Академический Документы
Профессиональный Документы
Культура Документы
Before we turn our attention to the various parts of a welding symbol, it is important that we understand some of the
terminology relating to these symbol. A basic distinction which must be pointed out is the difference between
the terms "weld symbol" and "welding symbol." As stated in AWS A2.4, "the weld symbol indicates the type
of weld. The welding symbol is a method of representing the weld symbol on drawing, and includes supplementary
information and consists of the following eight elements. Not all elements need be used unless required for
clarity."
In the construction of a welding symbol, the primary element which is always included is the reference line.
This is simply a horizontal line segment which provides the basis for all other parts of the symbol. It must appear
on the drawing as a horizontal line, because there is a significance wheter information lies above or below the line.
The next element of the welding symbol is the arrow. This line segment is connected to one side of the weld joint.
This now gives significance to the terms arrow side and other side. That is, the side to which the arrow points is
referred to as the arrow side, while the opposite side is called the other side.
Once the arrow side and other side have been assigned by the placement of the arrow, it is now possible to specify
information relating to either or both sides.
The AWS convention is that any information placed below the reference line relates to the arrow side of the joint,
and that information above the reference line describes what will occur on the other side of the joint.
2
This rule will never change, no matter which end of the reference line is attached to the arrow or which direction
the arrow may point. In this figure shows several welding symbols depicting arrow side welds,
but with the arrow oriented in different directions and at either end of the reference line. However, the operations
will be performed on the side of the joint to which the arrow point.
M : Machined
G : Grinded
C : Chipping
3
CURRENT CONDITIONS
BY SYAFRIZAL. S
0' ) +
1 + OR - 50
2 - 50
3 + 50
4 + OR - 70
5 - 70
6 + 70
7 + OR - 90
8 - 90
9 + 90
WELDING POSITION
1 : ALL POSITIONS
2 : ALL POSITIONS, EXCEPT
VERTICAL DOWNWARD
3 : FLAT BUTT WELD,
FLAT FILLET WELD
HORIZONTAL / VERTICAL
FILLET WELD
4 : FLAT BUTT WELD,
FLAT FILLET WELD
5 : AS 3 AND RECOMMENDED
FOR VERTICAL DOWNWARD
5
WELDER PERFORMANCE QUALIFICATION TEST REPORT
ASME STANDARD REQUIREMENT
WELD PREPARATION
WELD PREPARATION
WELD PREPARATION
Preheat has been carried out before and after first layered
by the E309L-17 electrodes to ensure the heat is covered
WPS required before carrying the next step or overlay with
the E316L-17 electrodes
( furnished with the run plate before touching up to test piece )
WELDING TECHNIQUE
SURFACE FINISH
ASME PARA 136.3 Inspection and Qualification of Authorized Inspector for Boiler External Piping
136.3.1 Piping for which inspection and stamping is required as determined in accordance with
Para.100.1.2 (A) shall be inspected during construction and after completion and at the option of the
Authorized Inspector at such stages of the work as he may designate. For specific requirements see
the applicable parts of section I of the ASME Boiler and Pressure Vessel Code, PG-104 through PG-113.
Each manufacturer is required to arrange for the services of Authorized Inspectors as defined
in PG-91 of the ASME Boiler and Pressure Vessel Code.
136.3.2 Certification by stamping and Data Reports, where required, shall be as per PG-104, PG-105,
PG-109, PG-110, PG-11, and PG-112 of section I of the ASME Boiler and Pressure Vessel Code.