PER JOB SUBCONTRACT AGREEMENT

This agreement has been made on __________________ between

CONTRACTOR: Sultan Saed Al- Zahrani Est.,


PO Box : 26974
Riyadh - KSA

and

SUBCONTRACTOR:

PROJECT NAME AND JOB NUMBER:

This agreement will terminate on__________________.

SUBCONTRACT WORK:

SCOPE OF WORK: BLOCK WORKS AT SEC HQ PROJECT

THE SUBCONTRACT DOCUMENTS:

1. CR COPY
2. CHAMBER OF COMMERCE
3. GOSSY
4. QUOTATION

1.1 SULTAN SAED AL ZAHRANI EST has entered into a contract (the "Construction Agreement") with
the client to perform the work for the each Project described in Addendums, which consist of the
Construction Agreement, the Specifications and Drawings prepared by the client which are a part thereof
Page | 1
any further documents referred to therein. The Subcontractor hereby agrees to furnish all necessary labor,
and/or equipment required, and perform all services and work necessary, to complete the portion of the
Work and any performance reasonably inferable from it (the Subcontract Work"), in accordance with the
Contract Documents.

1.2 The Subcontractor agrees that it may not for any purpose assign this Subcontract or any of its rights
to payment or duties hereunder without the prior written consent of SULTAN SAED AL ZAHRANI EST.

1.3 The Subcontractor represents and warrants that the Subcontractor Work shall be subject to any
warranty provided with respect to that portion of the Work in the Contract Documents. The Subcontractor
agrees to repair and replace at its own expense and promptly at the discretion of SULTAN SAED AL
ZAHRANI EST any defects in workmanship or materials which appear within one year after the date of the
final payment for the Project by the Owner to SULTAN SAED AL ZAHRANI EST or within any longer
period specified in the Contract Documents

1.4 Provide on the Project site a competent and experienced superintendent with full authority to accept
the directions of SULTAN SAED AL ZAHRANI EST and Architect/Engineer/Owner and to act in all
respects on behalf of the Subcontractor.

1.5 Inspect any surfaces to be covered by its material and notify SULTAN SAED AL ZAHRANI EST in
writing if any areas are not acceptable. If the Subcontractor proceeds without such notification, any defects
which subsequently appear are the Subcontractor's responsibility as to repairs, replacements and costs in
connection therewith.

2. TIME OF COMPLETION

2.1 The Subcontractor will man the job with a specified number of men per working day and it should
take approximately the specified time total to complete the scope of Work. The Subcontractor is responsible
for attending coordination and scheduling meeting as necessary through the duration of the project.

2.2 The Subcontractor shall commence the Work when notified to do so by SULTAN SAED AL
ZAHRANI ESTand shall diligently and continuously prosecute and complete the Work and coordinate the
Work with the other work being performed on the Project, in accordance with the project schedule, any
revisions to the project schedule, and any other scheduling requirements listed in this Agreement, so as not
to delay, impede, obstruct, hinder or interfere with the commencement, progress or completion of the whole
in any part of the Work or other work on the Project. Prosperity

2.3 Should the progress of the Work or the Project be delayed by any fault or neglect or act or failure to
act of the Subcontractor or any of its officers, agents, servants, employees, subcontractors or suppliers so as
to cause any additional cost, expense, liability or damage to SULTAN SAED AL ZAHRANI ESTor to the
Owner or any damages or additional costs or expenses for which SULTAN SAED AL ZAHRANI ESTor the
Owner may or shall become liable, the Subcontractor shall and does hereby agree to compensate SULTAN
SAED AL ZAHRANI ESTand the Owner for and indemnify them against all such costs, expenses, damages
and liability.

2.4 SULTAN SAED AL ZAHRANI EST, if it deems necessary, may direct the Subcontractor to work
overtime and if so directed the Subcontractor shall work said overtime and, provided that the Subcontractor
Page | 2
is not in default under any of the terms or provisions of this Agreement or of any of the other Contract
Documents, SULTAN SAED AL ZAHRANI ESTwill pay the Subcontractor for such actual additional
wages paid, if any, at rates which have been approved by SULTAN SAED AL ZAHRANI EST, plus taxes
imposed by law on such additional wages, plus workers' compensation insurance, liability insurance and
levies on such additional wages if required to be paid by the Subcontractor.

2.5 If, however, the progress of the Work or of the Project be delayed by any fault or neglect or act or
failure to act of the Subcontractor or any of its officers, agents, servants, employees, subcontractors, or
suppliers, then the Subcontractor shall, in addition to all of the other obligations imposed by this Agreement
upon the Subcontractor in such case, and at its own cost and expense, work such overtime as may be
necessary to make up for all time lost in the completion of the Work and of the Project due to such delay.
Should the Subcontractor fail to make up for the time lost by reason of such delay, SULTAN SAED AL
ZAHRANI ESTshall have the right to cause other subcontractors to work overtime and to take whatever
other action it deems necessary to avoid delay in the completion of the Work and of the Project, and the cost
and expense of such overtime and/or such other action shall be borne by the Subcontractor.

3. PRICE

3.1 The sum __________________ to be paid by SULTAN SAED AL ZAHRANI ESTout of funds
received from the owner, to the Subcontractor for the satisfactory performance and completion of the Work
and of all of the duties, obligations and responsibilities of the Subcontractor under this Agreement and the
other Contract Documents (hereinafter called the Price) shall be subject to addition and deductions as herein
provided.
3.2 The price includes all Federal, State, County, Municipal, and other taxes imposed by law and based
upon labor, services, materials, equipment or other items acquired, performed, furnished or used for or in
connection with the Work, including but not limited to sales, use and personal property taxes payable by or
levied or assessed against the Owner, SULTAN SAED AL ZAHRANI ESTor the Subcontractor. Where the
law requires any such taxes to be stated and charged separately, the total price of all items included in the
Work plus the amount of such taxes shall not exceed the Price.
3.3 The price for each individual project shall be set forth in an addendum, signed by SULTAN SAED
AL ZAHRANI ESTand SUBCONTRACTOR for an agreed amount.

4. PAYMENT SCHEDULE

4.1 All agreements will be determined in writing on a per project basis.

4.2 All invoices must be received by SULTAN SAED AL ZAHRANI ESTonce project is completed. The
invoices must be received by Wednesday before the close of business (4:00 p.m), at least 1 week prior to the
Friday SUBCONTRACTOR wishes to be paid. If the invoice is not received at the specified time
subcontractors will not be paid until the following check run takes place. In addition, each subcontractor is
only allowed to bill for work completed. All required documents must be received by SULTAN SAED AL
ZAHRANI ESTprior to any start of project, and must remain current at all times. The required documents
include but are not limited to certificate of insurance, certified payrolls, W-9 Form, Business Registration
Certificate, Public Works Certificate (if needed) Partial/Final waiver of lien. Etc. All back charges will be
held immediately against the first unpaid invoice. SUBCONTRACTOR is NOT allowed to use SULTAN

Page | 3
SAED AL ZAHRANI Ests office staff or equipment to conduct his administrative duties. Checks will be
ready for pickup on Fridays or at the accounting depts discretion, no exceptions.

4.3 The obligation of SULTAN SAED AL ZAHRANI ESTto make a payment under this Agreement,
whether a progress or final payment, or for extras or change orders or Delays to the Work, is subject to the
express condition precedent of payment therefore by the Owner. If SULTAN SAED AL ZAHRANI ESThad
provided payment or performance bonds, or a combination payment and performance bonds, the obligation
of SULTAN SAED AL ZAHRANI ESTand its surety under any of those bonds to make any payment
(whether a progress payment of final payment) to a claimant on that bond is similarly subject to the express
condition precedent of payment therefore by the Owner.

4.4 The Subcontractor agrees that, if and when requested to do so by SULTAN SAED AL ZAHRANI
EST, it shall furnish such information, evidence and substantiation as SULTAN SAED AL ZAHRANI
ESTmay require with respect to the nature and extent of all obligations incurred by the Subcontractor for or
in connection with the Work, all payments made by the Subcontractor thereon, and the amounts remaining
unpaid, to whom and the reasons there-for.

5. FINAL PAYMENT

5.1 Final payment to the Subcontractor shall be made only with funds received by SULTAN SAED AL
ZAHRANI ESTfrom the Owner, the Construction Lender or the Owners Agent as final payment for work
under the general contract. Final payment to SULTAN SAED AL ZAHRANI ESTby the Owner shall be an
express condition precedent, which must occur before SULTAN SAED AL ZAHRANI ESTshall be
obligated to make final payment to the Subcontractor. In addition, final payment by SULTAN SAED AL
ZAHRANI ESTto the Subcontractor shall not become due and payable until the following other express
condition precedent have been met: (1) the completion and acceptance of the Work by SULTAN SAED AL
ZAHRANI ESTand the Architect/Owner; (2) provision by the Subcontractor of evidence satisfactory to
SULTAN SAED AL ZAHRANI ESTthat there are no claims, obligations, or liens outstanding or unsatisfied
for labor, services, materials, equipment, taxes or other items performed, furnished or incurred for or in
connection with the Work; (3) execution and delivery by the Subcontractor, in a form satisfactory to
SULTAN SAED AL ZAHRANI EST, of a one year Warranty for workmanship and materials, or as
described in the specifications, whichever is more stringent; and (4) execution and delivery by the
Subcontractor, in a form satisfactory to SULTAN SAED AL ZAHRANI EST, of a General Release running
to and in favor of SULTAN SAED AL ZAHRANI ESTand the Owner. Should there prove to be any such
claim, obligation or lien after final payment is made, the Subcontractor shall refund to SULTAN SAED AL
ZAHRANI ESTall moneys that SULTAN SAED AL ZAHRANI ESTand/or the Owner shall pay in
satisfying, discharging or defending against any such claim, obligation, or lien or any action brought or
judgment recovered thereon and all costs and expenses, including legal fees and disbursements, incurred in
connection therewith. The final payment, less the percent retainage as specified in the Construction
Agreement, shall be due within forty (40) days after all of these express conditions precedent have been met.

5.2 No payment (final or otherwise) made under or in connection with this Agreement shall be
conclusive evidence of the performance of the Work or of this Agreement, in whole or in part, and no such
payment shall be construed to be an acceptance of defective, faulty or improper work or materials nor shall it
release the Subcontractor from any of its obligations under this Agreement: nor shall entrance and use by the
Owner constitute acceptance of the Work or any part thereof.

Page | 4
6. CHANGE ORDERS, ADDITIONS, AND DEDUCTIONS

6.1 SULTAN SAED AL ZAHRANI ESTreserves the right, from time to time, whether the Work or any
part thereon shall not have been completed, to make changes, additions and/or omissions in the Work as it
may deem necessary, upon written order to the Subcontractor. The value of the work to be changed, added
or omitted shall be stated in said written order and shall be added to or deducted from the Price.

6.2 The value of the work to be changed, added or omitted shall be determined by the lump sum or unit
prices, if any, stipulated herein for such work. If no such prices are stipulated, such value shall be
determined by whichever of the following, methods or combination thereof SULTAN SAED AL ZAHRANI
ESTmay elect:

(a) By adding or deducting a lump sum or an amount determined by a unit price agreed upon between
the parties hereto.

(b) By adding (1) the actual net cost to the Subcontractor of labor in accordance with the established
rates, including required union benefits, premiums the Subcontractor is required to pay for
workmen's compensation and liability insurance, and payroll taxes on such labor, (2) the actual cost
to the Subcontractor of materials and equipment and such other direct costs as may be approved by
SULTAN SAED AL ZAHRANI EST, less all savings, discounts, rebates and credits, (3) an
allowance of 10% for overhead on items (1) and (2) above, and (4) an allowance of 5% for profit on
items (1), (2) and (3) above.

(c) Should the parties hereto be unable to agree as to the value of the work to be changed, added or
omitted, the Subcontractor shall proceed with the work promptly under the written order of
SULTAN SAED AL ZAHRANI ESTfrom which order the stated value of the work shall be omitted,
and the determination of the value of the work shall be referred to the Architect whose decision shall
be final and binding upon the parties hereto.

6.3 All changes, additions or omissions in the Work ordered in writing by SULTAN SAED AL
ZAHRANI ESTshall be deemed to be a part of the Work there-under and shall be performed and furnished
in strict accordance with all of the terms and provisions of this Agreement and the other Contract
Documents.

7. LOSS OR DAMAGE TO WORK

7.1 SULTAN SAED AL ZAHRANI EST shall not be responsible for any loss or damage to the Work to
be performed and furnished under this Agreement, however caused, until after final acceptance thereof by
SULTAN SAED AL ZAHRANI EST and the Architect, nor shall SULTAN SAED AL ZAHRANI EST be
responsible for loss or damage to materials, tools, equipment, applicants or other personal property owned,
rented or used by the Subcontractor or anyone employed by it in the performance of the Work, however
caused.

8. CLEANING-UP

8.1 The Subcontractor shall, at its own cost and expense, (1) keep the Premises free at all times from all
waste materials, packaging materials and other rubbish accumulated in connection with the execution of its
Page | 5
Work by collecting and depositing said materials and rubbish in locations or containers as designated by
SULTAN SAED AL ZAHRANI EST from which it shall be removed by SULTAN SAED AL ZAHRANI
EST from the Premises without charge, (2) clean and remove from its own Work and from all contiguous
work of others any soiling, staining, mortar, plaster, concrete or dirt caused by the execution of its Work and
make good all defects resulting there-from (3) at the completion of its Work in each area, perform such
cleaning as may be required to leave the area "broom clean" and (4) at the entire completion of its Work
remove all of its tools, equipment, scaffolds, shanties and surplus materials. Should the Subcontractor fail to
perform any of the foregoing to SULTAN SAED AL ZAHRANI Ests satisfaction, SULTAN SAED AL
ZAHRANI EST shall have the right to perform and complete such work itself or through others and charge
the cost thereof to the Subcontractor.

9. ACCIDENT PREVENTION

9.1 The Subcontractor agrees that the prevention of accidents to workmen engaged upon or in the
vicinity of the Work is its responsibility. The Subcontractor agrees to comply with all Federal, State,
Municipal and local laws, ordinances, rules, regulations, codes, standards, orders, notices and requirements
concerning safety as shall be applicable to the Work, including, among others, the Federal Occupational
Safety and Health Act of 1970 (OSHA), as amended, and all standards, rules, regulations and orders which
have been or shall be adopted or issued there-under, and with the safety standards established during the
progress of the Work by SULTAN SAED AL ZAHRANI EST. When so ordered, the Subcontractor shall
stop any part of the Work which SULTAN SAED AL ZAHRANI EST deems unsafe until corrective
measures satisfactory to SULTAN SAED AL ZAHRANI EST have been taken, and the Subcontractor
agrees that it shall not have any claim for damages growing out of such stoppages. Should the
Subcontractor neglect to take such corrective measures, SULTAN SAED AL ZAHRANI EST, may do so at
the cost and expense of the Subcontractor and may deduct the cost thereof from any payments due or
become due to the Subcontractor. Failure on the part of SULTAN SAED AL ZAHRANI EST to stop
unsafe practices shall in no way relieve the Subcontractor of its responsibility there-for.

9.2 All work to be executed in strict accordance with ALL applicable safety regulations as published in
the Code of Federal Regulations and administered by OSHA, especially fall protection, reparatory
protection, confined space, lead health and safety, scaffold work, and hazard communication.

9.3 All materials and/or equipment used must be approved for use by OSHA construction and general
industry standards.

9.4 Any violations and fines received by the Subcontractor or SULTAN SAED AL ZAHRANI Est for
and work covered in the scope of this agreement will be paid by the Subcontractor.

10. CONTRACTOR'S SPECIAL REMEDIES FOR BREACH

10.1 It is understood that this agreement is for only one part of an overall job for which SULTAN SAED
AL ZAHRANI EST had total responsibility, and any failure of Subcontractor to diligently and properly
perform his part of the job could seriously disrupt and impair the whole job. Those circumstances relate not
only to the work itself, but to details such as insurance and Section 2 for whose enforcement SULTAN
SAED AL ZAHRANI EST may be under obligation to Owner or others and whose breach might impair the
whole General Contact or financing of the job. In recognition of the resulting importance of Subcontractor's
strictly complying with all his duties under this agreement: SULTAN SAED AL ZAHRANI EST may rescind
Page | 6
this agreement, discharge Subcontractor from the job, and replace Subcontractor with another upon: Three
days notice to correct what SULTAN SAED AL ZAHRANI EST deems, in SULTAN SAED AL ZAHRANI
Ests expert discretion, a failure by Subcontractor to diligently pursue schedule of the Work, or Three days
notice to correct what SULTAN SAED AL ZAHRANI EST deems, in SULTAN SAED AL ZAHRANI Ests
expert discretion, a performance which is defective. Or One day notice to correct omissions of obligations
under INSURANCE: or Reasonable notice in the circumstances for correction of any other breach: and
Subcontractor's having failed upon expiration of such time to fully resolve the matter(s) which motivated the
notice.

10.2 Such notice may be made by telephone if confirmed by same-day mailing of written notice. If
Subcontractor fails to take a telephone call from the number indicated for him on Page 1, the notice period
shall commence two days after the first class mailing or mailgram is dispatched to Subcontractor's address.
If Subcontractor has any employee on the job, notice will be effective by giving it in writing to such
employee. Remedies under this Section are additional to those which are generally available under law.

11. TERMINATION OF AGREEMENT

11.1 SULTAN SAED AL ZAHRANI EST shall have the right at any time by written notice to the
Subcontractor, to terminate this Agreement and require the Subcontractor to cease work there-under, in
which case, provided the Subcontractor be not then in default, SULTAN SAED AL ZAHRANI EST shall
indemnify the Subcontractor against any damage directly resulting from such termination, except that the
Subcontractor shall not be entitled to anticipated profits on work unperformed or on materials or equipment
unfurnished.

12. INSURANCE

12.1 Before commencing the Work, the Subcontractor shall procure and maintain, at its own expense,
until completion and final acceptance of the Work at least the following insurance from insurance companies
satisfactory to SULTAN SAED AL ZAHRANI EST.
1. WORKER'S COMPENSATION AND EMPLOYERS' LIABILITY INSURANCE: in accordance
with laws of the State in which the Work is situated.
2. COMPREHENSIVE GENERAL LIABILITY INSURANCE INCLUDING COMPLETED
OPERATIONS, CONTRACTUAL LIABILITY INSURANCE AGAINST THE LIABILITY
ASSUMED HEREIN ABOVE, and including CONTRACTORS' PROTECTIVE LIABILITY
INSURANCE if the Subcontractor sublets to another all or any portion of the Work.
Combined Single Limit $1,000,000
3. COMPREHENSIVE AUTOMOBILE LIABILITY INSURANCE covering all owned, non-owned
and hired automobiles used in connection with the Work, with the following limits:
Bodily Injury (including death) $1,000,000 Combined Single Limit and Property Damage

12.2 Before commencing the work, the Subcontractor shall furnish a certificate, satisfactory to SULTAN
SAED AL ZAHRANI EST, from each insurance company showing that the above insurance is in force,
stating policy numbers, dates of expiration, and limits of liability there-under, and further providing that the
insurance will not be canceled or changed until the expiration of at least thirty (30) days after written notice
of such cancellation or change has been mailed to and received by Scaturro Bros., Inc. t/a SULTAN SAED

Page | 7
AL ZAHRANI Est Painting & Sandblasting Contractors shall be named as an additional insured under these
policies of insurance.

13. INDEMNIFICATION

13.1 The Subcontractor hereby exculpates and agrees to indemnify and hold harmless SULTAN SAED AL
ZAHRANI EST and its officers, directors, agents, representatives, employees, successors and assigns from
and against any and all claims, losses, damages, liabilities and the like, including reasonable counsel fees
which SULTAN SAED AL ZAHRANI ESTmay incur, suffer, sustain or be required to pay by reason of the
injury or death of any person or the damage to any property whatsoever, caused or alleged to have been
caused by any act or omission of the Subcontractor or any of its suppliers or subcontractors, or the
employees, agents or representatives of the Subcontractor or any of its suppliers or subcontractors, arising
out of or in any manner connected with the performance of the subcontract Work whether or not caused in
whole or in part by any act, omission or negligence of SULTAN SAED AL ZAHRANI EST, its officers,
agents, representatives or employees.

13.2 The Subcontractor agrees to indemnify SULTAN SAED AL ZAHRANI ESTand its surety from and
against any and all actions, suits, proceedings, claims or demands arising out of or alleged to have arisen out
of the performance of or the operations under this Subcontract. In the event any action, suit or proceeding
is instituted against SULTAN SAED AL ZAHRANI ESTor its surety upon any liability of defect arising out
of or alleged to have arisen out of the performance of or the operations under the Subcontract, or in the
event of any claim, counterclaim, setoff, re-coupment or other defense is made or asserted against SULTAN
SAED AL ZAHRANI ESTupon any liability or defect arising out or alleged to have arisen out of the
performance of or the operations under this Subcontract, SULTAN SAED AL ZAHRANI ESTshall, within
thirty (30) days, give notice in writing thereof to the Subcontractor which, at its own cost and expense, shall
defend against such action, suit, proceeding, claim, counterclaim, setoff re-coupment or other defense and
take all such steps as SULTAN SAED AL ZAHRANI ESTmay deem necessary to prevent the obtaining of
judgment against or the. Successful maintenance of such claim, counterclaim, setoff, recoupment or other
defense against SULTAN SAED AL ZAHRANI EST. Notwithstanding the foregoing, SULTAN SAED AL
ZAHRANI ESTshall be permitted to be represented by its own counsel should SULTAN SAED AL
ZAHRANI ESTso desire.

13.3 The Subcontractor warrants that the delivery, erection and use of material supplied or erected under
this Subcontract, either alone or in combination with other materials, do not and will not infringe upon any
patents, United States or foreign. The Subcontractor shall indemnify and save harmless SULTAN SAED AL
ZAHRANI ESTand the Owner against all damages which they or either of them, may sustain by reason of
claims for infringement or patents or trademarks arising out of the Subcontract Work, or by reason of the
use of any patented appliances, products or processes in connection with the Subcontract Work. The
Subcontractor shall, at the sole expense of the Subcontractor, defend any action brought against SULTAN
SAED AL ZAHRANI ESTand the Owner, or either of them, found upon a claim of infringements of patent
rights, and shall reimburse SULTAN SAED AL ZAHRANI ESTand the Owner, or either of them, for all
expenses, including reasonable counsel fees, incurred by SULTAN SAED AL ZAHRANI ESTand the
Owner, or either of them, in defending any action brought for such alleged infringement. SULTAN SAED
AL ZAHRANI ESTand the Owner shall each be permitted to be represented by their own counsel in any
such or action should they, I or either of them, so desire.

Page | 8
13.4 In the event any action, suit, proceeding, claim or demand is made against SULTAN SAED AL
ZAHRANI EST, its surety, officers, directors, agents, representatives, employees, successors or assigns
against which the Subcontractor has herein agreed to indemnify SULTAN SAED AL ZAHRANI EST, then
SULTAN SAED AL ZAHRANI ESTmay withhold from any payment due or hereafter to become due to the
Subcontractor hereunder, an amount sufficient in its sole judgment to protect it from such action, suit,
proceeding, claim or demand, together with legal fees and disbursements.

14. BONDS

14.1 If required, the Subcontractor shall furnish to SULTAN SAED AL ZAHRANI ESTseparate
performance and payment bonds on the amounts of one hundred percent (100%) of the Subcontract price,
the form and contents of such bonds and the Sure or Sureties thereon to be satisfactory to SULTAN SAED
AL ZAHRANI EST.

15. SEVERABILITY

15.1 In the event that any provision or any part of a provision of this Agreement shall be finally
determined to be superseded, invalid, illegal or otherwise unenforceable pursuant to applicable laws by an
authority having jurisdiction, such determination shall not impair or otherwise affect the validity, legality or
enforceability of the remaining provisions or parts of provisions of this Agreement, which shall remain in full
force and effect as if the unenforceable provision or part deleted.

16. SIGNING

16.1 The individual(s) signing on behalf of the Subcontractor personally represents that the Subcontractor
is a corporation - partnership, - individual proprietorship in good standing in New Jersey and that he has full
authorization to bind it to this Contract.

17. ENTIRE AGREEMENT

17.1 This agreement constitutes the entire ANNUAL agreement between the parties hereto. No oral
representations or other agreements have been made to SULTAN SAED AL ZAHRANI EST except as
stated in the Agreement. This Agreement may not be changed in any way except as herein provided, and no
intention or provision hereof may be waived by SULTAN SAED AL ZAHRANI EST except in writing
signed by its duly authorized officer or agent.

The said parties, for themselves, their heirs, executors, administrators, successor and assigns, do hereby
agree to the full performance of all the terms and provisions herein contained. IN WITNESS WHEREOF
the parties to these presents have hereunto set their hands as of the day and year first above written.

Addendum #1

Re: Revision to Original Payment Schedule

As of April 1st, 2002 SULTAN SAED AL ZAHRANI Est Painting has instituted an addition to the previous
payment schedule for all of its subcontractors for the benefit of both of our firms. The revised plan will be
implemented, so that each subcontractor will be paid timely for the work that they complete.
Page | 9
All Subcontractors will be paid according to original payment schedule with the following exceptions.

a. All Subcontractors will be paid on a biweekly basis.


b. All Subcontractors must send in their paperwork to the office before payment due date, to ensure
enough payables in the system to cover payment request.
c. No Subcontractor will be paid for last minute invoicing. No exceptions.
d. All Subcontractors will be required to hand in a written proposal, to be signed by both parties before
the start work.
e. All Subcontractors must sign an annual contract with SULTAN SAED AL ZAHRANI Est Painting.

Addendum #2

NAME & LOCATION OF JOBSITE: Any and all Job Sites requiring the payment of Prevailing
Wage Rates to all workers

This addendum is to clarify that the subcontractor named above, understands and agrees to the requirements
set forth by any and all public works projects on payments of prevailing wage benefits to all of its employees
working on such prevailing wage projects

The employer/subcontractor understands that it is their sole responsibility to follow the guidelines of the
prevailing wage labor laws of the state in which the project is located, and that SULTAN SAED AL
ZAHRANI EstPainting will NOT be held liable for any and all claims arising from the negligence of such
subcontractor.

Addendum #3

Effective 04/01/2013

A 10% Retainage will be held on all jobs and payment will only be released to subcontractor upon payment
received by SULTAN SAED AL ZAHRANI Est from contractor

The Subcontractor also agrees that if any claims arise due to the subcontractors negligence to obey the
prevailing wage laws set forth, SULTAN SAED AL ZAHRANI Est Painting will have full authority to
withhold such amount from subcontractors contract to pay such claims and penalties that arises from its
negligence including attorneys fees and court costs.

18. PERSONS AUTHORIZED TO MAKE BINDING AGREEMENTS

1. Raja Ramaiya, Project Manager, SULTAN SAED AL ZAHRANI Est


Page | 10
2. Yasir Arafath, Project Engineer , SULTAN SAED AL ZAHRANI Est

1. __________________________________________ Subcontractor
2. __________________________________________ Subcontractor
3. __________________________________________ Subcontractor
Name Title

SULTAN SAED AL ZAHRANI Est Contractors


(sub name) __________________________

Date ______________________________ Date ________________________

Signature ______________________________ Signature ________________________

Name ______________________________ Name ________________________

Title ______________________________ Title ________________________

Subcontractor Fed. Id#: ______________

Page | 11