.
It has been proposed to develop internal roads of various hierarchies. The details of internal road for ECC
are presented in Table 5-11 below.
The entry points for trucks / multi-axle vehicles carrying display materials/ supplies to the exhibition/conference
have been proposed from the west side of the development. This will enable loading/ unloading of the supplies
in proximity to the proposed exhibition halls.
5.5 Will there be significant increase in traffic noise & vibrations? Give details of the sources and the measures
proposed for mitigation of the above.
Sources of Noise Pollution during Construction and Operation Phase
During the construction phase of the site, the sources of noise pollution are expected mainly from:
Construction equipments and machinery engaged for construction activities (such as excavation,
grading, erecting equipment, piling, etc) such as air compressors, backhoe, concrete mixer,
concrete mixer, cranes, dump-truck, pile driver, radial arm saw, DG set etc. The operation of heavy
equipment is likely to temporarily increase the ambient noise levels of the area.
An increase of 1 to 3 dB (A) noise levels of is expected in the adjoining area during day time during
peak construction activities. The trucks/ vehicles carrying construction material, machinery and
equipment
Noise generated from the Aircraft can also be a cause for physical and mental fatigues to the
people residing / using the ECC facilities.
Anticipated Impact
Noise generated can cause disturbance to the local population and can even lead to sleep disorder.
Workers working close to high noise area can be exposed to occupational hazards of noise
depending on the duration of exposure.
Mitigation Measures
The project will ensure that the EPC contractors should implement the following:
The construction areas shall be provided with sheet barriers or temporary walls along the boundary
close to any habitations;
Rubber padding shall be provided in the construction machinery for vibration control;
No noise generating activity shall be permitted from 22:00P.M-6:00AM ;
The EPC contractors will adopt measures such as regular maintenance of its vehicles and repair of
its equipment/ machinery.
Construction workers working near high noise generation shall be provided with ear plugs/ ear
muffs to limit exposure to occupational hazards.
Sound attenuators / acoustic lining shall be installed in the exhibition halls and convention centers.
Acoustic performance of the attenuators (net insertion loss) should meet or exceed the specified
values.
5.6 What will be the impact of D.G sets & other equipment on noise levels & vibration in & ambient air quality
around the project site? Provide details.
All DG sets shall be with acoustic enclosure and radiation cooled type. The noise level from DG
sets will not exceed 75dB (A) at 1m distance, during daytime and 70dB (A) during night time.
Independent flue pipe from each DG shall be taken out up to the highest level as per the
acceptable norms. Stack height for the flue pipe from the DG sets shall be as per CPCB norms.
6. Aesthetics
6.1 Will the proposed constructions in any way result in the obstruction of a view, scenic amenity or landscapes?
Are these considerations taken into account by the proponents?
The site falls in a peri-urban setup and will not result in obstruction of view, scenic amenity or landscape.
However, the green spaces planned will enhance the scenic view of the area.
6.2 Will there be any adverse impacts from new constructions on the existing structures? What are the
considerations taken into account?
The proposed project no adverse impact is anticipated on the existing structures due to the proposed
development. As per recent Notification of Ministry of Urban Development (MoUD) dated 12 May 2016, the
land use of 89.72 ha of land area (excluding any existing structures/ acquired land) was changed from
Commercial (Category C-2) to Public Semi Public (PS-1, socio-cultural facilities).
6.3 6Whether there are any local considerations of urban form & urban design influencing the design criteria?
They may be explicitly spelt out.
The project will follow Delhi Master Plan 2021, the applicable norms, laws and guidelines. The proposed
developments are also being planned in accordance with the DDA regulations and norms laid down in
National Building Code. As per recent Notification of Ministry of Urban Development (MoUD) dated 12 May
2016, the land use of 89.72 ha of land area (excluding any existing structures/ acquired land) was changed
from Commercial (Category C-2) to Public Semi Public (PS-1, socio-cultural facilities).
6.4 Are there any anthropological or archaeological sites or artifacts nearby? State if any other significant
features in the vicinity of the proposed site have been considered.
There are no anthropological or archaeological sites or artifacts near the site area.
7. Socio-Economic Aspects
7.1 Will the proposal result in any changes to the demographic structure of local population? Provide the
details.
The project area is spread across Sector 25 of Dwarka in the National Capital Territory (NCT) of
Delhi commonly known as Dwarka sub city in the South West District (also known as the study
7.2 Give details of the existing social infrastructure around the proposed project.
The social infrastructure indicates the development pattern of the area. The site is very near to the
National Highway 8 and is connected by a Link Road. Besides this, there is a DelhiAhmedabad
railway line which provides connectivity to the Bijwasan Railway Station at an approximate distance
of 3 km. This railway line connects the south west parts of the NCR with Rajasthan, Gujarat,
Madhya Pradesh and Punjab.
There is also an excellent transit connection in terms of the Delhi Metro Station from Sector 21
which is less than a kilometre away from the site and an Inter State Bus Terminal (ISBT), located in
Sector 22, is diagonally opposite the proposed ECC site.
Some of the higher educational institutes within 10 km of the site are Netaji Subhas Institute of
Technology, National Law University, Ambedkar University and Indian Institute of Health
Management Research. Further, some of the hospitals in close proximity are Bensups Hospital,
Aarogya Medical Center and Artemis Medical Center.
7.3 Will the project cause adverse effects on local communities, disturbance to sacred sites or other cultural
values? What are the safeguards proposed?
The project will not cause any adverse effects on the local communities.
Ministry of Urban Development (MoUD) has issued a notification dated 12 May 2016 regarding
change in the land use of 89.72 ha of land area (excluding any existing structures/ acquired land)
which is changed to Public Semi Public (PS-1, socio-cultural facilities) from the previous
Commercial (Category C-2)
Positive Impacts
With the onset of new project activities, employment opportunities might increase among the local
population. The unskilled local population of the adjoining areas will find job opportunities as
drivers, security guards, cleaners, housekeeping etc. which will improve their economic condition.
With the coming up of the project, there will be more transport facilities in the area thus, benefitting
the population living in the area in the long run.
With the proposed activities, the sewage facilities in the area will be improved, enhancing the
overall sanitation condition in the area .
Semi-skilled people proficient in handling small motor parts and light machineries among the local
adjoining population might be recruited for certain activities. This will not only open the gateway for
further skill development programs which can be initiated in the area but it will also give a
confidence boosting among the population on the benefits of the project;
8. Building Materials
8.1 May involve the use of building materials with high-embodied energy. Are the construction materials
produced with energy efficient processes? (Give details of energy conservation measures in the selection of
building materials and their energy efficiency).
The Exhibition-cum-Convention Centre (ECC) has been planned incorporating green building principles and
ECBC (Energy Conservation Building Code) standards. The project will include eco-friendly design, energy
efficient systems, state of the art technology and compliance to all statutory regulations. It has been
proposed to incorporate solar passive techniques in a building design to help minimize load on conventional
systems such as heating, cooling, ventilation & light. Following will be considered to achieve a solar passive
building design:
The project will incorporate green vegetated roofs on the commercial office buildings in order to reduce
external heat gains from the roof top.
The project can discharge around 20% of the total heat to the ground using geothermal wells. The
ambient air ventilated through this tunnel will get cooled in summer and warmed in winter.
30% extra fresh air over minimum requirements of ASHRAE 62 for well-being of occupants in exhibition
halls, commercial and hotel buildings
Optimised insulation will be done in building envelope (walls & roof) to reduce external heat gain for
better energy efficiency and reduced air-conditioning loads;
Mixed mode ventilation for free cooling in exhibition halls, convention centre and arena during
favourable weather conditions is proposed;
HVAC will be integrated with geo-thermal for higher energy efficiency as depicted in figure below:
Figure 8-1: Broad HVAC Design Strategies
8.3 Are recycled materials used in roads and structures? State the extent of savings achieved?
For this project, materials with recycled content will be considered such that the recycled content constitutes
at least 5%-10% of the total value of the materials.
8.4 Give details of the methods of collection, segregation & disposal of the garbage generated during the
operation phases of the project.
The collection and transportation of the solid waste generated during the operational phase of the project will
be as follows:
Municipal solid waste: a total of 75-80 tons of municipal waste is expected to be generated during peak
season from ECC (Phase 1 and Phase 2) after project commissioning.
During the non-peak season, it has been assumed that approximately 20% of the visitors will still visit
the ECC. Waste generated by these visitors, in addition to waste generated by the regular staff and
other areas will result in generation of approximately 23 25 TPD waste daily.
E-Waste Management: A plan for e-waste management shall be formulated which shall comply with the
requirements of E-waste (Management) Rules, 2016. All the e-waste generated within ECC to be
channelized through authorized collection center(s) or registered dismantler(s) or recycled or to be
returned to the pick up or take back services provided by the producers.
ECC to maintain records of e-waste generated, and make these records available for scrutiny by State
Pollution Control Board (SPCB) or the Pollution Control Committee (PCC) concerned.
Green waste collected from landscaped areas shall be disposed of through private waste collection
agencies or shredded and processed using a controlled composting technology to produce compost/
manure and use within ECC complex. Options shall be evaluated at the planning stage and finalized
after approval from the project proponent.
For biodegradable waste disposal, options shall be evaluated including disposing of the wastes
through waste pick up services facilitated by the local municipal corporation, or through portable
organic waste composter machines within the premises to produce compost, which can be used in the
landscaped areas; along with setting up small modular units of biogas plant (biogas generated can be
used for captive uses such as pantry/ kitchen of ECC);
A detailed assessment shall be carried out including area required, technical specifications, capital
expenditure, O&M costs etc.
9. Energy Conservation
9.1 Give details of the power requirements, source of supply, backup source etc. What is the energy
consumption assumed per square foot of built-up area? How have you tried to minimize energy
consumption?
The power demand is calculated after considering the different types of needs for heating, lighting, and
cooling facilities/ requirements for different land uses and power assumptions. Many of the services in the
Exhibition Centre, Convention Centre, Arena (Theme Destination) will be unmanned and fully automated,
requiring a significant amount of electrical power.
DG power backup shall be provided for the Exhibition Halls, Convention Centre, Arena, Administration and
common utility complex only.
Gas Insulated Substation (GIS) shall be provided with 3 No. (2 working & 1 standby) ONAN (oil natural air
natural) / ONAF (oil natural air force ventilation Transformers. On load tap changer shall be provided for
power transformers for better voltage regulation. Individual building shall receive the required power supply
from these substations at 11 kV through U/G XLPE Cables in trenches in ring mains configuration.
Generators shall be provided as back up to grid power, in case of grid power failure. Emergency power
generators shall produce power at 11 KV to exhibition halls, arena administration and common utility. All 11
kV generators shall be located in the planned energy centre, so that with auto changeover system shall
supply power from the main Gas Insulated Substation (GIS) to each local 11 KV sub-station located in
nearby building of exhibition halls, arena administration and common utility. 11 kV HT supply shall be feed
direct from the GIS by step down of voltage to other buildings in complex. HT Metering will be provided for
both feeders.
It has been proposed that the following buildings shall be provided with Emergency power back-up at 11 kV
through following DG sets at the following locations.
Table 9-1 : Emergency Power Back-up units for various land use for Phase I & II
3 Hotel (4 Star) _ 2 No. 1000 kVA & 2 No. 750 kVA & 1 No. 380 kVA
6 Retail _ 7 No. 2000 kVA & 2 X 1500 KVA 1 X 1000 KVA &
1 No. 250 kVA
7 Office _ 2 No. 1500 kVA & 8 No. 1000 kVA & 9 No. 750
kVA & 1 No. 500 kVA & 2 No. 320 kVA
Note: Nos. of DGs are based on the broad estimate and may change during operation phase.
DG sets shall be with acoustic enclosure and water cooled type. All DG sets shall be synchronized and shall
be capable of restoring power supply within 10-15 seconds of disruption (black-out or brown-out) of city
power.
Independent flue pipe from each DG set shall be taken out up to the highest level. The noise level from DG
sets will not exceed 75 dB (A) at 1 m distance, during day time and 70 dB (A) during night time. Stack height
for the flue pipe from the DG sets shall be as per CPCB norms.
9.2 What type of, and capacity of, power back-up do you plan to provide?
9.3 What are the characteristics of the glass you plan to use? Provide specifications of its characteristics related
to both short wave and long wave radiation?
Energy efficient double glazing windows shall be used for the project since they offer superior thermal
performance (Reduced solar heat gain) and help in significantly reducing unwanted external noise of traffic.
The specification of the glass used for the project is provided in Table 9-2.
9.4 What passive solar architectural features are being used in the building? Illustrate the applications made in
the proposed project./check ventilation
It is recommended to provide solar shading panels to block harsh summer & mid-season radiation while
allowing winter radiation in open exhibition space.
Commercial area: Streets in the commercial area shall be widened to allow more solar exposure during
the winter day time to improve social interaction. Temporary shades and deciduous trees can also be
used in the streets of commercial area to provide shade during summer and mid-season;
Double glazed units for all external glazing to prevent solar heat gain inside the building
Solar PV on roof of exhibition halls can generate electricity that can offset significant amount of internal
lighting requirement of the whole project;
Window areas shall be optimized in commercial and hotel buildings for daylight and for well-being of
occupants
9.5 Does the layout of streets & buildings maximize the potential for solar energy devices? Have you considered
the use of street lighting, emergency lighting and solar hot water systems for use in the building complex?
Substantiate with details.
Yes. It is proposed to install solar panels for street lighting. The layout has been designed to maximize
the potential for solar energy devices. Street lighting will be provided as per the required guidelines.
Emergency Lighting shall be installed in staircase while 20% lighting will be provided in circulation
space, corridors, lift, and lobby and plant room through UPS supply having 15 minutes battery backup.
9.6 Is shading effectively used to reduce cooling/heating loads? What principles have been used to maximize
the shading of Walls on the East and the West and the Roof? How much energy saving has been effected?
The following techniques have been adopted to reduce cooling/heating loads:
Solar shading shall benefit by reducing external solar heat gains through windows.
Fixed sun louvers shall be provided on the South West, West and east facades so that it blocks harsh
summer and mid-season radiation while allowing winter radiation in open exhibition space.
The project will incorporate green vegetated roofs on the commercial office buildings in order to reduce
external heat gains from the roof top.
Openings on the buildings will be placed such that to facilitate proper air flow in the entire site;
It is recommended to provide solar shading panels to block harsh summer & mid-season radiation while
allowing winter radiation in open exhibition space.
9.7 Do the structures use energy-efficient space conditioning, lighting and mechanical systems? Provide
technical details. Provide details of the transformers and motor efficiencies, lighting intensity and air-
conditioning load assumptions? Are you using CFC and HCFC free chillers? Provide specifications.
A central air conditioning system shall be designed to provide year round thermal and environmental
control. Air conditioning shall be provided by a variable flow chilled water recirculation systems for
maximum energy conservation.
Air handling Units (AHUs), cooling tower motors will have variable speed drives. Variable speed
pumping system (secondary and tertiary circuits) would be used.
The general lighting and the illumination level of spaces shall be as per National Lighting Code. Energy
efficient light fixtures shall be used.
9.8 What are the likely effects of the building activity in altering the micro-climates? Provide a self-assessment
on the likely impacts of the proposed construction on creation of heat island & inversion effects?
Heat emission from the proposed construction can be from the following sources: Heat absorbed from
the paved and concrete structures, heat generated from equipment /appliances and due to increased
population in the proposed ECC facility.
9.9 What are the thermal characteristics of the building envelope? (a) roof; (b) external walls; and (c)
fenestration? Give details of the material used and the U-values or the R values of the individual
components.
9.10 What precautions & safety measures are proposed against fire hazards? Furnish details of emergency
plans.
The fire protection system will be generally designed based on Part IV, Group I of National Building Code
(NBC) of India (2001), Tariff Advisory Committees TAC, fire protection manual (1998) and the latest Indian
and International standards/codes. Following functional system shall be provided; strictly in compliance with
the listed reference standards:
b. Fire water static Storage : Fire water static storage has been provided in accordance
to NBC requirement.
c. Fire Pumping system : Pumping system comprising of independent pumps for
hydrant, sprinkler & jockey application has been provided.
d. Hydrant system : External & internal hydrant complete with hose reel.
e. Sprinkler system : Sprinkler rating and type shall be selected for respective
areas.
f. Trolley mounted CO2 system : For LT Panel Room / DG Room, all as per local bye-laws.
g. High pressure water Mist system : For Transformer Room as required by CEA
h. Hand held fire Extinguishers : Strategically placed at designated areas.
Internal and External Fire Hydrant System: Internal and external standpipe fire hydrant system shall be
provided with landing valve, hose reel, first aid hose reels, complete with instantaneous pattern short
gunmetal pipe in the Complex.
External hydrant: External hydrants shall be provided all around the Complex. The hydrants shall be
controlled by a cast iron sluice valve or butterfly valve. Hydrants shall have instantaneous type 63mm dia
outlets. The hydrants shall be double outlet with CI duck foot bend and flanged riser or required height to
bring the hydrant to correct level above ground.
CO2 Extinguishing Systems: Trolley mounted carbon dioxide based fire extinguishing system shall be
provided in accordance with local Bye-Laws for transformer room, LT panel room and other critical /
sensitive areas.
Automatic Sprinkler System: Wet pipe sprinkler shall be provided for all habitable spaces such as guest
rooms, guest room corridors, restaurants, ball rooms/ meeting rooms and other public areas. Sprinkler shall
also be provided in all public toilets.
9.11 If you are using glass as wall material, provide details and specifications including emissivity and thermal
characteristics.
Energy saving double glazed windows with energy saving upto 12% as compared to single glazed windows
will be provided. In accordance with Energy Conservation Building (ECBC) Code 2007 (Revised version
may 2008) norms, New Delhi comes under Composite climate zone. Hence, based on the ECBC norms, U
Values considered are as follows:
Component Specification
Wall : U = 0.077 Btu/hr-sft-deg F
(0.44 W/Sqmdeg C)
Roof (Exposed to sun) with Thermal : U =0.046 Btu/hr-sft-deg F
insulation. (0.261 W/Sqmdeg C)
9.12 What is the rate of air infiltration into the building? Provide details of how you are mitigating the effects of
infiltration.
Following indoor design conditions for centrally air conditioned spaces are proposed.
Office Building 23 1C (73.4 2F) Less than 60% (5 CFM / Person + 0.06 CFM / Sqft)
Retail (Shops & Food 24 + 1C (75 + 2 F) Less than 60% (7.5 CFM / Person + 0.18 CFM / Sqft)
Court)
Atrium, Lobby & 25 + 1C (77 + 2 F) Less than 60% (5 CFM / Person + 0.06 CFM / Sqft
Corridors
Hotels 22 + 1C (72 + 2 F) Less than 60% 50 cfm/RoomTFA; 40 cfm exhaust
from toilet) OR as specified by Hotel
Operator
Mechanical Plant rooms / Electrical Rooms Mechanical ventilation
The proposed project will have a combination of central HVAC system and ventilation system to provide year
round thermal and environmental control. All air conditioning equipment shall be utilized with environment
friendly HFC/HCFC refrigerants and with latest state of the art technology to meeting highest energy efficient
criterion. Following standard & guidelines shall be adopted while designing the HVAC system.
9.13 To what extent the non-conventional energy technologies are utilized in the overall energy consumption?
Provide details of the renewable energy technologies used.
As per solar design calculations, 10 sqm areas required to generate 1 kWp of connected electrical load.
Hence, it is advised to explore the possibility of installing of solar photo voltaic system, which in turn shall be
synchronized with the electrical system. This power supply shall be converted in AC power supply and will
be synchronized with main grid power supply. The solar water heating system shall be 20% capacity or
higher of total hot water requirement. The solar panel for hot water shall be provided at terrace of each tower
wherever hot water required.
The detailed EMP for both construction and operation phase for the proposed project is enclosed.
1. Land - Change in land use pattern of the - Land clearing activities to be kept to absolute minimum, as per the requirment Engaged civil
Environment area to PSP - The movement and parking of heavy machinery and other vehicles will be contractor (bound by
- Topography of the area will change; restricted to identified routes and identified locations. his Agreement
lesser inltration and thereby - Good housekeeping at labour resting areas and in general, all construction area conditions), Project
increased runoff - Proper routing and adequate capacity of the storm water run-offs drains with catch Management Team of
pits ECC
2. Ambient Air - Emissions from construction - The removed humus/ rich top soil shall be stored in an appropriate manner
Quality equipment, vehicles - Wet suppression to be applied to at least 80 percent of all inactive disturbed Contractor, Project
- Improper handling and storage of surface Management Team
construction material - Limited vehicular movement shall be permitted
- Fugitive dust emissions - Use of covered trucks with suitable covering material/ tarpaulin
- Emissions from onsite operation of - DG sets will be used as a backup source only. They will have a stack height as per
diesel generators CPCB norms.
3. Ambient Noise - Noise due to construction activities - Appropriate scheduling of construction activities to avoid high noise levels to be
Quality (such as excavation, grading, erecting undertaken. Contractor, Project
equipment, piling, etc) - Acoustic enclosures, noise barriers to be provided in areas of high noise Management Team
- Noise due to operation of heavy generating sources.
equipment and machinery - Rubber padding to be provided for vibration control
- Movement of vehicles - Limitations on movement of vehicles during night time Construction workers to use
ear muffs in areas with potential for high noise generation.
- Provision of rubber padding / cushioning in all high noise generating equipment
- Regular maintenance of vehicles and repair of equipment.
- Working hours and construction activities to be limited.
4. Water - Construction activities will result in - Storm water drainage shall be developed during construction phase to tap all rain
Resources and disturbance of topsoil, which might get water. Contractor, Project
Quality eroded during heavy rains. - Silt fencing will be provided to protect water quality Management Team
- Sediment run off from construction - Adequate number of toilets (at least 8 toilets per 100 labour) and soak pits to be
area developed
- Unplanned disposal of sewage from
toilets of labour resting areas
- Improper disposal of sewage
5. Soil Resources - Movement of heavy vehicles and - Topsoil (upper 30 cm) will be removed prior to commencement of bulk earthwork Contractor, Project
machinery on unpaved surface - Minimum clearance of vegetation shall be carried out Management Team
- Potential contamination of soil may - Excavated soil shall be used/transported at the earliest for filling low lying areas
occur due to accidental spills of - Retention wall or bund shall be provided around the storage areas
Air Quality Emission from power backup/ DG sets DG sets will be located in the downwind direction with respect to residential areas.
Emissions from increase in traffic SPV developed for overview of power supply shall ensure that the power failure is Project Management
volume maintained at minimal. Team
Stack heights for DG sets to be maintained as per CPCB/MoEFCC norms.
All emission sources to be provided with adequate stack height as per CPCB /
MoEFCC norms.
Good housekeeping to be practiced.
Vegetative barriers in form of green belt will be provided around the ECC complex
which will minimize the built up of pollution level.
Ambient Noise Increase in noise levels in residential Sound attenuators / acoustic lining shall be installed in ducts in accordance with
Quality areas and adjoining villages requirements Project Management
Impact on avifaunal species due to DG sets will be provided with acoustic enclosures; Team
increased noise Trees with heavy foliage will be planted to minimise the noise pollution
Movement of vehicles A minimum distance of 50m-70m will be provided between the buildings and the rail
Noise generated from the proposed tracks
MRTS line being developed
Water No ground water usage will be made
Resources and for any activities. Water consumption will be minimized by a combination of water saving devices and Project Management
Quality use water from the allocated other domestic water conservation measures. Furthermore, to ensure ongoing water Team
Underground reservoirs of Delhi Jal conservation, an awareness programme will be introduced for the residents. The
Board which has a reserve quantum following section discusses the specific measures, which will be implemented:
thus impact on fresh water resources
Domestic and Commercial Usage
Use of water efficient plumbing fixtures (ultra-flow toilets and urinals, low flow sinks,
water efficient dishwashers and washing machines). Water efficient plumbing fixtures
use less water with no marked reduction in quality and service.
Leak detection and repair techniques.
Sweep with a broom and pan where possible, rather than hose down for external
areas.
Meter water usage; employ measurement and verification methods. Monitoring water
use is a precursor for management.
Awareness campaign to disseminate knowledge on strategies and technologies that
can be used for water conservation.
Landscaping
Harvested storm water will be utilized for artificial recharge of ground water sources
and waste water will be reused on site after treatment.
Rooftop Rainwater harvesting structures will be developed to store water which will be
used to meet the landscaping and HVAC requirements.
Solid Waste Inadequate collection and treatment of An integrated solid waste management will be put in place for collection, transport,
Disposal domestic waste treatment and disposal of solid waste generated from the activities. Project Management
Unhygienic conditions, odour problem Team
Localized flooding due to The recyclable waste like glass, metal, plastics, paper etc likely to be generated from
accumulation of waste along streets different land uses, will be collected separately and sold to authorized recyclers/
which can clog drains vendors
Contamination of soil and
groundwater For processing of biodegerable waste, an agreement with local ULB will be executed
Improper transportation of municipal for lifting the waste. Feasibility of installing a portable organic waste converter
solid waste machine will be carried out at detailed study stage.
Traffic Volume Increase in traffic flow The roads in general to be designed to carry the maximum traffic loads with
Increase in private traffic volume anticipated future development and on a par with IRC Standards; Project Management
Traffic congestion A 100m ROW road spanning 46km connecting as an Urban Extension Road-II (UER- Team
Irregular Parking II) has been proposed.
A monitoring plan matrix is being developed to specify the time frame when the environmental control activities need
to be carried out, who is responsible and what methods will be used to measure effectiveness. Monitoring plan for
various performance indicators for construction and monitoring stages is summarized in Table 10-3.
Construction Phase
Air RSPM, SO2, NOx, CO Project Site Three, 8 hr, sample Project Manager-
per day once every Environment
season for two years
Water Quality Monitor the effluent released during the Project Site Annual Project Manager-
project (1 sample/year) for Environment
two years
Noise Monitoring the noise level due to Project site Quarterly Project Manager-
construction machinery (4 samples/year) for Environment
two years
Soil Organic matter, C, H, N, Alkalinity, Project Site 1sample/year for two Project Manager-
Acidity, heavy metals and trace metal. years Environment
Alkalinity, Acidity
Operation Phase
Water Monitor the Rain Water Harvesting once during Pre- and Project Manager-
Resource activities post-monsoon Environment
Water Quality Monitor the grey water quality Parameters for Weekly (Continuous) Project Manager-
horticulture use Environment
BOD, pH, S.S,
Coliforms
Noise Monitor the noise due to the additional Equivalent noise Quarterly Project Manager-
traffic generated levels (4 samples/year) for Environment
two years
Project Vision
The project vision is therefore to create a state-of-the-art, world class Exhibition and Convention
Centre for India. ECC is envisaged as an internationally-recognized, architectural icon with innovative
design and novel green building features.
With the help of state-of-the-art technology and cutting-edge design, the ECC is intended to be
launched as an international brand to promote and stimulate future growth and development. The
ECC will be an integrated complex with a host of mutually beneficial facilities; exhibition halls,
convention center and meeting facilities, banquet halls, auditoria, hotels, F&B outlets and retail
services. These components will have the ability to be utilized independently or in conjunction with
each other, depending on the nature of the event.
The size and diversity of the project, suggests that each area will have unique features that define
both, the challenges and the opportunities to stimulate investment and generate a desirable level of
success. To that end, the concept for the facility has been worked with an in-depth and integrated
physical development approach.
1|P a g e
International Exhibition & Convention Centre, Dwarka, New Delhi
The facilities will be at par with the best in the industry worldwide, in size and quality; offering an
efficient and quality setting for international as well as national meetings, conferences, exhibitions
and trade shows. The project is envisioned to be on a scale of a Central Business District (CBD) with
supporting retail space, commercial office space, hospitality, and entertainment and lifestyle
opportunities for end-users.
State of the Art sustainable approaches to planning and implementation have been included in the
ECC Dwarka project. The approach incorporates sustainable planning and design solutions and
techniques in transportation, alternative energy production and energy conservation, water
resource management, land use planning and building design to create cost-effective and
measurable solutions for the district.
ECC is planned and proposed to be constructed in lines with green building principles and IGBC
(Indian Green Building Council) platinum rating standards. The project will offer eco-friendly design,
energy efficient systems, state of the art technology& compliance to all statuary regulations.
2|P a g e
International Exhibition & Convention Centre, Dwarka, New Delhi
Fig 2: Location map of proposed ECC, Sec. 25, Dwarka, New Delhi
o Dwarka Sub-City
o Integrated Passenger Terminal in Sector-21, Dwarka
o Indira Gandhi International Airport
o Inter State Bus Terminal
o Integrated Freight Complex
o Second Diplomatic Enclave and Golf Course at Sector-24, Dwarka.
The proposed site has well planned transport connectivity, including MRT connectivity. The site is in
close proximity to the Delhi Metro Station in Sector 21. The blue line and airport express line
presently terminates at this station. The airport express line is being extended for exclusive
connectivity to the ECC complex. The expansion of airport express line will start along with
development of ECC.
There are proposals to extend metro network from Sector 21 station southwards to Gurgaon,
further enhancing the connectivity of the site. The Inter State Bus Terminal (ISBT), located in Sector
22, is diagonally opposite the proposed ECC site. The site is thus in very close proximity to a host of
existing and proposed road, rail and transit links.
3|P a g e
International Exhibition & Convention Centre, Dwarka, New Delhi
Adjoining Facilities
- Proposed ISBT Site
It is one of the most important metro stations as it is the junction station of Blue line and Airport
Express line. The ECC site turns out to be more feasible because of its close proximity to this
metro station that allows extension of airport express line.
- Diplomatic Enclave and Golf Course
The site is in close proximity the new diplomatic enclave and upcoming new Golf Course
proposed in Sector 24, Dwarka. The site for same has been handed over by DDA to Ministry of
External Affairs.
- New rail station
The site is approximatel1 km from the proposed rail terminal in Sector 21. This new terminal will
be the hub for all west and south west bound trains.
Height Restriction
The site is under the runway funnel of IGI Airports new runway 11-29. The site is approximately 2.5
km from the end of the western edge of the runway. Permissible height of structures within the
proposed development is regulated in accordance with the provisions contained in the Ministry of
Civil Aviation notification published in Gazette of India
For the master planning purpose 7-8 floors for each building is assumed which may
increase/decrease or re-orientation of building blocks may change depending on the final height
approvals from Airports Authority of India.
4|P a g e
International Exhibition & Convention Centre, Dwarka, New Delhi
Modification to the Master Plan for Delhi 2021 vide Ministry of Urban development notification
no.1313 dated May 26, 2016 has been carried out permitting ground coverage of 40% with FAR of
120. Exhibition space, convention and meeting space to be minimum 40% of floor area. Retail trade,
office spaces/commercial offices, Hotels and related activities shall be up to maximum 60% of floor
area.
5|P a g e
International Exhibition & Convention Centre, Dwarka, New Delhi
Development Strategy
The ECC is intended to be launched as an
.