SCHEDULE OF PROPOSAL WORK FOR TERMINAL

ID Task Name Duration Start Finish November December


30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
1 PROPOSALFORTERMINAL 41days 11/1/16 12/28/16
2 General 22days 11/1/16 11/30/16
3 ProposalStart 1day 11/1/16 11/1/16
4 PMSDevelopment 10days 11/2/16 11/15/16
5 PMSReview(Desktop) 5days 11/16/16 11/22/16
6 PMSReviewMeeting 1day 11/23/16 11/23/16
7 UpdatingPMS 5days 11/24/16 11/30/16
8 ManningPlan 5days 11/24/16 11/30/16
9
10 Engineering 28days 11/2/16 12/9/16
11 UpdatePlotPlan(Terminal) 3days 11/2/16 11/4/16
12 UpdateProcessDatasheet 3days 11/7/16 11/9/16
13 EquipmentDatasheetUpdating 3days 11/7/16 11/9/16
14 TechnicalBidEvaluationforVendor 10days 11/28/16 12/9/16
15 BMBQUpdating 15days 11/7/16 11/25/16
16
17 Procurement 27days 11/7/16 12/13/16
18 InquiretoVendor 10days 11/7/16 11/18/16
19 ClarificationwithVendor 15days 11/14/16 12/2/16
20 FinalizeBidTabulation 5days 12/5/16 12/9/16
21 ProcurementCostSummary 2days 12/12/16 12/13/16
22
23 Construction 25days 11/2/16 12/6/16
24 PrepareInquiryPackage 5days 11/2/16 11/8/16
25 InquiretoSubcont 10days 11/9/16 11/22/16
26 ClarificationwithSubcont 10days 11/16/16 11/29/16
27 FinalizeBidTabulation 2days 11/30/16 12/1/16
28 ConstructionCostSummary 3days 12/2/16 12/6/16
29
30 COSTSUMMARYPreparation/Approval 15days 12/7/16 12/28/16
31 ProcurementCostEvaluation 1day 12/14/16 12/14/16
32 ConstructionCostEvaluation 1day 12/7/16 12/7/16
33 CostSteeringMeetingbyBOD 1day 12/15/16 12/15/16
34 ForwardtoCONSORTIUM 1day 12/16/16 12/16/16
35 SubmittoCustomer 0days 12/28/16 12/28/16 12/2

Page 1 Rev. 0