Академический Документы
Профессиональный Документы
Культура Документы
1X
Fig. 1 Vibration Trend of Steam Turbine from the year of 1996 to 2006
B. Performance
efficiently. And operation and power loss are neglect in this
The Steam Turbine performance test was reported in 2007 concept.
by EGAT production efficiency division following ASME So, this combined cycle plant which is gas-fired type of
PTC6 testing standard [2] , which showed that the heat rate HRSG, SB-C10, should be operated rather than other thermal
from 1998 to 2006 increased from 10216.37 to 10285.72 power plants where petroleum-fired type of boiler functioned
kJ/kWh respectively. Therefore, this result can be diagnosed in.
in 2 sections as follows. Obviously, Bangpakong Thermal Power Plant, BPK-T3,
1) Loss of fuel: The Efficiency of Steam Turbine decreased which is oil-fired plant, was selected to be an operating
only 0.24% in an 8-year operation. The assumption had been replacement by SB-C10 because fuel oil of BPK-T3 is in
identified that heat rate since 1995 will be increased in the highest cost rank. The fuel cost difference between BPK-T3
constant rate of 69.35 kJ/kwh per 8 years in case the Turbine and SB-C10 is 1.78. It is summarized that the current MO
is not performed with any maintenance activities. The power outage duration would reduce to 8 days as a result of
plant will lose in fuel cost as shown in the calculation below. avoidance to overhaul the Steam Turbine. The result was
calculated as shown below.
Fuel Cost of SB-C10 (Natural Gas) = 1.271 Baht/kwh Given, Standard MO duration = 45 days
Loss of Fuel MO – overhaul Steam Turbine duration = 37 days
= (1.27 Baht/kwh)(115 Mw)(24 hr/day)(1/2)(120.35(15) - If BPK-T3 was operated instead of SB-C10 which is
104.31(13) year.kJ/kwh) comprised of 2 x 110 Gas Turbine and 1x115 Steam Turbine
= 79.82 million Baht as a full block, the fuel cost would be increased:
= (1.78 Baht/kwh)(335 Mw)(24 hr/day)
Therefore, this Steam Turbine which is operated = 14.31 million Baht per day
continuously in this condition in the next 2 years must be
calculated for the loss of fuel to be 79.82 million Baht. Indeed, So, the fuel cost savings for 8 days operation would be:
the fuel price tendency is increased year after year, so the loss = 114.49 million Baht
of fuel as shown above is the minimum loss which can
possibly occur. Because we may lose the fuel cost upon the Comparatively, the fuel cost savings was approximately
performance, we have to conduct economic analysis to decide twice more than the fuel loss by lower efficiency; therefore,
whether we should shift the MO outage onto another 2 years. this outage plan had to be optimized to 37-day duration
2) Economic Analysis: According to the entire without Turbine overhaul, so the savings is 34.67 million Baht
organizational synergy, the replacement energy concept is by deducting 79.82 from 114.49 million Baht (1.06 million
applied. All EGAT power plants which are regularly base load US$; 32.58 Baht = 1 US$ [4]). Additionally, the operation and
operation type comprise coal, natural gas, and petroleum fired maintenance cost which was not included in this calculation
plants. would be considerably reduced.
They are classified by generating fuel cost as the first, C. Risk Assessment
second, and third rank respectively. The conceptual emphasis In addition, we need to identify the risk by multiplying the
on energy preservation and reduction of the overall fuel cost is failure effects and failure mode likelihood. Referring to Table
to manage electricity generation and distribution in Thailand I and II below, we can indicate risk in this case as 1 of “Very
unlikely” mode and multiply by 10 of failure effect weight
that can be affected in unit shutdown. However, the result is
equal to 10% as the moderate probability, we can mitigate by
our Steam Turbine life assessment record. Rarely the critical
failure, for example, stress corrosion cracking, corrosion
fatigue, thermal fatigue cracking, can be usually found earlier
than 20 years of its lifetime. Some failure damages such as
erosion at turbine nozzle or a crack on high-pressure casing
had been repaired by the mean of welding and/or grinding
simply.
TABLE I
FAILURE MODE LIKELIHOOD
1 Very unlikely has not happened to equipment or similar
equipment
2 Unlikely >2 times in 5-10 years to equipment or similar
equipment
3 Likely >3 times in last 5 years
TABLE II
WEIGHT OF CONSEQUENCE/FAILURE EFFECT
Fig. 2 Stethoscope Measurement of Bearing Noise Condition
Failure Effect Weight
Unit Shut down 10 As for vibration technique, the vibrometer told us the
Unit Through put Loss 8 overall vibration which was initially analyzed. The acceptance
criterion is ISO standard 10816-3[5] in velocity range and
Minor Through put Loss 4
mm/s rms unit of measurement.
Start up Delay 4 Our teamwork which comprised engineering team,
Personnel Hazard 10 operators and the owner had the meeting together to optimize
Personnel Hazard – Low Probability of Injury 5 the outage work scope by all of collected information and data.
The one of our report on condensate pump in appendix 2
Environment Regulations Event – Major Incident 10
shown as the example of condition monitoring inspection
Environment Regulations Event – Incident 7 sheet. Referring to their condition, we finally summarized
Environment Regulations Event – Near Miss 3 which Auxiliaries need to be overhauled and what the specific
parts need to be inspected in the overhaul. The result is
III. AUXILIARIES presented in table IV.
Biannually, managing the outage plan interval along with B. Performance
Time Based Maintenance (TBM), we determine the number of Not only was the Auxiliaries’ health, but also power
the Auxiliaries to overhaul. Most of Auxiliaries to be consumption which is derived from efficiency consideration.
considered in Condition Based Maintenance (CBM) are We identified power consumption at shop test and current
pumps as shown in quantity (EA.) in Table IV. The condition as shown in appendix 3, and then the optimum time
optimization of the work scope to overhaul the really needed to overhaul was found out from the concept when the
equipment by its health is our main concept. The primary cumulative cost of increased power consumption equals the
reason why there should be no standard of outage interval like overhaul cost.
TBM is to execute at the least cost of maintenance. The tool When; Pi = Intial Power Consumption, kW
that we applied in CBM plan is “Condition Monitoring” Po = Current Power Consumption, kW
which was started roughly 3 months before the outage. We M = Motor Efficiency, %
selected the auxiliary equipment to be inspected in the MO E = Electricity Cost per unit
scope from January 29th to March 3rd, 2008 as summarized in = 2.37 Baht/kwh (Updated June 2007)
table IV. C = Capacity of Operation, %
A. Condition Monitoring Therefore, the deterioration cost, d, is equal to;
In terms of human senses, we inspected various items such d = (Po – Pi)(E)(C) Baht/hr
as looseness, leakage, cleanliness, as well as tightness at base M
plate and bolts. We also measured noise level, cavitation The deterioration cost in 1 month, D, must be multiplied by
formation by stethoscope also noise condition at bearing as in 720 hr.
the following figure. Our professional team had diagnosed
noise pattern and pinpointed what can possibly be the source
of the abnormal noise. For thermal measurement, we applied
the infrared thermometer to indicate the bearing temperature.
TABLE III
OPTIMUM TIME TO OVERHAUL AUXILIARIES, SB-C10
TABLE IV
LIST OF AUXILIARIES AND OVERHAUL COST IN THE MO SCOPE, SB-C10
REFERENCES
[1] Mitsubishi Heavy Industry, Allowable Shaft Vibration, Japan, 1997.
[2] American Society of Mechanical Engineers (ASME) PTC6 Testing
Standard, Steam Turbine, 1996.
[3] Production Efficiency Division, Electricity Generating Authority of
Thailand, Marginal Cost/Price of Electricity in Thailand, 2006
[4] Oanda Corporation (2008) homepage [Online]. Available: ,
http://www.oanda.com/convert/fxhistory
[5] International Organization for Standardization, Mechanical Vibration
–Evaluation of Machine Vibration by Measurements on Non-Rotating
Parts, ISO 10816-3, 1st edition, French, 1998.
[6] H.P. Bloch, and A.R. Budris, Pump User’s Handbook: Life extension,
New York, 2004.