Вы находитесь на странице: 1из 41

Department of Transport and Main Roads Chapter 8

Road Drainage Manual Open Channel Design

Chapter 8
Open Channel
Design

March 2010
i
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

Chapter 8 Amendments Mar 2010


Revision Register
Issue/ Reference Description of Revision Authorised Date
Rev Section by
No.

1 - Initial Release of 2nd Ed of manual. Steering Mar


Committee 2010

March 2010
ii
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

Table of Contents
8.1 Introduction 8-1
8.1.1 Open Channels 8-1
8.2 General Considerations 8-2
8.3 Local Authority Requirements 8-2
8.4 Fundamentals of Open Channel Flow 8-3
8.4.1 Stream Dynamics 8-3
8.4.2 Assumptions for Analysis 8-4
8.4.3 Fundamental Equations 8-4
8.4.4 Application of Fundamental Equations 8-9
8.4.5 Energy Principles 8-11
8.4.6 Hydraulic Jump 8-14
8.4.7 Hydraulic Drop 8-20
8.5 Erosive Velocities in Natural Streams 8-20
8.6 Backwater 8-20
8.6.1 Tidal Waters 8-21
8.6.2 Downstream Tributary 8-24
8.7 Tailwater Levels 8-24
8.7.1 Tailwater Effects 8-24
8.7.2 Design Tailwater Levels 8-25 8
8.8 Open Channel Design 8-26
8.8.1 Design Methodology 8-26
8.8.2 Channel Transitions 8-29
8.8.3 Energy Losses in Channel Bends 8-30
8.8.4 Superelevation in Channel Bends 8-30
8.9 Grassed Channels 8-31
8.9.1 Normal Grassed Channels 8-31
8.9.2 Reinforced Grassed Channels 8-32
8.10 Channels Lined with Hard Facings 8-33
8.10.1 General 8-33
8.10.2 Riprap and Rock Filled Wire Mattresses / Gabions 8-33

March 2010
iii
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

8.10.3 Concrete Lined Channels 8-36


8.11 Channel Drops 8-36
8.12 Baffle Chutes 8-36

March 2010
iv
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

Chapter 8
Open Channel Design

atmosphere and/or there is no additional


8.1 Introduction
pressure on the flow other than atmospheric
Open channels are economical where large pressure. Flow is caused by gravity and
flows are to be carried and space is not streams tend to follow the path of least
restricted. An example on a newly resistance.
constructed, open channel is show in Figure Open channels may be constructed to
8.1. They have the advantages of specified criteria:
continuous collection of surface runoff, and
as part of the road drainage system
where the system surcharges, general
where space within the road reserve
shallow flow is the most likely outcome
is sufficient to provide for open
rather than more concentrated flooding at
channels;
upstream inlets of the closed drainage
system. as diversion channels, especially
where the road is being constructed
This manual focuses on the analysis and
generally along the line of a
design of smaller streams and creeks.
watercourse and severs one or more
Assessment of larger streams, creeks, rivers
meanders in the stream. Care must
and floodplains is complex and should be
be exercised as shortening of the
referred to Hydraulics Section, Engineering
stream will increase the gradient and
& Technology Division or a suitably pre-
hence velocity, which may induce
qualified consultant.
scouring and also prevent the
upstream passage of fish; and/or
from the outlets of culverts or
8
drainage systems.
Creeks and waterways, disturbed by
construction work, need to be left in a way
that the channel will continue to behave in a
hydraulic and ecological manner similar to
that of the undisturbed natural stream. New
open channels must be appropriately
Figure 8.1 - Bare Earth Open Channel integrated into the surrounding ecological,
visual, social and physical environments.
8.1.1 Open Channels
Department of Environment and Resource
An open channel is defined as a conduit or Management and relevant local authorities
conveyance (artificial or natural) in which should be consulted early in the planning
water flows with a free surface. A free process as they may have special
surface means that the surface is open to the

March 2010
8-1
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

requirements for existing channels which (e) Assessing the need for channel lining,
could be: particularly for erosion resistance,
including vegetation selection and
part of soil conservation programs;
aesthetics. Ensure future
stream rehabilitation or restoration maintainability of lining is considered;
plans;
(f) Calculating flow characteristics.
riparian improvement programs; Design for subcritical flow (refer
part of natural channel design Sections 8.4.5.2 and 8.4.5.3) is
programs; or recommended. In only a small
percentage of natural streams under
other ecologically sustainable
certain conditions, flow is not
programs.
subcritical. Supercritical flow (refer
Sections 8.4.5.2 and 8.4.5.3) with its
8.2 General
highly erosive velocities should be
Considerations
avoided in a design flood except at
Considerations in open channel design channel drops or energy dissipators
include: (refer Chapter 11);

(a) Establishing the ecological (g) Assessing the safety or the


requirements for the channel such as: appropriateness of an open channel in
certain locations, particularly in
determining the specific or generic developed areas;
riparian management requirements;
(h) Providing access for maintenance.
stream bank stability or erosion
guidelines; 8.3 Local Authority
water quality requirements; Requirements
natural channel design requirements;
8 use of the channel by fauna as a
The requirements of local government
should be sought for any significant open
fishway or wildlife corridor. channel design particularly in developed
areas or where the channel forms part of a
(b) Evaluating the most economical route
major drainage system as defined in
consistent with the land use and
Chapter 2.
topography;
There is a need to check the effects of flows
(c) Optimising the slope of the channel.
in excess of the design flood and to
To reduce the velocity, a flatter slope
understand the likely impacts. Where
than that existing may be adopted, by
flooding of property is a possibility, the
introducing drop structures or
effects of a flood in excess of the design
meanders. However, shortening the
flood should be analysed even if there is no
natural channel alignment will increase
local government requirement.
velocities;
Other local government requirements may
(d) Determining the width available for an
include the provision of access /
open channel in the road reserve or
maintenance berms, barrier fencing and
drainage easement;
appropriate warning signs to prevent access

March 2010
8-2
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

to the channel and a low flow channel to bridges.


take a minimum flow.
8.4.1.2 Governing Parameters
Water Sensitive Urban Design (WSUD) is
an important aspect of pollution control and All streams are governed by the same basic
the design of open channels should parameters:
consideration these requirements. Chapter
(a) Geological Factors
2 outlines the principles of WSUD while
Chapter 7 provides more information and soil conditions
detail.
(b) Hydrological Factors
8.4 Fundamentals of Open rainfall
Channel Flow (c) Geometric

8.4.1 Stream Dynamics channel slope and crossfall


(d) Hydraulic
It is important to have a basic
understanding of how streams work or fluid properties
behave to ensure that the planning and (e) Vegetation
design of drainage infrastructure is
appropriate and will work not only after the Native vegetation in channels / along
work is completed, but also in the future. banks

Streams are constantly changing and 8.4.1.3 Velocity Distribution


responding to external factors and are
therefore dynamic. However, to simplify The flow velocities within a stream are not
analysis and design, streams are generally uniformly distributed across the cross
considered as static, that is the stream is section. This is due to friction along the
divided into small, isolated parts and/or channel bed, banks and free surface.
sections and the flow within the channel is
analysed at a point in time.
The velocity of water particles near the bed
and banks (planes of highest friction) is the
8
slowest while the highest velocity is
8.4.1.1 Streams and Roads
typically found just below the free surface
Human interference can easily change / in the deepest part of the flow.
affect streams and it is critical to understand Figure 8.4.1.3 illustrates the velocity
that changes can affect stream behaviour distribution across channel flow. To map
both upstream and downstream. water particles of equal velocity, isovels are
Typical encroachments that would affect drawn (isovels trace equal velocity similar
normal stream flow as related to road to contour lines tracing equal ground
infrastructure are: height).

roadway embankments;
cross drainage culverts;
floodways; and

March 2010
8-3
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

Turbulent Flow is where the water


particles move in very irregular
paths. White water rapids are a good
example of turbulent flow.
Open channel flow can be in a variety or
combination of these types and states.

Figure 8.4.1.3 Velocity Distribution


8.4.2 Assumptions for Analysis
Across the Flow
Due to the dynamic nature of open channel
8.4.1.4 Types and States of Flow flow, it is difficult to model and/or analyse
the flow as it occurs in the natural
Open channel flow can be described in a environment. Therefore a number of
number of ways. The following outlines assumptions are made to enable and
the types of flow: simplify analysis. These assumptions are
Steady Flow is where the depth of considered reasonable and valid in the
flow at the same point does not context of the analysis and design
change over time. procedures described in this manual.

Unsteady Flow is where the depth The assumptions made are:


of flow at the same point does change Steady Flow;
over time.
Uniform Flow;
Uniform Flow is where the depth
Velocity is averaged over the whole
of flow is the same at every cross
cross section; and
section along the channel. This is
really only possible when the channel Flow is non-turbulent.
flow cross section, slope and Generally, these assumptions can be applied
8 roughness remain constant.
Non Uniform or Varied Flow - is
to most situations encountered in design.
However, where it is obvious that the
where the depth of flow changes assumptions cannot be applied, the analysis
along the length of channel. Varied and/or design should be referred to
flow can be further described as Hydraulics Section, Engineering &
either rapid or gradual (i.e. in Technology Division or a suitably
artificial channels). prequalified consultant.

The following outlines the states of flow: 8.4.3 Fundamental Equations


Laminar Flow is where the water
particles appear to move in smooth The most basic equation in the analysis of
paths or in very thin sheets (laminas) open channel flow defines the relationship
over the top of each other. Laminar between flow rate, velocity and the cross
flow is very smooth flow and is sectional area of flow and is represented by
rarely seen in the natural the following formula:
environment.

March 2010
8-4
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

Q V A P = wetted perimeter (m).


Where: In determining the hydraulic radius, the
wetted perimeter is defined as the length of
Q = flow rate (m3/s);
line (normal to the flow) where the water
V = average velocity (m/s); and touches the surface of the ground (channel)
A = cross-sectional area of flow (m2). or the perimeter of flow less the surface
(exposed to the atmosphere) length (refer
This equation also forms the basis of the Figure 8.4.3(a)).
theory behind the Continuity Equation.
The theory allows simple analysis over
changes in the channel irrespective of cross
section, slope or roughness. The theory
assumes no addition to or subtraction from
the flow between the 2 sections being
considered (i.e. Q1 = Q2). Figure 8.4.3(a) Wetted Perimeter

The Continuity Equation is: For natural channels the slope of the energy
line, S, is almost impossible to determine.
Q1 V1 A1 V2 A2 Q2
Therefore a suitable estimation of S is
The formula most commonly used for the required. The slope of the water (flow)
calculation of steady, uniform flow in open surface, Sw, could be used, however this is
channels is Mannings Equation. This also difficult to determine. The only easily
equation is used to determine the velocity available slope that can be used to estimate
of flow at a specific point in the channel, S is the channel bed, So, provided that the
and therefore the variables in the equation channel and the bed slope about the point
must be representative of the point being being assessed is reasonably uniform. If the
assessed. channel shape and bed slope is irregular,

Mannings Equation is:


2 1
Mannings Equation will not give
acceptable results and therefore the analysis 8
R S 3 2 / design should be referred to Hydraulics
V Section, Engineering & Technology
n
Division or a suitably pre-qualified
Where: consultant.
V = average velocity (m/s); In applying Mannings Equation,
R = hydraulic radius (m); particularly to natural channels, the greatest
difficulty lies in the determination of the
S = slope of energy line (m/m); and
roughness coefficient n. For artificial
n = Mannings roughness coefficient. channels values of n can be obtained from
The hydraulic radius is given by: Table 8.4.3(a).

A For natural channels, a comparison may be


R made with the photographs in Figure
P
8.4.3(b) and values of n in Table 8.4.3(b)
Where: for similar channels. However, for grassed
A = cross-sectional area of flow (m2); channels, and where the hydraulic radius

March 2010
8-5
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

for the flow is less than 1 m, vegetal appropriate vegetal retardance curve to be
retardance curves (Figures 8A.1 to 8A.5 in used.
Appendix 8A) should be used to determine
n. Table 8.4.3(c) is used to determine the

Table 8.4.3(a) - Mannings n Values for Artificial Channels / Conduits


Type of Structure n

1. Closed Conduits

(a) Concrete pipe 0.013

(b) Corrugated metal pipe or pipe-arch (small corrugation)


(i) plain or unpaved 0.024
(ii) paved invert-full flow
25% circumference paved 0.021
50% circumference paved 0.018
Fully paved 0.012

(c) Structural plate pipe or pipe-arch 0.030-0.033

(d) Monolithic concrete (box culvert) 0.012

(e) Vitrified clay pipe 0.012

2. Open channels - Lined

(a) Concrete - Smooth forms or trowelled 0.012

(b) Bituminous Concrete


(i) Smooth 0.013
(ii) Rough 0.016

3.Open Channels - Excavated (Straight alignment and natural lining)

(a) Earth - uniform section


(i) clean - new to weathered 0.016-0.020

8 (ii) with short grass, few weeds


(iii) in gravelly soil, clean

(b) Earth - uniform section


0.022-0.027
0.022-0.025

(i) no vegetation 0.022-0.025


(ii) grass, some weeds 0.025-0.030
(iii) dense weeds or plants in deep channel 0.030-0.035
(iv) sides clean, gravel bottom 0.025-0.030
(v) sides clean, cobble bottom 0.030-0.040

c) Dragline excavated or dredged


(i) no vegetation 0.028-0.033
(ii) light bush on banks 0.035-0.050

(d) Channels not maintained, weeds and brush uncut


(i) dense weeds, high as flow depth 0.08-0.12
(ii) clean bottom, brush on sides 0.05-0.08
(iii) same, highest stage of flow 0.07-0.11
(iv) dense brush, high stage 0.10-0.14

Source: Based on Bureau of Public Roads, 1965. Item 1(b) and 1(c) have been added based on values
recommended by Maccaferri in their publications.

March 2010
8-6
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

Table 8.4.3(b) - Mannings n Values for Natural Channels

Type of Channel n

Main Channel

1. Fairly Regular Section


(a) Some grass and weeds, little or no brush 0.0300.035
(b) Dense growth of weeds, depth of flow materially greater than weed height 0.0350.05
(c) Some weeds, light brush on banks 0.0350.05
(d) Some weeds, heavy brush on banks 0.050.07
(e) Some weeds, dense willows on banks 0.060.08
(I) Trees within channel with branches submerged at high stage Add 0.01
0.02

2. Irregular Section, with pools, slight channel meander Add 0.01


To (a) to (f) above as applicable 0.02

3. Mountain Streams, no vegetation in channel, banks usually steep, trees and brush
along banks submerged at high stage
(a) Bottom, gravel, shingle and few boulders 0.040.05
(b) Bottom, shingle with large boulders 0.050.07

Adjacent Flood Channels

1. Pasture, no Brush
(a) Short grass 0.0300.035
(b) High grass 0.0350.05

2. Cultivated Areas
(a) No crop 0.030.04
(b) Mature row crops 0.0350.045
(c) Mature field crops 0.040.05

3. Heavy Weeds, Scattered Brush 0.050.07

4. Light Brush and Trees 0.060.08

5. Medium to Dense Brush 0.100.16

6.

7.
Dense Willows, Summer, not bent over by Current

Cleared Land with Tree Stumps (250 to 450 per ha)


0.150.20 8
(a) No sprouts 0.040.05
(b) With heavy growth of sprouts 0.060.08

9. Heavy Stand of Timber, A Few Fallen Trees, Little Undergrowth


(a) Flood depth below branches 0.100.12
(b) Flood depth reaches branches 0.120.16

Major Streams (Surface width at flood stage > 30 m)


Roughness coefficient is usually less than for minor streams of similar description on 0.120.16
account of less effect offered by irregular banks or vegetation on banks. Values of n may
be somewhat reduced. The value of n for large streams of mostly regular section may be
in the range.

Source: Based on Austroads (1994)

March 2010
8-7
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

n = 0.03 n = 0.04-0.045

n = 0.05-0.06

n = 0.07 n = 0.08
Notes:
1) Increase in n value with an increase in grass, weeds, shrubs and trees.
2) In general, growth of trees in photographs tends to look denser than when seen on a site
inspection.
3) Except for n = 0.03, roughness is for bank full flood heights and/or floods in upper branches of the
trees.
4) Use photographs with caution. Use in conjunction with Table 8.4.3(b)

Figure 8.4.3(b) - Natural Streams in Queensland

March 2010
8-8
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

Table 8.4.3(c) - Guide to the Selection of Vegetal Retardance

Density of stand Average length of Degree of Examples


(see Note 1) vegetations (mm) retardance

Thick Longer than 750 A Rhodes grass in ungrazed scrub soil waterway

Thick 280 to 610 B Wheat 660mm tall in 180mm rows Rhodes grass

B Kikuyu under maximum fertility conditions, long


and green

B African star grass. Lucerne (see Note 2)

Thick 150 to 250 C Most grasses can be hold at this retardance with
mowing or grazing e.g. Rhodes grass, couch
grass, carpet grass, native grasses

Thick 50 to 150 D African star grass, kikuyu or couch grass, all


under heavy grazing

Thick Less than 50 E Mowed lawn. Any grass burned short

Fair Longer than 750 B -

Fair 280 to 610 C Rhodes grass under low fertility conditions

Fair 150 to 250 D African star grass under low fertility conditions.

Fair 50 to 150 D -

Fair Less than 50 E -

Notes:
1. Thickness of vegetation has an important bearing on retardance, possibly more important than species.
8
2. Vegetal retardance curves have been based on tests in experimental channels.
3. Values of n = 0.15 plus have been used for fields of standing sugar cane.
4. Refer to Appendix 8A for nomographs using different vegetal retardances.

Source: Based on Soil Conservation Handbook (DPI 1978) and Rouven et al., (1981)

Equation are the Normal Depth and Normal


It is important to understand that the depth
Velocity
and velocity of any given flow in a channel
operating under normal or natural
8.4.4 Application of
conditions is called the Normal Depth and
Fundamental Equations
Normal Velocity. The depth and velocity
of flow as determined using Mannings The primary usage of the fundamental
equations is to determine the basic flow

March 2010
8-9
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

characteristics of a given channel. These


characteristics are:
maximum flow capacity of the
channel;
velocity of flow when at maximum
capacity;
depth of flow for a specific
discharge; and
Figure 8.4.4(a) Stage-Discharge Curve
velocity of flow for a specific
discharge. To use the Stage-Discharge curve to
determine the depth of flow for a specific,
To determine these characteristics, a
discharge, plot the required flow rate (Qy)
representative cross section for the channel
onto the left y-axis and extend across the
needs to be chosen as well as channel slope
graph to the flow line and then project
(So) and Mannings n value.
down to x-axis. To determine the velocity
Mannings equation gives the velocity of of this flow, the cross sectional area of the
flow in a channel based on a selected depth flow needs to be calculated using the
of flow (which enables calculation of the determined depth of flow.
cross-sectional area of flow and wetted
However, the Stage-Discharge curve can be
perimeter). To determine the flow rate (Q),
easily modified to include velocity by
for the selected depth of flow and using
plotted the graph using depth of flow for
velocity as determined by Mannings
the x-axis, the flow rate for the left y-axis
equation, use the fundamental equation:
and velocity for right y-axis (refer Figure
Q V . A rewritten as V Q 8.4.4(b)).
A

8 If the selected depth of flow was based on


the maximum capacity of the channel, the
first two characteristics, as listed above,
have now been determined.
To determine the last two characteristics, a
Stage-Discharge curve (also known as a
rating curve) is required. A Stage-
Discharge curve plots the depth of flow
against the flow rate at a particular cross
section along a stream / channel. To plot a
Figure 8.4.4(b) Modified Stage-
Stage-Discharge curve, a series of iterations Discharge Curve
of the above calculations / process is
required, with depths selected from zero to To use the Modified Stage-Discharge curve
maximum capacity. to determine the depth and velocity of flow
for a specific discharge, plot the required
The curve is plotted using depth of flow for flow rate (Qy) onto the left y-axis and
the x-axis and flow rate for the y-axis (refer extend across the graph to the flow line and
Figure 8.4.4(a)).

March 2010
8-10
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

then project down to x-axis, to determine


depth, and up / down to velocity line and
then across to the right y-axis to determine
velocity.
The advantages to using a Stage-Discharge
Figure 8.4.4.1 Compound Channel
curve is that the curve can be used to
determine the depth and velocity of flows
Each section is analysed individually using
for several annual recurrences intervals. It
Mannings Equation to determine flow
should be noted that the Stage-Discharge
velocity based on the parameters (S or So, n,
curve is linked to the channel
A and P) specific to the sub-section. It is
characteristics. Should the analysis shift to
important to understand that the wetted
a different location where channel
perimeter (P) is determined by the length of
parameters are different (slope, shape n-
the Water / Channel Boundary for the
value and so on), a new Stage-Discharge
sub-section. The wetted perimeter is the
curve will be required.
component of the equation where effect of
8.4.4.1 Compound Channels friction is applied. The Water / Water
boundary, as shown by the red dashed line
Simple channels are often represented as a in figure 8.4.4.1, is not to be included as the
basic trapezoid (refer Figure 8.4.1.3), friction along this boundary is negligible.
assessed using one Mannings n-value Once all sub-sections have been calculated,
and/or based on one slope. This the total flow rate can be determined by:
methodology is reasonable for simple,
small channels. In reality, the shape of QTotal V A AA VB AB
channels is not a basic trapezoid. They are Review of the calculations shows that each
compound in shape (refer Figure 8.4.3(a)) section has a different average velocity.
with: While an average velocity can be calculated
high and low banks / possible small
overflow sections;
using QTotal and the cross sectional area of
the whole channel (AA + AB), the different
8
velocities across the channel represents
different n-values for banks and
reality reasonably well.
channel bed; and
potentially different slopes between 8.4.5 Energy Principles
main channel and overflow sections.
The energy in open channel flow can be
Assessment of compound channels uses the expressed as the total head in metres (m) of
same principal and methodology as water, which is equal to the sum of the
described earlier in this section, however elevation above a datum (elevation head),
the channel cross section is first divided the hydrostatic head and the velocity head.
into smaller sub-sections. The elevation head and hydrostatic head are
Figure 8.4.4.1 shows, diagrammatically, a components collectively known as the static
compound channel divided into two sub- head.
sections (labelled A & B).

March 2010
8-11
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

In conventional terms, energy has two y are of similar magnitude. While strictly
components: not correct, the terms can be
interchangeable (based on condition) as the
potential energy; and
difference is small, therefore the practice is
kinetic energy. acceptable.
Now, relating conventional terms to the It is important to understand that this
energy within water, potential energy is equation differs slightly from the normal
equal to the static head and kinetic energy is form of the energy equation for open
equal to the velocity head. To illustrate channels, which is:
this, a static body of water such as a lake,
V2
has potential energy while a moving body H ( z d cos )
of water such as a creek, has both potential 2g
energy and kinetic energy. Where:

8.4.5.1 Energy Equation = slope angle of channel bed; and


= coefficient accounting for
The total energy for an open channel
velocity distribution.
section is given by:
Channels assessed by the department for the
V2
H (z d ) installation of cross drainage culverts are
2g relatively flat and therefore is assumed to
Where: be zero.

H = total energy head (m); Referring to Section 8.4.2, it is assumed


that velocity is averaged across cross
z = height of channel bed above
section of flow, therefore, is equal to 1.
some reference datum (m), known as
elevation head; The energy equation is useful when
comparing two sections within a channel.
8 d = depth of flow normal to the
direction of flow (m), known as
Typically, as water flows along a channel,
energy is lost. However, the first law of
hydrostatic head;
thermodynamics tells us that energy can
V = velocity of flow (m/s); and neither be created nor destroyed.
g = gravitational acceleration (9.81 Therefore, when comparing the energy
m/s2). between two sections, the relationship can
be expressed as:
The term V
2
within this equation is
2g 2 2
V V
known as the velocity head. ( z1 d 1 ) 1 ( z 2 d 2 ) 2 h L
2g 2g
According to Chow (1959) and Henderson
Where:
(1966), the variable d describes the depth of
flow normal to the direction of flow hL = head loss (m).
(typically perpendicular to channel bed).
This relationship is best illustrated in Figure
The variable y, as used in other equations,
8.4.5.1
describes the vertical depth of flow. Where
channels are relatively flat (So < 18), d and

March 2010
8-12
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

8.4.5.2 Specific Energy When the depth of flow is plotted against


the specific energy for a given channel
Specific Energy (m) is defined as the section and discharge (only bed slope
energy per unit mass of water at any changes from flat to steep), a specific
section, measured with respect to the energy curve is obtained, as shown in
channel bed. The Specific Energy (Es) Figure 8.4.5.2. This curve shows that for a
equation (which is essentially a sub- given specific energy (Es), there are two
component of the energy equation) is: possible (conjugate) depths called alternate
V2 depths; y1 and y2.
Es y
2g

Figure 8.4.5.1 Comparing Energy between Points


8

Figure 8.4.5.2 - Specific Energy Curve (Source: Franzini & Finnemore (1997))

March 2010
8-13
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

At point C on the curve, the specific energy V


Fr and Fr Q B
is at a minimum and there is only one B
g A gA
3

depth. The depth corresponding to this


point is known as the critical depth yc. The Where:
corresponding velocity is the critical
A = cross sectional area of flow
velocity (Vc) and the slope is the critical
normal to direction of flow (m2);
slope (Sc).
B = width of flow at surface (m); and
When the depth of flow is greater than the
critical depth, the flow velocity is less than Q = flow rate (m3/s).
the critical velocity and is referred to as
These equations are valid for irregular
subcritical flow. When the depth of flow is
channel / stream sections.
less than critical depth, the flow is
supercritical. Subcritical flow is controlled Froudes Number indicates the state of
by downstream channel conditions, while flow. Critical Flow occurs when Fr = 1.
supercritical flow results from some When Fr is greater than 1, the flow is
upstream control condition. supercritical, and when it is less than 1 the
flow is subcritical. When Fr is close to 1 (>
8.4.5.3 Froudes Number 0.9 but < 1.1) the flow state is unstable and
waves appear on the water surface.
Another, simpler method to determine
Design is recommended to achieve a
subcritical / supercritical flow is by
Froude Number less than 0.9 (subcritical
determining the Froude Number (Fr) for the
flow).
flow.
Froudes Number is a dimensionless 8.4.6 Hydraulic Jump
number, the ratio of inertial forces to
gravitational forces, and defined as: A hydraulic jump is an abrupt rise of the
water surface which occurs when flow
V
8 Fr
gL
changes from supercritical to subcritical in
response to a downstream control
conditional causing a higher tailwater level.
Where:
The rapid (and turbulent) rise of water
V = velocity of flow (m/s); dissipates energy. The turbulence persists
g = gravitational acceleration (9.81 for some length after the rise before
m/s2); and settling.

L = characteristic length (m). The rise and trailing turbulence is called the
roller and is shown between points 1 and
The characteristic length (L) in open
2 on Figure 8.4.6.
channel flow is equal to the hydraulic
depth, which is defined as the cross The depth, y1 before the hydraulic jump is
sectional area of flow divided by the called the initial depth, and the depth y2,
surface width of flow. Using either the after the jump is called sequent depth.
hydraulic depth or flow rate for the stream, With reference to Figure 8.4.6, the sequent
there are two commonly used forms of the depth is always lower than the high stage
above equation: alternate depth, y2, due to the loss of

March 2010
8-14
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

energy, E, in the turbulence of the 8.4.6.1 Specific Force


hydraulic jump. Due to this loss of energy,
the solution to hydraulic jump problems As mentioned above, the solution to
cannot be found using the Specific Energy hydraulic jump problems cannot be found
curve alone. The principle of momentum using the Specific Energy curve alone. The
must also be used to develop a Specific hydraulic jump involves internal energy
Force or Force Momentum curve as shown losses which cannot be simply evaluated
in Figure 8.4.6. using the energy equation therefore the use
of the momentum principle is required.
The detailed analysis of hydraulic jumps is
difficult and complex. Full analysis of In applying the momentum principle to a
jumps should be undertaken by experienced short horizontal reach of a prismatic
hydraulic engineers and therefore should be channel, the Specific Force can be defined
referred to Hydraulics Section, Engineering as:
& Technology Division or a suitably pre- Q2
qualified consultant. F y A
gA
However, several models based on accepted
Where:
theory, experimentation, laboratory testing
in rectangular channels and observation, Q = discharge (m3/s);
have been developed to approximate key g = gravitational acceleration (9.81
parameters of hydraulic jumps in irregular m/s2);
open channels.
A = area of cross section (m2); and
These simple methods are considered
reasonable for analysing undular and weak = depth to the centre of gravity to
hydraulic jumps (refer Section 8.4.6.2) and cross section (m).
have been adopted by the department for
general use in analysing hydraulic jumps.

Figure 8.4.6 - Analysis Curves and the Hydraulic Jump


Source: Chow (1959)

March 2010
8-15
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

The first term is the momentum of the flow parameters are flow velocity, flow depth
passing though the channel section per unit and Froude Number.
time, per unit weight of water. The second
Using these parameters, the alternate or
is the force per unit weight of water.
sequent depth (y2) can be determined.
An examination of Figure 8.4.6 shows that
Considering;
while water flows at a depth (y1) for a given
discharge (Q) in any channel, there will energy and momentum principles;
always be another depth where the sum of using the initial flow velocity as V1;
the force due to velocity plus the
using the initial flow depth as y1; and
hydrostatic pressure for both depths will be
the same. experiments using a rectangular
channel.
This means that the specific forces of
sections 1 and 2 are equal, provided that the Rectangular Channels
external forces and the weight effect of
The following equation was developed to
water can be ignored. This generally can be
calculate the sequent depth (y2) in a
applied to horizontal channels with small
rectangular channel:
bed slopes (So 10%).
With respect to the rule that there is always
y2 1

y1 2

1 8 Fr2 1
two depths, the exception is at critical depth
(points C & C) where energy is at a OR

1 8F 1
minimum and there is only one depth of
y1
flow. y2 r
2

2
8.4.6.2 Jump Strength Where:

Hydraulic jumps can only form if the Fr V1 (rectangular section)


gy1
8 upstream flow is supercritical (i.e. has a
Froude Number greater than 1). As
Froudes Number increases, the strength of
This relationship is shown graphically in
Figure 8.4.6.3.
the jump also increases.
Trapezoidal Channels
Table 8.4.6.2 lists the different types of
jump and their defining characteristics. The determination of sequent depth (y2) in a
This table has been derived from research trapezoidal channel of reasonably small bed
studies undertaken in 1955 by the U.S. slope (So 10%), requires an iterative
Bureau of Reclamation (USA). solution. However, when applying the
Specific Energy and Specific Force
8.4.6.3 Sequent Depth Horizontal equations, it is possible to arrange these
Channels (SO 10%) equations into a dimensionless form,
allowing solution by means of a table.
The parameters of the supercritical,
upstream flow before the hydraulic jump
are known / can been determined. These

March 2010
8-16
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

Table 8.4.6.2 Jump Types and Strength


Jump Type Fr Energy Dissipated Characteristics

Undular 1.0 1.7 < 5% Very weak jump; standing waves

Weak 1.7 2.5 5 15% Weak jump; small roller; smooth rise

Oscillating 2.5 4.5 15 45% Unstable avoid

Stable, well defined jump; best design


Steady 4.5 9.0 45 70%
range

Strong > 9.0 70 85% Choppy; very turbulent; intermittent

Table 8.4.6.3 assists the designer with the


calculation of the sequent depth (depth after
the jump). This table has been derived
from the Handbook of Hydraulics, 7th Ed,
1996 by Brater et al. 8
y2 1
1 8 Fr2 1
y1 2

Fr V1 gy1

Fr

Source: Chow (1959)

Figure 8.4.6.3 - Relation between Froude


Number and Depths of Flow in a
Hydraulic Jump

March 2010
8-17
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

Table 8.4.6.3 - Sequent Depth for Trapezoidal Channels (So 10%)

8
Source: Brater et al. (1996)

larger than 10%. However the momentum


8.4.6.4 Sequent Depth Sloping
principle can be used to derive analogous
Channels (SO > 10%)
equations, which will contain an empirical
While the effect of the weight of water in function that has to be determined
the jump is negligible for horizontal experimentally. This work was undertaken
channels (So 10%), it is essential to by U.S. Bureau of Reclamation (1964) and
consider it in the analysis of hydraulic the research shows that the depth ratio y2/y1
jumps in sloping channels (So > 10%). can be shown as a function of Froude
Thus, the momentum equations for Number (F1) and Slope (So). The graph of
horizontal channels cannot be applied to this function is shown in Figure 8.4.6.4.
jumps on channels having a bed slope

March 2010
8-18
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

y2
y1

V1
Fr1
B
gA

Source: Chow (1959)


Figure 8.4.6.4 - Sequent Depth for Sloping Channels (SO > 10%)

alternate depth y1, the jump will start to


8.4.6.5 Location of Jump

The location of the jump is dependant


move into the mild channel.
8
primarily on the momentum of flow before
and after the jump and can occur either
before or after the trigger situation that
causes the initial supercritical flow to
slow to subcritical flow. For a closer
estimate of the jump position, the length of
the jump should be considered as described
in Section 8.4.6.6 below. Source: Chow (1959)

Figure 8.4.6.5 shows a channel having a Figure 8.4.6.5 Location of a Hydraulic


Jump
break in the bed slope (steep to mild
slope) and two possible locations for the
8.4.6.6 Length of Jump
jump. If the sequent depth y2 is greater than
the alternate depth y1, the jump will occur The length of a hydraulic jump is defined as
in the steep region. If the sequent depth y2 the distance measured from the front face of
is lowered to less than approximately the

March 2010
8-19
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

the jump to a point on the surface structure such as a culvert or to prevent


immediately downstream of the roller and is scouring in an open channel.
difficult to model and predict. Two
methods to determine the length of jump 8.4.7 Hydraulic Drop
are presented here.
The converse of the hydraulic jump, the
Method 1 hydraulic drop, can also occur due to an
Observation and measurements have shown abrupt change in channel slope or cross
that a good approximation of jump length is section. It can frequently occur near the
5 times the sequent depth (y2). In most entrance to a culvert flowing under inlet
cases, the jump length is between 4 and 6 control. (An explanation of culverts
times y2. flowing under inlet control is given in
Chapter 9).
Method 2
The length of the jump can be determined 8.5 Erosive Velocities in
from a relationship based on experimental Natural Streams
data prepared by the U.S. Bureau of
Reclamation (1964), as shown in Figure Natural streams may be part of an open
8.4.6.6. This curve was developed channel design or subject to outlet
primarily for jumps in rectangular channels velocities from drainage structure and
but may also be applied to approximate therefore a key design consideration is
undular and weak jumps formed in ensuring that any design changes to the
trapezoidal channels. flow in the natural stream do not create
erosive situations in the stream.
The length determined by either method
should be rounded up to the nearest meter. Erosive velocities in natural stream beds are
shown in Table 8.5 and have been derived
As the length of jump indicates the extent from curves in Neill (1973).
of turbulence, it is therefore the minimum
8 length of channel that should be armoured
against scour / erosion. When determining
8.6 Backwater
the length of jumps in open channels for Backwater is the accumulation of water in a
armouring purposes, Method 1 is stream that can be caused by:
recommended as it gives a more
an obstruction limiting downstream
conservative answer. Method two should
channel capacity (that causes afflux
only be used when in constrained situations.
in the stream);
8.4.6.7 Application of Hydraulic tidal flow (refer Section 8.6.1);
Jumps
a downstream body of water such as
a weir, dam or lake; or
There are many practical applications for
the hydraulic jump. The most practical of a higher-than-normal flow stage in a
these applications, for the purpose of road downstream connecting stream (refer
design, is its use as an energy dissipator to Section 8.6.2).
prevent scouring downstream of a hydraulic

March 2010
8-20
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

Source: Chow (1959)


Figure 8.4.6.6 - Length of Hydraulic Jump in Terms of Sequent (y2) in Horizontal Channels

have a level that is increased above normal


Table 8.5 - Erosive Velocities in Natural depth. The cause of backwater can be a
Streams significant distance away from, but still
affect, the site being assessed. Therefore
Stream Bed Type Velocity (m/s) designers should check the downstream
conditions of planned sites or designed
Silt less than 0.3 infrastructure for possible backwater
influence.
Sand Fine less than 0.3
Coarse less than 0.3
Calculating the effect of backwater on
normal stream flows can be difficult and is
beyond the scope of this manual. If it is
8
Gravel 6 mm 0.6 to 0.9
considered that backwater could be
25 mm 1.3 to 1.5 affecting stream flow, advice and/or
100 mm 2.0 to 3.0 assistance should be sought from the
departments Hydraulics Section or a
Clay Soft 0.3 to 0.6 suitably pre-qualified consultant.
Stiff 1.0 to 1.2
Hard 1.5 to 2.0 8.6.1 Tidal Waters

Rocks 150 mm 2.5 to 3.0 Backwater as a result of tidal flow can


affect stream flow and in turn drainage
300 mm 3.5 to 4.0
infrastructure design. When determining
backwater effects on tailwater levels for
streams discharging into tidal waters, three
The presence of backwater typically causes factors may influence the final design level:
an upstream section or body of water to
tide levels;

March 2010
8-21
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

storm surges; and It is important to note that:


climate change. mean sea level given for the location
may be different to Australian Height
8.6.1.1 Sea and Tide Levels Datum (AHD) which is the average
mean sea level of 42 locations around
Tide Tables are published by the
Australia;
Department of Transport and Main Roads
(previously Queensland Transport) for tide levels are given at or very close
various coastal locations in Queensland. to the coastline; and
This data is used to estimate backwater and tide levels are often specified in
tailwater levels for drainage designs. terms of low water datum.
The Mean High Water Spring (MHWS) tide It is very difficult to estimate the tide level
is often applied as a tailwater level since at a location in a stream some distance from
this is a reasonable high tide level, but not the coastline. The time for the tide to rise
overly conservative. Spring tides occur along the creek and to then flow back in the
approximately once a fortnight at full and opposite direction is one factor. Another is
new moon. The definition of different tidal the existence of local sand bars or raised
levels is provided in Figure 8.6.1.1, areas of the creek bed closer to the mouth
reproduced from the tide tables. of the stream, which may prevent a tide
Storm tides are an increase in ocean levels from reaching or falling below a certain
above the expected tidal levels caused by level at a particular road crossing. The
low pressure and wind effects. Storm tides transient nature of sand bars adds to the
can occur at any stage of the tidal cycle. difficulty in estimating the tidal reach.

As with other effects, the selection of a Although precise tide levels are not usually
storm tide needs to consider the combined necessary at an upstream road or bridge
risk of occurrence of the storm tide and the crossing, tide levels at the mouth of the

8 flood from the waterway. The probability


of a catchment flood at the same time as a
tidal stream are not sufficient to give tide
design parameters at the road or bridge.
storm tide is the product of the probabilities The absolute minimum survey requirements
of the separate events, resulting in a much at a road or bridge site are the times and
rarer combined recurrence interval than that levels for successive low - high - low tides.
of the separate events. Alternatively successive high - low - high
Storm tides have been analysed for tide information may be found. The more
locations around Queensland and levels are tidal cycles measured the better.
available from the Department of This information when compared with tide
Environment and Resource Management levels at the mouth of the creek will allow
(previously Queensland Environmental experienced hydraulic engineers to predict
Protection Agency) and local authorities. approximate design tides such as MHWS
and MLWS (Mean Low Water Springs) at
the project site.

March 2010
8-22
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

MSL
(Mean Sea-Level) The average level of the sea over a long period (preferably 18.6
years) or the average level which would exist in the absence of tides.
HAT (Highest Astronomical Tide) / LAT (Lowest Astronomical Tide) These are
the highest and lowest levels which can be predicated to occur under average
meteorological conditions and any combination of astronomical conditions. These
levels will not be reached every year. HAT and LAT are not the extreme levels
which can be reached, as storm surges may cause considerably higher and lower
levels to occur.
MHWS (Mean High Water Springs) Long term average of the heights of two
successive high waters during these periods of 24 hours (approximately once a
fortnight) when the range of tide is greatest, at full and new moon.
MLWS (Mean Low Water Springs) The long term average value of two successive
8
low waters over the same periods are defined for MHWN
AHD (Australia Height Datum) This Datum has been adopted by the National Mapping
Council as the datum to which all vertical control for mapping is to be referred.

Figure 8.6.1.1 - Tidal Planes

Storm surges occur as part of major storms


8.6.1.2 Storm Surge
such as cyclones where there are low
A storm surge is the rise (or fall) of open atmospheric pressures and the wind blows
coast water levels relative to the normal over reaches of the ocean.
water level and is due to the action of wind Some predicted surge heights have been
stress and atmospheric pressure on the produced by the Department of
water surface. Environment and Resource Management
and this data should be referenced.

March 2010
8-23
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

There is no correlation with tide levels, nor the relative sizes of the two streams, it may
are there any predictions for wave break not be realistic to expect floods to occur
setup and wave runup on the land. These together in the two streams.
factors will need consideration for any
design with storm surge as a factor. 8.7 Tailwater Levels
Storm surges would need to be considered Tailwater level refers to the normal water
with respect to coastal developments, the level, for a given flow, in a channel
protection of coastal roads, route immunity immediately downstream of a drainage
for evacuation purposes, and for major structure. For a proposed culvert, it is the
coastal drainage designs. Local depth of flow at the culvert outlet, measured
government may also have specific from the water surface in the downstream
requirements or data in relation to storm channel to the invert of the culvert and the
surge. depth can be significant. Tailwater levels
There is a low likelihood of occurrence of are an important control on the hydraulic
storm surge coinciding with flood events, performance of road drainage structures,
so calculation of design floods does not therefore the estimation of tailwater levels
need to consider both together, but the two is required for all hydraulic analyses for
effects should be considered independently. bridges and culverts.
Typically, tailwater level is defined by the
8.6.2 Downstream Tributary
downstream channel properties. If the
If the crossing is located on a stream which downstream channel and flow is uniform,
joins another watercourse (larger or the tailwater level may be determined using
smaller) downstream, other issues need to Mannings Equation (refer Section 8.4.3).
be considered. If the downstream flow is non-uniform, or
if it is being influenced by backwater, a
As the two open channels have different more sophisticated analysis by an

8 catchment sizes, they will peak at different


times. The combined flow at their junction
needs to be assessed.
experienced hydraulic engineer is required.
In this situation, advice and/or assistance in
this case can be provided the departments
In this case, two situations need to be Hydraulics Section or a suitably pre-
considered: qualified consultant.

(a) Major flood on tributary with 8.7.1 Tailwater Effects


limited flow in the main stream;
and As previously mentioned, tailwater is an
(b) Major flood on the main stream and important aspect required to determine the
limited flow in the tributary. hydraulic operation and performance of
drainage structures.
Both cases need to be analysed to provide
an understanding of the potential flood A low tailwater typically means the channel
conditions at the road. The risk of can drain the stormwater away fairly
coincidental flooding in the two streams quickly / easily. This is common where
needs to be considered to determine the drainage channels are less defined with low
combined risk of flooding. Depending on banks, allowing the stormwater to spread

March 2010
8-24
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

widely. Drainage structures with low proposed structure outlet, but


tailwater levels will most likely be representative of the downstream
controlled by inlet conditions and can have channel in general.
high outlet velocities, therefore erosion can
(b) Using a series of calculations
be an issue. A high tailwater level typically
(Mannings Equation & Q=A.V),
means the channel does not drain the
from no flow to maximum channel
stormwater away quickly. This is common
capacity, develop a stage-discharge
where drainage channels are reasonably
curve for the channel.
defined with mid-to-high banks, allowing
the channel to contain most stormwater (c) Using the stage-discharge curve
flows. Drainage structures with high and design discharge for the
tailwater will most likely be controlled by proposed structure, determine flow
outlet conditions and can have low outlet depth. This depth is adopted as the
velocities, therefore high headwater levels tailwater depth for the proposed
(afflux) can be an issue. structure analysis.
If the design discharge exceeds the
8.7.2 Design Tailwater Levels
maximum capacity of the channel, it means
the channel will overflow and the design
Typically, tailwater levels should be
discharge (flow) will spread. Review
determined based on an assessment of
survey data to see if there are any high
channel flow (and flow depths), for a given
banks or if cross section can be extended to
discharge, over a significant length of
allow for increased flow depth and if so,
undisturbed downstream channel. This
extend stage-discharge curve to incorporate
assessment is usually commenced at a point
additional waterway area. If the extended
well downstream of the proposed structure
cross section cannot contain the design
and calculated back / upstream towards the
discharge and the spread of flow is
proposed structure. This assessment is
significant (there would be little increase in
complex and hydraulic modelling software
is often used.
flow depth based on design discharge), then
the tailwater level could be set at the level
8
For the design of most drainage structures of maximum capacity for the defined
within the scope of this manual, the survey channel. Also, if there is not much of an
data gathered in relation to creeks / streams outlet channel (flat terrain / low banks) and
/ channels is usually limited to the road the design discharge easily overtops the
environment (constrained by property banks and/or spread of flow is significant,
boundaries), unless extended downstream then a low tailwater level should be
survey was specifically requested. adopted. Use survey data to produce a wide
Using available survey data and assuming flat cross section and then process as above
the channel is regular in shape and steady, to determine this low tailwater level. The
uniform flow conditions can be expected, old rule-of-thumb to adopt a tailwater
the tailwater level can be determined using level of barrel height of proposed culvert
Mannings formula as follows: is not considered accurate enough and can
result in inappropriate designs.
(a) Adopt a stream / channel cross
section just downstream of Furthermore, anecdotal information with
respect to channel flows should be sourced

March 2010
8-25
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

from local residents. Theoretical bare-earth channels. If a self-cleaning


predictions (proposed tailwater level) channel is required, designers should
should be checked against the anecdotal reference Section 2.8 for requirements.
evidence to see if both reasonably agree. If
Channel side slopes should be based on the
so, then the level of confidence in
slope stability of the material the channel is
prediction is increased. If not, then further
to be constructed in (channel is shaped
checks of calculations / gathered
before lining applied or grass grows).
information and so on is required. All
Typically, this will be in the range 1on 1 to
gathered information should be recorded.
1 on 4. Safe access for maintenance
equipment should also be considered.
8.8 Open Channel Design
Freeboard is the additional height of
The problem most likely to be faced by the channel required above the height of the
designer of artificial channels is the design flow. This allows for inaccuracies in
determination of a channel cross-section data used in calculation and possible
that will convey the design flow down a surcharge due to silt / debris build up and/or
slope producing a velocity which does not grass growth in the channel because of
create scour. delayed maintenance of the channel.

8.8.1 Design Methodology The freeboard to be adopted for open


channels, similar to QUDM (NR&W 2008),
There are two artificial channel types: is the greater of the following calculations:

hard lined channels; and 300 mm A;

vegetated / bare-earth channels. 20% of the flow depth; or

Each of these channel types has a specific velocity head B of the flow.
design methodology to determine the
channel cross section and these are detailed
8 in the following sections.
A
: Where flooding of adjacent land
and buildings does not represent a
8.8.1.1 General Considerations risk, the 300mm requirement can be
reduced to 150mm.
Further to the discussions in Sections 8.9 B
: Refer Section 8.4.5.1.
and 8.10, the following are aspects that
should be considered / established before
the design of the channel commences.
8.8.1.2 Hard Lined Channels
The velocity of flow in open channels is a
key aspect. Channel slope is an important With hard lined or rigid boundary channels,
factor in flow velocity. Generally, flow in the design procedure is relatively simple as
channels is intermittent, and the channel potentially erosive velocities are less
must be constructed to allow all stormwater important. Therefore, the cost of
to drain away (no ponding). Therefore the excavation and lining are primary factors in
minimum channel slope (So) for hard lined determining the geometry of the channel.
channels should not be less than 0.25% and
not be less than 0.5% for vegetated and

March 2010
8-26
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

In designing hard lined channels the (b) For best hydraulic section:
following must be initially considered:
by yX 2 y
R
lining
2 y 2 yX b
material (determines 2 2
Mannings n-value).
Based on the proposed channel lining, the and resolve for b as a function of y.
Mannings n-value can be selected from (c) Combining Mannings and Continuity
Table 8.4.3(a). Equations:
2 1
Research and experimentation has found AR 3 S f 2
that the most efficient, hydraulic section is Q
n
when the wetted perimeter (P) is minimised
for a given cross sectional area (A). Where:
Typically, in open channels, this occurs
A = by + Xy2 ; and
when the width of flow is twice the depth of
flow. Therefore the shape of channel that R = y/2
gives the best hydraulic efficiency (also So is used to approximate Sf (Friction
known as best hydraulic section) occurs Slope)
when the hydraulic radius is R
y
2 (d) Substitute b in equation with function
from (b) and solve for y.
Based on this requirement, the most
efficient shape is a semi-circle as it has the (e) With y, calculate b using function from
least wetted perimeter for a given area R (b).
is always equal to y/2 irrespective of Channel geometry can now be determined
dimensions. However the cost and and freeboard added.
difficulty of building semi-circular channels
prohibits their widespread use. Trapezoidal (f) Calculate Froude Number for channel
channels are more commonplace. The most section / flow and together with
efficient trapezoidal shape is the half-
hexagon.
velocity and depth of flow, check that
conditions are acceptable where the 8
designed channel discharges into an
For the design of hard lined channels: existing channel etc.
(a) Determine design discharge (Q), bed
slope (So), Mannings n-value and 8.8.1.3 Vegetated or Bare-earth
channel side slope (X) (refer Figure Channels
8.8.1.2).
Vegetated / bare-earth channels are erodible
boundary channels and the design
procedure is relatively simple, based on the
method of maximum permissible velocity.
This method assumes that the channel will
remain stable provided that the average
velocity of the design flow is below a
Figure 8.8.1.2 Trapezoidal Channel
Section determined threshold value. This method is

March 2010
8-27
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

not as realistic as shear-based / tractive For the design of vegetated / bare-earth


force methods but is considered reasonable. channels:
A key concern for vegetated channels is (a) Determine design discharge (Q), bed
what happens when the grass cover cannot slope (So), Mannings n-value, channel
be maintained, such as during drought or side slope (X) (refer Figure 8.8.1.2) and
after a bushfire. This aspect should be maximum permissible velocity (Vmax)
considered and if there is a reasonable risk from Table 8.8.1.3. For bare-earth
of occurrence and channel scour is likely / channel design, adopt 0% cover.
not desirable, then design should be
(b) Using the basic equation Q=V.A,
undertaken assuming bare-earth design
determine required waterway area.
values.
AQ
In designing vegetated / bare-earth channels Vmax
the following must be considered:
(c) Combining Mannings and Continuity
the material the channel is to be Equations:
constructed in;
2 1
a suitable grass species for the
AR 3 S o 2
Q
channel (where applicable); and n

an appropriate Mannings n-value. (d) rearrange and solve for wetted


perimeter (P):
A suitable grass species for a stormwater
3
channel should be quick to establish, be self A 5 3 S 12 2

repair, have a relatively short blade length P o


Qn
(< 50 mm), be able to survive short
durations of inundation, be able to
(e) Based on channel geometry, two
withstand proposed design velocities and be
expressions for A and P exist:
native to area. The species should be
8 chosen in consultation with a suitably
qualified landscape architect or
A b yX y ; and

horticulturalist. The reason for choosing a P 2y X 2 1 b


short blade length grass species is primarily Rearrange expression for A to isolate b:
that longer blade length species can reduce
A
flow velocity by increased flow resistance. b yX
This increases flow depth (surcharge) and y
ultimately can cause the channel to break its and substitute back into expression for P:
banks.
A
Table 8.8.1.3, largely derived from Soil P 2y X 2 1 yX
y
Conservation Measures Design Manual
for Queensland (NR&M 2004), gives Now calculate depth of flow (y). Solving
maximum permissible velocities, for use in for y requires rearrangement into the form
design, for consolidated, bare-earth of a quadratic equation.
channels and vegetated channels. ay 2 by c 0

March 2010
8-28
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

The general solution of a quadratic equation Table 8.8.1.3 - Maximum Permissible


Velocities (Design) for Consolidated,
is: Bare Channels and Vegetated Channels
b b 2 4ac Channel Permissible velocities (m/s) when
y gradient fraction of stable surface cover
2a is:

Solving a quadratic equation gives 2 roots. % 0.02 0.5 0.7 1.0


Substitute roots (y) into:
A Erosion resistant soils (e.g. Krasnozemsm &
b yX Red Earths)
y
0.5 0.8 1.8 2.4 2.8
and solve for b. Dismiss any negative
1 0.7 1.6 2.1 2.8
solution and adopt the positive (real) 2 0.6 1.4 1.8 2.5
solution for y. 3 0.5 1.3 1.7 2.4
Channel geometry can now be determined 4 1.3 1.6 2.3
and freeboard added. 5 1.2 1.6 2.2
6 1.5 2.1
If there are no real roots to the equation,
8 1.5 2.0
this means that the velocity will never reach 10 1.4 1.9
the maximum permissible for the given 15 1.3 1.8
discharge (Q) and roughness (n), regardless 20 1.3 1.7
of channel dimensions. In this case, use the
best hydraulic section design Easily eroded soils (e.g. Black Earths & fine
surface texture contrast soils)
methodology as detailed in Section 8.8.1.2
for the design of the vegetated channel, but 0.5 0.6 1.3 1.6 2.3
check that the average velocity of the 1 0.5 1.2 1.5 2.1
resultant channel section does not exceed 2 0.5 1.1 1.4 1.9
the maximum permissible velocity. 3 0.4 1.0 1.3 1.8
Calculate Froude Number for channel
section / flow and together with velocity
4
5
1.0
0.9
1.2
1.2
1.7
1.6 8
6 1.1 1.6
and depth of flow, check that conditions are
8 1.1 1.5
acceptable where the designed channel
10 1.1 1.5
discharges into an existing channel etc.
15 1.0 1.4
8.8.2 Channel Transitions 20 0.9 1.3

Changes from one channel cross-section to Notes:


another should be smoothly transitioned as 1. Assume the following species under average
conditions will provide the fraction of cover indicated:
energy losses occur with the changes.
- Kikuyu, Pangola and
It is recommended that maximum well maintained Couch species 1.0.
contraction rates of about 1 on 1, and - Rhodes grass, poorly maintained
Couch species - 0.7
maximum expansion rates of about 1 on 4 - Native species, tussock grasses - 0.5
be adopted as shown in Figure 8.8.2. 2. Applies to surface consolidated, but not cultivated

March 2010
8-29
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

Where:
hb = channel bend head loss (m);
B = channel width (m);

Figure 8.8.2 - Maximum Rates of V = average flow velocity (m/s);


Contraction and Expansion
g = acceleration due to gravity (9.81
m/s);
Transition head losses can be calculated
Rc = centreline radius of bend (m).
using the equation:
Results from using this equation should be
V 2 V 2
ht C u 1 2 considered as providing a conservative
2g 2g estimate of head loss.

Where: For bends between 0 and 90 degrees, linear


interpolation is recommended.
ht = transition head loss (m);
Cu = transition energy loss coefficient
Table 8.8.2 - Channel Transition Energy
(dimensionless); Loss Coefficients
V1 = average flow velocity upstream Transition Contraction Expansion
Type
of transition (m/s); Coefficient Coefficient
Cu Cu
V2 = average flow velocity
downstream of transition (m/s).
(i) Gradual 0.1 0.3
Table 8.8.2 gives contraction and expansion channel
coefficients (Cu) for use in this formula. transition

It will be noted that the more abrupt the (ii) Straight 0.3 0.5
transition, the greater the energy loss.
8 The difference in velocity head is always to
through
bridge
transition
be taken as positive even if mathematically
it is negative. In other words a change in
(iii) Square 0.6 0.8
section will always give a head loss.
edged abrupt
transition
8.8.3 Energy Losses in Channel
Bends Source: US Army Corps of Engineers

QUDM (NR&W 2008) gives an equation to


calculate the loss in a bend in an open 8.8.4 Superelevation in Channel
channel based on work by Mockmore Bends
(1944). The equation for channel bend
head loss for bends with changes in Water flowing around a bend in an open
direction between 90 to 180 degrees is: channel may show a superelevation with a
rise in water level on the outside of the
2 B V 2
hb bend and a corresponding dip in water
R
c 2 g levels on the inside of the bend. The

March 2010
8-30
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

maximum difference in these water levels is used where space permits to assist in
termed the superelevation (not to be minimising maintenance costs.
confused with the percentage
The maximum permissible velocity of flow
superelevation in geometric road design).
in a grass channel is the velocity which, if
The superelevation should be considered maintained for a reasonable length of time,
when a flood level is reported at a bend (the will not cause erosion. Permissible
exact location needing to be defined), or velocities for different vegetal covers,
where it is essential that the design flow channel slopes, and soil conditions are
does not exit from a man made channel at given in Table 8.8.1.3.
the outside edge of a bend.
The minimum non-silting velocity is
QUDM (NR&W 2008) gives the following uncertain. As a general rule the channel
equation to calculate the superelevation: velocity should not fall below 0.5 m/s.

R V 2 To function well, grassed channels


hsup 2 log e o
normally have slopes of from 0.2 to 0.6
Ri 2 g
percent. Where natural topography is
Where: steeper than the desired slope of the
hsup = superelevation of the water channel, drop structures / channel drops
surface across the channel (level (refer Section 8.11) should be considered.
difference) (m); Sharp curves which affect the flow in the
V = average flow velocity (m/s); channel should not be used. In general,
curves should be such that the minimum
g = acceleration due to gravity (9.81 radius at the centre line is equal to about
m/s); three times the width of the top of the
Ro= outside radius of bend (m); design flow.

Ri = inner radius of bend (m). Research by the United States Soil

8.9 Grassed Channels


Conservation Service (USSCS) has found
that, for a particular channel lined with a 8
certain species of grass of a definite length,
This section provides the guidelines for the value of n varies with the product of the
channels that will use grass as a protective mean velocity of flow V (m/s) and the
lining. Designers should refer to Chapter 7 hydraulic radius R (m). The relationship is
of this manual for further guidelines when a characteristic of the vegetation and is the
an open channel (such as a swale) is to also same for most common sections used.
be used for environmental reasons.
The vegetation characteristics were defined
8.9.1 Normal Grassed Channels by five degrees of retardance (A to E)
depending on the grass species and length.
The cross section shapes generally used for A channel lined with a grass having a high
grassed channels are trapezoidal (most retardance (A), such as 750 mm long
common), parabolic, or triangular. Flat side Rhodes grass, has its flow severely
slopes of absolute maximum steepness 1 on restricted by the grass, while any grass less
4 and desirable maximum 1 on 6 should be than 50 mm long, retardance (E), has little
effect on the flow. The relationship

March 2010
8-31
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

between grass species, length and degradation of habitat of ground-


retardance is given in Table 8.4.3(c). dwelling wildlife in a bushland
environment,
The original USSCS curves for degree of
retardance D and E have been replaced in die-off of grass owing to high
this Manual by curves based on work by sediment deposition (reinforced grass
Rouven et al. (1981) who found that the or turf can only be installed once the
original curves were not acceptable for contributing catchment is stable); and
short, stiff vegetation on slopes smaller than
loss of topsoil in the future when the
5%.
channel is removed, rebuilt,
The use of erosion control cut-off walls at reconditioned or relocated (the
regular intervals in a grassed channel is reinforced grass and its enclosed
desirable. Such cut-off walls will safeguard topsoil will likely need to be
a channel from serious erosion prior to the removed from the site, thus
grass becoming established or immediately preventing the reuse of the topsoil).
after a fire. These walls are usually of
The latter point can be a major concern in
unreinforced concrete or rock masonry,
areas where there is limited topsoil, which
approximately 200 mm wide and from 450
includes most of Queensland.
mm to 600 mm deep, extending across the
entire bed of the channel conforming to its There are several proprietary types of
shape. Where the banks of the channel may reinforced grass which are termed a form
erode, these walls should extend up the of geotextile protection in the U.S.A.
banks to the design water surface. Some tests of relatively small flows
indicate resistance to erosion for flows up
The designer needs to consider the impact
to 5 m/s. Caution should be exercised
of these walls on the conveyance of the
before adopting design velocities of this
channel and hence flood levels.
magnitude; the duration and depths of flow
on the actual job site will also need to be
8 8.9.2 Reinforced Grassed
Channels considered.
The reinforced grass may be considered an
The use of reinforced grass (or turf) in intermediate type of lining between
channel design provides the benefits of conventional grass and hard / impermeable
significantly increased allowable flow linings. Values of Mannings n for these
velocities, however, these products also linings can be found in Table 8.4.3(a).
come with disadvantages, including:
Example:
possible public safety problems
Section 3 (b) (ii) n value range 0.025
resulting from high flow velocities;
0.030 say use n = 0.028 for
maintenance personnel may not be conventional grass
aware of the existence of the grass
Section 2 (a) n = 0.012 for hard /
reinforcing and normal grading
impermeable
operations can result in costly
damage to the reinforcing mats; Average for reinforced grass n =
0.020
damage by grass fires;

March 2010
8-32
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

8.10 Channels Lined with possible requirements for an energy


Hard Facings dissipator at the end of the lined
channel section to manage the
8.10.1 General expected high flow velocities.

These channels are typically lined with 8.10.2 Riprap and Rock Filled
concrete, riprap or rock mattresses / gabions Wire Mattresses / Gabions
and are highly resistant to erosion. Design
velocities may be as high as 5 m/s, much Riprap is a conventional protection used to
higher than those for grassed channels. prevent channel bed and bank damage
upstream and downstream of hydraulic
Smaller cross-sections than those for
structures, at bends, at bridges and in other
grassed channels are possible to take the
channel areas where erosion potential exist.
same discharges, as side slopes of 1 on 1
are practical. Channels with hard facings The thickness of the riprap should be not
should be considered where the width is less than 1.5 times the largest diameter of
limited within the road environment. rock. Figure 8.10.2(b) shows the
relationship between bed velocity and rock
Other considerations for channels with hard
diameter (Rouven et al., 1981). When
faced linings include the provision of:
using Figure 8.10.2(b), bed velocity can be
contraction and expansion joints to taken as approximately 0.7 times the
minimise the risk of cracking and average channel velocity.
seepage and potential undermining;
Rock filled wire mattresses or gabions may
step irons (or similar device), for also be used to line the channel bank or bed
access / safety reasons, where the as shown in Figure 8.10.2(a). Smaller sized
channel side slope is steeper than 1 rocks can be used because the wire basket
on 2 and the channel depth exceeds surrounding the rock in the mattress or
0.9 m; gabion tends to make the mass act as a unit
pressure relief weep holes in
impermeable linings both within the
while retaining flexibility. Beside
providing protection against scour, rock
8
channel invert and within the channel filled gabions are useful as drops with
side slopes. Weep holes should be either vertical or stepped faces. At drops,
90 mm diameter at 1.8 m maximum the gabions should be keyed into both
centres (depends on detailed design banks, and a downstream cut-off wall
(structural) requirements); should be considered. Design and
construction of gabion protection should be
lateral protection against surface in accordance with manufacturers
flows undermining the side slopes. recommendations / specifications.
A minimum hard faced strip of width
0.45 m on both sides at the top of the
channel is recommended;
cut-off walls at the ends of the bed
and side linings. These should have
a minimum depth of 0.5 m; and

March 2010
8-33
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

Erosion: When used on the outside


of channel bends, rock filled
mattresses and gabions effectively
form a hydraulically smooth
surface. This smooth surface
causes high flow velocities to occur
immediately adjacent the wire
baskets. These high flow velocities
can then result in increased bed
erosion at the base of the gabion wall
(causing foundation problems), or
bank erosion immediately
downstream of the gabion protected
bank;
Figure 8.10.2(a) Channel Lined with Vegetation Cover: In some
Rock Filled Wire Mattresses.
installations, long-term stability is
8.10.2.1 Open Channel Lined with best achieved by having the gabion
Riprap and mattress structures covered with
vegetation. When this form of bank
When using riprap or rock filled wire stabilisation is placed under a wide-
mattresses over erodible underlying span bridge, light and rainfall
materials an appropriate geotextile fabric restrictions can limit or prevent
should be placed under and behind the vegetation cover, thus resulting in a
riprap, rock filled wire mattresses, or reduction of the expected life span of
gabions to prevent erosion and water piping the structure; and
through the gabion. Damage by Sediment: In channels

8 Some of the in-service problems associated


with rock filled wire mattresses and gabions
that transport large quantities of
coarse, bed-load sediment, the
expected design life of gabion and
are listed below:
rock mattress structures can be
Vegetation Problems: In some
reduced due to damage to both the
locations, such as South East
plastic and galvanised wire coatings.
Queensland, rock filled wire baskets
have been known to quickly vegetate Site specific designs need to be completed
with both native and non-native for every gabion or mattress application
weeds and vines. These vines can using design recommendations from the
then migrate into the surrounding suppliers of proprietary products.
bushland causing problems to native
trees;

March 2010
8-34
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

Figure 8.10.2(b) - Relationship between Bed Velocity and Rock Diameter

March 2010
8-35
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

Where channels are large enough, they


8.10.3 Concrete Lined Channels
should generally be accessible to vehicles
Concrete linings must be protected from for maintenance in which case the lining of
hydrostatic uplift forces which can be the base of the channel should be designed
created by a high water table after the flow for the appropriate vehicular loading and
in the channel has dropped. A free draining soil conditions.
perforated subsoil drainage pipe may be
required in large channels. In small 8.11 Channel Drops
channels, weepholes and porous backfill
The use of channel drops, waterfalls or
may be adequate.
scour checks may permit flatter channel
Where undermining along the top of the slopes to be employed. It is generally
lining is a risk, a cut-off lip or wall should desirable to use several low-head drops
be provided. In long lengths of lining, rather than fewer higher drops for safety
expansion joints are required. reasons. However, it is often more difficult
Care should be taken in the design of to control the hydraulics of low drops.
channels required to carry supercritical flow While vertical drops should generally be
to ensure that: avoided to minimise safety concerns and
curves are avoided if possible; erosion control problems, they may have to
be used in some circumstances. Also,
channels are free of obstructions depending on tailwater conditions,
which may cause oscillatory waves to supercritical flow often occurs on the apron
extend down the remaining length of of the drop and as a result, either a
the channels and into culverts; hydraulic jump or submerged jet will
pipes entering a channel are cut off usually form downstream.
flush with the lining; The use and design of channel drops are to
expansion joints are dowelled to be referred to Hydraulics Section,
8 prevent differential movement
between segments of the lining,
Engineering & Technology Division or a
suitably pre-qualified consultant.
which could otherwise allow high
velocity flow to enter the joints and 8.12 Baffle Chutes
cause uplift; and
Baffle chutes (Figure 8.12) are a
unintended hydraulic jumps do not satisfactory method of dissipating the
form. energy of flow in a channel where the slope
Channels designed for supercritical flow is steep. They require no tailwater to be
require a smooth surface which is provided effective.
by concrete lining. The thickness of lining The use and design of baffle chutes are to
and type of reinforcement required should be referred to Hydraulics Section,
be determined in consultation with the Engineering & Technology Division or a
departments Bridge Design Section or a suitably pre-qualified consultant.
suitably pre-qualified structural consultant.

March 2010
8-36
Department of Transport and Main Roads Chapter 8
Road Drainage Manual Open Channel Design

Figure 8.12 Diagram of a Baffle Chute

March 2010
8-37

Вам также может понравиться