The creation of releases (certain kinds of delivery schedule) under scheduling agreements is subject to the
following basic conditions:
Forecast delivery schedules are sent to the vendor to provide the latter with a rough idea of future
requirements. More concrete delivery data is provided to the vendor in the form of JIT schedules
o Forecast delivery schedules are transmitted once a month. The quantities are shown as monthly
quantities. The release horizon is nine months.
o JIT delivery schedules are created once a week. Changes to the overall delivery schedule in the system
also lead to the creation of new JIT schedules if these changes are not minor in comparison with the
previous JIT schedule and exceed certain tolerances.
If both situations (new weekly schedule due, changes to delivery schedule in the system) occur on the same day,
only one new JIT schedule is created.
JIT delivery schedules transmitted to the vendor set out the daily quantities for the next ten workdays.
JIT schedules determine backlogs and immediate requirements.
Planning runs and release creation take place on a daily basis.
Result
On the days on which the next FRC date (1st. Monday in the month) or the next JIT date (Monday each week) is
reached, scheduling agreements with the above profile settings are selected and SA releases (delivery schedules
to be issued to the vendor) created (because the next creation date has been reached).
Between these periods, the relevant scheduling agreements are also selected if the overall delivery schedule
stored in the system is changed significantly (either manually or via the materials planning and control system).
In this case, a JIT delivery schedule is generated, since this is defined in the creation strategy Changed or next
date. A forecast delivery schedule is not created, since this is subject to the strategy Next date only.
The frequency at which new JIT delivery schedules are created to reflect changes to the overall schedule is
defined via the tolerance profile.