PROGRESS REPORT FOR THE PERIOD ENDING MAY 26TH, 2017

Name of Contract CONSTRUCTION OF THE THOMAZO BRIDGE

Contract 1. Demolition and disposal of two bridge abutments and bridge deck
Description/Scope of 2. Construction of two new bridge abutments and bridge deck on piled foundation
Works 3. Construction of retaining walls to protect river banks
4. Construction of temporary by-pass roads
5. Construction of pedestrian sidewalks

Funding for Works TOTAL (EC$) CDB (EC$) GOSL (EC$)


$5,623,617.04 $4,890,101.77 $733,515.27

Contractor Integrated Development and Construction

Supervising
Engineer/Consultant Caribbean Consulting Engineers

Contract Start Date 25 July 2016

Revised Start Date 26 September 2016

Contract Time for


Completion 360 calendar days

Contract End date 21 September 2017

New Contract End Date 28 October 2017

Contract Price (Works)


(EC$) $5,623,617.04

Variations to date
(Works) $0.00
Revised Contract Price
(Works) $5,623,617.04

Extensions of time
granted to date NONE

Estimated Percentage
Completion to date 25%

Summary of Progress to 1. Setting of Site Office for Project Manager - 100%


date 2. Construction of By-Pass Road - 100% Note: Bypass Road was opeded on April 9th, 2017
Bridge Works
1. Demolition - 100%
2. Excavation - 50%
3.piling - North abument- 100%
4. Casting of north abutment ( Casties end) - footing- 100% ; Wall - 100%
5. Wing wall - 30%
Retaining wall Construction
1.Excavate for retaining wall ( downstream-north abutment) - 100%
2. Base - 100%
3. Stem - 100%
Pre-Casted Units
1. Slabs - 100%
2. Beams - 30%

Works (EC$)
Payments certified to CDB (EC$) GOSL (VAT) (EC$)
date 1,066,327.86 150,190.30
Problems/Delays/ The Project is still 5.5 months behind schedule . The Contractor have not been able to make up for time.
Challenges The Project Manger, Mr. Abel Martinez is no longer with the Project. The Contractor indicated that the
New Project Manger will assume post by May 28th, 2017.
Project Manger still not hired.

Summary of projected 1. Backfill behind north abutment wall. 2.


activities to next Continue with the construction of the upstream retaining wall
reporting period 3. Excavate and start piling for south abutment wall - Dennery End